PRINTER'S NO.  1440

  

THE GENERAL ASSEMBLY OF PENNSYLVANIA

  

HOUSE BILL

 

No.

1212

Session of

2009

  

  

INTRODUCED BY MILLARD, TURZAI, SAYLOR, BEYER, BOBACK, BOYD, BROOKS, CAUSER, CLYMER, D. COSTA, CREIGHTON, CUTLER, DALLY, EVERETT, GEIST, GINGRICH, GROVE, HARHART, HARRIS, HICKERNELL, KAUFFMAN, M. KELLER, MAJOR, MOUL, PHILLIPS, REICHLEY, ROCK, ROHRER, SCAVELLO, STERN, SWANGER, VULAKOVICH, WATSON AND BENNINGHOFF, APRIL 7, 2009

  

  

REFERRED TO COMMITTEE ON CONSUMER AFFAIRS, APRIL 7, 2009  

  

  

  

AN ACT

  

1

Amending Title 66 (Public Utilities) of the Pennsylvania

2

Consolidated Statutes, in restructuring of electric utility

3

industry, further providing for definitions; and providing

4

for rate phase-in plans.

5

The General Assembly of the Commonwealth of Pennsylvania

6

hereby enacts as follows:

7

Section 1.  Section 2803 of Title 66 of the Pennsylvania

8

Consolidated Statutes is amended by adding a definition to read:

9

§ 2803.  Definitions.

10

The following words and phrases when used in this chapter

11

shall have the meanings given to them in this section unless the

12

context clearly indicates otherwise:

13

* * *

14

"Overall rate."  The sum of all retail rates charged by an

15

electric distribution company for electric service, including

16

all applicable riders and surcharges.

17

"Rate phase-in plan" or "plan."  A plan filed with the

 


1

commission by an electric distribution company solely to phase

2

in any initial increase in the rate for generation service that

3

may occur upon the expiration of that electric distribution

4

company's generation rate cap. The plan may not address or

5

affect any other rate changes filed by the electric distribution

6

company.

7

* * *

8

Section 2.  Title 66 is amended by adding a section to read:

9

§ 2816.  Rate phase-in plans.

10

(a)  General rule.--Within 90 days of the effective date of

11

this section, each electric distribution company shall file a

12

rate phase-in plan with the commission to provide residential

13

and small commercial customers, who use up to 25 kw in maximum

14

registered peak load, the option to phase in any overall rate

15

increase that:

16

(1)  is greater than 25% for a customer class; and

17

(2)  results from an initial increase in the price for

18

default generation service that may occur

19

upon the expiration of the generation rate cap for such electric

20

distribution company specified under section 2804(4) (relating

21

to standards for restructuring of electric industry) or a

22

restructuring plan under section 2806(f) (relating to

23

implementation, pilot programs and performance-based rates) and

24

ending no later than three years after such expiration date.

25

Customer participation in any plan approved under this

26

subsection shall be voluntary.

27

(b)  Conditions.--Each rate phase-in plan shall be subject to

28

commission approval, which shall be granted no less than 90 days

29

prior to implementation of the phase-in plan in each electric

30

distribution company's service territory and shall meet the

- 2 -

 


1

following conditions:

2

(1)  The plan, which shall be implemented through a

3

nonbypassable credit or charge to customers' bills separate

4

from the default generation charge, shall offer a transition

5

to prices at the level permitted pursuant to a commission-

6

approved procurement plan beginning on the expiration date of

7

the generation rate cap for the electric distribution

8

company.

9

(2)  The plan shall provide for all of the following:

10

(i)  that the overall rate increase resulting from an

11

initial increase in the rate for default generation

12

service charged to each customer class under the plan

13

shall be phased in for as long as three years; and

14

(ii)  that the overall rate increase in the first

15

year shall not exceed 25% of the overall rate in effect

16

for that customer class on the last day prior to

17

expiration of the generation rate cap, and the overall

18

rate increase in the second year shall not exceed an

19

additional 25% of the overall rate in effect for that

20

customer class on the last day prior to expiration of the

21

generation rate cap.

22

(3)  The plan may offer the customer the option to begin

23

the phase-in period prior to the expiration of the generation

24

rate cap, provided that the customer accrues interest on any

25

prepaid amount at a rate of 6% compounded annually. Customer

26

participation in any plan approved under this subsection

27

shall be voluntary.

28

(4)  The plan shall specify the means of providing notice

29

to customers of the option to participate in such plan on a

30

voluntary basis.

- 3 -

 


1

(5)  Any customer is eligible to participate in a phase-

2

in plan as described under this section whether the customer

3

chooses to take electric generation service from an electric

4

distribution company or from an electric generation supplier.

5

(c)  Recovery.--

6

(1)  The electric distribution company shall fully

7

recover the expenses associated with implementing a plan,

8

including related administrative costs, and the amount of the

9

deferred payments resulting from customers' participation in

10

the plan and a carrying charge of 6% compounded annually on

11

the deferred payments from the customers by means of a

12

competitively neutral nonbypassable charge to each customer

13

class, subject to the conditions established under subsection

14

(b).

15

(2)  The charge shall be a reconcilable automatic

16

adjustment charge under section 1307 (relating to sliding

17

scale of rates; adjustments), be applied to participating

18

customers on a customer class basis, be included in other

19

charges on the electric distribution company's bill and not

20

appear as a separate line item on a customer's bill.

21

(3)  Any rate phase-in plan approved by the commission

22

shall be considered a new service offered for the first time

23

under section 2804(4)(vi).

24

(4)  The amounts deferred together with the carrying

25

charges thereon shall be deemed to be transition costs for

26

the purposes of section 2812 (relating to approval of

27

transition bonds); and upon issuance by the commission of a

28

qualified rate order under section 2812, such amounts

29

together with any cost related to the issuance of transition

30

bonds shall be deemed qualified transition expenses.

- 4 -

 


1

(d)  Deferred amounts.--The commission shall permit deferred

2

costs and associated carrying charges to be recorded for

3

accounting purposes on an electric distribution company's books

4

of account as a regulatory asset where the electric distribution

5

company is the default service provider.

6

(e)  Credit.--If a customer enrolled in a plan that begins

7

prior to the expiration of the electric distribution company's

8

generation rate cap leaves the electric distribution company's 

9

system prior to the full distribution of amounts collected, a

10

credit shall be applied to the customer's final bill and any

11

remainder shall be refunded to the customer.

12

(f)  Intangible transition property.--

13

(1)  An electric distribution company's right to recover

14

costs under an approved phase-in plan shall be deemed

15

intangible transition property for the purposes of sections

16

2808(e) and 2812, but not for any other sections of this

17

chapter.

18

(2)  The commission may issue a qualified rate order

19

under section 2812 with respect to such costs and to issue

20

other orders and take actions as may be necessary or proper

21

for the electric distribution company or its assignee to

22

issue transition bonds, as provided under section 2812,

23

secured by such intangible transition property; and upon

24

issuance by the commission of a qualified rate order, the

25

amounts authorized to be imposed on customer bills shall be

26

deemed intangible transition charges for the purposes of

27

section 2812.

28

(g)  Penalty for failure to file.--If any electric

29

distribution company fails to file a rate phase-in plan with the

30

time required by subsection (a), the commission shall impose a

- 5 -

 


1

fine of $100,000 per day on that electric distribution company

2

until it files such plan.

3

Section 3.  This act shall take effect immediately.

- 6 -