PRINTER'S NO. 1970
No. 1589 Session of 2007
INTRODUCED BY D. EVANS, JUNE 18, 2007
REFERRED TO COMMITTEE ON APPROPRIATIONS, JUNE 18, 2007
AN ACT 1 Providing for the capital budget for the fiscal year 2007-2008; 2 itemizing public improvement projects, furniture and 3 equipment projects, transportation assistance projects, 4 redevelopment assistance capital projects, flood control 5 projects, Keystone Recreation, Park and Conservation Fund 6 projects, Environmental Stewardship Fund projects, Motor 7 License Fund projects, State forestry bridge projects and 8 federally funded projects to be constructed or acquired or 9 assisted by the Department of General Services, the 10 Department of Community and Economic Development, the 11 Department of Conservation and Natural Resources, the 12 Department of Environmental Protection and the Department of 13 Transportation, together with their estimated financial 14 costs; authorizing the incurring of debt without the approval 15 of the electors for the purpose of financing the projects to 16 be constructed, acquired or assisted by the Department of 17 General Services, the Department of Community and Economic 18 Development, the Department of Conservation and Natural 19 Resources, the Department of Environmental Protection or the 20 Department of Transportation; stating the estimated useful 21 life of the projects; providing an exemption; providing for 22 limitation on certain capital projects, for special 23 provisions for certain redevelopment assistance capital 24 projects and for preemption of local ordinances for 25 Department of Corrections projects; and making 26 appropriations. 27 The General Assembly of the Commonwealth of Pennsylvania 28 hereby enacts as follows: 29 Section 1. Short title.
1 This act shall be known and may be cited as the Capital 2 Budget Project Itemization Act of 2007-2008. 3 Section 2. Total authorizations. 4 (a) Public improvements.--The total authorization for the 5 additional capital projects in the category of public 6 improvement projects itemized in section 3 and to be acquired or 7 constructed by the Department of General Services, its 8 successors or assigns and to be financed by the incurring of 9 debt shall be $1,122,566,000. 10 (b) Furniture and equipment.--The total authorization for 11 the additional capital projects in the category of public 12 improvement projects consisting of the acquisition of original 13 movable furniture and equipment to complete public improvement 14 projects itemized in section 4 and to be acquired by the 15 Department of General Services, its successors or assigns and to 16 be financed by the incurring of debt shall be $64,846,000. 17 (c) Transportation assistance.--The total authorization for 18 the capital projects in the category of transportation 19 assistance projects itemized in section 5 with respect to which 20 an interest is to be acquired in or constructed by the 21 Department of Transportation, its successors or assigns and to 22 be financed by the incurring of debt shall be $47,148,000. 23 (d) (Reserved). 24 (e) Flood control.--The total authorization for the capital 25 projects in the category of flood control projects itemized in 26 section 7 and to be constructed by the Department of 27 Environmental Protection, its successors or assigns, and to be 28 financed by the incurring of debt, shall be $4,350,000. 29 (f) Keystone Recreation, Park and Conservation Fund.--The 30 total authorization for the capital projects in the category of 20070H1589B1970 - 2 -
1 public improvement projects itemized in section 8 and to be 2 constructed by the Department of Conservation and Natural 3 Resources, its successors or assigns and to be financed from 4 current revenues in the Keystone Recreation, Park and 5 Conservation Fund shall $28,613,000. 6 (g) Environmental Stewardship Fund projects.--The total 7 authorization for the capital projects in the category of public 8 improvement projects itemized in section 9 and to be constructed 9 by the Department of Conservation and Natural Resources, its 10 successors or assigns and to be financed from current revenues 11 in the Environmental Stewardship Fund shall be $142,255,000. 12 (h) State forestry bridge projects.--The total authorization 13 for the capital projects itemized in section 10 to be 14 constructed by the Department of Conservation and Natural 15 Resources, its successors or assigns and to be financed by oil 16 company franchise tax revenues pursuant to 75 Pa.C.S. § 17 9502(a)(2)(iv) (relating to imposition of tax) shall be 18 $8,300,000. 19 (i) General Fund current revenue projects.--The total 20 authorization for the capital projects in the category of public 21 improvement projects itemized in section 11 and to be developed 22 or constructed by the Department of General Services, its 23 successors or assigns and to be financed from current revenues 24 in the General Fund shall be $8,100,000. 25 Section 3. Itemization of public improvement capital projects. 26 Additional capital projects in the category of public 27 improvement projects to be constructed or acquired by the 28 Department of General Services, its successors or assigns, and 29 to be financed by the incurring of debt, are hereby itemized, 30 together with their respective estimated financial costs, as 20070H1589B1970 - 3 -
1 follows: 2 Total 3 Project 4 Project Allocation 5 (1) Office of Administration 6 (i) Statewide mobile radio and microwave 7 system 8 (A) Additional funds for DGS project 950- 9 10, Statewide mobile radio and 10 microwave system 36,100,000 11 (Base Project Allocation - $36,100,000) 12 (2) Department of Agriculture 13 (i) Health Diagnostic Laboratory 14 (A) Construct a new Pennsylvania Animal 15 Health Diagnostic Laboratory (PADLS) 16 with Bio-Safety Level-3 capabilities to 17 support PADLS 33,000,000 18 (Base Project Allocation - $29,700,000) 19 (Design and Contingencies - $3,300,000) 20 (ii) State Dairy Farm 21 (A) Rehabilitate and construct several 22 support facilities for State dairy farm 23 to complement existing dairy operation 500,000 24 (Base Project Allocation - $450,000) 25 (Design and Contingencies - $50,000) 26 (3) Department of Conservation and Natural 27 Resources 28 (i) Bald Eagle State Park 29 (A) Rehabilitate and develop a family 30 campground at the State park including 20070H1589B1970 - 4 -
1 infrastructure 2,000,000 2 (Base Project Allocation - $2,000,000) 3 (ii) Chester County 4 (A) Acquire the Strawbridge Property lands 5 in Chester County 4,000,000 6 (Land Allocation - $4,000,000) 7 (iii) Clear Creek State Park 8 (A) Construct new maintenance facility 9 including infrastructure 1,800,000 10 (Base Project Allocation - $1,800,000) 11 (iv) Cook Forest State Park 12 (A) Replace the office/visitors' center 2,500,000 13 (Base Project Allocation - $2,000,000) 14 (Design and Contingencies - $500,000) 15 (B) Replace the pit latrines with modern 16 flush facilities including 17 infrastructure 1,000,000 18 (Base Project Allocation - $800,000) 19 (Design and Contingencies - $200,000) 20 (v) Erie Bluffs State Park 21 (A) Provide for construction of the 22 initial development of 540 acre area 23 including infrastructure, roads, 24 trails, parking lots and boating 25 facilities 10,000,000 26 (Base Project Allocation - $8,000,000) 27 (Design and Contingencies - $2,000,000) 28 (vi) Forest District 3 29 (A) Rehabilitate and improve the Gunter 30 Valley Dam to return it to a safe 20070H1589B1970 - 5 -
1 condition and in compliance with 2 current requirements 7,000,000 3 (Base Project Allocation - $5,600,000) 4 (Design and Contingencies - $1,400,000) 5 (vii) Forest District 4 6 (A) Repair and repave roads including 7 returning a portion back to a gravel 8 road 5,000,000 9 (Base Project Allocation - $4,000,000) 10 (Design and Contingencies - $1,000,000) 11 (viii) Forest District 7 12 (A) Rehabilitate roadways throughout the 13 forest to ensure safety and to provide 14 public access for outdoor activities 3,000,000 15 (Base Project Allocation - $2,400,000) 16 (Design and Contingencies - $600,000) 17 (ix) Forest District 9 18 (A) Rehabilitate roadways throughout the 19 forest to ensure safety and to provide 20 public access for outdoor activities 3,000,000 21 (Base Project Allocation - $2,400,000) 22 (Design and Contingencies - $600,000) 23 (x) Forest District 10 24 (A) Rehabilitate roadways throughout the 25 forest to ensure safety and to provide 26 public access for outdoor activities 3,000,000 27 (Base Project Allocation - $2,400,000) 28 (Design and Contingencies - $600,000) 29 (xi) Forest District 12 30 (A) Rehabilitate roadways throughout the 20070H1589B1970 - 6 -
1 forest to ensure safety and to provide 2 public access for outdoor activities 3,000,000 3 (Base Project Allocation - $2,400,000) 4 (Design and Contingencies - $600,000) 5 (xii) Forest District 13 6 (A) Rehabilitate roadways throughout the 7 forest to ensure safety and to provide 8 public access for outdoor activities 3,000,000 9 (Base Project Allocation - $2,400,000) 10 (Design and Contingencies - $600,000) 11 (xiii) Forest District 15 12 (A) Rehabilitate roadways throughout the 13 forest to ensure safety and to provide 14 public access for outdoor activities 3,000,000 15 (Base Project Allocation - $2,400,000) 16 (Design and Contingencies - $600,000) 17 (xiv) Forest District 16 18 (A) Rehabilitate roadways throughout the 19 forest to ensure safety and to provide 20 public access for outdoor activities 3,000,000 21 (Base Project Allocation - $2,400,000) 22 (Design and Contingencies - $600,000) 23 (xv) Forest District 20 24 (A) Rehabilitate roadways throughout the 25 forest to ensure safety and to provide 26 public access for outdoor activities 3,000,000 27 (Base Project Allocation - $2,400,000) 28 (Design and Contingencies - $600,000) 29 (B) Rehabilitate rest facilities, parking 30 lots and multiple use trails and 20070H1589B1970 - 7 -
1 refurbish living quarters as a 2 departmental training facility with 3 necessary equipment 2,500,000 4 (Base Project Allocation - $2,000,000) 5 (Design and Contingencies - $500,000) 6 (xvi) Gouldsboro State Park 7 (A) Rehabilitate day use area and provide 8 for the replacement of lifeguard 9 building, bathhouse, boat rental 10 building and comfort station including 11 infrastructure 2,500,000 12 (Base Project Allocation - $2,000,000) 13 (Design and Contingencies - $500,000) 14 (xvii) Lehigh Gorge State Park 15 (A) Provide for the acquisition of land 16 necessary to complete the scheme for 17 the park in conformance with Statewide 18 recreation plan 3,500,000 19 (Land Allocation - $3,500,000) 20 (xviii) Montgomery County 21 (A) Acquire the Erdenheim Farm lands in 22 Montgomery County 4,000,000 23 (Land Allocation -$4,000,000) 24 (xix) Nescopeck State Park 25 (A) Develop day use area and provide for 26 the development of recreational and 27 educational facilities for day use 3,000,000 28 (Base Project Allocation - $2,500,000) 29 (Design and Contingencies - $500,000) 30 (xx) Promised Land State Park 20070H1589B1970 - 8 -
1 (A) Rehabilitate and improve lower lake 2 dam to return it to a safe condition 3 and in compliance with current 4 requirements 3,500,000 5 (Base Project Allocation - $2,800,000) 6 (Design and Contingencies - $700,000) 7 (xxi) Quehanna Wild Area 8 (A) Provide for the remediation of land of 9 radioactive materials within the 10 Quehanna wild area at the former 11 nuclear reactor site 2,500,000 12 (Base Project Allocation - $2,500,000) 13 (B) Facilitate the cleanup and reclamation 14 of the Quehanna reactor site at 15 Moshannon State Forest 1,834,000 16 (Base Project Allocation - $1,834,000) 17 (xxii) Ricketts Glen State Park 18 (A) Repair and repave roads including 19 returning a portion back to a gravel 20 road 3,500,000 21 (Base Project Allocation - $2,800,000) 22 (Design and Contingencies - $700,000) 23 (xxiii) S.B. Elliott State Park 24 (A) Additional funding to complete the 25 visitors' center and overnight lodging 26 including furnishings and equipment 3,500,000 27 (Base Project Allocation - $3,500,000) 28 (xxiv) Shikellamy State Park 29 (A) Rehabilitate marina damaged by flood 30 waters in 2005 and 2006 including new 20070H1589B1970 - 9 -
1 docks, railings, concrete bulkheads and 2 courtesy docks 1,500,000 3 (Base Project Allocation - $1,200,000) 4 (Design and Contingencies - $300,000) 5 (4) Department of Corrections 6 (i) State Correctional Institution at 7 Cambridge Springs 8 (A) Construct a new 128-cell L-3 close 9 security housing unit with 230-bed 10 capacity with infrastructure upgrade 13,500,000 11 (Base Project Allocation - $10,800,000) 12 (Design and Contingencies - $2,700,000) 13 (ii) State Correctional Institution at Camp 14 Hill 15 (A) Additional funds for DGS project 573- 16 26, replacement of Group 1 plumbing 17 components 8,000,000 18 (Base Project Allocation - $6,400,000) 19 (Design and Contingencies - $1,600,000) 20 (B) Additional funds for DGS project 573- 21 27, provide additional funding for 22 Phase 2 to complete the plumbing 23 repairs started under project 573-27 6,000,000 24 (Base Project Allocation - $4,800,000) 25 (Design and Contingencies - $1,200,000) 26 (iii) State Correctional Institution at Coal 27 Township 28 (A) Construct a new 128-cell L-3 close 29 security housing unit with 230-bed 30 capacity with infrastructure upgrade 13,500,000 20070H1589B1970 - 10 -
1 (Base Project Allocation - $10,800,000) 2 (Design and Contingencies - $2,700,000) 3 (iv) State Correctional Institution at Cresson 4 (A) Renovate and upgrade the heating and 5 air conditioning system serving the 6 medical building 550,000 7 (Base Project Allocation - $440,000) 8 (Design and Contingencies - $110,000) 9 (v) State Correctional Institution at Dallas 10 (A) Construct a new 2,300-bed L-3 Medium 11 Security prison on the grounds of SCI 12 Dallas including infrastructure and 13 road work to incorporate the two 14 facilities at this site 189,000,000 15 (Base Project Allocation - 16 $151,200,000) 17 (Design and Contingencies - 18 $37,800,000) 19 (vi) State Correctional Institution at Forest 20 (A) Construct a new 128-cell L-5 close 21 security housing unit with 22 infrastructure upgrade 15,500,000 23 (Base Project Allocation - $12,400,000) 24 (Design and Contingencies - $3,100,000) 25 (vii) State Correctional Institution at 26 Frackville 27 (A) Replace and upgrade the institution's 28 main electrical switchgear 520,000 29 (Base Project Allocation - $416,000) 30 (Design and Contingencies - $104,000) 20070H1589B1970 - 11 -
1 (viii) State Correctional Institution at 2 Huntingdon 3 (A) Construct a new 2,000-bed L-3 medium 4 security prison on the grounds of SCI 5 Huntingdon including infrastructure and 6 road work to incorporate the two 7 facilities at this site 175,000,000 8 (Base Project Allocation - 9 $140,000,000) 10 (Design and Contingencies - 11 $35,000,000) 12 (ix) State Correctional Institution at Laurel 13 Highlands 14 (A) Replace roofs on dietary building No. 15 4 and housing unit building C 800,000 16 (Base Project Allocation - $640,000) 17 (Design and Contingencies - $160,000) 18 (x) State Regional Correctional Facility at 19 Mercer 20 (A) Replace roofs on Medical Building, M 21 Block and G Block 650,000 22 (Base Project Allocation - $520,000) 23 (Design and Contingencies - $130,000) 24 (xi) State Correctional Institution at Muncy 25 (A) Replace roofs on administration, 26 laundry, storeroom and kitchen 27 buildings and housing units A Block, M 28 Block, K Block and F Block 2,300,000 29 (Base Project Allocation - $1,840,000) 30 (Design and Contingencies - $460,000) 20070H1589B1970 - 12 -
1 (xii) State Correctional Institution at Pine 2 Grove 3 (A) Construct a new 128-cell L-3 close 4 security housing unit with 230-bed 5 capacity with infrastructure upgrade 13,500,000 6 (Base Project Allocation - $10,800,000) 7 (Design and Contingencies - $2,700,000) 8 (xiii) State Correctional Institution at 9 Rockview 10 (A) Construct a new 2,000-bed L-3 Medium 11 Security prison on the grounds of SCI 12 Rockview including infrastructure and 13 road work to incorporate the two 14 facilities at this site 175,000,000 15 (Base Project Allocation - 16 $140,000,000) 17 (Design and Contingencies - 18 $35,000,000) 19 (5) Department of Education 20 (i) Scranton State School for the Deaf 21 (A) Provide improvements and upgrades to 22 the emergency, mechanical and 23 electrical systems throughout the 24 campus 7,560,000 25 (Base Project Allocation - $6,574,000) 26 (Design and Contingencies - $986,000) 27 (ii) Pennsylvania State University 28 (A) Provide for the capital renewal for 29 campuses in the eastern region of the 30 university including code compliances 20070H1589B1970 - 13 -
1 and infrastructure upgrades 7,000,000 2 (Base Project Allocation - $7,000,000) 3 (B) Provide for the capital renewal for 4 campuses in the central region of the 5 university including code compliances 6 and infrastructure upgrades 7,000,000 7 (Base Project Allocation - $7,000,000) 8 (C) Provide for the capital renewal for 9 campuses in the western region of the 10 university including code compliances 11 and infrastructure upgrades 7,000,000 12 (Base Project Allocation - $7,000,000) 13 (iii) University of Pittsburgh 14 (A) Providing for upgrades and deferred 15 maintenance needs on all campuses 20,000,000 16 (Base Project Allocation - $16,667,000) 17 (Design and Contingencies - $3,333,000) 18 (iv) Lincoln University 19 (A) Renovate Langston Hughes Library and 20 correct problems from structural design 21 flaws 7,000,000 22 (Base Project Allocation - $5,600,000) 23 (Design and Contingencies - $1,400,000) 24 (B) Renovate Wright Hall building systems, 25 classrooms and laboratory including ADA 26 requirements 4,000,000 27 (Base Project Allocation - $3,200,000) 28 (Design and Contingencies - $800,000) 29 (6) Department of Environmental Protection 30 (i) Cambria County 20070H1589B1970 - 14 -
1 (A) Additional funds for Patton Flood 2 Project to the upstream section and 3 remove existing levee in the downstream 4 section 3,600,000 5 (Base Project Allocation - $3,000,000) 6 (Design and Contingencies - $600,000) 7 (B) Construct Lancashire No.15 acid mine 8 drainage treatment plant to improve an 9 estimated 25 miles of the west branch 10 of the Susquehanna River 10,025,000 11 (Base Project Allocation - $10,025,000) 12 (ii) Clearfield and/or Cambria County 13 (A) Construct active acid mine drainage 14 facility for currently untreated mine 15 pool discharge in the Susquehanna River 16 basin to offset agricultural 17 consumptive use demands 6,000,000 18 (Base Project Allocation - $6,000,000) 19 (iii) Clearfield and Elk Counties 20 (A) Construct active acid mine drainage 21 facility near the Village of Hollywood, 22 Huston Township, Clearfield County, to 23 restore water quality in the Bennett 24 Branch Sinnemahoning Creek in support 25 of the PA Wilds initiative 12,125,000 26 (Base Project Allocation - $12,125,000) 27 (iv) Fulton County 28 (A) Reconstruct two streams currently 29 flowing into abandoned surface mine 30 pits in order to restore the natural 20070H1589B1970 - 15 -
1 stream flow to the Great Trough Creek 2,000,000 2 (Base Project Allocation - $2,000,000) 3 (v) Indiana County 4 (A) Construct active acid mine drainage 5 facility near the abandoned Wehrum 6 shaft to treat discharges from two 7 abandoned mine complexes discharging to 8 Blacklick Creek 6,000,000 9 (Base Project Allocation - $6,000,000) 10 (vi) Luzerne County 11 (A) Additional funds for DGS Project 184- 12 23, flood control project on Mill 13 Creek, Avoca Borough 1,200,000 14 (Base Project Allocation - $1,000,000) 15 (Design and Contingencies - $200,000) 16 (7) Department of General Services 17 (i) Dauphin County 18 (A) Provide for steam plant replacements 19 and upgrades in Capitol Annex 1,563,000 20 (Base Project Allocation - $1,250,000) 21 (Design and Contingencies - $313,000) 22 (B) Provide for remediation of mold, 23 asbestos and other hazmat in buildings 24 and equipment areas in Capitol Annex 5,625,000 25 (Base Project Allocation - $4,500,000) 26 (Design and Contingencies - $1,125,000) 27 (C) Upgrade building heating system and 28 install new air conditioning system in 29 Capitol Annex 3,750,000 30 (Base Project Allocation - $3,000,000) 20070H1589B1970 - 16 -
1 (Design and Contingencies - $750,000) 2 (D) Replace main Capitol Complex 3 Substation switchgears including 4 control status board along with 5 transformers and circuit breakers 25,000,000 6 (Base Project Allocation - $20,000,000) 7 (Design and Contingencies - $5,000,000) 8 (E) Replace existing 15kv distribution 9 feeders throughout the Capitol Complex 10 and reset the system primary and 11 secondary circuit breakers for proper 12 overall system coordination 10,625,000 13 (Base Project Allocation - $8,500,000) 14 (Design and Contingencies - $2,125,000) 15 (F) Refurbish Capital Park by providing 16 for a new retaining wall along Walnut 17 Street including new grading and 18 installation of a water conduction 19 system 1,000,000 20 (Base Project Allocation - $750,000) 21 (Design and Contingencies - $250,000) 22 (G) Replace all cloth ceilings in halls of 23 the Capitol East Wing 1,000,000 24 (Base Project Allocation - $750,000) 25 (Design and Contingencies - $250,000) 26 (H) Replace existing macadam with new 27 covering and sealant to prevent water 28 leakage and replace drains and piping 29 at the parking facility at 22nd and 30 Forster Streets, Harrisburg 1,100,000 20070H1589B1970 - 17 -
1 (Base Project Allocation - $880,000) 2 (Design and Contingencies - $220,000) 3 (I) Repair the roof membrane and replace 4 broken pavers at the Rachel Carson 5 State Office Building 750,000 6 (Base Project Allocation - $600,000) 7 (Design and Contingencies - $150,000) 8 (8) Pennsylvania Historical and Museum Commission 9 (i) Daniel Boone Homestead 10 (A) Provide for site improvements and 11 restore the boyhood home of Daniel 12 Boone 960,000 13 (Base Project Allocation - $800,000) 14 (Design and Contingencies - $160,000) 15 (ii) Landis Valley Museum 16 (A) Provide for the design and 17 construction of a new maintenance 18 building 960,000 19 (Base Project Allocation - $800,000) 20 (Design and Contingencies - $160,000) 21 (iii) Pennsbury Manor 22 (A) Rehabilitate up to 23 buildings and 23 site development of infrastructure 24 throughout the site 1,920,000 25 (Base Project Allocation - $1,600,000) 26 (Design and Contingencies - $320,000) 27 (iv) Pennsylvania Lumber Museum 28 (A) Reconfigure entrance to the building 29 to permit one coordinated exhibit 30 gallery rather than two disjointed 20070H1589B1970 - 18 -
1 galleries 2,400,000 2 (Base Project Allocation - $2,000,000) 3 (Design and Contingencies - $400,000) 4 (9) Department of Military and Veterans Affairs 5 (i) Pittsburgh Hunt Readiness Center, 6 Allegheny County 7 (A) Rehabilitate readiness center 8 including assembly hall, classrooms, 9 administrative offices, storage spaces, 10 restrooms, locker rooms and mechanical 11 rooms 3,000,000 12 (Base Project Allocation - $2,400,000) 13 (Design and Contingencies - $600,000) 14 (ii) Southwestern Veterans Center, Allegheny 15 County 16 (A) Replace sewer main 331,000 17 (Base Project Allocation - $248,000) 18 (Design and Contingencies - $83,000) 19 (iii) Hollidaysburg Veterans Home, Blair 20 County 21 (A) Rehabilitate fire alarm and sprinkler 22 systems in Arnold, Dietary, Eisenhower 23 and MacArthur Halls to meet life safety 24 compliance 2,722,000 25 (Base Project Allocation - $2,268,000) 26 (Design and Contingencies - $454,000) 27 (iv) Harrisburg Military Post, Dauphin County 28 (A) Rehabilitate various buildings and 29 facilities on the military post 30 including assembly halls, classrooms, 20070H1589B1970 - 19 -
1 administrative offices, storage spaces, 2 restrooms, locker rooms, mechanical 3 rooms and expanded parking 6,000,000 4 (Base Project Allocation - $4,800,000) 5 (Design and Contingencies - $1,200,000) 6 (v) Wilkes-Barre Readiness Center, Luzerne 7 County 8 (A) Rehabilitate readiness center 9 including assembly hall, classrooms, 10 administrative offices, storage spaces, 11 restrooms, locker rooms, mechanical 12 rooms and rehabilitation and expansion 13 of parking 4,000,000 14 (Base Project Allocation - $3,200,000) 15 (Design and Contingencies - $800,000) 16 (vi) Southeastern Veterans Center, Montgomery 17 County 18 (A) Rehabilitate fire alarm and sprinkler 19 systems to meet life safety compliance 1,276,000 20 (Base Project Allocation - $1,063,000) 21 (Design and Contingencies - $213,000) 22 (vii) Philadelphia Lancaster Avenue Readiness 23 Center, Philadelphia County 24 (A) Rehabilitate readiness center to 25 include assembly hall, classrooms, 26 administrative offices, storage spaces, 27 restrooms, locker rooms and mechanical 28 rooms 6,000,000 29 (Base Project Allocation - $5,000,000) 30 (Design and Contingencies - $1,000,000) 20070H1589B1970 - 20 -
1 (viii) Philadelphia Southampton Road Armory, 2 Philadelphia County 3 (A) Replace several air handling units and 4 associated pumps and motors and install 5 new chiller with ice storage capacity 6 to be made at night that will 7 distribute cooling during the day 1,500,000 8 (Base Project Allocation - $1,300,000) 9 (Design and Contingencies - $200,000) 10 (10) Department of Public Welfare 11 (i) Allentown State Hospital 12 (A) Upgrade three coal boilers currently 13 in poor condition and replace traveling 14 grate stokers and controls 3,600,000 15 (Base Project Allocation - $3,000,000) 16 (Design and Contingencies - $600,000) 17 (ii) Clarks Summit State Hospital 18 (A) Replace the electrical distribution 19 center at the sewage treatment plant 20 and install new 400 amp service, motor 21 control center, new transformer and new 22 back-up supply 1,200,000 23 (Base Project Allocation - $1,000,000) 24 (Design and Contingencies - $200,000) 25 (iii) Ebensburg Center 26 (A) Replace all roofed areas which cover 27 residential housing units 1,440,000 28 (Base Project Allocation - $1,200,000) 29 (Design and Contingencies - $240,000) 30 (B) Replace current emergency generators 20070H1589B1970 - 21 -
1 with stand alone outside units in all 2 seven residential units 1,500,000 3 (Base Project Allocation - $1,250,000) 4 (Design and Contingencies - $250,000) 5 (iv) Loysville Youth Development Center 6 (A) Construct a modular multipurpose 7 gym/kitchen/classroom building 3,000,000 8 (Base Project Allocation - $2,500,000) 9 (Design and Contingencies - $500,000) 10 (v) Loysville Complex, South Mountain Secure 11 Treatment Unit 12 (A) Construct a modular multipurpose 13 gym/kitchen/classroom building 3,000,000 14 (Base Project Allocation - $2,500,000) 15 (Design and Contingencies - $500,000) 16 (vi) Mayview State Hospital 17 (A) Upgrade the primary electrical system 18 including all central feeder circuits 3,000,000 19 (Base Project Allocation - $2,500,000) 20 (Design and Contingencies - $500,000) 21 (vii) Norristown State Hospital 22 (A) Renovate the boiler plant for building 23 60, Phase 3 of DGS project 509-29, 24 reconstruction or replacement of 25 boilers to meet emissions requirements 26 and upgrade the steam distribution 27 system 1,800,000 28 (Base Project Allocation - $1,500,000) 29 (Design and Contingencies - $300,000) 30 (viii) Polk Center 20070H1589B1970 - 22 -
1 (A) Replace valves, backwash pump and 2 replenish filters with new media in 3 order to keep water plant in compliance 4 with regulations 1,400,000 5 (Base Project Allocation - $1,120,000) 6 (Design and Contingencies - $280,000) 7 (ix) Selinsgrove Center 8 (A) Upgrade the boiler controls for the 9 facility 600,000 10 (Base Project Allocation - $500,000) 11 (Design and Contingencies - $100,000) 12 (B) Purchase and install package boiler 13 for more efficient handling of summer 14 steam load 960,000 15 (Base Project Allocation - $800,000) 16 (Design and Contingencies - $160,000) 17 (x) South Mountain Restoration Center 18 (A) Purchase and install package boiler 19 for more efficient handling of summer 20 steam load 840,000 21 (Base Project Allocation - $700,000) 22 (Design and Contingencies - $140,000) 23 (xi) Torrance State Hospital 24 (A) Bore two horizontal wells into a 25 mountainside to expand and improve 26 freshwater collection 720,000 27 (Base Project Allocation - $600,000) 28 (Design and Contingencies - $120,000) 29 (xii) Wernersville State Hospital 30 (A) Upgrade coal boiler refractory and 20070H1589B1970 - 23 -
1 structural components 360,000 2 (Base Project Allocation - $300,000) 3 (Design and Contingencies - $60,000) 4 (xiii) White Haven Center 5 (A) Replace the heating systems in 6 residential buildings from existing old 7 radiant heat to more modern, digitally- 8 controlled, high-efficiency HVAC 9 systems 2,400,000 10 (Base Project Allocation - $2,000,000) 11 (Design and Contingencies - $400,000) 12 (11) Pennsylvania State Police 13 (i) Dunmore Headquarters, Lackawanna County 14 (A) Construct a new headquarters facility, 15 garage and hangar to replace existing 16 facilities in Lackawanna County 10,800,000 17 (Base Project Allocation - $9,000,000) 18 (Design and Contingencies - $1,800,000) 19 (12) State System of Higher Education 20 (i) Bloomsburg University of Pennsylvania 21 (A) Additional funding for the renovation 22 of the Nelson Field House while 23 providing additional athletic and 24 office space 1,000,000 25 (ii) Cheyney University of Pennsylvania 26 (A) Additional funding to replace Browne 27 Hall including upgrading infrastructure 28 according to modern codes and fire 29 safety code requirements 1,000,000 30 (iii) East Stroudsburg University of 20070H1589B1970 - 24 -
1 Pennsylvania 2 (A) Additional funding for the replacement 3 of Rosenkrans Hall, providing 4 additional classroom, laboratory and 5 office space 8,000,000 6 (iv) Edinboro University of Pennsylvania 7 (A) Renovate or replace Ross Hall 8 including infrastructure and exterior 9 surfaces 10,000,000 10 (13) Department of Transportation 11 (i) Clearfield County 12 (A) Replace or rehabilitate District 2-0 13 Office including an addition on current 14 site and infrastructure improvements 12,000,000 15 (Base Project Allocation - $10,000,000) 16 (Design and Contingencies - $2,000,000) 17 (ii) Dauphin County 18 (A) Construct or acquire a new county 19 maintenance facility including salt and 20 equipment storage buildings and site 21 development 13,800,000 22 (Base Project Allocation - $11,000,000) 23 (Land Allocation - $1,000,000) 24 (Design and Contingencies - $1,800,000) 25 (B) Construct or acquire a new PennDOT 26 driver and motor vehicle central 27 office/service center including design, 28 site acquisition and construction 58,000,000 29 (Base Project Allocation - $50,000,000) 30 (Land Allocation - $3,000,000) 20070H1589B1970 - 25 -
1 (Design and Contingencies - $5,000,000) 2 (iii) Mifflin County 3 (A) Construct or acquire a new county 4 maintenance facility including salt and 5 equipment storage buildings and site 6 development 13,800,000 7 (Base Project Allocation - $11,000,000) 8 (Land Allocation - $1,000,000) 9 (Design and Contingencies - $1,800,000) 10 (iv) Wyoming County 11 (A) Construct or acquire a new county 12 maintenance facility including salt and 13 equipment storage buildings and site 14 development 13,800,000 15 (Base Project Allocation - $11,000,000) 16 (Land Allocation - $1,000,000) 17 (Design and Contingencies - $1,800,000) 18 Section 4. Itemization of furniture and equipment projects. 19 Additional capital projects in the category of public 20 improvement projects consisting of the acquisition of movable 21 furniture and equipment to complete public improvement projects 22 and to be purchased by the Department of General Services, its 23 successors or assigns and to be financed by the incurring of 24 debt are hereby itemized, together with their respective 25 estimated financial costs, as follows: 26 Total 27 Project 28 Project Allocation 29 (1) Office of Administration 30 (i) Statewide mobile radio and microwave 20070H1589B1970 - 26 -
1 system 2 (A) Additional funds for original 3 furniture and equipment to make the 4 Statewide radio and microwave system 5 DGS project 950-10 operational 21,000,000 6 (2) Department of Conservation and Natural 7 Resources 8 (i) Benjamin Rush State Park 9 (A) Original furniture and equipment for 10 current capital projects 217,000 11 (ii) Cook Forest State Park 12 (A) Original furniture and equipment for 13 current capital projects 114,000 14 (iii) Delaware Canal State Park 15 (A) Original furniture and equipment for 16 current capital projects 200,000 17 (iv) Kinzua Bridge State Park 18 (A) Original furniture and equipment for 19 current capital projects 3,000,000 20 (v) Nescopeck State Park 21 (A) Original furniture and equipment for 22 current capital projects 150,000 23 (vi) Pine Grove Furnace State Park 24 (A) Original furniture and equipment for 25 current capital projects 200,000 26 (vii) Presque Isle State Park 27 (A) Original furniture and equipment for 28 current capital projects 400,000 29 (viii) Sinnemahoning State Park 30 (A) Original furniture and equipment for 20070H1589B1970 - 27 -
1 current capital projects 2,000,000 2 (3) Department of Corrections 3 (i) State Correctional Institution at Dallas 4 (A) Original furniture and equipment for 5 the new institution 6,500,000 6 (ii) State Correctional Institution at 7 Huntingdon 8 (A) Original furniture and equipment for 9 the new institution 6,500,000 10 (iii) State Correctional Institution at 11 Rockview 12 (A) Original furniture and equipment for 13 the new institution 6,500,000 14 (4) Department of Education 15 (i) Scranton School for the Deaf 16 (A) Movable furniture and equipment to 17 allow modernization of classrooms and 18 other buildings to meet current 19 standards 2,625,000 20 (ii) Lincoln University 21 (A) Movable furniture and equipment to 22 allow construction project at Wright 23 Hall to become operational 3,000,000 24 (B) Movable furniture and equipment at 25 Langston Hughes Library for use for the 26 completely renovated facility 4,000,000 27 (5) Pennsylvania Historical and Museum Commission 28 (i) Eckley Miners' Village 29 (A) Replacement of original furniture and 30 equipment associated with the visiting 20070H1589B1970 - 28 -
1 public 1,920,000 2 (ii) Graeme Park 3 (A) Original furniture and equipment 4 associated with the new orientation 5 exhibit 720,000 6 (iii) Landis Valley Museum 7 (A) Construct new museum exhibits for the 8 expanded visitors' center building and 9 other buildings 1,800,000 10 (iv) State Records Center 11 (A) Original furniture and equipment 12 including a mobile high density storage 13 system 1,800,000 14 (6) State System of Higher Education 15 (i) Kutztown University of Pennsylvania 16 (A) Supplemental funding for the purchase 17 of movable furniture and equipment to 18 allow Schaffer Auditorium construction 19 project to become operational 500,000 20 (ii) Millersville University of Pennsylvania 21 (A) Supplemental funding for the purchase 22 of movable furniture and equipment to 23 allow Theatre Arts Education Building 24 construction project to become 25 operational 200,000 26 (iii) Shippensburg University of Pennsylvania 27 (A) Supplemental funding for the purchase 28 of movable furniture and equipment to 29 allow Huber Arts Center construction 30 project to become operational 500,000 20070H1589B1970 - 29 -
1 (iv) Slippery Rock University of Pennsylvania 2 (A) Supplemental funding for the purchase 3 of movable furniture and equipment to 4 allow Performing Arts Center 5 construction project to become 6 operational 1,000,000 7 Section 5. Itemization of transportation assistance projects. 8 (a) Mass transit.--Additional capital projects in the 9 category of transportation assistance projects for mass transit 10 in which an interest is to be acquired or constructed by the 11 Department of Transportation, its successors or assigns and to 12 be financed by the incurring of debt are hereby itemized, 13 together with their estimated financial costs, as follows: 14 Total 15 Project 16 Project Allocation 17 (1) Beaver County Transit Authority 18 (i) Provide for improvements in bus 19 circulation, passenger waiting and terminal 20 areas at the Rochester Transportation 21 Center (RTC), pedestrian improvements with 22 the Transit Revitalization Investment 23 District (TRID) area and from the RTC to 24 the Rochester riverfront development and 25 signal preemption/prioritization request 26 system in the TRID area 317,000 27 (Base Project Allocation - $285,000) 28 (Design and Contingencies - $32,000) 29 (2) Berks Area Reading Transit Authority 30 (i) Purchase and install an Auto Vehicle 20070H1589B1970 - 30 -
1 Locator System for both fixed route and 2 paratransit systems 167,000 3 (Base Project Allocation - $150,000) 4 (Design and Contingencies -$17,000) 5 (3) Cambria County Transit Authority 6 (i) Replace bus wash system, upgrade 7 communication system and purchase security 8 surveillance system 100,000 9 (Base Project Allocation - $90,000) 10 (Design and Contingencies - $10,000) 11 (ii) Construct rural transfer center to 12 increase service efficiency, attract new 13 riders and provide easier transfers for 14 riders 100,000 15 (Base Project Allocation - $90,000) 16 (Design and Contingencies - $10,000) 17 (4) Capital Area Transit 18 (i) Improve and renovate CAT's maintenance 19 building to include three bays to repair 20 and service 40-foot low floor buses 233,000 21 (Base Project Allocation - $210,000) 22 (Design and Contingencies - $23,000) 23 (5) Centre Area Transportation Authority 24 (i) Purchase 16 buses to replace buses which 25 have met their useful life 167,000 26 (Base Project Allocation - $150,000) 27 (Design and Contingencies - $17,000) 28 (ii) Purchase automatic vehicle locator system 29 with the first phase to equip buses and 30 service vehicles with such items as the 20070H1589B1970 - 31 -
1 automatic enunciators, electronic 2 performance monitoring, stop-by-stop 3 passenger counts, real time passenger 4 information via the Internet and at major 5 stops 156,000 6 (Base Project Allocation - $140,000) 7 (Design and Contingencies - $16,000) 8 (6) Crawford Area Transportation Authority 9 (i) Construct administrative intermodal center 10 in downtown Meadville and purchase bus 11 related equipment 333,000 12 (Base Project Allocation - $300,000) 13 (Design and Contingencies - $33,000) 14 (7) Erie Metropolitan Transit Authority 15 (i) Acquire five buses to replace five 16 existing buses which have exceeded their 17 useful life 379,000 18 (Base Project Allocation - $341,000) 19 (Design and Contingencies - $38,000) 20 (ii) Renovate administration/maintenance 21 facility and purchase shop and 22 miscellaneous equipment 39,000 23 (Base Project Allocation - $35,000) 24 (Design and Contingencies - $4,000) 25 (iii) Purchase technology upgrades to radio 26 and fare box systems and complete system 27 wide signage 33,000 28 (Base Project Allocation - $30,000) 29 (Design and Contingencies - $3,000) 30 (8) Red Rose Transit Authority 20070H1589B1970 - 32 -
1 (i) Replace bus washer and renovation and 2 expand bus storage building 375,000 3 (Base Project Allocation - $337,000) 4 (Design and Contingencies - $38,000) 5 (ii) Design and construct new station on 6 AMTRAK Harrisburg to Philadelphia line in 7 Paradise Township, Lancaster County 200,000 8 (Base Project Allocation - $180,000) 9 (Design and Contingencies - $20,000) 10 (9) Shenango Valley Shuttle Service 11 (i) Construct a maintenance facility including 12 equipment and land acquisition 250,000 13 (Base Project Allocation - $225,000) 14 (Design and Contingencies - $25,000) 15 (10) Southeastern Pennsylvania Transportation 16 Authority 17 (i) Provide for the rehabilitation of 18 improvements at Croyden and Levittown 19 Stations located in Bucks County with 20 improvements to include the installation of 21 bus shelters and transit signage, station 22 improvements, bus access improvements at 23 both stations and parking expansion 3,500,000 24 (Base Project Allocation - $3,150,000) 25 (Design and Contingencies - $350,000) 26 (ii) Provide for the rehabilitation of 27 improvements to bus and rail intermodal 28 connections at the Glenside and Jenkintown 29 Stations in Montgomery County with 30 improvements to include design and 20070H1589B1970 - 33 -
1 construction of a multilevel 384 space 2 parking garage at Glenside Station and a 3 multilevel 700 space parking garage at 4 Jenkintown Station 6,700,000 5 (Base Project Allocation - $6,030,000) 6 (Design and Contingencies - $670,000) 7 (iii) FFY 2008 Transit Enhancement Program, 8 provide for renovation and preservation of 9 historic train stations and related 10 activities including bus shelters, 11 landscaping, street lights, pedestrian 12 access and walkways, bicycle access, 13 signage and enhanced access to transit for 14 persons with disabilities 670,000 15 (Base Project Allocation - $603,000) 16 (Design and Contingencies - $67,000) 17 (iv) Provide for construction of a multilevel 18 parking structure and pedestrian overpass 19 over AMTRAK tracks, to connect the west 20 side of the campus of Villanova to the main 21 campus, with parking for approximately 22 1,000 vehicles and be handicapped 23 accessible 625,000 24 (Base Project Allocation - $562,000) 25 (Design and Contingencies - $63,000) 26 (v) FFY 2002 Section 5309 Transit Enhancement 27 Program, provide additional funding for the 28 acquisition of 104 new rail cars for SEPTA 29 Regional Rail service 2,000,000 30 (Base Project Allocation - $1,800,000) 20070H1589B1970 - 34 -
1 (Design and Contingencies - $200,000) 2 (11) Union and Snyder Transit Authority 3 (i) Construct maintenance facility including 4 equipment and land acquisition 304,000 5 (Base Project Allocation - $273,000) 6 (Design and Contingencies - $31,000) 7 (12) Department of Transportation 8 (i) Provide for rail passenger improvements 9 across this Commonwealth including matching 10 funds for the Keystone Corridor Federal 11 funding 15,000,000 12 (Base Project Allocation - $13,500,000) 13 (Design and Contingencies - $1,500,000) 14 (ii) Provide for Intercity Bus Capital 15 Assistance Intermodal Projects and ADA 16 related facilities/equipment improvements 2,000,000 17 (Base Project Allocation - $1,800,000) 18 (Design and Contingencies - $200,000) 19 (b) Rural and intercity rail.--Additional capital projects 20 in the category of transportation assistance projects for rural 21 and intercity rail service projects to be constructed or with 22 respect to which an interest is to be acquired by the Department 23 of Transportation, its successors or assigns and to be financed 24 by the incurring of debt are hereby itemized, together with 25 their respective estimated financial costs, as follows: 26 Total 27 Project 28 Project Allocation 29 (1) Buffalo and Pittsburgh Railroad 30 (i) Rehabilitate mainline track in Armstrong, 20070H1589B1970 - 35 -
1 Clearfield, Indiana and Jefferson Counties, 2 from Kittanning to Dubois and Punxsutawney 3 to Homer City with work to include tie and 4 rail replacement, surfacing, bridge repair, 5 switch, road crossing, signal, 6 communication and any other related work 5,000,000 7 (2) Lehigh Valley Rail Management 8 (i) Construct access and storage tanks and 9 rehabilitate track within and around the 10 Bethlehem Commerce Center 3,500,000 11 (c) Air transportation.--Additional capital projects in the 12 category of transportation assistance projects for air 13 transportation service to which an interest is to be acquired by 14 the Department of Transportation, its successors or assigns and 15 to be financed by the incurring of debt are hereby itemized, 16 together with their respective estimated financial costs, as 17 follows: 18 Total 19 Project 20 Project Allocation 21 (1) Lehigh County 22 (i) Lehigh Valley International Airport 23 (A) Provide for the economic development 24 and safety enhancement at the airport 5,000,000 25 (Base Project Allocation - $4,500,000) 26 (Design and Contingencies - $500,000) 27 Section 6. Itemization of redevelopment assistance capital 28 projects. 29 (Reserved) 30 Section 7. Itemization of flood control projects. 20070H1589B1970 - 36 -
1 Additional capital projects in the category of flood control 2 projects to be constructed by the Department of Environmental 3 Protection, its successors or assigns, and to be financed by the 4 incurring of debt are hereby itemized, together with their 5 respective estimated costs, as follows: 6 Total 7 Project 8 Project Allocation 9 (1) Department of Environmental Protection 10 (i) Crawford County 11 (A) Conneautville Dam rehabilitation 750,000 12 (ii) Monroe County 13 (A) Additional funds to refurbish Brady's 14 Lake Dam in order to rebid the project 15 due to delays and poor performance in 16 concrete mix design 3,600,000 17 Section 8. Itemization of Keystone Recreation, Park and 18 Conservation Fund projects. 19 Projects in the category of public improvement projects to be 20 constructed by the Department of Conservation and Natural 21 Resources, its successors or assigns, and to be financed by 22 current revenues of the Keystone Recreation, Park and 23 Conservation Fund are hereby itemized, together with their 24 respective estimated costs, as follows: 25 Total 26 Project 27 Project Allocation 28 (1) Department of Conservation and Natural 29 Resources 30 (i) Black Moshannon State Park 20070H1589B1970 - 37 -
1 (A) Rehabilitate dam spillway and boat 2 launch 400,000 3 (Base Project Allocation - $400,000) 4 (ii) Blue Knob State Park 5 (A) Rehabilitate park facilities 900,000 6 (Base Project Allocation - $900,000) 7 (B) Rehabilitate day use area 1,000,000 8 (Base Project Allocation - $1,000,000) 9 (iii) Caledonia State Park 10 (A) Replace two bridges on main park road 600,000 11 (Base Project Allocation - $600,000) 12 (B) Rehabilitate park campgrounds 1,100,000 13 (Base Project Allocation - $1,100,000) 14 (iv) Codorus State Park 15 (A) Provide paving in park 350,000 16 (Base Project Allocation - $350,000) 17 (v) Denton Hill State Park 18 (A) Replace main park road/parking area 400,000 19 (Base Project Allocation - $400,000) 20 (vi) Forest District 19 21 (A) Rehabilitate Egypt Meadows Dam 750,000 22 (Base Project Allocation - $750,000) 23 (vii) Forest District 20 24 (A) Provide new resource management 25 center 4,000,000 26 (Base Project Allocation - $4,000,000) 27 (viii) Little Pine State Park 28 (A) Renovate restroom and lower picnic 29 area 300,000 30 (Base Project Allocation - $300,000) 20070H1589B1970 - 38 -
1 (ix) Moshannon State Forest 2 (A) Provide cleanup to Quehanna reactor 3 site 2,400,000 4 (Base Project Allocation - $2,400,000) 5 (x) Prince Gallitzin State Park 6 (A) Replace two restrooms at the park 300,000 7 (Base Project Allocation - $300,000) 8 (B) Pave roads within the park 350,000 9 (Base Project Allocation - $350,000) 10 (xi) Reeds Gap State Park 11 (A) Relocate park office building 1,500,000 12 (Base Project Allocation - $1,500,000) 13 (B) Replace existing swimming pool 1,000,000 14 (Base Project Allocation - $1,000,000) 15 (xii) S.B. Elliott State Park 16 (A) Provide ADA cabins and renovate 17 washhouse 1,250,000 18 (Base Project Allocation - $1,250,000) 19 (xiii) Shawnee State Park 20 (A) Repair joints in concrete spillway 300,000 21 (Base Project Allocation - $300,000) 22 (xiv) Shikellamy State Park 23 (A) Project (PW 4182) to provide dock 24 rehabilitation transient and launch 25 areas 663,000 26 (Base Project Allocation - $663,000) 27 (B) Renovate overlook road in the park 400,000 28 (Base Project Allocation - $400,000) 29 (xv) Sinnemahoning State Park 30 (A) Repair dam spillway 650,000 20070H1589B1970 - 39 -
1 (Base Project Allocation - $650,000) 2 (xvi) Various Parks and Forest Districts, 3 Statewide 4 (A) Acquire land to be incorporated within 5 the park system according to the 6 Commonwealth's master plan 10,000,000 7 (Land Allocation - $10,000,000) 8 Section 9. Itemization of Environmental Stewardship Fund 9 projects. 10 Projects in the category of public improvement projects to be 11 constructed by the Department of Conservation and Natural 12 Resources, its successors or assigns and to be financed by 13 current revenues of the Environmental Stewardship Fund are 14 hereby itemized together with their respective estimated 15 financial costs as follows: 16 Total 17 Project 18 Project Allocation 19 (1) Department of Conservation and Natural 20 Resources 21 (i) Bald Eagle State Park 22 (A) Rehabilitate roads within the park 1,600,000 23 (Base Project Allocation - $1,600,000) 24 (B) Replace courtesy docks at eight public 25 boat launches 300,000 26 (Base Project Allocation - $300,000) 27 (C) Rehabilitate office and visitors' 28 center 1,750,000 29 (Base Project Allocation - $1,750,000) 30 (ii) Beltzville State Park 20070H1589B1970 - 40 -
1 (A) Rehabilitate sewage treatment plant 2 and correct sewer line infiltration 400,000 3 (Base Project Allocation - $400,000) 4 (iii) Bendigo State Park 5 (A) Replace bathhouse, lifeguard station 6 and day use restrooms in the park 1,000,000 7 (Base Project Allocation - $1,000,000) 8 (iv) Canoe Creek State Park 9 (A) Rehabilitate sewage treatment plant 300,000 10 (Base Project Allocation - $300,000) 11 (v) Chapman State Park 12 (A) Rehabilitate beach house and comfort 13 station 1,900,000 14 (Base Project Allocation - $1,900,000) 15 (vi) Cherry Springs State Park 16 (A) Replace pit latrines with flush 17 restrooms and sewers 770,000 18 (Base Project Allocation - $770,000) 19 (vii) Clear Creek State Park 20 (A) Rehabilitate water system and replace 21 pit latrines 2,000,000 22 (Base Project Allocation - $2,000,000) 23 (B) Rehabilitate park roads and bridges 1,500,000 24 (Base Project Allocation - $1,500,000) 25 (viii) Colonel Denning State Park 26 (A) Provide new day restroom, sewage and 27 shower house 350,000 28 (Base Project Allocation - $350,000) 29 (B) Provide bathhouse, concession, 30 restroom and sewage 500,000 20070H1589B1970 - 41 -
1 (Base Project Allocation - $500,000) 2 (ix) Cook Forest State Park 3 (A) Rehabilitation of trail, Phase II 250,000 4 (Base Project Allocation - $250,000) 5 (B) Rehabilitate five campground 6 washhouses 600,000 7 (Base Project Allocation - $600,000) 8 (C) Replace park office and visitors' 9 center 2,000,000 10 (Base Project Allocation - $2,000,000) 11 (D) Replace six river cabins 2,200,000 12 (Base Project Allocation - $2,200,000) 13 (E) Rehabilitate sewage system and 14 repairs 750,000 15 (Base Project Allocation - $750,000) 16 (F) Provide repairs to the water system 750,000 17 (Base Project Allocation - $750,000) 18 (G) Rehabilitate road and parking lot 1,100,000 19 (Base Project Allocation - $1,100,000) 20 (x) Colton Point State Park 21 (A) Replace two pit latrines with 22 composting restroom, playground, picnic 23 area and campground shower house 1,500,000 24 (Base Project Allocation - $1,500,000) 25 (xi) Elk State Park 26 (A) Replace comfort station 150,000 27 (Base Project Allocation - $150,000) 28 (xii) Erie Bluffs State Park 29 (A) Construct entrance to the park 300,000 30 (Base Project Allocation - $300,000) 20070H1589B1970 - 42 -
1 (xiii) Evansburg State Park 2 (A) Provide road paving for the park 335,000 3 (Base Project Allocation - $335,000) 4 (B) Replace sewer lines 250,000 5 (Base Project Allocation - $250,000) 6 (C) Replace temporary restrooms, Phase II 250,000 7 (Base Project Allocation - $250,000) 8 (xiv) Forest District 2 9 (A) Construct new resource management 10 center 3,500,000 11 (Base Project Allocation - $3,500,000) 12 (xv) Forest District 3 13 (A) Establish new maintenance headquarter 14 buildings in Juniata, Mifflin and Perry 15 Counties 800,000 16 (Base Project Allocation - $800,000) 17 (B) Rehabilitate Gunter Valley Dam in 18 Perry County 5,000,000 19 (Base Project Allocation - $5,000,000) 20 (xvi) Forest District 4 21 (A) Rehabilitate Linn Run Road 2,500,000 22 (Base Project Allocation - $2,500,000) 23 (xvii) Forest District 5 24 (A) Rehabilitate resource management 25 center 1,500,000 26 (Base Project Allocation - $1,500,000) 27 (xviii) Forest District 8 28 (A) Rehabilitate Kittanning Resource 29 Management Center 1,500,000 30 (Base Project Allocation - $1,500,000) 20070H1589B1970 - 43 -
1 (xix) Forest District 14 2 (A) Rehabilitate historic stone house 250,000 3 (Base Project Allocation - $250,000) 4 (xx) Forest District 18 5 (A) SR 54 comfort station and parking 500,000 6 (Base Project Allocation - $500,000) 7 (B) New resource management center 3,500,000 8 (Base Project Allocation - $3,500,000) 9 (C) Rehabilitate Roaring Creek tract 10 facilities 600,000 11 (Base Project Allocation - $600,000) 12 (D) Rehabilitate Roaring Creek tract 13 trails and bridges 1,155,000 14 (Base Project Allocation - $1,155,000) 15 (E) Maintenance to Haldeman complex 300,000 16 (Base Project Allocation - $300,000) 17 (xxi) Forest District 19 18 (A) New resource management center 3,500,000 19 (Base Project Allocation - $3,500,000) 20 (B) Rehabilitate Little Summit Fire 21 Station maintenance complex 300,000 22 (Base Project Allocation - $300,000) 23 (C) Project for Pine Flats Road 200,000 24 (Base Project Allocation - $200,000) 25 (D) Project for Flat Ridge Road 200,000 26 (Base Project Allocation - $200,000) 27 (xxii) Forest District 20 28 (A) Pave Dry Run Road 300,000 29 (Base Project Allocation - $300,000) 30 (B) Provide for Hillsgrove storage 20070H1589B1970 - 44 -
1 building 300,000 2 (Base Project Allocation - $300,000) 3 (C) Pave High Knob Road 500,000 4 (Base Project Allocation - $500,000) 5 (xxiii) Frances Slocum State Park 6 (A) Rehabilitate sewage treatment plant 7 and lines 600,000 8 (Base Project Allocation - $600,000) 9 (xxiv) French Creek State Park 10 (A) Rehabilitate Scotts Run area 1,500,000 11 (Base Project Allocation - $1,500,000) 12 (xxv) Gifford Pinchot State Park 13 (A) Phase II rehabilitation of camp area 14 washhouse 400,000 15 (Base Project Allocation - $400,000) 16 (xxvi) Gouldsboro State Park 17 (A) Repair dam at the park 750,000 18 (Base Project Allocation - $750,000) 19 (B) Replace pit bathhouse, comfort station 20 and boat rental 600,000 21 (Base Project Allocation - $600,000) 22 (xxvii) Greenwood Furnace State Park 23 (A) Make repairs to sewage treatment 24 plant 900,000 25 (Base Project Allocation - $900,000) 26 (xxviii) Hickory Run State Park 27 (A) Replace pit latrines and water tank 1,800,000 28 (Base Project Allocation - $1,800,000) 29 (B) Phase II of group camp roof 30 replacement 200,000 20070H1589B1970 - 45 -
1 (Base Project Allocation - $200,000) 2 (C) Replace office and visitors' center 2,000,000 3 (Base Project Allocation - $2,000,000) 4 (D) Replace pit toilets and four 5 buildings 1,250,000 6 (Base Project Allocation - $1,250,000) 7 (xxix) Hills Creek State Park 8 (A) Rehabilitate spillway 600,000 9 (Base Project Allocation - $600,000) 10 (B) Provide office renovation addition and 11 visitors' center 2,100,000 12 (Base Project Allocation - $2,100,000) 13 (xxx) Hyner Run State Park 14 (A) Rehabilitate two park bridges and pave 15 roadway 600,000 16 (Base Project Allocation - $600,000) 17 (B) Replace two day use restrooms 300,000 18 (Base Project Allocation - $300,000) 19 (xxxi) Kettle Creek State Park 20 (A) Provide bathhouse, shower house and 21 sewage 1,800,000 22 (Base Project Allocation - $1,800,000) 23 (xxxii) Kooser State Park 24 (A) Rehabilitate park roads and bridges 1,300,000 25 (Base Project Allocation - $1,300,000) 26 (xxxiii) Lackawanna State Park 27 (A) Replace park office 1,500,000 28 (Base Project Allocation - $1,500,000) 29 (B) Rehabilitate pool complex and day use 30 area 3,000,000 20070H1589B1970 - 46 -
1 (Base Project Allocation - $3,000,000) 2 (xxxiv) Laurel Hill State Park 3 (A) Breach Spruce Run Dam 250,000 4 (Base Project Allocation - $250,000) 5 (B) Provide Jones Mill Run Dam dredging 250,000 6 (Base Project Allocation - $250,000) 7 (C) Rehabilitate group camp three sewage 8 lines 250,000 9 (Base Project Allocation - $250,000) 10 (D) Provide camping cottage shower house 11 at the park 650,000 12 (Base Project Allocation - $650,000) 13 (E) Rehabilitate contact station and 14 parking 500,000 15 (Base Project Allocation - $500,000) 16 (xxxv) Laurel Ridge State Park 17 (A) Replace turnpike trail bridge 18 superstructure 1,200,000 19 (Base Project Allocation - $1,200,000) 20 (xxxvi) Little Pine State Park 21 (A) Rehabilitate dam 500,000 22 (Base Project Allocation - $500,000) 23 (xxxvii) Lyman Run State Park 24 (A) Provide construction to the spillway 25 bridge 500,000 26 (Base Project Allocation - $500,000) 27 (xxxviii) Marsh Creek State Park 28 (A) Pave all parking lots in the park 325,000 29 (Base Project Allocation - $325,000) 30 (B) Provide ADA office expansion 150,000 20070H1589B1970 - 47 -
1 (Base Project Allocation - $150,000) 2 (xxxix) McConnells Mill State Park 3 (A) Rehabilitate the park road 275,000 4 (Base Project Allocation - $275,000) 5 (xl) Moraine State Park 6 (A) Resurface bike trail in park 1,200,000 7 (Base Project Allocation - $1,200,000) 8 (B) Rehabilitate Old 422 launch and road 1,000,000 9 (Base Project Allocation - $1,000,000) 10 (xli) Neshaminy State Park 11 (A) Rehabilitate jetty 350,000 12 (Base Project Allocation - $350,000) 13 (xlii) Nockamixon State Park 14 (A) Provide paving in the park 500,000 15 (Base Project Allocation - $500,000) 16 (B) Replace three pit toilets 1,000,000 17 (Base Project Allocation - $1,000,000) 18 (xliii) Ohiopyle State Park 19 (A) Rehabilitate residence 250,000 20 (Base Project Allocation - $250,000) 21 (B) Replace bridge 0902-CSX 2288 300,000 22 (Base Project Allocation - $300,000) 23 (C) Construct parking above new office 900,000 24 (Base Project Allocation - $900,000) 25 (D) Provide park office accessibility 2,000,000 26 (Base Project Allocation - $2,000,000) 27 (E) Provide bathhouse, shower house and 28 sewage 275,000 29 (Base Project Allocation - $275,000) 30 (xliv) Oil Creek State Park 20070H1589B1970 - 48 -
1 (A) Rehabilitate Boughton Bridge 400,000 2 (Base Project Allocation - $400,000) 3 (B) Phase I to repair trail slips 300,000 4 (Base Project Allocation - $300,000) 5 (xlv) Parker Dam State Park 6 (A) Rehabilitate dam spillway 350,000 7 (Base Project Allocation - $350,000) 8 (xlvi) Park Region 1 9 (A) Rehabilitate surface water 10 systems/filter 300,000 11 (Base Project Allocation - $300,000) 12 (B) Rehabilitate surface and well water 13 supplies in Region 1 State parks 1,500,000 14 (Base Project Allocation - $1,500,000) 15 (xlvii) Park Region 2 16 (A) Rehabilitate the residence 250,000 17 (Base Project Allocation - $250,000) 18 (xlviii) Pine Grove Furnace State Park 19 (A) Rehabilitate water treatment plant 2,000,000 20 (Base Project Allocation - $2,000,000) 21 (B) Rehabilitate various buildings 3,400,000 22 (Base Project Allocation - $3,400,000) 23 (xlix) Presque Isle State Park 24 (A) Provide bike trail extension to the 25 Tom Ridge Environmental Center 1,800,000 26 (Base Project Allocation - $1,800,000) 27 (l) Prince Gallitzin State Park 28 (A) Rehabilitate sewage treatment plant 800,000 29 (Base Project Allocation - $800,000) 30 (B) Rehabilitate Beaver Valley Marina 2,900,000 20070H1589B1970 - 49 -
1 (Base Project Allocation - $2,900,000) 2 (li) Promised Land State Park 3 (A) Rehabilitate sewer line 750,000 4 (Base Project Allocation - $750,000) 5 (B) Replace bridge and spillway 3,100,000 6 (Base Project Allocation - $3,100,000) 7 (C) Rehabilitate Pickerel Point and 8 Deerfield campgrounds 3,000,000 9 (Base Project Allocation - $3,000,000) 10 (D) Rehabilitate boat rental area 500,000 11 (Base Project Allocation - $500,000) 12 (E) Rehabilitate dump station 300,000 13 (Base Project Allocation - $300,000) 14 (F) Rehabilitate bridges 120,000 15 (Base Project Allocation - $120,000) 16 (lii) Pymatuning State Park 17 (A) Rehabilitate Espyville south launch 18 and environs 1,500,000 19 (Base Project Allocation - $1,500,000) 20 (B) Rehabilitate Jamestown beach house 650,000 21 (Base Project Allocation - $650,000) 22 (C) Rehabilitate sanitary facilities on 23 the west side 2,200,000 24 (Base Project Allocation - $2,200,000) 25 (liii) Raccoon Creek State Park 26 (A) Provide roadway slip repairs 800,000 27 (Base Project Allocation - $800,000) 28 (B) Phase II rehabilitation of roads 300,000 29 (Base Project Allocation - $300,000) 30 (liv) Ralph Stover State Park 20070H1589B1970 - 50 -
1 (A) Replace pit latrines and sewer 500,000 2 (Base Project Allocation - $500,000) 3 (lv) Ricketts Glen State Park 4 (A) Rehabilitate bathhouse and comfort 5 stations 2,800,000 6 (Base Project Allocation - $2,800,000) 7 (B) Rehabilitate roads and provide paving 8 for parking lots 650,000 9 (Base Project Allocation - $650,000) 10 (C) Replace pit latrine Route 118 picnic 11 area 400,000 12 (Base Project Allocation - $400,000) 13 (D) Repair infiltration, sewage treatment 14 plant and water system 550,000 15 (Base Project Allocation - $550,000) 16 (lvi) Ridley Creek State Park 17 (A) Reroof maintenance building 400,000 18 (Base Project Allocation - $400,000) 19 (B) Pave parking lot 300,000 20 (Base Project Allocation - $300,000) 21 (lvii) Salt Springs State Park 22 (A) Replace vault latrine 300,000 23 (Base Project Allocation - $300,000) 24 (lviii) Samuel S. Lewis State Park 25 (A) Provide two new comfort stations with 26 on-lot sewage 750,000 27 (Base Project Allocation - $750,000) 28 (lix) Shawnee State Park 29 (A) Rehabilitate water treatment plant 1,200,000 30 (Base Project Allocation - $1,200,000) 20070H1589B1970 - 51 -
1 (lx) Sinnemahoning State Park 2 (A) Rehabilitate main park road and 3 replace bridges 1,000,000 4 (Base Project Allocation - $1,000,000) 5 (lxi) Sizerville State Park 6 (A) Modernize pit latrines and bathhouse 2,000,000 7 (Base Project Allocation - $2,000,000) 8 (B) Provide new park office and visitors' 9 center 1,800,000 10 (Base Project Allocation - $1,800,000) 11 (lxii) Tiadaghton State Forest 12 (A) Construct Tiadaghton Management 13 Center 4,500,000 14 (Base Project Allocation - $4,500,000) 15 (lxiii) Tobyhanna State Park 16 (A) Rehabilitate day use area and 17 campground 2,500,000 18 (Base Project Allocation - $2,500,000) 19 (lxiv) Whipple Dam State Park 20 (A) Provide new multifunction beach 21 building 1,200,000 22 (Base Project Allocation - $1,200,000) 23 (lxv) Yellow Creek State Park 24 (A) Provide camping cottage shower house 650,000 25 (Base Project Allocation - $650,000) 26 (lxvi) White Clay Creek Preserve 27 (A) Rebuild London Tract wall 150,000 28 (Base Project Allocation - $150,000) 29 (lxvii) Worlds End State Park 30 (A) Rehabilitate campground and day use 20070H1589B1970 - 52 -
1 area roads 350,000 2 (Base Project Allocation - $350,000) 3 (lxviii) Various parks, Statewide 4 (A) Acquire land to be incorporated within 5 the park system according to the 6 Commonwealth's master plan 10,000,000 7 (Land Allocation - $10,000,000) 8 Section 10. Itemization of State forestry bridge projects. 9 Projects in the category of State forestry bridge projects to 10 be constructed by the Department of Conservation and Natural 11 Resources, its successors or assigns, and to be financed by oil 12 company franchise tax revenues pursuant to 75 Pa.C.S. § 13 9502(a)(2)(iv) (relating to imposition of tax) are hereby 14 itemized, together with their respective estimated costs, as 15 follows: 16 Total 17 Project 18 Project Allocation 19 (1) Centre County 20 (i) Forest District 9 21 (A) Project for Meyers Run Road and Black 22 Moshannon Creek 400,000 23 (B) Project for North Run Road over Smays 24 Run 300,000 25 (2) Clearfield County 26 (i) Forest District 9 27 (A) Project for Shirks Road over Black 28 Moshannon Creek bridge No. 9-0028 300,000 29 (B) Project for Reservoir Road over Upper 30 Three Run 300,000 20070H1589B1970 - 53 -
1 (C) Project for Little Medix Road over 2 Little Medix Run, bridge No. 9-0012 300,000 3 (3) Clinton County 4 (i) Forest District 10 5 (A) Project for Beaver Dam Road over 6 Beaver Dam Run 300,000 7 (B) Project for Birch Island Road over 8 Amos Branch, bridge No. 10-0040 300,000 9 (4) Elk County 10 (i) Forest District 13 11 (A) Project for East Hicks Road over Barr 12 Hollow 300,000 13 (B) Project for Little Dents Road over 14 Dents Run Bridge No. 13-0032 300,000 15 (C) Project for Dents Run Road over Little 16 Bear Run 300,000 17 (D) Project for Dents Run Road over 18 Weatherboard Run 300,000 19 (E) Project for bridge over North Fork 300,000 20 (5) Huntingdon County 21 (i) Forest District 5 22 (A) Project for Krise Valley Road bridge 300,000 23 (6) Lycoming County 24 (i) Forest District 12 25 (A) Project for Trout Run Road and 26 bridges 600,000 27 (B) Project for Frances Road over unnamed 28 tributary near Black Forest Trail 300,000 29 (7) Perry County 30 (i) Forest District 3 20070H1589B1970 - 54 -
1 (A) Project for the Second Narrows Road 2 bridge 300,000 3 (8) Tioga County 4 (i) Forest District 12 5 (A) Project for Francis Road over unnamed 6 tributary at Pipeline Road 300,000 7 (B) Project for Francis Road over Woodward 8 Hollow 300,000 9 (C) Project for Francis Road over Randall 10 Hollow bridge No. 12-9003 300,000 11 (D) Project for Francis Road over Kramer 12 Hollow bridge No. 12-9016 300,000 13 (E) Project for Francis Road over Francis 14 Branch bridge No. 12-0048 300,000 15 (ii) Forest District 16 16 (A) Project for Spoor Hollow Road over 17 Norris Brook bridge No. 16-0001 300,000 18 (B) Project for Cedar Mountain Road over 19 Cedar Run bridge No. 16-0014 300,000 20 (9) Union County 21 (i) Forest District 7 22 (A) Replace Brandon Road bridge 300,000 23 (B) Project for Cooper Mill Road bridge 300,000 24 (10) Clearfield and Elk Counties 25 (i) Forest District 9 26 (A) Project for three culverts on Little 27 Medix Road over Little Medix Run 400,000 28 Section 11. Itemization of General Fund current revenue 29 projects. 30 The individual capital projects in the category of public 20070H1589B1970 - 55 -
1 improvement projects to be constructed or acquired by the 2 Department of General Services, its successors or assigns, and 3 to be financed from General Fund current revenues, are hereby 4 itemized, together with their respective estimated financial 5 costs, as follows: 6 Total 7 Project 8 Project Allocation 9 (1) Department of Corrections 10 (i) State Correctional Institution at Laurel 11 Highlands 12 (A) Lease and/or purchase an emergency 13 housing facility along with related 14 infrastructure improvements 2,500,000 15 (Base Project Allocation - $2,500,000) 16 (ii) State Correctional Institution at Pine 17 Grove 18 (A) Lease and/or purchase an emergency 19 housing facility along with related 20 infrastructure improvements 2,500,000 21 (Base Project Allocation - $2,500,000) 22 (iii) State Correctional Institution at 23 Retreat 24 (A) Lease and/or purchase an emergency 25 housing facility along with related 26 infrastructure improvements 2,500,000 27 (Base Project Allocation - $2,500,000) 28 (2) Pennsylvania Historical and Museum Commission 29 (i) Pennsylvania Military Museum 30 (A) Design and construct a 2,500-square- 20070H1589B1970 - 56 -
1 foot storage building for historical 2 military vehicles 600,000 3 (Base Project Allocation - $500,000) 4 (Design and Contingencies - $100,000) 5 Section 12. Debt authorization. 6 (a) Public improvements.--The Governor, Auditor General and 7 State Treasurer are hereby authorized and directed to borrow 8 from time to time in addition to any authorization heretofore or 9 hereafter enacted, on the credit of the Commonwealth, subject to 10 the limitations provided in the current capital budget, money 11 not exceeding in the aggregate the sum of $1,122,556,000 as may 12 be found necessary to carry out the acquisition and construction 13 of the public improvement projects specifically itemized in a 14 capital budget. 15 (b) Furniture and equipment.--The Governor, Auditor General 16 and State Treasurer are hereby authorized and directed to borrow 17 from time to time in addition to any authorization heretofore or 18 hereafter enacted, on the credit of the Commonwealth, subject to 19 the limitations provided in the current capital budget, money 20 not exceeding in the aggregate the sum of $64,846,000 as may be 21 found necessary to carry out the acquisition and construction of 22 the public improvement projects consisting of the acquisition of 23 original movable furniture and equipment specifically itemized 24 in a capital budget. 25 (c) Transportation assistance.--The Governor, Auditor 26 General and State Treasurer are hereby authorized and directed 27 to borrow from time to time in addition to any authorization 28 heretofore or hereafter enacted, on the credit of the 29 Commonwealth, subject to the limitations provided in the current 30 capital budget, money not exceeding in the aggregate the sum of 20070H1589B1970 - 57 -
1 $47,148,000 as may be found necessary to carry out the 2 acquisition and construction of the transportation assistance 3 projects specifically itemized in a capital budget. 4 (d) (Reserved). 5 (e) Flood control.--The Governor, Auditor General and State 6 Treasurer are hereby authorized and directed to borrow from time 7 to time in addition to any authorization heretofore or hereafter 8 enacted, on the credit of the Commonwealth, subject to the 9 limitations provided in the current capital budget, money not 10 exceeding in the aggregate the sum of $4,350,000 as may be found 11 necessary to carry out the acquisition and construction of the 12 flood control projects specifically itemized in a capital 13 budget. 14 Section 13. Issue of bonds. 15 The indebtedness authorized in this act shall be incurred 16 from time to time and shall be evidenced by one or more series 17 of general obligation bonds of the Commonwealth in such 18 aggregate principal amount for each series as the Governor, the 19 Auditor General and the State Treasurer shall determine, but the 20 latest stated maturity date shall not exceed the estimated 21 useful life of the projects being financed as stated in section 22 15. 23 Section 14. Estimated useful life and term of debt. 24 (a) Estimated useful life.--The General Assembly states that 25 the estimated useful life of the public improvement projects 26 itemized in this act is as follows: 27 (1) Public improvement projects, 30 years. 28 (2) Furniture and equipment projects, 10 years. 29 (3) Transportation assistance projects: 30 (i) Rolling stock, 15 years. 20070H1589B1970 - 58 -
1 (ii) Passenger buses, 12 years. 2 (iii) Furniture and equipment, 10 years. 3 (iv) All others, 30 years. 4 (b) Term of debt.--The maximum term of the debt authorized 5 to be incurred under this act is 30 years. 6 Section 15. Appropriations. 7 (a) Public improvements.--The net proceeds of the sale of 8 the obligations authorized in this act are hereby appropriated 9 from the Capital Facilities Fund to the Department of General 10 Services in the maximum amount of $1,122,556,000 to be used by 11 it exclusively to defray the financial cost of the public 12 improvement projects specifically itemized in a capital budget. 13 After reserving or paying the expenses of the sale of the 14 obligation, the State Treasurer shall pay to the Department of 15 General Services the moneys as required and certified by it to 16 be legally due and payable. 17 (b) Furniture and equipment.--The net proceeds of the sale 18 of the obligations authorized in this act are hereby 19 appropriated from the Capital Facilities Fund to the Department 20 of General Services in the maximum amount of $64,846,000 to be 21 used by it exclusively to defray the financial cost of the 22 public improvement projects consisting of the acquisition of 23 original movable furniture and equipment specifically itemized 24 in a capital budget. After reserving or paying the expenses of 25 the sale of the obligation, the State Treasurer shall pay to the 26 Department of General Services the moneys as required and 27 certified by it to be legally due and payable. 28 (c) Transportation assistance.--The net proceeds of the sale 29 of the obligations authorized in this act are hereby 30 appropriated from the Capital Facilities Fund to the Department 20070H1589B1970 - 59 -
1 of Transportation in the maximum amount of $47,148,000 to be 2 used by it exclusively to defray the financial cost of the 3 transportation assistance projects specifically itemized in a 4 capital budget. After reserving or paying the expenses of the 5 sale of the obligation, the State Treasurer shall pay to the 6 Department of Transportation the moneys as required and 7 certified by it to be legally due and payable. 8 (d) (Reserved). 9 (e) Flood control.--The net proceeds of the sale of the 10 obligations authorized in this act are hereby appropriated from 11 the Capital Facilities Fund to the Department of Environmental 12 Protection in the maximum amount of $4,350,000 to be used by it 13 exclusively to defray the financial cost of the flood control 14 projects specifically itemized in a capital budget. After 15 reserving or paying the expenses of the sale of the obligation, 16 the State Treasurer shall pay to the Department of Environmental 17 Protection the moneys as required and certified by it to be 18 legally due and payable. 19 Section 16. Federal funds. 20 In addition to those funds appropriated in section 15, all 21 moneys received from the Federal Government for the projects 22 specifically itemized in this act are also hereby appropriated 23 for those projects. 24 Section 17. Delegation. 25 Notwithstanding any provision of law to the contrary, the 26 Department of General Services may delegate the design and 27 construction of the project contained in section 3(9)(iv)(A) to 28 Drexel University. 29 Section 18. Department of Corrections facilities. 30 (a) Preemption of local ordinances.--Capital projects in the 20070H1589B1970 - 60 -
1 category of public improvement projects specifically itemized 2 for the Department of Corrections in section 3(4)(i), (iii), 3 (v), (vi), (viii), (xii) and (xiii) are hereby authorized to be 4 constructed, erected or acquired by the Department of General 5 Services, its successors or assigns, of the Department of 6 Corrections, notwithstanding any zoning ordinance, land use 7 ordinance, building code or other regulation adopted or enacted 8 by a political subdivision under the authority of any statute or 9 under the authority of any home rule charter authorized and 10 adopted under any statute or the Constitution of Pennsylvania. 11 (b) Preemption of local ordinances for 2005-2006 projects.-- 12 Capital projects in the category of public improvement projects 13 specifically itemized for the Department of Corrections in 14 section 3(5)(iv.2)(A), (iv.4)(A) and (v.1)(A) of the act of July 15 7, 2006 (P.L.390, No.83), known as the Capital Budget Project 16 Itemization Act of 2005-2006, are hereby authorized to be 17 constructed, erected or acquired by the Department of General 18 Services, its successors or assigns, of the Department of 19 Corrections, notwithstanding any zoning ordinance, land use 20 ordinance, building code or other regulation adopted or enacted 21 by a political subdivision under the authority of any statute or 22 under the authority of any home rule charter authorized and 23 adopted under any statute or the Constitution of Pennsylvania. 24 (c) Preemption of local ordinances for 2001-2002 projects.-- 25 The capital projects in the category of public improvement 26 projects specifically itemized for the Department of Corrections 27 in section 3(4)(xi)(A) of the act of October 30, 2002 (P.L.891, 28 No.131), known as the Capital Budget Project Itemization Act of 29 2001-2002, are hereby authorized to be constructed, erected or 30 acquired by the Department of General Services, its successors 20070H1589B1970 - 61 -
1 or assigns, of the Department of Corrections, notwithstanding 2 any zoning ordinance, land use ordinance, building code or other 3 regulation adopted or enacted by a political subdivision under 4 the authority of any statute or under the authority of any home 5 rule charter authorized and adopted under any statute or the 6 Constitution of Pennsylvania. 7 Section 19. Editorial changes. 8 In editing and preparing this act for printing following the 9 final enactment, the Legislative Reference Bureau shall insert 10 or revise letters or numbers for projects where the letters or 11 numbers are missing or require revision. The bureau shall also 12 revise the total monetary amounts for the total authorization, 13 debt authorization, appropriations and departmental totals as 14 necessary to agree with the total monetary amounts of the 15 projects. 16 Section 20. Effective date. 17 This act shall take effect July 1, 2007, or immediately, 18 whichever is later. D9L72RZ/20070H1589B1970 - 62 -