PRIOR PRINTER'S NOS. 179, 445 PRINTER'S NO. 698
No. 186 Session of 1997
INTRODUCED BY CORMAN AND STOUT, JANUARY 23, 1997
SENATOR TILGHMAN, APPROPRIATIONS, RE-REPORTED AS AMENDED, MARCH 11, 1997
A SUPPLEMENT 1 To the act of December 8, 1982 (P.L.848, No.235), entitled "An 2 act providing for the adoption of capital projects related to 3 the repair, rehabilitation or replacement of highway bridges 4 to be financed from current revenue or by the incurring of 5 debt and capital projects related to highway and safety 6 improvement projects to be financed from current revenue of 7 the Motor License Fund," itemizing additional local and State 8 bridge projects. 9 The General Assembly of the Commonwealth of Pennsylvania 10 hereby enacts as follows: 11 Section 1. Short title. 12 This act shall be known and may be cited as the Highway- 13 Railroad and Highway Bridge Capital Budget Supplemental Act for 14 1996-1997. 15 Section 2. Definitions. 16 The following words and phrases when used in this act shall 17 have the meanings given to them in this section unless the 18 context clearly indicates otherwise: 19 "Account." The Highway Bridge Improvement Restricted Account 20 within the Motor License Fund.
1 "Capital project." A capital project as defined in section 2 1602-B of the act of April 9, 1929 (P.L.343, No.176), known as 3 The Fiscal Code, and shall include a county or municipal bridge 4 rehabilitation, replacement or improvement project as set forth 5 in this act. 6 "Department." The Department of Transportation of the 7 Commonwealth. 8 "Secretary." The Secretary of Transportation of the 9 Commonwealth. 10 Section 3. Total authorization for bridge projects. 11 (a) Total projects.--The total authorization for the costs 12 of the projects itemized pursuant to this act and to be financed 13 from current revenue or by the incurring of debt shall be 14 $1,246,492,000 $1,309,837,000. <-- 15 (b) State projects.--The authorization for capital projects 16 in the category of highway bridge projects and forestry bridge 17 projects to be constructed by the Department of Transportation 18 or the Department of Conservation and Natural Resources, or 19 their successors or assigns, and to be financed by the incurring 20 of debt or from the highway account, itemized in this act under 21 the category of State bridges, shall be $962,844,000 <-- 22 $989,925,000. 23 (c) Non-State projects.--The authorization for non-State 24 highway bridge projects to be constructed by municipalities and 25 to be financed in part with grants not exceeding 80% of the non- 26 Federal share of the costs made to the local government 27 municipalities by the department from revenues deposited in the 28 account itemized in this act under the category of local 29 bridges, shall be $283,648,000 $319,912,000. <-- 30 Section 4. Itemization of bridge projects. 19970S0186B0698 - 2 -
1 The individual capital projects in the category of highway 2 projects to be constructed by the Department of Transportation, 3 its successors or assigns, and to be financed from current 4 revenue or by the incurring of debt are hereby itemized, 5 together with their estimated financial costs, in the following 6 sections. 7 Section 5. Adams County. 8 (a) Local Bridges 9 (1) Cumberland Township, T-338, Herr's 10 Ridge Road Bridge over Willoughby Run, 11 Bridge Rehabilitation 170,000 12 (Base Construction Allocation - 13 $100,000) 14 (Land Allocation - $10,000) 15 (Design and Contingencies - $60,000) 16 (2) Cumberland Township, T-402, Horner 17 Road Bridge over Marsh Creek, County 18 Bridge No.111, Bridge Replacement 1,075,000 19 (Base Construction Allocation - 20 $725,000) 21 (Land Allocation - $25,000) 22 (Design and Contingencies - $325,000) 23 (3) Cumberland Township, T-417, Goulden 24 Road Bridge over Rock Creek, County 25 Bridge No.123, Bridge Rehabilitation 330,000 26 (Base Construction Allocation - 27 $250,000) 28 (Land Allocation - $5,000) 29 (Design and Contingencies - $75,000) 30 (4) Cumberland and Freedom Townships, 19970S0186B0698 - 3 -
1 Sach's Mill Covered Bridge over Marsh 2 Creek, Pedestrian Bridge, Bridge 3 Rehabilitation 600,000 4 (Base Construction Allocation - 5 $500,000) 6 Design and Contingencies - $100,000 7 (b) State Bridges (Reserved) 8 Section 6. Allegheny County. 9 (a) Local Bridges 10 (1) Plum Borough, Mary Street Bridge over 11 Plum Creek, Bridge Replacement 630,000 12 (Base Construction Allocation - 13 $400,000) 14 (Land Allocation - $50,000) 15 (Design and Contingencies - $180,000) 16 (2) City of Pittsburgh, Glenwood Bridge, 17 Phase II over Monongahela River, Three 18 Railroads and Carson Street, Bridge 19 Rehabilitation 4,180,000 20 (Base Construction Allocation - 21 $3,905,000) 22 (Design and Contingencies - $275,000) 23 (3) Elizabeth Township, Patterson Road, 24 Boyd Hollow Bridge, Bridge Replacement 225,000 25 (Base Construction Allocation - 26 $180,000) 27 (Land Allocation - $11,000) 28 (Design and Contingencies - $34,000) 29 (4) Elizabeth Township, Yates Street 30 Bridge, Bridge Replacement 198,000 19970S0186B0698 - 4 -
1 (Base Construction Allocation - 2 $158,000) 3 (Land Allocation - $10,000) 4 (Design and Contingencies - $30,000) 5 (5) Shaler Township, South of Martha 6 Avenue, Anderson Road over Wible Run, 7 Bridge Replacement 500,000 8 (Base Construction Allocation - 9 $400,000) 10 (Design and Contingencies - $100,000) 11 (6) Baldwin Borough, Old Clairton Road 12 over CSX Railroad, Bridge 13 Rehabilitation 80,000 14 (Base Construction Allocation - 15 $65,000) 16 (Design and Contingencies - $15,000) 17 (7) Ben Avon Borough, Spruce Run Road over 18 Spruce Run, Bridge Rehabilitation 265,000 19 (Base Construction Allocation - 20 $200,000) 21 (Land Allocation - $5,000) 22 (Design and Contingencies - $60,000) 23 (8) City of Pittsburgh, Swinburne Street, 24 Bridge Painting 1,530,000 25 (Base Construction Allocation - 26 $1,500,000) 27 (Design and Contingencies - $30,000) 28 (9) City of Pittsburgh, Railroad Bridge 29 (Hot Metal Bridge) at Former LTV Steel 30 Company over Monongahela River, Bridge 19970S0186B0698 - 5 -
1 Rehabilitation 25,000,000 2 (Base Construction Allocation - 3 $22,500,000) 4 (Design and Contingencies - $2,500,000) 5 (10) Edgeworth Borough, Beaver Street over 6 Little Sewickley Creek, Bridge 7 Replacement 358,000 8 (Base Construction Allocation - 9 $250,000) 10 (Land Allocation - $8,000) 11 (Design and Contingencies - $100,000) 12 (11) Forward Township, Pangburn Hollow 13 Road over Pangburn Run, Bridge 14 Replacement 200,000 15 (Base Construction Allocation - 16 $150,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $40,000) 19 (12) Hampton Township, Duncan Avenue over 20 Pine Creek, Bridge Replacement 200,000 21 (Base Construction Allocation - 22 $150,000) 23 (Land Allocation - $10,000) 24 (Design and Contingencies - $40,000) 25 (13) Harrison Township, Natrona Road over 26 Small Branch of Allegheny River, Bridge 27 Rehabilitation 210,000 28 (Base Construction Allocation - 29 $160,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 6 -
1 (Design and Contingencies - $40,000) 2 (14) Jefferson Borough, Coal Valley Road 3 Bridge No.2 over McRoberts Run, Bridge 4 Rehabilitation 200,000 5 (Base Construction Allocation - 6 $150,000) 7 (Land Allocation - $10,000) 8 (Design and Contingencies - $40,000) 9 (15) Jefferson Borough, Coal Valley Road 10 Bridge No.4 over McRoberts Run, Bridge 11 Rehabilitation 200,000 12 (Base Construction Allocation - 13 $150,000) 14 (Land Allocation - $10,000) 15 (Design and Contingencies - $40,000) 16 (16) Leetsdale Borough, Beaver Road over 17 Big Sewickley Creek, Bridge 18 Replacement 420,000 19 (Base Construction Allocation - 20 $300,000) 21 (Land Allocation - $10,000) 22 (Design and Contingencies - $110,000) 23 (17) Municipality of Penn Hills, Mt. 24 Carmel Road over Sandy Creek, Bridge 25 Replacement 230,000 26 (Base Construction Allocation - 27 $170,000) 28 (Land Allocation - $10,000) 29 (Design and Contingencies - $50,000) 30 (18) Municipality of Penn Hills, Lincoln 19970S0186B0698 - 7 -
1 Road Bridge No.6 over Sandy Creek, 2 Bridge Replacement 215,000 3 (Base Construction Allocation - 4 $150,000) 5 (Land Allocation - $5,000) 6 (Design and Contingencies - $60,000) 7 (19) Municipality of Penn Hills, Lincoln 8 Road Bridge No.12 over Sandy Creek, 9 Bridge Replacement 215,000 10 (Base Construction Allocation - 11 $150,000) 12 (Land Allocation - $5,000) 13 (Design and Contingencies - $60,000) 14 (20) Sewickley Heights Borough, Blackburn 15 Road over Kilbuck Run, Bridge 16 Rehabilitation 145,000 17 (Base Construction Allocation - 18 $110,000) 19 (Land Allocation - $5,000) 20 (Design and Contingencies - $30,000) 21 (21) South Park Township, Sleepy Hollow 22 Road over Sleepy Hollow, Bridge 23 Replacement 295,000 24 (Base Construction Allocation - 25 $200,000) 26 (Land Allocation - $5,000) 27 (Design and Contingencies - $90,000) 28 (22) South Park Township, Cochran's Mill 29 Road over Licks Run, Bridge 30 Replacement 215,000 19970S0186B0698 - 8 -
1 (Base Construction Allocation - 2 $150,000) 3 (Land Allocation - $5,000) 4 (Design and Contingencies - $60,000) 5 (23) Hampton Township, T-357, Bridge over 6 Gourdhead Run, Bridge Rehabilitation 320,000 7 (Base Construction Allocation - 8 $280,000) 9 (Design and Contingencies - $40,000) 10 (24) Hampton Township, T-984, South 11 Pioneer Road Bridge No.1 over Crouse 12 Run, Bridge Rehabilitation 250,000 13 (Base Construction Allocation - 14 $210,000) 15 (Design and Contingencies - $40,000) 16 (25) Hampton Township, T-984, South 17 Pioneer Road Bridge No.2 over Crouse 18 Run, Bridge Rehabilitation 250,000 19 (Base Construction Allocation - 20 $210,000) 21 (Design and Contingencies - $40,000) 22 (26) Marshall Township, T-482, Northgate 23 Drive Bridge over Brush Creek, Bridge 24 Replacement 320,000 25 (Base Construction Allocation - 26 $280,000) 27 (Land Allocation - $5,000) 28 (Design and Contingencies - $35,000) 29 (27) Town of McCandless, Blazier Drive 30 Bridge No.1 over Pine Creek, Bridge 19970S0186B0698 - 9 -
1 Rehabilitation 17,000 2 (Base Construction Allocation - 3 $15,000) 4 (Design and Contingencies - $2,000) 5 (28) Town of McCandless, Blazier Drive 6 Bridge No.2 over Pine Creek, Bridge 7 Rehabilitation 28,000 8 (Base Construction Allocation - 9 $26,000) 10 (Design and Contingencies - $2,000) 11 (29) Town of McCandless, Blazier Drive 12 Bridge No.3 over Pine Creek, Bridge 13 Rehabilitation 3,000 14 (Base Construction Allocation - $2,000) 15 (Design and Contingencies - $1,000) 16 (30) Town of McCandless, Oakridge Drive 17 over Pine Creek, Bridge Rehabilitation 10,000 18 (Base Construction Allocation - $8,000) 19 (Design and Contingencies - $2,000) 20 (31) Town of McCandless, Meinert Road over 21 Pine Creek, Bridge Rehabilitation 3,000 22 (Base Construction Allocation - $2,000) 23 (Design and Contingencies - $1,000) 24 (32) Collier Township, Thom's Run Road- 25 Oakdale Road No.4 over Thom's Run, 26 Bridge Replacement 210,000 27 (Base Construction Allocation - 28 $160,000) 29 (Land Allocation - $10,000) 30 (Design and Contingencies - $40,000) 19970S0186B0698 - 10 -
1 (33) Collier Township, Thom's Run Road- 2 Oakdale Road No.5 over Thom's Run, 3 Bridge Replacement 210,000 4 (Base Construction Allocation - 5 $160,000) 6 (Land Allocation - $10,000) 7 (Design and Contingencies - $40,000) 8 (34) Collier Township, Thom's Run Road- 9 Oakdale Road No.9 over Thom's Run, 10 Bridge Replacement 180,000 11 (Base Construction Allocation - 12 $130,000) 13 (Land Allocation - $10,000) 14 (Design and Contingencies - $40,000) 15 (35) Etna Borough, Dewey Street over 16 Little Pine Creek, Bridge 17 Rehabilitation 23,000 18 (Base Construction Allocation - 19 $20,000) 20 (Design and Contingencies - $3,000) 21 (36) Forward Township, Roberts Hollow Road 22 over Fallen Timber Run, Bridge 23 Replacement 200,000 24 (Base Construction Allocation - 25 $160,000) 26 (Land Allocation - $10,000) 27 (Design and Contingencies - $30,000) 28 (37) Hampton Township, Duncan Avenue over 29 Stillhouse Run, Bridge Replacement 230,000 30 (Base Construction Allocation - 19970S0186B0698 - 11 -
1 $170,000) 2 (Land Allocation - $10,000) 3 (Design and Contingencies - $50,000) 4 (38) Penn Hills Township, Lincoln Road 5 over Ryans Run, Bridge Replacement 190,000 6 (Base Construction Allocation - 7 $140,000) 8 (Land Allocation - $10,000) 9 (Design and Contingencies - $40,000) 10 (39) Penns Hills Township, Lincoln Road 11 over Sandy Creek, Bridge Replacement 195,000 12 (Base Construction Allocation - 13 $150,000) 14 (Land Allocation - $5,000) 15 (Design and Contingencies - $40,000) 16 (40) North Versailles Township, Crooked 17 Run Road over Crooked Run, Bridge 18 Replacement 170,000 19 (Base Construction Allocation - 20 $130,000) 21 (Land Allocation - $10,000) 22 (Design and Contingencies - $30,000) 23 (41) O'Hara Township, Brownhill Road over 24 Little Pine Creek, Bridge Replacement 275,000 25 (Base Construction Allocation - 26 $231,000) 27 (Design and Contingencies - $44,000) 28 (42) Ross Township, Thompson Run Road over 29 South Branch of Pine Creek, Bridge 30 Replacement 210,000 19970S0186B0698 - 12 -
1 (Base Construction Allocation - 2 $160,000) 3 (Land Allocation - $8,000) 4 (Design and Contingencies - $42,000) 5 (43) Moon Township, T-114, Becks Run Road 6 over Flaugherty Run, Bridge 7 Replacement 420,000 8 (Base Construction Allocation - 9 $350,000) 10 (Land Allocation - $20,000) 11 (Design and Contingencies - $50,000) 12 (44) Homestead Borough, High Level Bridge, 13 Bridge Rehabilitation and Upgrade 250,000 14 (45) North Braddock Borough, Hawkins 15 Avenue Bridge, Bridge Rehabilitation 300,000 16 (46) Penn Hills Borough, Beechtree Road 17 Box Culvert Bridge, Bridge 18 Rehabilitation 100,000 19 (47) Whitaker Borough, Rankin Bridge, 20 Bridge Rehabilitation 100,000 21 (48) SWISSVALE BOROUGH, KENMAUR BRIDGE <-- 22 CONNECTING SWISSVALE AND RANKIN, BRIDGE 23 REPLACEMENT 320,000 24 (BASE CONSTRUCTION ALLOCATION - 25 $270,000) 26 (DESIGN AND CONTINGENCIES - $50,000) 27 (49) WILKINS TOWNSHIP, BROWN AVENUE BRIDGE 28 OVER BROWN RUN, BRIDGE REPLACEMENT 475,000 29 (BASE CONSTRUCTION ALLOCATION - 30 $380,000) 19970S0186B0698 - 13 -
1 (DESIGN AND CONTINGENCIES - $95,000) 2 (50) WILKINS TOWNSHIP, IVY STREET BRIDGE 3 OVER BROWN RUN, BRIDGE REPLACEMENT 268,000 4 (BASE CONSTRUCTION ALLOCATION - 5 $214,000) 6 (DESIGN AND CONTINGENCIES - $54,000) 7 (51) WILKINS TOWNSHIP, BAKER STREET BRIDGE 8 OVER CHALFANT RUN, BRIDGE REPLACEMENT 205,000 9 (BASE CONSTRUCTION ALLOCATION - 10 $164,000) 11 (DESIGN AND CONTINGENCIES - $41,000) 12 (52) UPPER ST. CLAIR TOWNSHIP, WALTHER 13 LANE BRIDGE, BRIDGE REPLACEMENT 700,000 14 (BASE CONSTRUCTION ALLOCATION - 15 $650,000) 16 (DESIGN AND CONTINGENCIES - $50,000) 17 (53) GREEN TREE BOROUGH, TRUMBALL DRIVE 18 BRIDGE OVER WHEELING AND LAKE ERIE 19 RAILROAD, BRIDGE REHABILITATION 575,000 20 (BASE CONSTRUCTION ALLOCATION - 21 $500,000) 22 (DESIGN AND CONTINGENCIES - $75,000) 23 (b) State Bridges 24 (1) SR 0028, Etna Bridge, Northbound 25 Bridge No.4 to Existing SR 0028, Etna 26 Borough, Shaler Township, Sharpsburg 27 Borough and O'Hara Township, Bridge 28 Rehabilitation 7,415,000 29 (Base Construction Allocation - 30 $7,115,000) 19970S0186B0698 - 14 -
1 (Land Allocation - $300,000) 2 (2) SR 0028, Etna Bridge to 62nd Street 3 Bridge, Etna Borough, Shaler Township, 4 Sharpsburg Borough and O'Hara Township, 5 Bridge Rehabilitation 17,222,000 6 (Base Construction Allocation - 7 $17,022,000) 8 (Land Allocation - $200,000) 9 (3) SR 0030, Ardmore Westbound Electric 10 over SR 2112, Chalfant Borough, Bridge 11 Replacement 3,100,000 12 (Base Construction Allocation - 13 $3,000,000) 14 (Design and Contingencies - $100,000) 15 (4) SR 0030, Ardmore Eastbound Electric 16 over SR 2112, Chalfant Borough, Bridge 17 Replacement 2,500,000 18 (Base Construction Allocation - 19 $2,400,000) 20 (Design and Contingencies - $100,000) 21 (5) SR 0030, Ardmore Boulevard Bridge No.1 22 over Falls Run, North of SR 8012 23 Interchange, Forest Hills Borough, 24 Bridge Replacement 550,000 25 (Base Construction Allocation - 26 $400,000) 27 (Land Allocation - $50,000) 28 (Design and Contingencies - $100,000) 29 (6) SR 0048, Boston Hollow Road Bridge 30 over Unnamed Stream, North of Lincoln 19970S0186B0698 - 15 -
1 Borough, Elizabeth Borough, Bridge 2 Replacement 340,000 3 (Base Construction Allocation - 4 $200,000) 5 (Land Allocation - $40,000) 6 (Design and Contingencies - $100,000) 7 (7) SR 0050, Bridge over Chartiers Creek, 8 Northbound Lane, Heidelberg Borough, 9 Scott Township, Bridge Rehabilitation 3,750,000 10 (Base Construction Allocation - 11 $3,300,000) 12 (Land Allocation - $50,000) 13 (Design and Contingencies - $400,000) 14 (8) SR 0060, South Main Street Bridge over 15 Saw Mill Run, South of West End Circle, 16 City of Pittsburgh, Bridge Painting 178,000 17 (Base Construction Allocation - 18 $173,000) 19 (Design and Contingencies - $5,000) 20 (9) SR 0130, Tri-Borough Extended Bridge 21 over Patton Street at SR 8076 22 Interchange, Wilmerding Borough, Bridge 23 Rehabilitation 505,000 24 (Base Construction Allocation - 25 $400,000) 26 (Land Allocation - $30,000) 27 (Design and Contingencies - $75,000) 28 (10) SR 0148, Bridge over Crooked Run 29 Creek near SR 2037, White Oak Borough, 30 Bridge Replacement 350,000 19970S0186B0698 - 16 -
1 (Base Construction Allocation - 2 $200,000) 3 (Land Allocation - $50,000) 4 (Design and Contingencies - $100,000) 5 (11) SR 0791, Bridge over Chalfont Run at 6 SR 2048, Wilkins Township, Bridge 7 Replacement 450,000 8 (Base Construction Allocation - 9 $300,000) 10 (Land Allocation - $50,000) 11 (Design and Contingencies - $100,000) 12 (12) SR 0837, Northbound Ramp A to SR 0885 13 Southbound, City of Pittsburgh, Bridge 14 Rehabilitation 1,350,000 15 (Base Construction Allocation - 16 $1,250,000) 17 (Design and Contingencies - $100,000) 18 (13) SR 0978, Miller's Run Road Bridge 19 over Dolphin Run, South Fayette 20 Township, Bridge Replacement 300,000 21 (Base Construction Allocation - 22 $200,000) 23 (Design and Contingencies - $100,000) 24 (14) SR 1001, West 7th Avenue Bridge over 25 Bull Creek, Tarentum Borough, Bridge 26 Replacement 400,000 27 (Base Construction Allocation - 28 $300,000) 29 (Design and Contingencies - $100,000) 30 (15) SR 1011, Guys Run Road Bridge over 19970S0186B0698 - 17 -
1 Guys Run, North of SR 0028, Harmar 2 Township, Bridge Replacement 350,000 3 (Base Construction Allocation - 4 $200,000) 5 (Land Allocation - $50,000) 6 (Design and Contingencies - $100,000) 7 (16) SR 2001, Glassport-Elizabeth Road 8 Bridge over Burns Run, North of 9 Elizabeth Township, Lincoln Borough, 10 Bridge Replacement 350,000 11 (Base Construction Allocation - 12 $200,000) 13 (Land Allocation - $50,000) 14 (Design and Contingencies - $100,000) 15 (17) SR 2081, Turtle Creek-Monroeville 16 Road over US 22 Business, Monroeville 17 Borough, Bridge Replacement 1,060,000 18 (Base Construction Allocation - 19 $960,000) 20 (Design and Contingencies - $100,000) 21 (18) SR 2094, Jerome Street Bridge over SR 22 2027, Youghiogheny River, McKeesport 23 Borough, Bridge Rehabilitation 4,600,000 24 (Base Construction Allocation - 25 $4,500,000) 26 (Design and Contingencies - $100,000) 27 (19) SR 3066, Steubenville Pike Bridge 28 over US 22, North Fayette Township, 29 Bridge Rehabilitation 500,000 30 (Base Construction Allocation - 19970S0186B0698 - 18 -
1 $400,000) 2 (Land Allocation - $25,000) 3 (Design and Contingencies - $75,000) 4 (20) SR 3069, Liberty Tunnel Airshaft 5 between SR 0051 and Liberty Bridge, 6 City of Pittsburgh, Airshaft 7 Restoration 1,570,000 8 (Base Construction Allocation - 9 $1,370,000) 10 (Design and Contingencies - $200,000) 11 (21) SR 3104, McKees Rocks Sidewalk over 12 Harriet Street, McKees Rocks Borough, 13 Bridge Rehabilitation 6,800,000 14 (Base Construction Allocation - 15 $6,700,000) 16 (Design and Contingencies - $100,000) 17 (22) SR 4036, Big Sewickley Creek Road 18 over Big Sewickley Creek at SR 2003, 19 Bell Acres Borough, Bridge 20 Rehabilitation 500,000 21 (Base Construction Allocation - 22 $400,000) 23 (Land Allocation - $25,000) 24 (Design and Contingencies - $75,000) 25 (23) SR 8043, Southbound Ramp Bridge over 26 SR 0019 and SR 0065, City of 27 Pittsburgh, Bridge Rehabilitation 2,400,000 28 (Base Construction Allocation - 29 $2,100,000) 30 (Land Allocation - $50,000) 19970S0186B0698 - 19 -
1 (Design and Contingencies - $250,000) 2 (24) SR 8045, Ramp at Stadium over SR 0065 3 and Stadium Drive, City of Pittsburgh, 4 Bridge Rehabilitation 600,000 5 (Base Construction Allocation - 6 $600,000) 7 (25) SR 8049, SR 0019 Bridge Ramp, Chateau 8 Street to SR 0019, City of Pittsburgh, 9 Bridge Rehabilitation 2,350,000 10 (Base Construction Allocation - 11 $2,000,000) 12 (Land Allocation - $50,000) 13 (Design and Contingencies - $300,000) 14 (26) SR 8049, Bridge Ramp from SR 0065 15 Northbound to SR 0019, City of 16 Pittsburgh, Bridge Rehabilitation 2,850,000 17 (Base Construction Allocation - 18 $2,500,000) 19 (Land Allocation - $50,000) 20 (Design and Contingencies - $300,000) 21 (27) SR 8049, I-279 Bridge Ramp to SR 0065 22 Northbound, City of Pittsburgh, Bridge 23 Rehabilitation 1,730,000 24 (Base Construction Allocation - 25 $1,500,000) 26 (Land Allocation - $30,000) 27 (Design and Contingencies - $200,000) 28 (28) SR 0030, Ardmore Boulevard Bridge 29 No.2 over Falls Run, North of SR 8012 30 Interchange, Forest Hills Borough, 19970S0186B0698 - 20 -
1 Bridge Replacement 550,000 2 (Base Construction Allocation - 3 $400,000) 4 (Land Allocation - $50,000) 5 (Design and Contingencies - $100,000) 6 (29) SR 3004, McLaughlin Road Bridge over 7 McLaughlin Run, Bridgeville Borough, 8 Bridge Replacement 227,000 9 (Base Construction Allocation - 10 $177,000) 11 (Land Allocation - $10,000) 12 (Design and Contingencies - $40,000) 13 (30) SR 0028, Northbound Bridge over 14 Pennsylvania Turnpike, Harmar Township, 15 Bridge Rehabilitation 344,000 16 (Base Construction Allocation - 17 $314,000) 18 (Design and Contingencies - $30,000) 19 (31) SR 0028, Southbound Bridge over 20 Pennsylvania Turnpike, Harmar Township, 21 Bridge Rehabilitation 356,000 22 (Base Construction Allocation - 23 $325,000) 24 (Design and Contingencies - $31,000) 25 (32) SR 0028, Northbound Bridge over SR 26 1028, Harrison Township, Bridge 27 Rehabilitation 106,000 28 (Base Construction Allocation - 29 $97,000) 30 (Design and Contingencies - $9,000) 19970S0186B0698 - 21 -
1 (33) SR 0028, Southbound Bridge over SR 2 1028, Harrison Township, Bridge 3 Rehabilitation 105,000 4 (Base Construction Allocation - 5 $96,000) 6 (Design and Contingencies - $9,000) 7 (34) SR 0050, Washington Avenue Bridge 8 over Chartiers Creek, Bridgeville 9 Borough, Bridge Rehabilitation 119,000 10 (Base Construction Allocation - 11 $109,000) 12 (Design and Contingencies - $10,000) 13 (35) SR 0051, Clairton Boulevard Bridge 14 over Lewis Run, Pleasant Hills Borough, 15 Bridge Replacement 600,000 16 (Base Construction Allocation - 17 $500,000) 18 (Design and Contingencies - $100,000) 19 (36) SR 0065, Ohio River Boulevard Bridge 20 over Forest Avenue, Ben Avon Borough, 21 Bridge Replacement 396,000 22 (Base Construction Allocation - 23 $360,000) 24 (Design and Contingencies - $36,000) 25 (37) SR 0065, Bridge over Ramps, Railroad 26 and Chateau Street, City of Pittsburgh, 27 Bridge Rehabilitation 13,284,000 28 (Base Construction Allocation - 29 $12,784,000) 30 (Design and Contingencies - $500,000) 19970S0186B0698 - 22 -
1 (38) SR 0079, Neville Island Bridge over 2 Ohio River, Neville Township, Bridge 3 Rehabilitation 12,700,000 4 (Base Construction Allocation - 5 $11,200,000) 6 (Design and Contingencies - $1,500,000) 7 (39) SR 0088, Library Road Bridge No.1 8 over Piney Fork Creek, Bethel Park 9 Borough, Bridge Replacement 161,000 10 (Base Construction Allocation - 11 $128,000) 12 (Land Allocation - $20,000) 13 (Design and Contingencies - $13,000) 14 (40) SR 0088, Library Road Bridge No.2 15 over Branch of Piney Fork Creek, Bethel 16 Park Borough, Bridge Replacement 161,000 17 (Base Construction Allocation - 18 $128,000) 19 (Land Allocation - $20,000) 20 (Design and Contingencies - $13,000) 21 (41) SR 0885, Mifflin Road Bridge over 22 Branch of Streets Run, City of 23 Pittsburgh, Bridge Replacement 600,000 24 (Base Construction Allocation - 25 $500,000) 26 (Design and Contingencies - $100,000) 27 (42) SR 0910, Gibsonia Road Bridge over 28 Rawlins Run, Indiana Township, Bridge 29 Deck Replacement 132,000 30 (Base Construction Allocation - 19970S0186B0698 - 23 -
1 $120,000) 2 (Design and Contingencies - $12,000) 3 (43) SR 1027, Pleasantville Road Bridge 4 over Little Bull Creek, Harrison 5 Township, Bridge Replacement 400,000 6 (Base Construction Allocation - 7 $300,000) 8 (Design and Contingencies - $100,000) 9 (44) SR 1032, Burtner Road Bridge over 10 Little Bull Creek, Harrison Township, 11 Bridge Deck Replacement 198,000 12 (Base Construction Allocation - 13 $180,000) 14 (Design and Contingencies - $18,000) 15 (45) SR 2008, Lovedale Road Bridge over 16 Wylie Run Creek, Elizabeth Township, 17 Bridge Replacement 430,000 18 (Base Construction Allocation - 19 $300,000) 20 (Land Allocation - $30,000) 21 (Design and Contingencies - $100,000) 22 (46) SR 2017, Pineview Drive Bridge No.1 23 over Gillespie Run, Elizabeth Township, 24 Bridge Deck Replacement 255,000 25 (Base Construction Allocation - 26 $135,000) 27 (Land Allocation - $20,000) 28 (Design and Contingencies - $100,000) 29 (47) SR 2017, Pineview Drive Bridge No.2 30 over Gillespie Run, Elizabeth Township, 19970S0186B0698 - 24 -
1 Bridge Deck Replacement 243,000 2 (Base Construction Allocation - 3 $123,000) 4 (Land Allocation - $20,000) 5 (Design and Contingencies - $100,000) 6 (48) SR 2018, West Smithfield Road Bridge 7 over Unnamed Creek, Elizabeth Township, 8 Bridge Deck Replacement 218,000 9 (Base Construction Allocation - 10 $118,000) 11 (Design and Contingencies - $100,000) 12 (49) SR 2031, Lincoln Way Bridge over Long 13 Run, White Oak Borough, Bridge 14 Replacement 600,000 15 (Base Construction Allocation - 16 $500,000) 17 (Design and Contingencies - $100,000) 18 (50) SR 2051, Brinton Road Bridge over I- 19 376, Edgewood Borough, Bridge 20 Rehabilitation 996,000 21 (Base Construction Allocation - 22 $846,000) 23 (Design and Contingencies - $150,000) 24 (51) SR 4019, Mount Royal Boulevard Bridge 25 over Pine Creek, Hampton Township, 26 Bridge Rehabilitation 94,000 27 (Base Construction Allocation - 28 $89,000) 29 (Design and Contingencies - $5,000) 30 (52) SR 4043, Big Sewickley Road Bridge 19970S0186B0698 - 25 -
1 over Branch of Big Sewickley Creek, 2 Franklin Park Borough, Bridge 3 Replacement 84,000 4 (Base Construction Allocation - 5 $76,000) 6 (Design and Contingencies - $8,000) 7 (53) SR 8002, Crosstown Boulevard Bridge 8 over Forbes and Diamond Street and 9 Ramps, City of Pittsburgh, Bridge 10 Painting 310,000 11 (Base Construction Allocation - 12 $300,000) 13 (Design and Contingencies - $10,000) 14 (54) SR 8002, Ramp L Road Bridge over 15 Forbes and Diamond Streets, City of 16 Pittsburgh, Bridge Painting 110,000 17 (Base Construction Allocation - 18 $100,000) 19 (Design and Contingencies - $10,000) 20 (55) SR 8015, Ramp D Road Bridge over Ohio 21 River Back Channel, Neville Township, 22 Bridge Rehabilitation 800,000 23 (Base Construction Allocation - 24 $700,000) 25 (Design and Contingencies - $100,000) 26 (56) SR 8015, Ramp E Road Bridge over PC&Y 27 Railroad, Neville Township, Bridge 28 Rehabilitation 670,000 29 (Base Construction Allocation - 30 $500,000) 19970S0186B0698 - 26 -
1 (Design and Contingencies - $170,000) 2 (57) SR 8015, I-79 Ramp H Bridge over PC&Y 3 Railroad, Neville Township, Bridge 4 Rehabilitation 700,000 5 (Base Construction Allocation - 6 $600,000) 7 (Design and Contingencies - $100,000) 8 (58) SR 8015, Ramp J Road Bridge over 9 Neville Road, Neville Township, Bridge 10 Rehabilitation 220,000 11 (Base Construction Allocation - 12 $200,000) 13 (Design and Contingencies - $20,000) 14 (59) SR 8017, Ramp B2 Road Bridge over SR 15 4025 and SR 4033, Glenfield Borough, 16 Bridge Rehabilitation 110,000 17 (Base Construction Allocation - 18 $100,000) 19 (Design and Contingencies - $10,000) 20 (60) SR 8017, Ramp B Road Bridge over Ramp 21 A and SR 4033, Glenfield Borough, 22 Bridge Rehabilitation 120,000 23 (Base Construction Allocation - 24 $110,000) 25 (Design and Contingencies - $10,000) 26 (61) SR 8017, Ramp B1 Road Bridge over SR 27 0065 Ramps A1 and R, Glenfield Borough, 28 Bridge Rehabilitation 165,000 29 (Base Construction Allocation - 30 $150,000) 19970S0186B0698 - 27 -
1 (Design and Contingencies - $15,000) 2 (62) SR 8017, Ramp A Road Bridge over Ramp 3 B3, Glenfield Borough, Bridge 4 Rehabilitation 110,000 5 (Base Construction Allocation - 6 $100,000) 7 (Design and Contingencies - $10,000) 8 (63) SR 0028, Etna Bridges, Phase III, 9 Northbound Bridge No.4 to Existing SR 10 0028, Two Structures, Etna and 11 Sharpsburg Boroughs, Bridge 12 Rehabilitation 6,300,000 13 (Base Construction Allocation - 14 $6,000,000) 15 (Land Allocation - $300,000) 16 (64) SR 0028, Etna Bridge, Phase II, 17 Southbound Bridge No.3 and Northbound 18 Bridge for SR 0008 Connection, Etna and 19 Sharpsburg Boroughs and Shaler 20 Township, Bridge Rehabilitation 13,200,000 21 (Base Construction Allocation - 22 $12,200,000) 23 (Land Allocation - $1,000,000) 24 (65) SR 2013, Monessen-Elizabeth Road 25 Bridge over Becketts Run, Forward 26 Township, Bridge Replacement 450,000 27 (Base Construction Allocation - 28 $300,000) 29 (Land Allocation - $50,000) 30 (Design and Contingencies - $100,000) 19970S0186B0698 - 28 -
1 (66) SR 2016, JEFFERSON HEIGHTS ROAD <-- 2 BRIDGE OVER I-376, WILKINS TOWNSHIP, 3 BRIDGE RECONSTRUCTION 1,600,000 4 (BASE CONSTRUCTION ALLOCATION - 5 $1,200,000) 6 (DESIGN AND CONTINGENCIES - $400,000) 7 Section 7. Armstrong County. 8 (a) Local Bridges 9 (1) Boggs Township, T-850, Scrubgrass 10 Bridge over Scrubgrass Creek, Bridge 11 Rehabilitation 230,000 12 (Base Construction Allocation - 13 $170,000) 14 (Land Allocation - $10,000) 15 (Design and Contingencies - $50,000) 16 (2) Boggs Township, T-632, Scrubgrass 17 Bridge No.2 over Scrubgrass Creek, 18 Bridge Rehabilitation 185,000 19 (Base Construction Allocation - 20 $150,000) 21 (Land Allocation - $10,000) 22 (Design and Contingencies - $25,000) 23 (3) Boggs Township, T-821, Pine Creek 24 Bridge over North Fork of Pine Creek, 25 Bridge Rehabilitation 140,000 26 (Base Construction Allocation - 27 $100,000) 28 (Land Allocation - $10,000) 29 (Design and Contingencies - $30,000) 30 (4) North Buffalo Township, T-300, Blaine 19970S0186B0698 - 29 -
1 Bridge over Buffalo Creek, Bridge 2 Replacement 500,000 3 (Base Construction Allocation - 4 $400,000) 5 (Land Allocation - $20,000) 6 (Design and Contingencies - $80,000) 7 (5) North Buffalo Township, T-414, Church 8 Road Bridge over Stream, Bridge 9 Replacement 150,000 10 (Base Construction Allocation - 11 $100,000) 12 (Land Allocation - $10,000) 13 (Design and Contingencies - $40,000) 14 (6) West Kittanning Borough, T-759, Bridge 15 over Stream, Bridge Replacement 325,000 16 (Base Construction Allocation - 17 $265,000) 18 (Land Allocation - $10,000) 19 (Design and Contingencies - $50,000) 20 (b) State Bridges 21 (1) SR 0028, Buffalo Creek Bridge over 22 Buffalo Creek and Conrail, South 23 Buffalo Township, Bridge Painting 3,010,000 24 (Base Construction Allocation - 25 $3,000,000) 26 (Design and Contingencies - $10,000) 27 (2) SR 3023, Iron Bridge Road, Pine Run 28 Bridge Replacement, South Buffalo 29 Township, Bridge Replacement 550,000 30 (Base Construction Allocation - 19970S0186B0698 - 30 -
1 $510,000) 2 (Land Allocation - $20,000) 3 (Design and Contingencies - $20,000) 4 (3) SR 0156, Long Run Bridge over Long 5 Run, Kiskiminetas Township, Bridge 6 Painting 75,000 7 (Base Construction Allocation - 8 $60,000) 9 (Design and Contingencies - $15,000) 10 (4) SR 0422, US 422 Eastbound Overpass 11 Bridge over SR 0028, East Franklin 12 Township, Bridge Painting 190,000 13 (Base Construction Allocation - 14 $175,000) 15 (Design and Contingencies - $15,000) 16 (5) SR 0422, US 422 Westbound Overpass 17 Bridge over SR 0028, East Franklin 18 Township, Bridge Painting 190,000 19 (Base Construction Allocation - 20 $175,000) 21 (Design and Contingencies - $15,000) 22 (6) SR 1028, Oscar Bridge over Pine Creek, 23 Boggs Township, Bridge Painting 95,000 24 (Base Construction Allocation - 25 $80,000) 26 (Design and Contingencies - $15,000) 27 (7) SR 0028, Buffalo Creek Bridge over 28 Buffalo Creek, South Buffalo Township, 29 Bridge Painting 1,730,000 30 (Base Construction Allocation - 19970S0186B0698 - 31 -
1 $1,700,000) 2 (Design and Contingencies - $30,000) 3 (8) SR 0066, Guffy Run Bridge over Guffy 4 Run, Parks Township, Bridge Painting 85,000 5 (Base Construction Allocation - 6 $70,000) 7 (Design and Contingencies - $15,000) 8 (9) SR 0066, Garrett's Run Bridge over 9 Garrett's Run and Old 66, Manor 10 Township, Bridge Painting 1,230,000 11 (Base Construction Allocation - 12 $1,200,000) 13 (Design and Contingencies - $30,000) 14 (10) SR 0128, Cadogan Bridge over 15 Tributary of Allegheny River, Cadogan 16 Township, Bridge Painting 380,000 17 (Base Construction Allocation - 18 $360,000) 19 (Design and Contingencies - $20,000) 20 (11) SR 0422, Judge Graff Bridge over 21 Allegheny River, North Buffalo 22 Township, Bridge Painting 2,930,000 23 (Base Construction Allocation - 24 $2,900,000) 25 (Design and Contingencies - $30,000) 26 (12) SR 0422, Ramp C and F Bridge over End 27 of Bypass, Manor Township, Bridge 28 Painting 180,000 29 (Base Construction Allocation - 30 $165,000) 19970S0186B0698 - 32 -
1 (Design and Contingencies - $15,000) 2 (13) SR 0422, Ramp F Bridge over SR 0066, 3 Manor Township, Bridge Painting 190,000 4 (Base Construction Allocation - 5 $175,000) 6 (Design and Contingencies - $15,000) 7 (14) SR 1021, Eddyville Bridge over Pine 8 Run, Redbank Township, Bridge Painting 100,000 9 (Base Construction Allocation - 10 $85,000) 11 (Design and Contingencies - $15,000) 12 (15) SR 1028, Bryan Bridge over Branch of 13 Pine Creek, Cowanshannock Township, 14 Bridge Painting 50,000 15 (Base Construction Allocation - 16 $35,000) 17 (Design and Contingencies - $15,000) 18 (16) SR 1034, Mosgrove Bridge over North 19 Fork of Pine Creek, Boggs Township, 20 Bridge Painting 65,000 21 (Base Construction Allocation - 22 $50,000) 23 (Design and Contingencies - $15,000) 24 (17) SR 1037, Echo Bridge over Pine Creek, 25 Wayne Township, Bridge Painting 85,000 26 (Base Construction Allocation - 27 $70,000) 28 (Design and Contingencies - $15,000) 29 (18) SR 2001, Rural Valley Bridge over 30 Cowanshannock Creek, Rural Valley 19970S0186B0698 - 33 -
1 Borough, Bridge Painting 130,000 2 (Base Construction Allocation - 3 $115,000) 4 (Design and Contingencies - $15,000) 5 (19) SR 2005, Brick Church Bridge over 6 Branch of Cherry Run, Burrell Township, 7 Bridge Painting 75,000 8 (Base Construction Allocation - 9 $60,000) 10 (Design and Contingencies - $15,000) 11 (20) SR 2005, Cherry Run Bridge over 12 Cherry Run, Plumcreek Township, Bridge 13 Painting 85,000 14 (Base Construction Allocation - 15 $70,000) 16 (Design and Contingencies - $15,000) 17 (21) SR 2005, Elgin Cemetery Bridge over 18 Cowanshannock Creek, Cowanshannock 19 Township, Bridge Painting 85,000 20 (Base Construction Allocation - 21 $70,000) 22 (Design and Contingencies - $15,000) 23 (22) SR 2010, Garrett's Run Bridge over 24 Garrett's Run, Manor Township, Bridge 25 Painting 75,000 26 (Base Construction Allocation - 27 $60,000) 28 (Design and Contingencies - $15,000) 29 (23) SR 2023, Wheel-in-Campground Bridge 30 over Plum Creek, Plumcreek Township, 19970S0186B0698 - 34 -
1 Bridge Painting 125,000 2 (Base Construction Allocation - 3 $110,000) 4 (Design and Contingencies - $15,000) 5 (24) SR 2025, Garrett's Run Bridge No.1 6 over Garrett's Run, Manor Township, 7 Bridge Painting 80,000 8 (Base Construction Allocation - 9 $65,000) 10 (Design and Contingencies - $15,000) 11 (25) SR 2025, Garrett's Run Bridge No.2 12 over Garrett's Run, Manor Township, 13 Bridge Painting 80,000 14 (Base Construction Allocation - 15 $65,000) 16 (Design and Contingencies - $15,000) 17 (26) SR 2025, Garrett's Run Bridge No.3 18 over Garrett's Run, Manor Township, 19 Bridge Painting 90,000 20 (Base Construction Allocation - 21 $75,000) 22 (Design and Contingencies - $15,000) 23 (27) SR 2027, Girty Bridge over Crooked 24 Creek, South Bend Township, Bridge 25 Painting 155,000 26 (Base Construction Allocation - 27 $140,000) 28 (Design and Contingencies - $15,000) 29 (28) SR 2029, Kelly's Station Road Bridge 30 over Taylor Run, Bethel Township, 19970S0186B0698 - 35 -
1 Bridge Painting 60,000 2 (Base Construction Allocation - 3 $45,000) 4 (Design and Contingencies - $15,000) 5 (29) SR 2036, Stilt's Run Bridge over 6 Stilt's Run, Parks Township, Bridge 7 Painting 50,000 8 (Base Construction Allocation - 9 $35,000) 10 (Design and Contingencies - $15,000) 11 (30) SR 2036, Carnahan Run Bridge over 12 Carnahan Run, Parks Township, Bridge 13 Painting 75,000 14 (Base Construction Allocation - 15 $60,000) 16 (Design and Contingencies - $15,000) 17 (31) SR 2050, Rattling Run Bridge over 18 Rattling Run, Kiskiminetas Township, 19 Bridge Painting 65,000 20 (Base Construction Allocation - 21 $50,000) 22 (Design and Contingencies - $15,000) 23 (32) SR 2051, Flat Run Bridge over Flat 24 Run, Kiskiminetas Township, Bridge 25 Painting 55,000 26 (Base Construction Allocation - 27 $40,000) 28 (Design and Contingencies - $15,000) 29 (33) SR 2051, Equitable Bridge over 30 Rattling Run, Kiskiminetas Township, 19970S0186B0698 - 36 -
1 Bridge Painting 55,000 2 (Base Construction Allocation - 3 $40,000) 4 (Design and Contingencies - $15,000) 5 (34) SR 2057, Parks Pump Station Bridge 6 No.1 over Carnahan Run, Parks Township, 7 Bridge Painting 80,000 8 (Base Construction Allocation - 9 $65,000) 10 (Design and Contingencies - $15,000) 11 (35) SR 2058, Parks Pump Station Bridge 12 No.2 over Carnahan Run, Parks Township, 13 Bridge Painting 75,000 14 (Base Construction Allocation - 15 $60,000) 16 (Design and Contingencies - $15,000) 17 (36) SR 3005, Glade Run Bridge over Glade 18 Run, North Buffalo Township, Bridge 19 Painting 75,000 20 (Base Construction Allocation - 21 $60,000) 22 (Design and Contingencies - $15,000) 23 (37) SR 3013, Little Buffalo Bridge over 24 Little Buffalo Creek, West Franklin 25 Township, Bridge Painting 100,000 26 (Base Construction Allocation - 27 $85,000) 28 (Design and Contingencies - $15,000) 29 (38) SR 3013, Harrigan Run Bridge over 30 Harrigan Run, West Franklin Township, 19970S0186B0698 - 37 -
1 Bridge Painting 60,000 2 (Base Construction Allocation - 3 $45,000) 4 (Design and Contingencies - $15,000) 5 (39) SR 3017, West Penn Power Bridge over 6 SR 0422 and SR 0028, East Franklin 7 Township, Bridge Painting 375,000 8 (Base Construction Allocation - 9 $360,000) 10 (Design and Contingencies - $15,000) 11 (40) SR 4007, Kaylor Bridge over Sugar 12 Creek, Bradys Bend Township, Bridge 13 Painting 60,000 14 (Base Construction Allocation - 15 $45,000) 16 (Design and Contingencies - $15,000) 17 (41) SR 4013, Foster Mills Bridge over 18 Branch of Patterson Run, Sugarcreek 19 Township, Bridge Painting 70,000 20 (Base Construction Allocation - 21 $55,000) 22 (Design and Contingencies - $15,000) 23 (42) SR 8008, Ford City Ramp from Judge 24 Graff Bridge over a ravine, Manor 25 Township, Bridge Painting 555,000 26 (Base Construction Allocation - 27 $540,000) 28 (Design and Contingencies - $15,000) 29 (43) SR 4035, Craigsville Bridge over 30 Buffalo Creek, West Franklin Township, 19970S0186B0698 - 38 -
1 Bridge Painting 140,000 2 (Base Construction Allocation - 3 $125,000) 4 (Design and Contingencies - $15,000) 5 (44) SR 0068, Kaylor Overpass, Railroad 6 over PA 68, Bradys Bend Township, 7 Bridge Removal 560,000 8 (Base Construction Allocation - 9 $500,000) 10 (Land Allocation - $10,000) 11 (Design and Contingencies - $50,000) 12 (45) SR 0068, B&LE Railroad Overpass, 13 Bradys Bend Township, Bridge Removal 55,000 14 (Base Construction Allocation - 15 $50,000) 16 (Design and Contingencies - $5,000) 17 Section 8. Beaver County. 18 (a) Local Bridges 19 (1) Ambridge and Aliquippa Boroughs, 20 Ambridge - Aliquippa Bridge over Ohio 21 River, Bridge Construction 38,000,000 22 (Base Construction Allocation - 23 $30,000,000) 24 (Land Allocation - $4,000,000) 25 (Design and Contingencies - $4,000,000) 26 (2) Vanport Township, Vanport Bridge No.6 27 over Two Mile Run, Bridge Replacement 465,000 28 (Base Construction Allocation - 29 $375,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 39 -
1 (Design and Contingencies - $80,000) 2 (3) Vanport Township, Vanport Bridge No.7 3 over Two Mile Run, Bridge Replacement 470,000 4 (Base Construction Allocation - 5 $380,000) 6 (Land Allocation - $10,000) 7 (Design and Contingencies - $80,000) 8 (4) Vanport Township, Vanport Bridge No.8 9 over Two Mile Run, Bridge Replacement 510,000 10 (Base Construction Allocation - 11 $420,000) 12 (Land Allocation - $10,000) 13 (Design and Contingencies - $80,000) 14 (5) Vanport Township, Vanport Bridge No.9 15 over Two Mile Run, Bridge Replacement 440,000 16 (Base Construction Allocation - 17 $350,000) 18 (Land Allocation - $10,000) 19 (Design and Contingencies - $80,000) 20 (6) BOROUGH OF NEW GALILEE, WASHINGTON <-- 21 STREET BRIDGE OVER JORDAN RUN, BRIDGE 22 REPLACEMENT 1,000,000 23 (b) State Bridges 24 (1) SR 0051, Bridge over New York Avenue, 25 Ramp A, Rochester Borough, Bridge Deck 26 Replacement 5,600,000 27 (Base Construction Allocation - 28 $5,500,000) 29 (Design and Contingencies - $100,000) 30 (2) SR 0351, 5th Street, Koppel-Ellwood 19970S0186B0698 - 40 -
1 Bridge over Beaver River, Koppel 2 Borough and North Sewickley Township, 3 Bridge Replacement, Phase I 33,500,000 4 (Base Construction Allocation - 5 $30,000,000) 6 (Land Allocation - $1,000,000) 7 (Design and Contingencies - $2,500,000) 8 (3) SR 1014, Wise's Grove Road Bridge over 9 Brush Creek, Marion Township, Bridge 10 Rehabilitation 750,000 11 (Base Construction Allocation - 12 $600,000) 13 (Land Allocation - $50,000) 14 (Design and Contingencies - $100,000) 15 (4) SR 1022, 13th Street Bridge over 16 Blockhouse Run at Pulaski County Line, 17 New Brighton Borough, Bridge 18 Replacement 780,000 19 (Base Construction Allocation - 20 $480,000) 21 (Land Allocation - $50,000) 22 (Design and Contingencies - $250,000) 23 (5) SR 4032, Engle Road Bridge over Six 24 Mile Run Creek, Industry Borough, 25 Bridge Replacement 350,000 26 (Base Construction Allocation - 27 $200,000) 28 (Land Allocation - $50,000) 29 (Design and Contingencies - $100,000) 30 (6) SR 4033, Wildwood Road Bridge over 19970S0186B0698 - 41 -
1 Brady's Run, Patterson Township, Bridge 2 Replacement 400,000 3 (Base Construction Allocation - 4 $250,000) 5 (Land Allocation - $50,000) 6 (Design and Contingencies - $100,000) 7 (7) SR 8035, Ramp A at LR 641 over Slope, 8 Rochester Borough, Bridge 9 Rehabilitation 1,200,000 10 (Base Construction Allocation - 11 $1,000,000) 12 (Land Allocation - $50,000) 13 (Design and Contingencies - $150,000) 14 (8) SR 8037, Ramp F over TR 51 and TR 65 15 Northbound, Rochester Borough, Bridge 16 Replacement 550,000 17 (Base Construction Allocation - 18 $400,000) 19 (Land Allocation - $50,000) 20 (Design and Contingencies - $100,000) 21 (9) SR 8039, Ramp AD, SR 0168 over TR 51, 22 Bridgewater Borough, Bridge 23 Rehabilitation 700,000 24 (Base Construction Allocation - 25 $550,000) 26 (Land Allocation - $50,000) 27 (Design and Contingencies - $100,000) 28 (10) SR 3018, Culvert-pipe Style Bridge 29 over Moody's Run, Greene Township, 30 Bridge Construction 385,000 19970S0186B0698 - 42 -
1 (Base Construction Allocation - 2 $350,000) 3 (Design and Contingencies - $35,000) 4 (11) SR 0051, Pennsylvania Avenue Bridge 5 over Brady's Run Creek, Fallston 6 Borough, Bridge Replacement 757,000 7 (Base Construction Allocation - 8 $637,000) 9 (Land Allocation - $20,000) 10 (Design and Contingencies - $100,000) 11 (12) SR 0060, Beaver Valley Extension 12 Southbound Bridge over T-535, Brighton 13 Township, Bridge Rehabilitation 167,000 14 (Base Construction Allocation - 15 $153,000) 16 (Design and Contingencies - $14,000) 17 (13) SR 0060, Beaver Valley Extension 18 Northbound Bridge over T-535, Brighton 19 Township, Bridge Rehabilitation 178,000 20 (Base Construction Allocation - 21 $163,000) 22 (Design and Contingencies - $15,000) 23 (14) SR 0060, Beaver Valley Expansion 24 Bridge over SR 0151, Hopewell Township, 25 Bridge Deck Replacement 1,125,000 26 (Base Construction Allocation - 27 $1,000,000) 28 (Design and Contingencies - $125,000) 29 (15) SR 0588, Riverview Road Bridge over 30 Pine Run, Marion Township, Bridge 19970S0186B0698 - 43 -
1 Replacement 250,000 2 (Base Construction Allocation - 3 $150,000) 4 (Design and Contingencies - $100,000) 5 (16) SR 1009, Hartzel Road Bridge over 6 Connoquenessing Creek, Marion Township, 7 Bridge Replacement 1,150,000 8 (Base Construction Allocation - 9 $1,000,000) 10 (Land Allocation - $50,000) 11 (Design and Contingencies - $100,000) 12 (17) SR 1016, Tatko Road Bridge over Brush 13 Creek, New Sewickley Township, Bridge 14 Replacement 420,000 15 (Base Construction Allocation - 16 $300,000) 17 (Land Allocation - $20,000) 18 (Design and Contingencies - $100,000) 19 (18) SR 1032, New York Avenue Bridge over 20 Conrail, SR 1032 and Local Street, 21 Rochester Borough, Bridge 22 Rehabilitation 3,100,000 23 (Base Construction Allocation - 24 $3,000,000) 25 (Design and Contingencies - $100,000) 26 (19) SR 4035, Sebring Road Bridge over SR 27 0060, Brighton Township, Bridge 28 Rehabilitation 394,000 29 (Base Construction Allocation - 30 $361,000) 19970S0186B0698 - 44 -
1 (Design and Contingencies - $33,000) 2 (20) SR 3032, Kendal Harshavile Road 3 Bridge over Branch of Traverse Creek, 4 Hanover Township, Bridge Replacement 250,000 5 (Base Construction Allocation - 6 $100,000) 7 (Land Allocation - $50,000) 8 (Design and Contingencies - $100,000) 9 Section 9. Bedford County. 10 (a) Local Bridges 11 (1) Broad Top Township, T-550, Mosquito 12 Bridge over Six Mile Run, Bridge 13 Replacement 505,000 14 (Base Construction Allocation - 15 $400,000) 16 (Land Allocation - $10,000) 17 (Design and Contingencies - $95,000) 18 (2) Broad Top Township, T-553, Langdondale 19 Bridge over Sandy Run, Bridge 20 Replacement 395,000 21 (Base Construction Allocation - 22 $300,000) 23 (Land Allocation - $10,000) 24 (Design and Contingencies - $85,000) 25 (3) Broad Top Township, T-583, Longs Run 26 Bridge over Longs Run, Bridge 27 Replacement 395,000 28 (Base Construction Allocation - 29 $300,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 45 -
1 (Design and Contingencies - $85,000) 2 (4) Harrison Township, T-418, Turner 3 Covered Bridge over Juniata River, 4 Bridge Rehabilitation 825,000 5 (Base Construction Allocation - 6 $700,000) 7 (Land Allocation - $25,000) 8 (Design and Contingencies - $100,000) 9 (5) Monroe Township, T-354, Sideling Hill 10 over East Branch Sideling Hill Creek, 11 Bridge Replacement 335,000 12 (Base Construction Allocation - 13 $250,000) 14 (Land Allocation - $10,000) 15 (Design and Contingencies - $75,000) 16 (6) South Woodbury Township, T-705 over 17 Three Springs Run, Bridge Replacement 450,000 18 (Base Construction Allocation - 19 $325,000) 20 (Land Allocation - $50,000) 21 (Design and Contingencies - $75,000) 22 (7) West St. Clair Township, T-565 over 23 Dunning Creek, Bridge Replacement 550,000 24 (Base Construction Allocation - 25 $450,000) 26 (Land Allocation - $25,000) 27 (Design and Contingencies - $75,000) 28 (8) Londonderry Township, T-653 over Wills 29 Creek, Bridge Replacement 945,000 30 (Base Construction Allocation - 19970S0186B0698 - 46 -
1 $850,000) 2 (Land Allocation - $20,000) 3 (Design and Contingencies - $75,000) 4 (9) East Providence Township, T-419 over 5 Brush Creek, Bridge Replacement 1,170,000 6 (Base Construction Allocation - 7 $1,000,000) 8 (Land Allocation - $20,000) 9 (Design and Contingencies - $150,000) 10 (10) Broadtop Township, T-677, Riddlesburg 11 Bridge, County Bridge No.35 over Six 12 Mile Run, Bridge Replacement 190,000 13 (Base Construction Allocation - 14 $150,000) 15 (Land Allocation - $5,000) 16 Design and Contingencies - $35,000) 17 (b) State Bridges 18 (1) SR 0220, US 220, Northbound Bridge 19 over Pennsylvania Turnpike, Bedford 20 Township, Bridge Painting 180,000 21 (Base Construction Allocation - 22 $150,000) 23 (Design and Contingencies - $30,000) 24 (2) SR 0220, US 220, Southbound Bridge 25 over Pennsylvania Turnpike, Bedford 26 Township, Bridge Painting 170,000 27 (Base Construction Allocation - 28 $140,000) 29 (Design and Contingencies - $30,000) 30 Section 10. Berks County. 19970S0186B0698 - 47 -
1 (a) Local Bridges 2 (1) City of Reading, Fritz Island Bridge 3 over Angelica Creek, Bridge 4 Rehabilitation 23,000 5 (Base Construction Allocation - 6 $20,000) 7 (Design and Contingencies - $3,000) 8 (2) City of Reading, Bernadine Street over 9 Angelica Creek, Bridge Rehabilitation 175,000 10 (Base Construction Allocation - 11 $145,000) 12 (Design and Contingencies - $30,000) 13 (3) City of Reading, Tulpehocken Street 14 Footbridge, Bridge Rehabilitation 6,000 15 (Base Construction Allocation - $5,000) 16 (Design and Contingencies - $1,000) 17 (4) West Reading Borough, Museum Road over 18 Wyomissing Creek, Bridge 19 Rehabilitation 15,000 20 (Base Construction Allocation - 21 $12,000) 22 (Design and Contingencies - $3,000) 23 (5) Amity Township, Lake Drive over 24 Tributary of Schuylkill River, Bridge 25 Rehabilitation 86,000 26 (Base Construction Allocation - 27 $75,000) 28 (Design and Contingencies - $11,000) 29 (6) Amity Township, Browns Mill Road over 30 Spring Creek, Bridge Rehabilitation 6,000 19970S0186B0698 - 48 -
1 (Base Construction Allocation - $5,000) 2 (Design and Contingencies - $1,000) 3 (7) Amity Township, Valley Road over 4 Spring Creek, Bridge Rehabilitation 10,000 5 (Base Construction Allocation - $8,000) 6 (Design and Contingencies - $2,000) 7 (8) Amity Township, Monocacy Road over 8 Monocacy Creek, Bridge Rehabilitation 11,000 9 (Base Construction Allocation - $9,000) 10 (Design and Contingencies - $2,000) 11 (9) Bethel Township, T-492 over Little 12 Swatara Creek, Bridge Replacement 700,000 13 (Base Construction Allocation - 14 $500,000) 15 (Land Allocation - $50,000) 16 (Design and Contingencies - $150,000) 17 (10) Bethel Township, T-682 over Crosskill 18 Creek, Bridge Replacement 750,000 19 (Base Construction Allocation - 20 $550,000) 21 (Land Allocation - $50,000) 22 (Design and Contingencies - $150,000) 23 (11) Lenhartsville Borough, Penn Avenue 24 over Maiden Creek, Bridge Replacement 960,000 25 (Base Construction Allocation - 26 $750,000) 27 (Land Allocation - $10,000) 28 (Design and Contingencies - $200,000) 29 (12) Mohnton Borough, Main Street over 30 Wyomissing Creek, Bridge Replacement 750,000 19970S0186B0698 - 49 -
1 (Base Construction Allocation - 2 $550,000) 3 (Land Allocation - $50,000) 4 (Design and Contingencies - $150,000) 5 (13) Muhlenberg Township, Hain Avenue over 6 Laurel Run, Bridge Rehabilitation 100,000 7 (Base Construction Allocation - 8 $80,000) 9 (Design and Contingencies - $20,000) 10 (14) Oley Township, T-500 over Furnace 11 Creek, Bridge Replacement 700,000 12 (Base Construction Allocation - 13 $500,000) 14 (Land Allocation - $50,000) 15 (Design and Contingencies - $150,000) 16 (15) Robesonia Borough, Freeman Street 17 over Furnace Creek, Bridge Replacement 700,000 18 (Base Construction Allocation - 19 $500,000) 20 (Land Allocation - $50,000) 21 (Design and Contingencies - $150,000) 22 (16) Washington Township, T-884 over Swamp 23 Creek, Bridge Replacement 700,000 24 (Base Construction Allocation - 25 $500,000) 26 (Land Allocation - $50,000) 27 (Design and Contingencies - $150,000) 28 (17) Upper Bern Township, Mill Hill Road, 29 T-712 over Mill Creek, Bridge 30 Replacement 70,000 19970S0186B0698 - 50 -
1 (Base Construction Allocation - 2 $40,000) 3 (Land Allocation - $10,000) 4 (Design and Contingencies - $20,000) 5 (18) North Heidelberg Township, T-501, 6 Milestone Road Bridge over Tributary of 7 Spring Creek, Bridge Replacement 94,000 8 (Base Construction Allocation - 9 $82,000) 10 (Land Allocation - $4,000) 11 (Design and Contingencies - $8,000) 12 (19) Robeson Township, T-366, Bridge over 13 Allegheny Creek, Bridge Replacement 133,000 14 (Base Construction Allocation - 15 $117,000) 16 (Land Allocation - $5,000) 17 (Design and Contingencies - $11,000) 18 (b) State Bridges 19 (1) SR 0010, Reading Road over Tributary 20 of Conestoga Creek, Caernarvon 21 Township, Bridge Rehabilitation 775,000 22 (Base Construction Allocation - 23 $490,000) 24 (Land Allocation - $100,000) 25 (Design and Contingencies - $185,000) 26 (2) SR 0222, SR 0222 Northbound over SR 27 0737 Exit, Maxatawny Township, Bridge 28 Painting 45,000 29 (Base Construction Allocation - 30 $45,000) 19970S0186B0698 - 51 -
1 (3) SR 0222, North Elm Street over SR 2 0222, Kutztown Borough, Bridge 3 Painting 45,000 4 (Base Construction Allocation - 5 $45,000) 6 (4) SR 0222, SR 0222 Northbound over SR 7 8015, Ramp G, Maxatawny Township, 8 Bridge Painting 45,000 9 (Base Construction Allocation - 10 $45,000) 11 (5) SR 0222, SR 0222 Southbound over SR 12 8015, Ramp G, Maxatawny Township, 13 Bridge Painting 45,000 14 (Base Construction Allocation - 15 $45,000) 16 (6) SR 2038, Grist Mill Road over 17 Ironstone Creek, Douglass Township, 18 Bridge Replacement 405,000 19 (Base Construction Allocation - 20 $235,000) 21 (Land Allocation - $70,000) 22 (Design and Contingencies - $100,000) 23 (7) SR 0073, Bridge over Railroad, Maiden 24 Creek Township, Bridge Rehabilitation 14,000 25 (Base Construction Allocation - 26 $12,000) 27 (Design and Contingencies - $2,000) 28 (8) SR 2014, Spring Street Subway, City of 29 Reading, Bridge Rehabilitation 18,000 30 (Base Construction Allocation - 19970S0186B0698 - 52 -
1 $15,000) 2 (Design and Contingencies - $3,000) 3 (9) SR 0073, SR 0073 over Manatawny Creek, 4 Oley Township, Bridge Rehabilitation 500,000 5 (Base Construction Allocation - 6 $450,000) 7 (Design and Contingencies - $50,000) 8 (10) SR 0061, SR 0061 over Blue Mountain 9 Railroad, Borough of Hamburg, Bridge 10 Rehabilitation 200,000 11 (Base Construction Allocation - 12 $175,000) 13 (Design and Contingencies - $25,000) 14 (11) SR 0078, SR 0078 over SR 1024, 15 Greenwich Township, Bridge 16 Rehabilitation 500,000 17 (Base Construction Allocation - 18 $450,000) 19 (Design and Contingencies - $50,000) 20 (12) SR 0078, SR 0078 over T-808, Windsor 21 Township, Bridge Rehabilitation 500,000 22 (Base Construction Allocation - 23 $450,000) 24 (Design and Contingencies - $50,000) 25 (13) SR 0078, SR 0078 over Fifth Street, 26 Borough of Hamburg, Bridge 27 Rehabilitation 200,000 28 (Base Construction Allocation - 29 $175,000) 30 (Design and Contingencies - $25,000) 19970S0186B0698 - 53 -
1 (14) SR 0078, SR 0078 over T-688, Bethel 2 Township, Bridge Rehabilitation 250,000 3 (Base Construction Allocation - 4 $225,000) 5 (Design and Contingencies - $25,000) 6 (15) SR 0176, SR 0176 over T-568, Robeson 7 Township, Bridge Rehabilitation 250,000 8 (Base Construction Allocation - 9 $200,000) 10 (Design and Contingencies - $50,000) 11 (16) SR 0176, SR 0176 2/10 mile south of 12 SR 0422, Cumru Township, Bridge 13 Rehabilitation 350,000 14 (Base Construction Allocation - 15 $300,000) 16 (Design and Contingencies - $50,000) 17 (17) SR 1083, SR 0183 over Little 18 Northkill Creek, Jefferson Township, 19 Bridge Replacement 1,000,000 20 (Base Construction Allocation - 21 $750,000) 22 (Land Allocation - $100,000) 23 (Design and Contingencies - $150,000) 24 (18) SR 0222, SR 0222 over Abandoned 25 Railroad, City of Reading, Bridge 26 Rehabilitation 200,000 27 (Base Construction Allocation - 28 $150,000) 29 (Design and Contingencies - $50,000) 30 (19) SR 0422, SR 0422 over Tulpehocken 19970S0186B0698 - 54 -
1 Creek, Borough of Womelsdorf, Bridge 2 Rehabilitation 200,000 3 (Base Construction Allocation - 4 $150,000) 5 (Design and Contingencies - $50,000) 6 (20) SR 0568, SR 0568 over Allegheny 7 Creek, Robeson Township, Bridge 8 Rehabilitation 100,000 9 (Base Construction Allocation - 10 $80,000) 11 (Design and Contingencies - $20,000) 12 (21) SR 0737, SR 0737 2.63 miles north of 13 Kutztown, Greenwich Township, Bridge 14 Rehabilitation 500,000 15 (Base Construction Allocation - 16 $450,000) 17 (Design and Contingencies - $50,000) 18 (22) SR 0737, SR 0737 2.82 miles north of 19 Kutztown, Greenwich Township, Bridge 20 Rehabilitation 500,000 21 (Base Construction Allocation - 22 $450,000) 23 (Design and Contingencies - $50,000) 24 (23) SR 2025, SR 2025 1/2 mile east of SR 25 0422, Amity Township, Bridge 26 Replacement 300,000 27 (Base Construction Allocation - 28 $200,000) 29 (Land Allocation - $15,000) 30 (Design and Contingencies - $85,000) 19970S0186B0698 - 55 -
1 (24) SR 2031, SR 2031 over Hay Creek, 2 Robeson Township, Bridge 3 Rehabilitation 500,000 4 (Base Construction Allocation - 5 $450,000) 6 (Design and Contingencies - $50,000) 7 (25) SR 2032, SR 2032 over Tributary of 8 Swamp Creek, Washington Township, 9 Bridge Replacement 500,000 10 (Base Construction Allocation - 11 $375,000) 12 (Land Allocation - $25,000) 13 (Design and Contingencies - $100,000) 14 (26) SR 2039, SR 2039 over SR 0422, Exeter 15 Township, Bridge Replacement 2,750,000 16 (Base Construction Allocation - 17 $2,000,000) 18 (Land Allocation - $250,000) 19 (Design and Contingencies - $500,000) 20 (27) SR 2041, SR 2041 2 miles west of 21 Weavertown, Amity Township, Bridge 22 Replacement 200,000 23 (Base Construction Allocation - 24 $125,000) 25 (Land Allocation - $15,000) 26 (Design and Contingencies - $60,000) 27 (28) SR 2057, SR 2057 over Leaf Creek, 28 Amity Township, Bridge Replacement 600,000 29 (Base Construction Allocation - 30 $425,000) 19970S0186B0698 - 56 -
1 (Land Allocation - $25,000) 2 (Design and Contingencies - $150,000) 3 (29) SR 3003, SR 3003 over Angelica Creek, 4 Cumru Township, Bridge Replacement 200,000 5 (Base Construction Allocation - 6 $125,000) 7 (Land Allocation - $15,000) 8 (Design and Contingencies - $60,000) 9 (30) SR 4026, SR 4026 over Irish Creek, 10 Borough of Centerport, Bridge 11 Rehabilitation 250,000 12 (Base Construction Allocation - 13 $225,000) 14 (Design and Contingencies - $25,000) 15 (31) SR 0073, Bridge over Maiden Creek, 16 Ontelaunee Township, Bridge 17 Replacement 2,120,000 18 (Base Construction Allocation - 19 $2,000,000) 20 (Land Allocation - $20,000) 21 (Design and Contingencies - $100,000) 22 (32) SR 2021, Mineral Spring Road, 23 Lindbergh Viaduct, City of Reading, 24 Bridge Rehabilitation 4,000,000 25 Section 11. Blair County. 26 (a) Local Bridges 27 (1) Antis Township, T-490, Becker Road 28 Bridge over Tributary of Little Juniata 29 River, Bridge Replacement 310,000 30 (Base Construction Allocation - 19970S0186B0698 - 57 -
1 $250,000) 2 (Land Allocation - $10,000) 3 (Design and Contingencies - $50,000) 4 (2) Taylor Township, T-332, Halter Creek 5 Bridge over Halter Creek, Bridge 6 Replacement 395,000 7 (Base Construction Allocation - 8 $300,000) 9 (Land Allocation - $10,000) 10 (Design and Contingencies - $85,000) 11 (3) Greenfield Township, T-531 over South 12 Poplar Run, Construct new bridge 280,000 13 (Base Construction Allocation - 14 $200,000) 15 (Land Allocation - $20,000) 16 (Design and Contingencies - $60,000) 17 (4) Greenfield Township, T-531 over Big 18 Lick Branch of South Poplar Run, Bridge 19 Replacement 565,000 20 (Base Construction Allocation - 21 $465,000) 22 (Land Allocation - $30,000) 23 (Design and Contingencies - $70,000) 24 (5) Greenfield Township, County Road 101 25 over Polecat Run, Bridge Replacement 520,000 26 (Base Construction Allocation - 27 $400,000) 28 (Land Allocation - $20,000) 29 (Design and Contingencies - $100,000) 30 (6) Newry Borough, Allegheny Street over 19970S0186B0698 - 58 -
1 Tributary of Poplar Run, Bridge 2 Rehabilitation 425,000 3 (Base Construction Allocation - 4 $350,000) 5 (Land Allocation - $25,000) 6 (Design and Contingencies - $50,000) 7 (7) Allegheny Township, Ellenberger Road, 8 Quarry Bridge over Mill Run Creek, 9 Bridge Replacement 319,000 10 (Base Construction Allocation - 11 $277,000) 12 (Design and Contingencies - $42,000) 13 (b) State bridges 14 (1) SR 0022, Canal Park Bridges over the 15 Juniata River, Hollidaysburg Borough, 16 Bridge Replacement 3,000,000 17 (Base Construction Allocation - 18 $2,000,000) 19 (Land Allocation - $650,000) 20 (Design and Contingencies - $350,000) 21 (2) SR 4008, SR 4008 over Tributary of 22 Glenwhite Run, Logan Township, Bridge 23 Replacement 240,000 24 (Base Construction Allocation - 25 $200,000) 26 (Land Allocation - $5,000) 27 (Design and Contingencies - $35,000) 28 Section 12. Bradford County. 29 (a) Local Bridges 30 (1) Burlington Township, T-547 over Wallis 19970S0186B0698 - 59 -
1 Run, Bridge Replacement 395,000 2 (Base Construction Allocation - 3 $310,000) 4 (Land Allocation - $10,000) 5 (Design and Contingencies - $75,000) 6 (2) Pike Township, T-790 over Gaylord 7 Creek and South Creek, Bridge 8 Replacement 495,000 9 (Base Construction Allocation - 10 $410,000) 11 (Land Allocation - $10,000) 12 (Design and Contingencies - $75,000) 13 (3) Canton Township, T-889, County Bridge 14 No.45 over Towanda Creek, Bridge 15 Replacement 480,000 16 (Base Construction Allocation - 17 $400,000) 18 (Land Allocation - $25,000) 19 (Design and Contingencies - $55,000) 20 (4) Tuscarora Township, T-874, County 21 Bridge No.36 over Fargo Creek, Bridge 22 Replacement 265,000 23 (Base Construction Allocation - 24 $215,000) 25 (Land Allocation - $15,000) 26 (Design and Contingencies - $35,000) 27 (5) Franklin Township, T-358, County 28 Bridge No.12 over Towanda Creek, Bridge 29 Replacement 1,020,000 30 (Base Construction Allocation - 19970S0186B0698 - 60 -
1 $850,000) 2 (Land Allocation - $50,000) 3 (Design and Contingencies - $120,000) 4 (6) Litchfield Township, T-900, Parks 5 Creek Structure Bridge over Parks 6 Creek, Bridge Replacement 390,000 7 (Base Construction Allocation - 8 $220,000) 9 (Land Allocation - $20,000) 10 (Design and Contingencies - $150,000) 11 (7) Albany Township, T-377, Bridge over 12 Bowman Creek 390,000 13 (Base Construction Allocation - 14 $250,000) 15 (Land Allocation - $10,000) 16 (Design and Contingencies - $130,000) 17 (8) TOWANDA TOWNSHIP, T-545, BRIDGE OVER <-- 18 SUGAR CREEK, BRIDGE REPLACEMENT 1,247,000 19 (BASE CONSTRUCTION ALLOCATION - 20 $1,033,000) 21 (LAND ALLOCATION - $65,000) 22 (DESIGN AND CONTINGENCIES - $149,000) 23 (9) WELLS TOWNSHIP, T-763, BRIDGE OVER 24 SEELY CREEK, BRIDGE REPLACEMENT 428,000 25 (BASE CONSTRUCTION ALLOCATION - 26 $355,000) 27 (LAND ALLOCATION - $22,000) 28 (DESIGN AND CONTINGENCIES - $51,000) 29 (10) TERRY TOWNSHIP, T-420, BRIDGE OVER 30 FOSTER BRANCH OF SUGAR CREEK, BRIDGE 19970S0186B0698 - 61 -
1 REPLACEMENT 663,000 2 (BASE CONSTRUCTION ALLOCATION - 3 $550,000) 4 (LAND ALLOCATION - $33,000) 5 (DESIGN AND CONTINGENCIES - $80,000) 6 (b) State Bridges 7 (1) SR 0006, North Bridge over Sugar 8 Creek, South of Longs Pond Road, Bridge 9 Replacement 1,139,000 10 (Base Construction Allocation - 11 $911,000) 12 (Land Allocation - $57,000) 13 (Design and Contingencies - $171,000) 14 (2) SR 0409, Billing Creek Bridge, Village 15 of Camptown, Bridge Replacement 318,000 16 (Base Construction Allocation - 17 $254,000) 18 (Land Allocation - $16,000) 19 (Design and Contingencies - $48,000) 20 (3) SR 3029, Towanda Creek Bridges between 21 T-327 and T-326 on Gulf Road, Village 22 of Granville Center, Bridge 23 Replacement 593,000 24 (Base Construction Allocation - 25 $474,000) 26 (Land Allocation - $30,000) 27 (Design and Contingencies - $89,000) 28 (4) SR 4008, Bridge over Tributary of 29 Sugar Creek, Columbia Township, Bridge 30 Replacement 298,000 19970S0186B0698 - 62 -
1 (Base Construction Allocation -
2 $238,000)
3 (Land Allocation - $15,000)
4 (Design and Contingencies - $45,000)
5 (5) SR 0414, Bridge over Towanda Creek,
6 Bradford Borough, Bridge Painting 195,000
7 (Base Construction Allocation -
8 $185,000)
9 (Design and Contingencies - $10,000)
10 (6) US 6, US 6 over Sugar Creek, Sylvania
11 Borough, Bridge Replacement 633,000
12 (Base Construction Allocation -
13 $506,000)
14 (Land Allocation - $32,000)
15 (Design and Contingencies - $95,000)
16 (7) SR 0014, SR 0014 over Tributary of
17 Sugar Creek, Troy Township, Bridge
18 Replacement 410,000
19 (Base Construction Allocation -
20 $280,000)
21 (Land Allocation - $30,000)
22 (Design and Contingencies - $100,000)
23 (8) SR 0187, SR 0187 over Wappensing <--
24 WAPPASENING Creek, Windham Township, <--
25 Bridge Replacement 2,000,000
26 (Base Construction Allocation -
27 $1,600,000)
28 (Land Allocation - $100,000)
29 (Design and Contingencies - $300,000)
30 (9) SR 0414, SR 0414 over Tributary of
19970S0186B0698 - 63 -
1 Towanda Creek, Canton Township, Bridge 2 Replacement 320,000 3 (Base Construction Allocation - 4 $256,000) 5 (Land Allocation - $16,000) 6 (Design and Contingencies - $48,000) 7 (10) SR 0467, SR 0467 over Johnsons Creek, 8 Orwell Township, Bridge Replacement 751,000 9 (Base Construction Allocation - 10 $601,000) 11 (Land Allocation - $37,000) 12 (Design and Contingencies - $113,000) 13 (11) SR 0514, SR 0514 over North Branch of 14 Towanda Creek, Granville Township, 15 Bridge Replacement 638,000 16 (Base Construction Allocation - 17 $510,000) 18 (Land Allocation - $32,000) 19 (Design and Contingencies - $96,000) 20 (12) SR 1022, Ulster Bridge, Ulster 21 Township, Bridge Painting 6,299,000 22 (Base Construction Allocation - 23 $5,039,000) 24 (Land Allocation - $315,000) 25 (Design and Contingencies - $945,000) 26 (13) SR 1026, SR 1026 over Wyalusing 27 Creek, Pike Township, Bridge 28 Replacement 650,000 29 (Base Construction Allocation - 30 $520,000) 19970S0186B0698 - 64 -
1 (Land Allocation - $30,000) 2 (Design and Contingencies - $100,000) 3 (14) SR 1049, SR 1049 over Tributary of 4 Pendleton Creek, Warren Township, 5 Bridge Replacement 340,000 6 (Base Construction Allocation - 7 $270,000) 8 (Land Allocation - $15,000) 9 (Design and Contingencies - $55,000) 10 (15) SR 1055, SR 1055 over Parks Creek, 11 Rome Township, Bridge Replacement 315,000 12 (Base Construction Allocation - 13 $250,000) 14 (Land Allocation - $15,000) 15 (Design and Contingencies - $50,000) 16 (16) SR 2018, SR 2018 over Tributary of 17 Susquehanna River, Asylum Township, 18 Bridge Replacement 260,000 19 (Base Construction Allocation - 20 $208,000) 21 (Land Allocation - $39,000) 22 (Design and Contingencies - $13,000) 23 (17) SR 3005, SR 3005 over Towanda Creek, 24 Canton Township, Bridge Replacement 666,000 25 (Base Construction Allocation - 26 $533,000) 27 (Land Allocation - $33,000) 28 (Design and Contingencies - $100,000) 29 (18) SR 3029, SR 3029 over Mud Creek, Troy 30 Township, Bridge Replacement 457,000 19970S0186B0698 - 65 -
1 (Base Construction Allocation - 2 $366,000) 3 (Land Allocation - $23,000) 4 (Design and Contingencies - $68,000) 5 (19) SR 4002, SR 4002 over Browns Creek, 6 Burlington Township, Bridge 7 Replacement 561,000 8 (Base Construction Allocation - 9 $449,000) 10 (Land Allocation - $28,000) 11 (Design and Contingencies - $84,000) 12 (20) SR 4013, SR 4013 over Justice Run, 13 Ridgebury Township, Bridge Replacement 351,000 14 (Base Construction Allocation - 15 $281,000) 16 (Land Allocation - $18,000) 17 (Design and Contingencies - $52,000) 18 (21) SR 4014, SR 4014 over Branch of 19 Tomjack Creek, Smithfield Township, 20 Bridge Replacement 360,000 21 (Base Construction Allocation - 22 $288,000) 23 (Land Allocation - $18,000) 24 (Design and Contingencies - $54,000) 25 (22) SR 4015, SR 4015 over Mill Creek, 26 Springfield Township, Bridge 27 Replacement 390,000 28 (Base Construction Allocation - 29 $312,000) 30 (Land Allocation - $20,000) 19970S0186B0698 - 66 -
1 (Design and Contingencies - $58,000) 2 (23) SR 4031, SR 4031 over Tributary of 3 Beckwith Creek, Wells Township, Bridge 4 Replacement 243,000 5 (Base Construction Allocation - 6 $196,000) 7 (Land Allocation - $10,000) 8 (Design and Contingencies - $37,000) 9 (24) SR 2024, Bridge over Towanda Creek, 10 Towanda Township, Bridge Replacement 1,740,000 11 (Base Construction Allocation - 12 $1,400,000) 13 (Land Allocation - $40,000) 14 (Design and Contingencies - $300,000) 15 (25) SR 4015, Bridge over Mill Creek, 16 Springfield Township, Bridge 17 Replacement 740,000 18 (Base Construction Allocation - 19 $600,000) 20 (Land Allocation - $20,000) 21 (Design and Contingencies - $120,000) 22 (26) PA 514, Bridge over North Branch of 23 Towanda Creek, Granville Township, 24 Bridge Replacement 630,000 25 (Base Construction Allocation - 26 $500,000) 27 (Land Allocation - $30,000) 28 (Design and Contingencies - $100,000) 29 (27) US 6, Bridge over Sugar Creek, 30 Sylvania Borough, Bridge Replacement 680,000 19970S0186B0698 - 67 -
1 (Base Construction Allocation - 2 $550,000) 3 (Land Allocation - $30,000) 4 (Design and Contingencies - $100,000) 5 (28) PA 549, Bridge over Daggett Creek, 6 Wells Township, Bridge Replacement 1,180,000 7 (Base Construction Allocation - 8 $950,000) 9 (Land Allocation - $30,000) 10 (Design and Contingencies - $200,000) 11 (29) SR 4002, Bridge over Browns Creek, 12 Burlington Township, Bridge 13 Replacement 560,000 14 (Base Construction Allocation - 15 $450,000) 16 (Land Allocation - $30,000) 17 (Design and Contingencies - $80,000) 18 (30) SR 1026, Bridge over Wyalusing Creek, 19 Pike Township, Bridge Replacement 650,000 20 (Base Construction Allocation - 21 $520,000) 22 (Land Allocation - $30,000) 23 (Design and Contingencies - $100,000) 24 (31) PA 187, Bridge over Wappasening 25 Creek, Windham Township, Bridge 26 Replacement 2,000,000 27 (Base Construction Allocation - 28 $1,600,000) 29 (Land Allocation - $100,000) 30 (Design and Contingencies - $300,000) 19970S0186B0698 - 68 -
1 (32) PA 199, Bridge over Chemung River 2 Overflow Channel, Athens Township, 3 Bridge Replacement 2,000,000 4 (Base Construction Allocation - 5 $1,600,000) 6 (Land Allocation - $100,000) 7 (Design and Contingencies - $300,000) 8 (33) US 220, Bridge over Bridge Street, 9 Towanda Borough, Bridge Rehabilitation 385,000 10 (Base Construction Allocation - 11 $350,000) 12 (Design and Contingencies - $35,000) 13 (34) US 220, Bridge over SR 3020, Towanda 14 Township, Bridge Rehabilitation 495,000 15 (Base Construction Allocation - 16 $450,000) 17 (Design and Contingencies - $45,000) 18 (35) US 220, Bridge over SR 2036, North 19 Towanda Township, Bridge 20 Rehabilitation 715,000 21 (Base Construction Allocation - 22 $650,000) 23 (Design and Contingencies - $65,000) 24 (36) US 220, Bridge over SR 3022, North 25 Towanda Township, Bridge 26 Rehabilitation 770,000 27 (Base Construction Allocation - 28 $700,000) 29 (Design and Contingencies - $70,000) 30 (37) US 220, Bridge over US 6, North 19970S0186B0698 - 69 -
1 Towanda Township, Bridge 2 Reconstruction 1,700,000 3 (Base Construction Allocation - 4 $1,500,000) 5 (Design and Contingencies - $200,000) 6 Section 13. Bucks County. 7 (a) Local Bridges 8 (1) Springfield Township, I-479, Bridge 9 Street Bridge over Cooks Creek, Bridge 10 Replacement 500,000 11 (Base Construction Allocation - 12 $365,000) 13 (Land Allocation - $35,000) 14 (Design and Contingencies - $100,000) 15 (2) Springfield Township, T-404, Hawks 16 Mill County Bridge No.196, Shale Road 17 over Cooks Creek, Bridge 18 Rehabilitation 100,000 19 (Base Construction Allocation - 20 $90,000) 21 (Design and Contingencies - $10,000) 22 (b) State Bridges 23 (1) SR 0032, River Road at Fleecydale over 24 Paunacussing Creek, Solebury Township, 25 Bridge Replacement 1,400,000 26 (Base Construction Allocation - 27 $1,200,000) 28 (Design and Contingencies - $200,000) 29 (2) SR 2002, Otter Street Bridge over 30 Otter Creek, Bristol Borough, Bridge 19970S0186B0698 - 70 -
1 Replacement 1,150,000 2 (Base Construction Allocation - 3 $900,000) 4 (Land Allocation - $50,000) 5 (Design and Contingencies - $200,000) 6 (3) SR 2025, Bristol Road Bridge over 7 Little Neshaminy Creek, Warwick 8 Township, Bridge Replacement 1,120,000 9 (Base Construction Allocation - 10 $900,000) 11 (Land Allocation - $80,000) 12 (Design and Contingencies - $140,000) 13 (4) SR 2047, Hulmeville Avenue Bridge over 14 Conrail, Middletown, Bridge 15 Replacement 5,600,000 16 (Base Construction Allocation - 17 $4,000,000) 18 (Land Allocation - $800,000) 19 (Design and Contingencies - $800,000) 20 (5) SR 4033, Upper Ridge Road Bridge over 21 Unami Creek, Milford Township, Bridge 22 Replacement 2,000,000 23 (Base Construction Allocation - 24 $1,600,000) 25 (Land Allocation - $100,000) 26 (Design and Contingencies - $300,000) 27 (6) SR 4091, Kellers Church Road Bridge 28 over Deep Run, Bedminster, Bridge 29 Replacement 2,000,000 30 (Base Construction Allocation - 19970S0186B0698 - 71 -
1 $1,500,000) 2 (Land Allocation - $150,000) 3 (Design and Contingencies - $350,000) 4 (7) SR 0202, Doylestown Bypass (Five 5 Bridges) over SR 0611, Doylestown 6 Township, Bridge Rehabilitations 2,200,000 7 (Base Construction Allocation - 8 $2,000,000) 9 (Land Allocation - $50,000) 10 (Design and Contingencies - $150,000) 11 (8) SR 0611, Easton Road (Two Bridges) 12 over Tohickon and Deep Run Creeks, 13 Bedminister Township, Bridge 14 Replacements 1,650,000 15 (Base Construction Allocation - 16 $1,500,000) 17 (Land Allocation - $50,000) 18 (Design and Contingencies - $100,000) 19 (9) SR 2089, Almshouse Road Bridge over 20 Neshaminy Creek, Doylestown Township, 21 Bridge Replacement 1,800,000 22 (Base Construction Allocation - 23 $1,500,000) 24 (Land Allocation - $150,000) 25 (Design and Contingencies - $150,000) 26 (10) SR 0013, Bristol Pike over Otter 27 Creek, Bristol Township, Bridge 28 Replacement 1,600,000 29 (Base Construction Allocation - 30 $1,200,000) 19970S0186B0698 - 72 -
1 (Land Allocation - $100,000) 2 (Design and Contingencies - $300,000) 3 (11) SR 0413, Bridge over Mill Creek, 4 Bristol Township, Bridge Replacement 600,000 5 (Base Construction Allocation - 6 $350,000) 7 (Land Allocation - $50,000) 8 (Design and Contingencies - $200,000) 9 (12) SR 2002, State Road over Neshaminy 10 Creek, Bristol Township, Bridge 11 Replacement 3,700,000 12 (Base Construction Allocation - 13 $3,000,000) 14 (Land Allocation - $250,000) 15 (Design and Contingencies - $450,000) 16 (13) SR 0013, Bristol Pike over St. 17 Francis Creek, Bensalem Township, 18 Bridge Replacement 550,000 19 (Base Construction Allocation - 20 $400,000) 21 (Land Allocation - $50,000) 22 (Design and Contingencies - $100,000) 23 (14) SR 0013, SR 0013 over Conrail and 24 Newbold Road, Falls Township, Bridge 25 Replacement 5,000,000 26 (Base Construction Allocation - 27 $4,500,000) 28 (Land Allocation - $150,000) 29 (Design and Contingencies - $350,000) 30 (15) SR 0032, West Bridge Street over 19970S0186B0698 - 73 -
1 Tributary of Delaware River, 2 Morrisville Borough, Bridge 3 Replacement 550,000 4 (Base Construction Allocation - 5 $400,000) 6 (Land Allocation - $50,000) 7 (Design and Contingencies - $100,000) 8 (16) SR 0213, West Maple Avenue over 9 Neshaminy Creek, Middletown Township, 10 Bridge Replacement 2,000,000 11 (Base Construction Allocation - 12 $1,700,000) 13 (Land Allocation - $100,000) 14 (Design and Contingencies - $200,000) 15 (17) SR 1004, Cold Spring Creamery Road 16 over Branch of Pine Run Creek, 17 Buckingham Township, Bridge 18 Replacement 450,000 19 (Base Construction Allocation - 20 $380,000) 21 (Land Allocation - $10,000) 22 (Design and Contingencies - $60,000) 23 (18) SR 2005, Cornwells Avenue over 24 Poquessing Creek, Bensalem Township, 25 Bridge Replacement 350,000 26 (Base Construction Allocation - 27 $250,000) 28 (Land Allocation - $25,000) 29 (Design and Contingencies - $75,000) 30 (19) SR 2026, Trenton Avenue over Rock 19970S0186B0698 - 74 -
1 Run, Falls Township, Bridge 2 Replacement 700,000 3 (Base Construction Allocation - 4 $500,000) 5 (Land Allocation - $50,000) 6 (Design and Contingencies - $150,000) 7 (20) SR 2037, Lincoln Highway Eastbound 8 over Queen Anne Creek, Falls Township, 9 Bridge Replacement 700,000 10 (Base Construction Allocation - 11 $500,000) 12 (Land Allocation - $75,000) 13 (Design and Contingencies - $125,000) 14 (21) SR 2037, Lincoln Highway over Branch 15 of Queen Anne Creek, Falls Township, 16 Bridge Replacement 500,000 17 (Base Construction Allocation - 18 $350,000) 19 (Land Allocation - $50,000) 20 (Design and Contingencies - $100,000) 21 (22) SR 2047, Hulmeville Avenue over 22 Conrail, Middletown Township, Bridge 23 Replacement 1,200,000 24 (Base Construction Allocation - 25 $1,000,000) 26 (Land Allocation - $75,000) 27 (Design and Contingencies - $125,000) 28 Section 14. Butler County. 29 (a) Local Bridges 30 (1) Muddy Creek and Worth Townships, T- 19970S0186B0698 - 75 -
1 348, Muddy Creek Bridge over Muddy 2 Creek, Bridge Replacement 730,000 3 (Base Construction Allocation - 4 $550,000) 5 (Land Allocation - $15,000) 6 (Design and Contingencies - $165,000) 7 (2) Allegheny Township, T-542, Farrington 8 Bridge, Bridge Replacement 700,000 9 (Base Construction Allocation - 10 $500,000) 11 (Land Allocation - $25,000) 12 (Design and Contingencies - $175,000) 13 (3) Concord Township, T-508, Greece City 14 Bridge, Bridge Replacement 700,000 15 (Base Construction Allocation - 16 $500,000) 17 (Land Allocation - $25,000) 18 (Design and Contingencies - $175,000) 19 (4) Cranberry Township, T-326 over Brush 20 Creek, Bridge Replacement 700,000 21 (Base Construction Allocation - 22 $500,000) 23 (Land Allocation - $25,000) 24 (Design and Contingencies - $175,000) 25 (5) Cranberry Township, T-300, Bridge 26 Replacement 700,000 27 (Base Construction Allocation - 28 $500,000) 29 (Land Allocation - $25,000) 30 (Design and Contingencies - $175,000) 19970S0186B0698 - 76 -
1 (6) Jackson Township, T-323, Senn Bridge, 2 Bridge Replacement 700,000 3 (Base Construction Allocation - 4 $500,000) 5 (Land Allocation - $25,000) 6 (Design and Contingencies - $175,000) 7 (7) Jackson Township, T-325, Eidewau 8 Bridge, Bridge Replacement 700,000 9 (Base Construction Allocation - 10 $500,000) 11 (Land Allocation - $25,000) 12 (Design and Contingencies - $175,000) 13 (8) Jefferson Township, T-844 over Thorn 14 Creek, Bridge Replacement 700,000 15 (Base Construction Allocation - 16 $500,000) 17 (Land Allocation - $25,000) 18 (Design and Contingencies - $175,000) 19 (9) Mars Borough, Hook Street, Bridge 20 Replacement 700,000 21 (Base Construction Allocation - 22 $500,000) 23 (Land Allocation - $25,000) 24 (Design and Contingencies - $175,000) 25 (10) Mars Borough, Church Street, Kocher 26 Bridge, Bridge Replacement 700,000 27 (Base Construction Allocation - 28 $500,000) 29 (Land Allocation - $25,000) 30 (Design and Contingencies - $175,000) 19970S0186B0698 - 77 -
1 (11) Middlesex Township, T-380 over Glade 2 Run, Bridge Replacement 700,000 3 (Base Construction Allocation - 4 $500,000) 5 (Land Allocation - $25,000) 6 (Design and Contingencies - $175,000) 7 (12) Worth Township, T-318, Payne Bridge, 8 Bridge Replacement 700,000 9 (Base Construction Allocation - 10 $500,000) 11 (Land Allocation - $25,000) 12 (Design and Contingencies - $175,000) 13 (13) Cranberry Township, T-326 over 14 Tributary of Brush Creek, Bridge 15 Replacement 167,000 16 (Base Construction Allocation - 17 $135,000) 18 (Land Allocation - $19,000) 19 (Design and Contingencies - $13,000) 20 (b) State Bridges 21 (1) SR 0228, Houseville Bridge over B&LE 22 Railroad, Clinton Township, Bridge Deck 23 Replacement 636,000 24 (Base Construction Allocation - 25 $600,000) 26 (Design and Contingencies - $36,000) 27 (2) SR 0019, Rose Point Bridge over SR 28 0422, Muddycreek Township, Bridge 29 Painting 115,000 30 (Base Construction Allocation - 19970S0186B0698 - 78 -
1 $100,000) 2 (Design and Contingencies - $15,000) 3 (3) SR 0058, Blocks Run Bridge No.1 over 4 Blocks Run, Marion Township, Bridge 5 Painting 65,000 6 (Base Construction Allocation - 7 $50,000) 8 (Design and Contingencies - $15,000) 9 (4) SR 0058, Blocks Run Bridge No.2 over 10 Blocks Run, Venango Township, Bridge 11 Painting 60,000 12 (Base Construction Allocation - 13 $45,000) 14 (Design and Contingencies - $15,000) 15 (5) SR 0058, Murrin Run Bridge over Murrin 16 Run, Venango Township, Bridge Painting 60,000 17 (Base Construction Allocation - 18 $45,000) 19 (Design and Contingencies - $15,000) 20 (6) SR 0068, Glade Run Bridge over Glade 21 Run, Zelienople Borough, Bridge 22 Painting 70,000 23 (Base Construction Allocation - 24 $55,000) 25 (Design and Contingencies - $15,000) 26 (7) SR 0079, Muddy Creek Bridge Northbound 27 over SR 0422 and Muddy Creek, Muddy 28 Creek Township, Bridge Painting 255,000 29 (Base Construction Allocation - 30 $240,000) 19970S0186B0698 - 79 -
1 (Design and Contingencies - $15,000) 2 (8) SR 0079, Muddy Creek Bridge Southbound 3 over SR 0422 and Muddy Creek, Muddy 4 Creek Township, Bridge Painting 255,000 5 (Base Construction Allocation - 6 $240,000) 7 (Design and Contingencies - $15,000) 8 (9) SR 0108, Slippery Rock Exit Bridge 9 over I-79, Worth Township, Bridge 10 Painting 225,000 11 (Base Construction Allocation - 12 $210,000) 13 (Design and Contingencies - $15,000) 14 (10) SR 0138, Glades Wildlife Lake Bridge 15 over South Branch of Slippery Rock 16 Creek, Concord Township, Bridge 17 Painting 85,000 18 (Base Construction Allocation - 19 $70,000) 20 (Design and Contingencies - $15,000) 21 (11) SR 0258, Wolf Creek Bridge over Wolf 22 Creek, Slippery Rock Township, Bridge 23 Painting 125,000 24 (Base Construction Allocation - 25 $110,000) 26 (Design and Contingencies - $15,000) 27 (12) SR 0308, Renick Bridge over Stoney 28 Run and Railroad, Center Township, 29 Bridge Painting 405,000 30 (Base Construction Allocation - 19970S0186B0698 - 80 -
1 $390,000) 2 (Design and Contingencies - $15,000) 3 (13) SR 0422, Mount Chestnut Bridge 4 Eastbound over Little Connoquenessing 5 Creek and SR 3007, Butler Township, 6 Bridge Painting 355,000 7 (Base Construction Allocation - 8 $340,000) 9 (Design and Contingencies - $15,000) 10 (14) SR 0422, Bonnie Brook Bridge over 11 Bonnie Brook, Summit Township, Bridge 12 Painting 90,000 13 (Base Construction Allocation - 14 $75,000) 15 (Design and Contingencies - $15,000) 16 (15) SR 1004, Bruin Bridge over Bear 17 Creek, Bruin Borough, Bridge Painting 85,000 18 (Base Construction Allocation - 19 $70,000) 20 (Design and Contingencies - $15,000) 21 (16) SR 1011, Rattigan Bridge No.1 over 22 Buffalo Creek, Donegal Township, Bridge 23 Painting 55,000 24 (Base Construction Allocation - 25 $40,000) 26 (Design and Contingencies - $15,000) 27 (17) SR 1016, Eastland Drive Bridge over 28 Connoquenessing Creek, Butler Township, 29 Bridge Painting 80,000 30 (Base Construction Allocation - 19970S0186B0698 - 81 -
1 $65,000) 2 (Design and Contingencies - $15,000) 3 (18) SR 1019, Rough Run Bridge over Rough 4 Run, Windfield Township, Bridge 5 Painting 95,000 6 (Base Construction Allocation - 7 $80,000) 8 (Design and Contingencies - $15,000) 9 (19) SR 1019, Chicora Bridge over Buffalo 10 Creek, Chicora Borough, Bridge 11 Painting 70,000 12 (Base Construction Allocation - 13 $55,000) 14 (Design and Contingencies - $15,000) 15 (20) SR 1021, Rattigan Bridge No.2 over 16 Buffalo Creek, Donegal Township, Bridge 17 Painting 70,000 18 (Base Construction Allocation - 19 $55,000) 20 (Design and Contingencies - $15,000) 21 (21) SR 1025, Bonnie Brook Bridge No.1 22 over Bonnie Brook, Summit Township, 23 Bridge Painting 90,000 24 (Base Construction Allocation - 25 $75,000) 26 (Design and Contingencies - $15,000) 27 (22) SR 2004, Connoquenessing Creek Bridge 28 over Connoquenessing Creek, Butler 29 City, Bridge Painting 135,000 30 (Base Construction Allocation - 19970S0186B0698 - 82 -
1 $120,000) 2 (Design and Contingencies - $15,000) 3 (23) SR 2004, Bonnie Brook Bridge No.2 4 over Bonnie Brook, East Butler Borough, 5 Bridge Painting 90,000 6 (Base Construction Allocation - 7 $75,000) 8 (Design and Contingencies - $15,000) 9 (24) SR 2011, Lardintown Run Bridge No.1 10 over Lardintown Run, Clinton Township, 11 Bridge Painting 75,000 12 (Base Construction Allocation - 13 $60,000) 14 (Design and Contingencies - $15,000) 15 (25) SR 2011, Lardintown Run Bridge No.2 16 over Lardintown Run, Clinton Township, 17 Bridge Painting 65,000 18 (Base Construction Allocation - 19 $50,000) 20 (Design and Contingencies - $15,000) 21 (26) SR 2011, Lardintown Run Bridge No.3 22 over Lardintown Run, Clinton Township, 23 Bridge Painting 65,000 24 (Base Construction Allocation - 25 $50,000) 26 (Design and Contingencies - $15,000) 27 (27) SR 3004, McCalmont Bridge over 28 Connoquenessing Creek, Butler Township, 29 Bridge Painting 105,000 30 (Base Construction Allocation - 19970S0186B0698 - 83 -
1 $90,000) 2 (Design and Contingencies - $15,000) 3 (28) SR 3007, Reinfrew Bridge over 4 Connoquenessing Creek, Penn Township, 5 Bridge Painting 115,000 6 (Base Construction Allocation - 7 $100,000) 8 (Design and Contingencies - $15,000) 9 (29) SR 3010, Zeno Bridge over Glade Run, 10 Forward Township, Bridge Painting 105,000 11 (Base Construction Allocation - 12 $90,000) 13 (Design and Contingencies - $15,000) 14 (30) SR 3017, Kaufman Run Bridge over 15 Kaufman Run, Adams Township, Bridge 16 Painting 70,000 17 (Base Construction Allocation - 18 $55,000) 19 (Design and Contingencies - $15,000) 20 (31) SR 3017, Breakneck Creek Bridge over 21 Breakneck Creek, Adams Township, Bridge 22 Painting 105,000 23 (Base Construction Allocation - 24 $90,000) 25 (Design and Contingencies - $15,000) 26 (32) SR 3025, Little Connoquenessing Creek 27 Bridge over Little Connoquenessing 28 Creek, Lancaster Township, Bridge 29 Painting 125,000 30 (Base Construction Allocation - 19970S0186B0698 - 84 -
1 $110,000) 2 (Design and Contingencies - $15,000) 3 (33) SR 4006, Keister's Bridge over 4 Slippery Rock Creek, Slippery Rock 5 Township, Bridge Painting 105,000 6 (Base Construction Allocation - 7 $90,000) 8 (Design and Contingencies - $15,000) 9 (34) SR 4007, Lake Arthur Tributary Bridge 10 over a tributary of Lake Arthur, Worth 11 Township, Bridge Painting 50,000 12 (Base Construction Allocation - 13 $35,000) 14 (Design and Contingencies - $15,000) 15 (35) SR 4007, I-79 North Bridge No.1 over 16 I-79, Worth Township, Bridge Painting 245,000 17 (Base Construction Allocation - 18 $230,000) 19 (Design and Contingencies - $15,000) 20 (36) SR 4007, I-79 North Bridge No.2 over 21 I-79, Worth Township, Bridge Painting 215,000 22 (Base Construction Allocation - 23 $200,000) 24 (Design and Contingencies - $15,000) 25 (37) SR 4010, Bull Valley Bridge over Bull 26 Valley Creek, Washington Township, 27 Bridge Painting 65,000 28 (Base Construction Allocation - 29 $50,000) 30 (Design and Contingencies - $15,000) 19970S0186B0698 - 85 -
1 (38) SR 4012, Seaton Creek Bridge over 2 Seaton Creek, Marion Township, Bridge 3 Painting 65,000 4 (Base Construction Allocation - 5 $50,000) 6 (Design and Contingencies - $15,000) 7 (39) SR 8002, North Shore Exit Bridge over 8 Muddy Creek, Worth Township, Bridge 9 Painting 85,000 10 (Base Construction Allocation - 11 $70,000) 12 (Design and Contingencies - $15,000) 13 (40) SR 0422, Route 422 Overpass, 14 Muddycreek Township, Bridge 15 Replacement 1,450,000 16 (Base Construction Allocation - 17 $1,000,000) 18 (Land Allocation - $100,000) 19 (Design and Contingencies - $350,000) 20 (41) SR 0008, B&LE Railroad Overpass, 21 Mercer Township, Bridge Replacement 1,450,000 22 (Base Construction Allocation - 23 $1,000,000) 24 (Land Allocation - $100,000) 25 (Design and Contingencies - $350,000) 26 (42) SR 0038, B&LE Railroad Overpass, 27 Concord Township, Bridge Replacement 1,050,000 28 (Base Construction Allocation - 29 $750,000) 30 (Land Allocation - $50,000) 19970S0186B0698 - 86 -
1 (Design and Contingencies - $250,000) 2 (43) SR 2002, Conrail Railroad Overpass, 3 Summit Township, Bridge Replacement 1,050,000 4 (Base Construction Allocation - 5 $750,000) 6 (Land Allocation - $50,000) 7 (Design and Contingencies - $250,000) 8 (44) SR 2012, B&LE Railroad Overpass, 9 Jefferson Township, Bridge Replacement 1,050,000 10 (Base Construction Allocation - 11 $750,000) 12 (Land Allocation - $50,000) 13 (Design and Contingencies - $250,000) 14 (45) SR 3004, B&LE Railroad Overpass, 15 Butler Township, Bridge Replacement 595,000 16 (Base Construction Allocation - 17 $400,000) 18 (Land Allocation - $20,000) 19 (Design and Contingencies - $175,000) 20 (46) SR 0008, Bridge over Armco Private 21 Drive, Butler Township, Bridge 22 Replacement 1,450,000 23 (Base Construction Allocation - 24 $1,000,000) 25 (Land Allocation - $100,000) 26 (Design and Contingencies - $350,000) 27 (47) SR 0019, Scholars Run Bridge, Jackson 28 Township, Bridge Replacement 1,050,000 29 (Base Construction Allocation - 30 $750,000) 19970S0186B0698 - 87 -
1 (Land Allocation - $50,000) 2 (Design and Contingencies - $250,000) 3 (48) SR 0019, SR 0019 over SR 0422, 4 Muddycreek Township, Bridge 5 Replacement 1,050,000 6 (Base Construction Allocation - 7 $750,000) 8 (Land Allocation - $50,000) 9 (Design and Contingencies - $250,000) 10 (49) SR 0058, McMurray Run Bridge, Marion 11 Township, Bridge Replacement 1,050,000 12 (Base Construction Allocation - 13 $750,000) 14 (Land Allocation - $50,000) 15 (Design and Contingencies - $250,000) 16 (50) SR 0068, Sullivan Run Bridge, Butler 17 Township, Bridge Replacement 1,450,000 18 (Base Construction Allocation - 19 $1,000,000) 20 (Land Allocation - $100,000) 21 (Design and Contingencies - $350,000) 22 (51) SR 0080, I-80 over TR 540, Allegheny 23 Township, Bridge Replacement 1,450,000 24 (Base Construction Allocation - 25 $1,000,000) 26 (Land Allocation - $100,000) 27 (Design and Contingencies - $350,000) 28 (52) SR 0138, Muddy Creek Bridge, Clay 29 Township, Bridge Replacement 595,000 30 (Base Construction Allocation - 19970S0186B0698 - 88 -
1 $400,000) 2 (Land Allocation - $20,000) 3 (Design and Contingencies - $175,000) 4 (53) SR 0173, Slippery Rock Creek Bridge, 5 Slippery Rock Township, Bridge 6 Replacement 1,050,000 7 (Base Construction Allocation - 8 $750,000) 9 (Land Allocation - $50,000) 10 (Design and Contingencies - $250,000) 11 (54) SR 0079, I-79 North Bridge over Ramp, 12 Jackson Township, Bridge Replacement 1,450,000 13 (Base Construction Allocation - 14 $1,000,000) 15 (Land Allocation - $100,000) 16 (Design and Contingencies - $350,000) 17 (55) SR 0079, I-79 South Bridge over Ramp, 18 Jackson Township, Bridge Replacement 1,450,000 19 (Base Construction Allocation - 20 $1,000,000) 21 (Land Allocation - $100,000) 22 (Design and Contingencies - $350,000) 23 (56) SR 0079, I-79 over SR 0068, Jackson 24 Township, Bridge Replacement 1,450,000 25 (Base Construction Allocation - 26 $1,000,000) 27 (Land Allocation - $100,000) 28 (Design and Contingencies - $350,000) 29 (57) SR 0079, I-79 over TR 347, Lancaster 30 Township, Bridge Replacement 1,450,000 19970S0186B0698 - 89 -
1 (Base Construction Allocation - 2 $1,000,000) 3 (Land Allocation - $100,000) 4 (Design and Contingencies - $350,000) 5 (58) SR 0079, I-79 North Bridge over SR 6 0422, Worth Township, Bridge 7 Replacement 1,450,000 8 (Base Construction Allocation - 9 $1,000,000) 10 (Land Allocation - $100,000) 11 (Design and Contingencies - $350,000) 12 (59) SR 0079, I-79 South Bridge over SR 13 0422, Worth Township, Bridge 14 Replacement 1,450,000 15 (Base Construction Allocation - 16 $1,000,000) 17 (Land Allocation - $100,000) 18 (Design and Contingencies - $350,000) 19 (60) SR 0422, SR 0422 over SR 4005, 20 Muddycreek Township, Bridge 21 Replacement 1,450,000 22 (Base Construction Allocation - 23 $1,000,000) 24 (Land Allocation - $100,000) 25 (Design and Contingencies - $350,000) 26 (61) SR 0528, SR 0528 over SR 0422, 27 Franklin Township, Bridge Replacement 1,050,000 28 (Base Construction Allocation - 29 $750,000) 30 (Land Allocation - $50,000) 19970S0186B0698 - 90 -
1 (Design and Contingencies - $250,000) 2 (62) SR 1010, Bear Creek Bridge, Fairview 3 Township, Bridge Replacement 1,050,000 4 (Base Construction Allocation - 5 $750,000) 6 (Land Allocation - $50,000) 7 (Design and Contingencies - $250,000) 8 (63) SR 1014, Bonnie Brook Bridge over 9 Bonnie Brook, Summit Township, Bridge 10 Replacement 595,000 11 (Base Construction Allocation - 12 $400,000) 13 (Land Allocation - $20,000) 14 (Design and Contingencies - $175,000) 15 (64) SR 1016, Connoquenessing Creek 16 Bridge, Summit Township, Bridge 17 Replacement 595,000 18 (Base Construction Allocation - 19 $400,000) 20 (Land Allocation - $20,000) 21 (Design and Contingencies - $175,000) 22 (65) SR 2006, SR 2006 over SR 0422, Summit 23 Township, Bridge Replacement 1,050,000 24 (Base Construction Allocation - 25 $750,000) 26 (Land Allocation - $50,000) 27 (Design and Contingencies - $250,000) 28 (66) SR 2010, Bridge over Branch of Thorn 29 Creek, Jefferson Township, Bridge 30 Replacement 1,050,000 19970S0186B0698 - 91 -
1 (Base Construction Allocation - 2 $750,000) 3 (Land Allocation - $50,000) 4 (Design and Contingencies - $250,000) 5 (67) SR 2010, Little Buffalo Creek Bridge, 6 Winfield Township, Bridge Replacement 1,050,000 7 (Base Construction Allocation - 8 $750,000) 9 (Land Allocation - $50,000) 10 (Design and Contingencies - $250,000) 11 (68) SR 2011, Bridge over Branch of Bull 12 Creek, Clinton Township, Bridge 13 Replacement 595,000 14 (Base Construction Allocation - 15 $400,000) 16 (Land Allocation - $20,000) 17 (Design and Contingencies - $175,000) 18 (69) SR 2011, Little Bull Run Bridge No.4 19 over Bull Run, Clinton Township, Bridge 20 Replacement 595,000 21 (Base Construction Allocation - 22 $400,000) 23 (Land Allocation - $20,000) 24 (Design and Contingencies - $175,000) 25 (70) SR 2018, Bridge No.1 over Branch of 26 Buffalo Creek, Winfield Township, 27 Bridge Replacement 1,050,000 28 (Base Construction Allocation - 29 $750,000) 30 (Land Allocation - $50,000) 19970S0186B0698 - 92 -
1 (Design and Contingencies - $250,000) 2 (71) SR 2018, Bridge No.2 over Branch of 3 Buffalo Creek, Winfield Township, 4 Bridge Replacement 1,050,000 5 (Base Construction Allocation - 6 $750,000) 7 (Land Allocation - $50,000) 8 (Design and Contingencies - $250,000) 9 (72) SR 3025, Little Connoquenessing Creek 10 Bridge, Lancaster Township, Bridge 11 Replacement 595,000 12 (Base Construction Allocation - 13 $400,000) 14 (Land Allocation - $20,000) 15 (Design and Contingencies - $175,000) 16 (73) SR 4007, SR 4007 over SR 0422, Worth 17 Township, Bridge Replacement 1,050,000 18 (Base Construction Allocation - 19 $750,000) 20 (Land Allocation - $50,000) 21 (Design and Contingencies - $250,000) 22 (74) SR 4007, Park Road Bridge, Worth 23 Township, Bridge Replacement 1,050,000 24 (Base Construction Allocation - 25 $750,000) 26 (Land Allocation - $50,000) 27 (Design and Contingencies - $250,000) 28 (75) SR 4010, Long Run Bridge, Slippery 29 Rock Township, Bridge Replacement 595,000 30 (Base Construction Allocation - 19970S0186B0698 - 93 -
1 $400,000) 2 (Land Allocation - $20,000) 3 (Design and Contingencies - $175,000) 4 (76) SR 8005, SR 8005 over SR 0019, 5 Jackson Township, Bridge Replacement 595,000 6 (Base Construction Allocation - 7 $400,000) 8 (Land Allocation - $20,000) 9 (Design and Contingencies - $175,000) 10 (77) SR 0008, William Flynn Bridge, 11 Middlesex Township, Bridge Replacement 1,450,000 12 (Base Construction Allocation - 13 $1,000,000) 14 (Land Allocation - $100,000) 15 (Design and Contingencies - $350,000) 16 (78) SR 0008, Glade Run Bridge, Middlesex 17 Township, Bridge Rehabilitation 1,450,000 18 (Base Construction Allocation - 19 $1,000,000) 20 (Land Allocation - $100,000) 21 (Design and Contingencies - $350,000) 22 (79) SR 0008, Little Glade Run Bridge 23 No.1, Middlesex Township, Bridge 24 Rehabilitation 1,450,000 25 (Base Construction Allocation - 26 $1,000,000) 27 (Land Allocation - $100,000) 28 (Design and Contingencies - $350,000) 29 (80) SR 0008, Little Glade Run Bridge 30 No.2, Middlesex Township, Bridge 19970S0186B0698 - 94 -
1 Rehabilitation 1,450,000 2 (Base Construction Allocation - 3 $1,000,000) 4 (Land Allocation - $100,000) 5 (Design and Contingencies - $350,000) 6 (81) SR 0008, Glade Run Bridge No.2, 7 Middlesex Township, Bridge 8 Rehabilitation 1,450,000 9 (Base Construction Allocation - 10 $1,000,000) 11 (Land Allocation - $100,000) 12 (Design and Contingencies - $350,000) 13 (82) SR 0008, Bulcher Run Bridge, Butler 14 Township, Bridge Rehabilitation 1,450,000 15 (Base Construction Allocation - 16 $1,000,000) 17 (Land Allocation - $100,000) 18 (Design and Contingencies - $350,000) 19 (83) SR 0008, Bridge No.2 over Branch of 20 Muddy Creek, Clay Township, Bridge 21 Rehabilitation 1,450,000 22 (Base Construction Allocation - 23 $1,000,000) 24 (Land Allocation - $100,000) 25 (Design and Contingencies - $350,000) 26 (84) SR 0008, Muddy Creek Bridge, Clay 27 Township, Bridge Rehabilitation 1,450,000 28 (Base Construction Allocation - 29 $1,000,000) 30 (Land Allocation - $100,000) 19970S0186B0698 - 95 -
1 (Design and Contingencies - $350,000)
2 (85) SR 0008, Glade Run Bridge No.3, Brady
3 Township, Bridge Rehabilitation 1,450,000
4 (Base Construction Allocation -
5 $1,000,000)
6 (Land Allocation - $100,000)
7 (Design and Contingencies - $350,000)
8 (86) SR 0008, McDonalds Run Bridge, Mercer
9 Township, Bridge Replacement 1,450,000
10 (Base Construction Allocation -
11 $1,000,000)
12 (Land Allocation - $100,000)
13 (Design and Contingencies - $350,000)
14 (87) SR 0008, McMurry MCMURRAY Run Bridge, <--
15 Mercer Township, Bridge Rehabilitation 1,450,000
16 (Base Construction Allocation -
17 $1,000,000)
18 (Land Allocation - $100,000)
19 (Design and Contingencies - $350,000)
20 (88) SR 0019, Glade Run Bridge No.2,
21 Jackson Township, Bridge
22 Rehabilitation 1,050,000
23 (Base Construction Allocation -
24 $750,000)
25 (Land Allocation - $50,000)
26 (Design and Contingencies - $250,000)
27 (89) SR 0019, Glade Run Bridge No.2,
28 Jackson Township, Bridge
29 Rehabilitation 1,050,000
30 (Base Construction Allocation -
19970S0186B0698 - 96 -
1 $750,000) 2 (Land Allocation - $50,000) 3 (Design and Contingencies - $250,000) 4 (90) SR 0038, Connoquenessing Creek 5 Bridge, Center Township, Bridge 6 Rehabilitation 1,050,000 7 (Base Construction Allocation - 8 $750,000) 9 (Land Allocation - $50,000) 10 (Design and Contingencies - $250,000) 11 (91) SR 0038, Pine Run Bridge, Oakland 12 Township, Bridge Rehabilitation 1,050,000 13 (Base Construction Allocation - 14 $750,000) 15 (Land Allocation - $50,000) 16 (Design and Contingencies - $250,000) 17 (92) SR 0038, Concord Bridge, Concord 18 Township, Bridge Rehabilitation 1,050,000 19 (Base Construction Allocation - 20 $750,000) 21 (Land Allocation - $50,000) 22 (Design and Contingencies - $250,000) 23 (93) SR 0038, Little Connoquenessing Creek 24 Bridge No.1, Concord Township, Bridge 25 Rehabilitation 1,050,000 26 (Base Construction Allocation - 27 $750,000) 28 (Land Allocation - $50,000) 29 (Design and Contingencies - $250,000) 30 (94) SR 0038, Little Connoquenessing Creek 19970S0186B0698 - 97 -
1 Bridge, Concord Township, Bridge 2 Rehabilitation 1,050,000 3 (Base Construction Allocation - 4 $750,000) 5 (Land Allocation - $50,000) 6 (Design and Contingencies - $250,000) 7 (95) SR 0038, Little Scrubgrass Creek 8 Bridge, Allegheny Township, Bridge 9 Rehabilitation 1,050,000 10 (Base Construction Allocation - 11 $750,000) 12 (Land Allocation - $50,000) 13 (Design and Contingencies - $250,000) 14 (96) SR 0038, Bridge over Tributary of 15 Scrubgrass Creek, Allegheny Township, 16 Bridge Rehabilitation 1,050,000 17 (Base Construction Allocation - 18 $750,000) 19 (Land Allocation - $50,000) 20 (Design and Contingencies - $250,000) 21 (97) SR 0058, Murrin Run Bridge, Venango 22 Township, Bridge Rehabilitation 1,050,000 23 (Base Construction Allocation - 24 $750,000) 25 (Land Allocation - $50,000) 26 (Design and Contingencies - $250,000) 27 (98) SR 0068, B&LE Railroad Bridge, Summit 28 and Butler Townships, Bridge 29 Rehabilitation 1,450,000 30 (Base Construction Allocation - 19970S0186B0698 - 98 -
1 $1,000,000) 2 (Land Allocation - $100,000) 3 (Design and Contingencies - $350,000) 4 (99) SR 0068, Connoquenessing Creek 5 Bridge, Summit Township, Bridge 6 Rehabilitation 1,050,000 7 (Base Construction Allocation - 8 $750,000) 9 (Land Allocation - $50,000) 10 (Design and Contingencies - $250,000) 11 (100) SR 0068, Buffalo Creek Bridge, 12 Chicora Township, Bridge 13 Rehabilitation 1,050,000 14 (Base Construction Allocation - 15 $750,000) 16 (Land Allocation - $50,000) 17 (Design and Contingencies - $250,000) 18 (101) SR 0068, Buffalo Run Bridge, 19 Fairview Township, Bridge 20 Rehabilitation 1,050,000 21 (Base Construction Allocation - 22 $750,000) 23 (Land Allocation - $50,000) 24 (Design and Contingencies - $250,000) 25 (102) SR 0079, Bridge over Tributary of 26 Glade Run, Jackson Township, Bridge 27 Rehabilitation 1,450,000 28 (Base Construction Allocation - 29 $1,000,000) 30 (Land Allocation - $100,000) 19970S0186B0698 - 99 -
1 (Design and Contingencies - $350,000) 2 (103) SR 0079, Bridge No.1 over Branch of 3 Yellow Creek, Lancaster Township, 4 Bridge Rehabilitation 1,450,000 5 (Base Construction Allocation - 6 $1,000,000) 7 (Land Allocation - $100,000) 8 (Design and Contingencies - $350,000) 9 (104) SR 0079, Bridge No.2 over Branch of 10 Yellow Creek, Lancaster Township, 11 Bridge Rehabilitation 1,450,000 12 (Base Construction Allocation - 13 $1,000,000) 14 (Land Allocation - $100,000) 15 (Design and Contingencies - $350,000) 16 (105) SR 0079, Bridge No.3 over Branch of 17 Yellow Creek, Lancaster Township, 18 Bridge Rehabilitation 1,450,000 19 (Base Construction Allocation - 20 $1,000,000) 21 (Land Allocation - $100,000) 22 (Design and Contingencies - $350,000) 23 (106) SR 0079, Little Yellow Creek Bridge, 24 Lancaster Township, Bridge 25 Rehabilitation 1,450,000 26 (Base Construction Allocation - 27 $1,000,000) 28 (Land Allocation - $100,000) 29 (Design and Contingencies - $350,000) 30 (107) SR 0079, Bridge No.4 over Branch of 19970S0186B0698 - 100 -
1 Yellow Creek, Muddycreek Township, 2 Bridge Rehabilitation 1,450,000 3 (Base Construction Allocation - 4 $1,000,000) 5 (Land Allocation - $100,000) 6 (Design and Contingencies - $350,000) 7 (108) SR 0079, Bridge at Milepost 100, 8 Worth Township, Bridge Rehabilitation 1,450,000 9 (Base Construction Allocation - 10 $1,000,000) 11 (Land Allocation - $100,000) 12 (Design and Contingencies - $350,000) 13 (109) SR 0079, Black Run Bridge, Worth 14 Township, Bridge Rehabilitation 1,450,000 15 (Base Construction Allocation - 16 $1,000,000) 17 (Land Allocation - $100,000) 18 (Design and Contingencies - $350,000) 19 (110) SR 0268, Bridge over Branch of Bear 20 Creek, Petrolia Borough, Bridge 21 Rehabilitation 1,050,000 22 (Base Construction Allocation - 23 $750,000) 24 (Land Allocation - $50,000) 25 (Design and Contingencies - $250,000) 26 (111) SR 0268, Lowrey Run Bridge, 27 Allegheny Township, Bridge 28 Rehabilitation 1,050,000 29 (Base Construction Allocation - 30 $750,000) 19970S0186B0698 - 101 -
1 (Land Allocation - $50,000) 2 (Design and Contingencies - $250,000) 3 (112) SR 0308, B&LE Railroad Bridge, 4 Center Township, Bridge Rehabilitation 1,050,000 5 (Base Construction Allocation - 6 $750,000) 7 (Land Allocation - $50,000) 8 (Design and Contingencies - $250,000) 9 (113) SR 0308, Stony Run Bridge, Center 10 Township, Bridge Rehabilitation 1,050,000 11 (Base Construction Allocation - 12 $750,000) 13 (Land Allocation - $50,000) 14 (Design and Contingencies - $250,000) 15 (114) SR 0356, Little Buffalo Creek 16 Bridge, Buffalo Township, Bridge 17 Rehabilitation 1,050,000 18 (Base Construction Allocation - 19 $750,000) 20 (Land Allocation - $50,000) 21 (Design and Contingencies - $250,000) 22 (115) SR 0356, Big Coal Run Bridge, Summit 23 Township, Bridge Rehabilitation 1,050,000 24 (Base Construction Allocation - 25 $750,000) 26 (Land Allocation - $50,000) 27 (Design and Contingencies - $250,000) 28 (116) SR 0422, Lake Arthur Bridge, 29 Franklin Township, Bridge 30 Rehabilitation 1,450,000 19970S0186B0698 - 102 -
1 (Base Construction Allocation - 2 $1,000,000) 3 (Land Allocation - $100,000) 4 (Design and Contingencies - $350,000) 5 (117) SR 0422, Big Run Bridge, Franklin 6 Township, Bridge Rehabilitation 1,450,000 7 (Base Construction Allocation - 8 $1,000,000) 9 (Land Allocation - $100,000) 10 (Design and Contingencies - $350,000) 11 (118) SR 0422, Mulligan Run Bridge, 12 Franklin Township, Bridge 13 Rehabilitation 1,450,000 14 (Base Construction Allocation - 15 $1,000,000) 16 (Land Allocation - $100,000) 17 (Design and Contingencies - $350,000) 18 (119) SR 0422, Big Mulligan Run Bridge, 19 Franklin Township, Bridge 20 Rehabilitation 1,450,000 21 (Base Construction Allocation - 22 $1,000,000) 23 (Land Allocation - $100,000) 24 (Design and Contingencies - $350,000) 25 (120) SR 0422, Big Sullivan Run Bridge, 26 Butler Township, Bridge Rehabilitation 1,450,000 27 (Base Construction Allocation - 28 $1,000,000) 29 (Land Allocation - $100,000) 30 (Design and Contingencies - $350,000) 19970S0186B0698 - 103 -
1 (121) SR 0422, Connoquenessing Creek 2 Bridge, Butler Township, Bridge 3 Rehabilitation 1,450,000 4 (Base Construction Allocation - 5 $1,000,000) 6 (Land Allocation - $100,000) 7 (Design and Contingencies - $350,000) 8 (122) SR 0422, Bridge No.1 over Tributary 9 of Connoquenessing Creek, Summit 10 Township, Bridge Rehabilitation 1,450,000 11 (Base Construction Allocation - 12 $1,000,000) 13 (Land Allocation - $100,000) 14 (Design and Contingencies - $350,000) 15 (123) SR 0422, Bridge No.2 over Tributary 16 of Bonnie Brook, Butler Township, 17 Bridge Rehabilitation 1,450,000 18 (Base Construction Allocation - 19 $1,000,000) 20 (Land Allocation - $100,000) 21 (Design and Contingencies - $350,000) 22 (124) SR 0422, Bonnie Brook Bridge No.1, 23 Summit Township, Bridge Rehabilitation 1,450,000 24 (Base Construction Allocation - 25 $1,000,000) 26 (Land Allocation - $100,000) 27 (Design and Contingencies - $350,000) 28 (125) SR 0422, Bridge No.3 over Tributary 29 of Bonnie Brook, Summit Township, 30 Bridge Rehabilitation 1,450,000 19970S0186B0698 - 104 -
1 (Base Construction Allocation - 2 $1,000,000) 3 (Land Allocation - $100,000) 4 (Design and Contingencies - $350,000) 5 (126) SR 0422, Bonnie Brook Bridge No.2, 6 Summit Township, Bridge Rehabilitation 1,450,000 7 (Base Construction Allocation - 8 $1,000,000) 9 (Land Allocation - $100,000) 10 (Design and Contingencies - $350,000) 11 (127) SR 0422, Bridge No.4 over Tributary 12 of Bonnie Brook, Summit Township, 13 Bridge Rehabilitation 1,450,000 14 (Base Construction Allocation - 15 $1,000,000) 16 (Land Allocation - $100,000) 17 (Design and Contingencies - $350,000) 18 (128) SR 0422, Little Buffalo Creek 19 Bridge, Clearfield Township, Bridge 20 Rehabilitation 1,450,000 21 (Base Construction Allocation - 22 $1,000,000) 23 (Land Allocation - $100,000) 24 (Design and Contingencies - $350,000) 25 (129) SR 0422, Buffalo Creek Bridge, 26 Clearfield Township, Bridge 27 Rehabilitation 1,450,000 28 (Base Construction Allocation - 29 $1,000,000) 30 (Land Allocation - $100,000) 19970S0186B0698 - 105 -
1 (Design and Contingencies - $350,000) 2 (130) SR 0528, Likens Run Bridge, Evans 3 City Borough, Bridge Rehabilitation 1,050,000 4 (Base Construction Allocation - 5 $750,000) 6 (Land Allocation - $50,000) 7 (Design and Contingencies - $250,000) 8 (131) SR 1010, Glade Run Bridge, Brady 9 Township, Bridge Rehabilitation 595,000 10 (Base Construction Allocation - 11 $400,000) 12 (Land Allocation - $20,000) 13 (Design and Contingencies - $175,000) 14 (132) SR 1010, Big Bear Creek Bridge, 15 Fairview Township, Bridge 16 Rehabilitation 595,000 17 (Base Construction Allocation - 18 $400,000) 19 (Land Allocation - $20,000) 20 (Design and Contingencies - $175,000) 21 (133) SR 1011, Buffalo Creek Bridge, 22 Fairview Township, Bridge 23 Rehabilitation 595,000 24 (Base Construction Allocation - 25 $400,000) 26 (Land Allocation - $20,000) 27 (Design and Contingencies - $175,000) 28 (134) SR 1019, Big Buffalo Run Bridge, 29 Donegal Township, Bridge 30 Rehabilitation 1,050,000 19970S0186B0698 - 106 -
1 (Base Construction Allocation - 2 $750,000) 3 (Land Allocation - $50,000) 4 (Design and Contingencies - $250,000) 5 (135) SR 1025, Bonnie Brook Bridge, Summit 6 Township, Bridge Rehabilitation 1,050,000 7 (Base Construction Allocation - 8 $750,000) 9 (Land Allocation - $50,000) 10 (Design and Contingencies - $250,000) 11 (136) SR 2002, Coal Run Bridge, City of 12 Butler and Butler Township, Bridge 13 Rehabilitation 1,050,000 14 (Base Construction Allocation - 15 $750,000) 16 (Land Allocation - $50,000) 17 (Design and Contingencies - $250,000) 18 (137) SR 2004, Bonnie Brook Bridge, Summit 19 Township, Bridge Rehabilitation 1,050,000 20 (Base Construction Allocation - 21 $750,000) 22 (Land Allocation - $50,000) 23 (Design and Contingencies - $250,000) 24 (138) SR 2012, Thorn Creek Bridge No.1, 25 Jefferson Township, Bridge 26 Rehabilitation 1,050,000 27 (Base Construction Allocation - 28 $750,000) 29 (Land Allocation - $50,000) 30 (Design and Contingencies - $250,000) 19970S0186B0698 - 107 -
1 (139) SR 2012, Thorn Creek Bridge No.2, 2 Jefferson Township, Bridge 3 Rehabilitation 1,050,000 4 (Base Construction Allocation - 5 $750,000) 6 (Land Allocation - $50,000) 7 (Design and Contingencies - $250,000) 8 (140) SR 3001, West Butler Creek Bridge, 9 Butler Township, Bridge Rehabilitation 1,450,000 10 (Base Construction Allocation - 11 $1,000,000) 12 (Land Allocation - $100,000) 13 (Design and Contingencies - $350,000) 14 (141) SR 3007, Thorn Creek Bridge, Butler 15 Township, Bridge Rehabilitation 1,050,000 16 (Base Construction Allocation - 17 $750,000) 18 (Land Allocation - $50,000) 19 (Design and Contingencies - $250,000) 20 (142) SR 3009, Cranberry Run Bridge, Penn 21 Township, Bridge Rehabilitation 595,000 22 (Base Construction Allocation - 23 $400,000) 24 (Land Allocation - $20,000) 25 (Design and Contingencies - $175,000) 26 (143) SR 3010, Saw Mill Run Bridge, Penn 27 Township, Bridge Rehabilitation 595,000 28 (Base Construction Allocation - 29 $400,000) 30 (Land Allocation - $20,000) 19970S0186B0698 - 108 -
1 (Design and Contingencies - $175,000) 2 (144) SR 3015, Bridge No.2 over Tributary 3 of Wolf Run, Forward Township, Bridge 4 Rehabilitation 1,050,000 5 (Base Construction Allocation - 6 $750,000) 7 (Land Allocation - $50,000) 8 (Design and Contingencies - $250,000) 9 (145) SR 3015, Bridge No.3 over Tributary 10 of Wolf Run, Forward Township, Bridge 11 Rehabilitation 1,050,000 12 (Base Construction Allocation - 13 $750,000) 14 (Land Allocation - $50,000) 15 (Design and Contingencies - $250,000) 16 (146) SR 3025, Bridge over Branch of 17 Yellow Creek, Lancaster Township, 18 Bridge Rehabilitation 595,000 19 (Base Construction Allocation - 20 $400,000) 21 (Land Allocation - $20,000) 22 (Design and Contingencies - $175,000) 23 (147) SR 3031, SR 3031 over US 422, Butler 24 Township, Bridge Rehabilitation 595,000 25 (Base Construction Allocation - 26 $400,000) 27 (Land Allocation - $20,000) 28 (Design and Contingencies - $175,000) 29 (148) SR 3034, Bridge over Branch of 30 Semiconon, Prospect Borough, Bridge 19970S0186B0698 - 109 -
1 Rehabilitation 595,000 2 (Base Construction Allocation - 3 $400,000) 4 (Land Allocation - $20,000) 5 (Design and Contingencies - $175,000) 6 (149) SR 4001, SR 4001 over US 422, Butler 7 Township, Bridge Rehabilitation 1,050,000 8 (Base Construction Allocation - 9 $750,000) 10 (Land Allocation - $50,000) 11 (Design and Contingencies - $250,000) 12 (150) SR 4002, Bridge over Branch of Muddy 13 Creek, Clay Township, Bridge 14 Rehabilitation 1,050,000 15 (Base Construction Allocation - 16 $750,000) 17 (Land Allocation - $50,000) 18 (Design and Contingencies - $250,000) 19 (151) T-716, Old Plank Road Bridge, Penn 20 Township, Bridge Replacement 390,000 21 (Base Construction Allocation - 22 $300,000) 23 (Land Allocation - $10,000) 24 (Design and Contingencies - $80,000) 25 (152) SR 3007, Crooked Run Bridge, Center 26 Township, Bridge Replacement 1,050,000 27 (Base Construction Allocation - 28 $750,000) 29 (Land Allocation - $50,000) 30 (Design and Contingencies - $250,000) 19970S0186B0698 - 110 -
1 (153) SR 3010, Glade Run Bridge, Forward
2 Township, Bridge Replacement 595,000
3 (Base Construction Allocation -
4 $400,000)
5 (Land Allocation - $20,000)
6 (Design and Contingencies - $175,000)
7 (154) SR 3013, Big Connoquessing <--
8 CONNOQUENESSING Bridge, Forward <--
9 Township, Bridge Replacement 595,000
10 (Base Construction Allocation -
11 $400,000)
12 (Land Allocation - $20,000)
13 (Design and Contingencies - $175,000)
14 (155) SR 0019, SR 0019 over Brush Creek,
15 Cranberry Township, Bridge Replacement 1,050,000
16 (Base Construction Allocation -
17 $800,000)
18 (Land Allocation - $75,000)
19 (Design and Contingencies - $175,000)
20 (156) SR 0079, SR 0079 over Big Brush
21 Creek, Cranberry Township, Bridge
22 Replacement 1,450,000
23 (Base Construction Allocation -
24 $1,100,000)
25 (Land Allocation - $75,000)
26 (Design and Contingencies - $275,000)
27 (157) SR 0079, SR 0079 over Coal Run,
28 Cranberry Township, Bridge Replacement 1,450,000
29 (Base Construction Allocation -
30 $1,100,000)
19970S0186B0698 - 111 -
1 (Land Allocation - $75,000) 2 (Design and Contingencies - $275,000) 3 (158) SR 0228, SR 0228 over CSX Railroad, 4 Adams Township, Bridge Replacement 1,450,000 5 (Base Construction Allocation - 6 $1,100,000) 7 (Land Allocation - $75,000) 8 (Design and Contingencies - $275,000) 9 (159) SR 3015, Breakneck Bridge, Adams 10 Township, Bridge Replacement 595,000 11 (Base Construction Allocation - 12 $400,000) 13 (Land Allocation - $20,000) 14 (Design and Contingencies - $175,000) 15 (160) SR 3022, SR 3022 over Brush Creek, 16 Cranberry Township, Bridge Replacement 1,050,000 17 (Base Construction Allocation - 18 $800,000) 19 (Land Allocation - $75,000) 20 (Design and Contingencies - $175,000) 21 (161) SR 3024, SR 3024 over Big Brush 22 Creek, Cranberry Township, Bridge 23 Replacement 595,000 24 (Base Construction Allocation - 25 $400,000) 26 (Land Allocation - $20,000) 27 (Design and Contingencies - $175,000) 28 Section 15. Cambria County 29 (a) Local Bridges 30 (1) Summerhill Township, T-346, Bridge 19970S0186B0698 - 112 -
1 No.1, Howard Avenue over Beaverdam Run, 2 Bridge Replacement 450,000 3 (Base Construction Allocation - 4 $350,000) 5 (Design and Contingencies - $100,000) 6 (2) West Carroll Township, T-505 over 7 Blacklick Creek, Bridge Replacement 235,000 8 (Base Construction Allocation - 9 $200,000) 10 (Land Allocation - $10,000) 11 (Design and Contingencies - $25,000) 12 (3) West Carroll Township, T-626 over Fox 13 Run, Bridge Replacement 235,000 14 (Base Construction Allocation - 15 $200,000) 16 (Land Allocation - $10,000) 17 (Design and Contingencies - $25,000) 18 (b) State Bridges 19 (1) SR 1030, Carl Road over Slate Lick 20 Creek, Clearfield Township, Bridge 21 Replacement 240,000 22 (Base Construction Allocation - 23 $200,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $30,000) 26 (2) SR 0271, Maple Avenue Bridge over 27 Little Conemaugh River and Conrail, 28 Phase II, City of Johnstown, Bridge 29 Painting 500,000 30 (Base Construction Allocation - 19970S0186B0698 - 113 -
1 $500,000) 2 (3) SR 3033, PA 56 Detour Bridge over 3 Solomon Run, Richland Township, Bridge 4 Replacement 350,000 5 (Base Construction Allocation - 6 $250,000) 7 (Land Allocation - $15,000) 8 (Design and Contingencies - $85,000) 9 Section 16. (Reserved). 10 Section 17. Carbon County. 11 (a) Local Bridges 12 (1) Penn Forest Township, T-481, County 13 Bridge No.21 over Panther Creek, Bridge 14 Replacement 290,000 15 (Base Construction Allocation - 16 $180,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $100,000) 19 (2) MAHONING TOWNSHIP, T-390, BRIDGE OVER <-- 20 MAHONING CREEK, BRIDGE REPLACEMENT 92,000 21 (BASE CONSTRUCTION ALLOCATION - 22 $80,000) 23 (LAND ALLOCATION - $4,000) 24 (DESIGN AND CONTINGENCIES - $8,000) 25 (3) LAUSANNE TOWNSHIP, T-502, BRIDGE OVER 26 SCHAFFERS RUN, BRIDGE REPLACEMENT 320,000 27 (BASE CONSTRUCTION ALLOCATION - 28 $212,000) 29 (LAND ALLOCATION - $8,000) 30 (DESIGN AND CONTINGENCIES - $100,00) 19970S0186B0698 - 114 -
1 (4) TOWAMENSING TOWNSHIP, T-435, BRIDGE 2 OVER WILD CREEK, BRIDGE REPLACEMENT 357,000 3 (BASE CONSTRUCTION ALLOCATION - 4 $220,000) 5 (LAND ALLOCATION - $9,000) 6 (DESIGN AND CONTINGENCIES - $128,000) 7 (5) BOWMANSTOWN BOROUGH, ORE STREET BRIDGE 8 OVER FIRELINE CREEK, BRIDGE 9 REPLACEMENT 360,000 10 (BASE CONSTRUCTION ALLOCATION - 11 $250,000) 12 (LAND ALLOCATION - $10,000) 13 (DESIGN AND CONTINGENCIES - $100,000) 14 (6) PACKER TOWNSHIP, T-463, BRIDGE OVER 15 WETZEL CREEK, BRIDGE REPLACEMENT 360,000 16 (BASE CONSTRUCTION ALLOCATION - 17 $250,000) 18 (LAND ALLOCATION - $10,000) 19 (DESIGN AND CONTINGENCIES - $100,000) 20 (7) EAST PENN TOWNSHIP, T-354, COUNTY 21 BRIDGE NO.6 OVER LIZARD CREEK, BRIDGE 22 REPLACEMENT 974,000 23 (BASE CONSTRUCTION ALLOCATION - 24 $600,000) 25 (LAND ALLOCATION - $300,000) 26 (DESIGN AND CONTINGENCIES - $74,000) 27 (b) State Bridges 28 (1) SR 2002, Delaware Avenue over Palmer 29 Creek, Palmerton Borough, Bridge 30 Replacement 568,000 19970S0186B0698 - 115 -
1 (Base Construction Allocation - 2 $318,000) 3 (Land Allocation - $150,000) 4 (Design and Contingencies - $100,000) 5 (2) SR 4010, SR 4010 over Quakake Creek, 6 Packer Township, Bridge Replacement 412,000 7 (Base Construction Allocation - 8 $202,000) 9 (Land Allocation - $150,000) 10 (Design and Contingencies - $60,000) 11 (3) SR 0209, SR 0209 Turnpike Ramp, 12 Mahoning Interchange, Franklin 13 Township, Bridge Replacement 1,260,000 14 (Base Construction Allocation - 15 $750,000) 16 (Land Allocation - $300,000) 17 (Design and Contingencies - $210,000) 18 (4) SR 0248, SR 0248 over Pohopoco Creek, 19 Parryville Borough Line, Lower 20 Towamensing Township, Bridge 21 Rehabilitation 415,000 22 (Base Construction Allocation - 23 $315,000) 24 (Design and Contingencies - $100,000) 25 (5) SR 4010, SR 4010 over Hartz Creek, 26 Packer Township, Bridge Replacement 615,000 27 (Base Construction Allocation - 28 $370,000) 29 (Land Allocation - $150,000) 30 (Design and Contingencies - $95,000) 19970S0186B0698 - 116 -
1 (6) SR 0534, SR 0534 over Sand Spring Run, 2 2 Miles South of Lehigh Tannery, Kidder 3 Township, Bridge Replacement 340,000 4 (Base Construction Allocation - 5 $160,000) 6 (Land Allocation - $125,000) 7 (Design and Contingencies - $55,000) 8 (7) SR 0209, SR 0209 over Pohopoco Creek, 9 Village of Harrity, Franklin Township, 10 Bridge Rehabilitation 885,000 11 (Base Construction Allocation - 12 $680,000) 13 (Design and Contingencies - $205,000) 14 (8) SR 0534, Pa 534 over I-80, Kidder 15 Township, Bridge Rehabilitation 540,000 16 (Base Construction Allocation - 17 $440,000) 18 (Design and Contingencies - $100,000) 19 (9) SR 0248, BRIDGE OVER AQUASHICOLA <-- 20 CREEK, LOWER TOWAMENSING TOWNSHIP, 21 BRIDGE REHABILITATION 310,000 22 (BASE CONSTRUCTION ALLOCATION - 23 $300,000) 24 (DESIGN AND CONTINGENCIES - $10,000) 25 (10) SR 0534, BRIDGE OVER HICKORY RUN, 26 KIDDER TOWNSHIP, BRIDGE REHABILITATION 830,000 27 (BASE CONSTRUCTION ALLOCATION - 28 $700,000) 29 (LAND ALLOCATION - $30,000) 30 (DESIGN AND CONTINGENCIES - $100,000) 19970S0186B0698 - 117 -
1 (11) SR 0903, BRIDGE OVER LEHIGH RIVER, 2 JIM THORPE BOROUGH, BRIDGE 3 REHABILITATION 1,250,000 4 (BASE CONSTRUCTION ALLOCATION - 5 $1,000,000) 6 (LAND ALLOCATION - $50,000) 7 (DESIGN AND CONTINGENCIES - $200,000) 8 (12) SR 0940, BRIDGE OVER BLACK CREEK, 9 KIDDER TOWNSHIP, BRIDGE REPLACEMENT 185,000 10 (BASE CONSTRUCTION ALLOCATION - 11 $150,000) 12 (DESIGN AND CONTINGENCIES - $35,000) 13 (13) SR 2006, BRIDGE OVER BUCKWHA CREEK, 14 LOWER TOWAMENSING TOWNSHIP, BRIDGE 15 REPLACEMENT 1,240,000 16 (BASE CONSTRUCTION ALLOCATION - 17 $700,000) 18 (LAND ALLOCATION - $90,000) 19 (DESIGN AND CONTINGENCIES - $450,000) 20 (14) SR 2008, BRIDGE OVER POHOPOCO CREEK, 21 PARRYVILLE BOROUGH, BRIDGE REPLACEMENT 920,000 22 (BASE CONSTRUCTION ALLOCATION - 23 $600,000) 24 (LAND ALLOCATION - $90,000) 25 (DESIGN AND CONTINGENCIES - $230,000) 26 (15) SR 3005, BRIDGE OVER MAHONING CREEK, 27 MAHONING TOWNSHIP, BRIDGE REPLACEMENT 308,000 28 (BASE CONSTRUCTION ALLOCATION - 29 $280,000) 30 (DESIGN AND CONTINGENCIES - $28,000) 19970S0186B0698 - 118 -
1 (16) SR 4014, BRIDGE OVER TRIBUTARY OF 2 INDIAN RUN, LEHIGH TOWNSHIP, BRIDGE 3 REPLACEMENT 153,000 4 (BASE CONSTRUCTION ALLOCATION - 5 $130,000) 6 (LAND ALLOCATION - $10,000) 7 (DESIGN AND CONTINGENCIES - $13,000) 8 (17) SR 4014, BRIDGE OVER TRIBUTARY OF 9 INDIAN RUN, LEHIGH TOWNSHIP, BRIDGE 10 REPLACEMENT 88,000 11 (BASE CONSTRUCTION ALLOCATION - 12 $80,000) 13 (DESIGN AND CONTINGENCIES - $8,000) 14 Section 18. Centre County. 15 (a) Local Bridges 16 (1) Greene Township, T-350, Stover Road 17 Bridge, Bridge Replacement 230,000 18 (Base Construction Allocation - 19 $180,000) 20 (Land Allocation - $10,000) 21 (Design and Contingencies - $40,000) 22 (2) Howard Township, T-398 over Bullit 23 Run, Bridge Rehabilitation 11,000 24 (Base Construction Allocation - $9,000) 25 (Design and Contingencies - $2,000) 26 (3) Halfmoon Township, T-307 over 27 Loveville Creek, Bridge Replacement 21,000 28 (Base Construction Allocation - 29 $19,000) 30 (Design and Contingencies - $2,000) 19970S0186B0698 - 119 -
1 (4) Penn Township, T-839 over Pine Creek, 2 Bridge Rehabilitation 80,000 3 (Base Construction Allocation - 4 $60,000) 5 (Design and Contingencies - $20,000) 6 (5) Port Matilda Borough, Pedestrian 7 Bridge over Bald Eagle Creek, Bridge 8 Rehabilitation 200,000 9 (Base Construction Allocation - 10 $175,000) 11 (Design and Contingencies - $25,000) 12 (6) Spring Township, T-367, Hill Road 13 Bridge, Bridge Replacement 200,000 14 (Base Construction Allocation - 15 $150,000) 16 (Land Allocation - $10,000) 17 (Design and Contingencies - $40,000) 18 (b) State Bridges 19 (1) SR 0080, I-80 Viaduct over Moshannon 20 Creek and Conrail, Rush Township, 21 Bridge Rehabilitation 14,510,000 22 (Base Construction Allocation - 23 $13,210,000) 24 (Design and Contingencies - $1,300,000) 25 (2) SR 1002, Marsh Creek Bridge over Marsh 26 Creek, Boggs Township, Bridge 27 Replacement 760,000 28 (Base Construction Allocation - 29 $630,000) 30 (Land Allocation - $20,000) 19970S0186B0698 - 120 -
1 (Design and Contingencies - $110,000) 2 (3) SR 1002, Little Marsh Creek Bridge 3 over Little Marsh Creek, Curtin 4 Township, Bridge Replacement 700,000 5 (Base Construction Allocation - 6 $600,000) 7 (Land Allocation - $20,000) 8 (Design and Contingencies - $80,000) 9 (4) SR 2012, Penns Creek Bridge Northwest 10 of the Village of Spring Mills, Gregg 11 Township, Bridge Replacement 470,000 12 (Base Construction Allocation - 13 $360,000) 14 (Land Allocation - $20,000) 15 (Design and Contingencies - $90,000) 16 (5) SR 0220, SR 0220 over Laurel Run, Port 17 Matilda Borough, Bridge Rehabilitation 450,000 18 (Base Construction Allocation - 19 $400,000) 20 (Design and Contingencies - $50,000) 21 Section 19. Chester County. 22 (a) Local Bridges 23 (1) Parkesburg Borough, State Street 24 Pedestrian Bridge over Amtrak, Bridge 25 Replacement 1,700,000 26 (Base Construction Allocation - 27 $1,000,000) 28 (Land Allocation - $500,000) 29 (Design and Contingencies - $200,000) 30 (2) East Fallowfield Township, T-362, 19970S0186B0698 - 121 -
1 Timacuia Road under Penn Central 2 Railroad, Bridge Removal 445,000 3 (Base Construction Allocation - 4 $400,000) 5 (Land Allocation - $30,000) 6 (Design and Contingencies - $15,000) 7 (3) East Marlborough Township, T-402, 8 County Bridge No.65, Mill Road Bridge 9 over West Branch of Red Clay Creek, 10 Bridge Replacement 345,000 11 (Base Construction Allocation - 12 $291,000) 13 (Land Allocation - $25,000) 14 (Design and Contingencies - $29,000) 15 (4) Oxford Borough, Broad Street Bridge 16 over SEPTA, Bridge Replacement 1,304,000 17 (Base Construction Allocation - 18 $1,125,000) 19 (Land Allocation - $20,000) 20 (Design and Contingencies - $159,000) 21 (5) Penn Township, County Bridge No.260, 22 Posey Mill Road Bridge over Big Elk 23 Creek, Bridge Replacement 425,000 24 (Base Construction Allocation - 25 $300,000) 26 (Land Allocation - $25,000) 27 (Design and Contingencies - $100,000) 28 (6) Tredyffrin Township, Old Lancaster 29 Pike Bridge over Amtrak, Bridge 30 Rehabilitation 465,000 19970S0186B0698 - 122 -
1 (Base Construction Allocation - 2 $400,000) 3 (Land Allocation - $30,000) 4 (Design and Contingencies - $35,000) 5 (7) Tredyffrin Township, T-807, Evans Road 6 Bridge over Conrail, Bridge 7 Replacement 195,000 8 (Base Construction Allocation - 9 $150,000) 10 (Land Allocation - $30,000) 11 (Design and Contingencies - $15,000) 12 (8) West Caln and West Brandywine 13 Townships, County Bridge No.283, Reid 14 Road Bridge over West Branch of 15 Brandywine Creek, Bridge Replacement 740,000 16 (Base Construction Allocation - 17 $600,000) 18 (Land Allocation - $40,000) 19 (Design and Contingencies - $100,000) 20 (9) West Goshen Township, T-210, Old 21 Eachus Mill Road Bridge over SEPTA, 22 Bridge Replacement 615,000 23 (Base Construction Allocation - 24 $500,000) 25 (Land Allocation - $15,000) 26 (Design and Contingencies - $100,000) 27 (10) West Goshen Township, T-328, Bridge 28 over Penn Central Railroad, Bridge 29 Removal 132,000 30 (Base Construction Allocation - 19970S0186B0698 - 123 -
1 $110,000) 2 (Land Allocation - $5,000) 3 (Design and Contingencies - $17,000) 4 (11) West Marlborough Township, T-368, 5 Creek Road Bridge under Penn Central 6 Railroad, Bridge Removal 580,000 7 (Base Construction Allocation - 8 $500,000) 9 (Land Allocation - $5,000) 10 (Design and Contingencies - $75,000) 11 (12) West Marlborough Township, Bridge 12 over Doe Run, Bridge Replacement 915,000 13 (Base Construction Allocation - 14 $750,000) 15 (Land Allocation - $25,000) 16 (Design and Contingencies - $140,000) 17 (13) East Coventry Township, Zeiber Road 18 over Pigeon Creek, Bridge Replacement 375,000 19 (Base Construction Allocation - 20 $300,000) 21 (Land Allocation - $15,000) 22 (Design and Contingencies - $60,000) 23 (14) South Coventry Township, Young Road 24 over Pigeon Creek, Bridge 25 Rehabilitation 6,000 26 (Base Construction Allocation - $6,000) 27 (15) Franklin Township, T-356, Mount 28 Olivet Road Bridge over Unnamed 29 Tributary of Big Elk Creek, Bridge 30 Rehabilitation 8,100,000 <-- 19970S0186B0698 - 124 -
1 (Base Construction Allocation - 2 $6,600,000) 3 (Design and Contingencies - $1,500,000) 4 REHABILITATION 9,000 <-- 5 (BASE CONSTRUCTION ALLOCATION - $7,000) 6 (DESIGN AND CONTINGENCIES - $2,000) 7 (16) NORTH COVENTRY TOWNSHIP, SOUTH KEIM 8 STREET, BRIDGE NO.270 OVER SMALL RUN, 9 BRIDGE REPLACEMENT 510,000 10 (BASE CONSTRUCTION ALLOCATION - 11 $150,000) 12 (LAND ALLOCATION - $10,000) 13 (DESIGN AND CONTINGENCIES - $350,000) 14 (b) State Bridges 15 (1) SR 1010, Swedesford Road Bridge over 16 US 422, Drummers Lane and Warner Road, 17 Tredyffrin, Chester County, Upper 18 Merion, Montgomery County, Bridge 19 Replacement 6,795,000 20 (Base Construction Allocation - 21 $6,210,000) 22 (Land Allocation - $180,000) 23 (Design and Contingencies - $405,000) 24 (2) SR 1045, Hares Hill Road Bridge over 25 French Creek, East Pikeland Township, 26 Bridge Rehabilitation 1,000,000 27 (Base Construction Allocation - 28 $740,000) 29 (Land Allocation - $60,000) 30 (Design and Contingencies - $200,000) 19970S0186B0698 - 125 -
1 (3) SR 3014, Lees Road Bridge over Black 2 Run, West Nottingham Township, Bridge 3 Replacement 1,125,000 4 (Base Construction Allocation - 5 $850,000) 6 (Land Allocation - $75,000) 7 (Design and Contingencies - $200,000) 8 (4) SR 3030, Street Road Bridge over 9 Octoraro Creek, Upper Oxford Township, 10 Bridge Replacement 1,875,000 11 (Base Construction Allocation - 12 $1,600,000) 13 (Land Allocation - $75,000) 14 (Design and Contingencies - $200,000) 15 (5) SR 0003, Gay Street Bridge over 16 Abandoned Conrail, West Chester 17 Borough, Bridge Removal 180,000 18 (Base Construction Allocation - 19 $150,000) 20 (Land Allocation - $10,000) 21 (Design and Contingencies - $20,000) 22 (6) SR 0842, Shaws Bridges (Two Bridges) 23 over Branch of Brandywine Creek, East 24 Bradford and Pocopson Townships, Bridge 25 Replacement 1,500,000 26 (Base Construction Allocation - 27 $1,288,000) 28 (Land Allocation - $100,000) 29 (Design and Contingencies - $112,000) 30 (7) SR 0842, Bridge Road Bridge over East 19970S0186B0698 - 126 -
1 Branch of Brandywine Creek, East 2 Bradford Township, Bridge Painting 214,000 3 (Base Construction Allocation - 4 $186,000) 5 (Design and Contingencies - $28,000) 6 (8) SR 1049, Rapp's Dam Covered Bridge, 7 East Pikeland Township, Bridge 8 Painting 47,000 9 (Base Construction Allocation - 10 $41,000) 11 (Design and Contingencies - $6,000) 12 (9) SR 2011, Phoenixville Pike Bridge 13 under Abandoned Penn Central Railroad, 14 West Goshen Township, Bridge Removal 125,000 15 (Base Construction Allocation - 16 $100,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $15,000) 19 (10) SR 2018, Green Hill Road Bridge under 20 Abandoned Penn Central Railroad, West 21 Goshen Township, Bridge Removal 125,000 22 (Base Construction Allocation - 23 $100,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $15,000) 26 (11) SR 3045, Springdell Road Bridge under 27 Abandoned Penn Central Railroad, West 28 Marborough Township, Bridge Removal 125,000 29 (Base Construction Allocation - 30 $100,000) 19970S0186B0698 - 127 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $15,000) 3 (12) SR 3049, Hilltop View Road Bridge 4 over Buck and Doe Run Creek, Newlin 5 Township, Bridge Replacement 1,450,000 6 (Base Construction Allocation - 7 $1,300,000) 8 (Land Allocation - $50,000) 9 (Design and Contingencies - $100,000) 10 (13) SR 1012, Bridge over Trout Creek, 11 Tredyffrin Township, Bridge 12 Replacement 850,000 13 (Base Construction Allocation - 14 $550,000) 15 (Land Allocation - $50,000) 16 (Design and Contingencies - $250,000) 17 Section 20. Clarion County. 18 (a) Local Bridges 19 (1) Beaver Township, T-400, Canoe Creek 20 Bridge over Canoe Creek, Bridge 21 Replacement 380,000 22 (Base Construction Allocation - 23 $300,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $70,000) 26 (2) Beaver Township, T-422, Deer Creek 27 Bridge over Deer Creek, Bridge 28 Replacement 540,000 29 (Base Construction Allocation - 30 $450,000) 19970S0186B0698 - 128 -
1 (Land Allocation - $30,000) 2 (Design and Contingencies - $60,000) 3 (3) Clarion and Millcreek Townships, T- 4 490, Mill Creek Bridge over Mill Creek, 5 Bridge Replacement 540,000 6 (Base Construction Allocation - 7 $450,000) 8 (Land Allocation - $10,000) 9 (Design and Contingencies - $80,000) 10 (4) Elk Township, T-424, Deer Creek Bridge 11 over Deer Creek, Bridge Replacement 620,000 12 (Base Construction Allocation - 13 $500,000) 14 (Land Allocation - $20,000) 15 (Design and Contingencies - $100,000) 16 (5) Farmington Township, T-562, Walley Run 17 Bridge over Walley Run, Bridge 18 Replacement 375,000 19 (Base Construction Allocation - 20 $300,000) 21 (Land Allocation - $5,000) 22 (Design and Contingencies - $70,000) 23 (6) Knox Township, T-850, Toby Creek 24 Bridge over Toby Creek, Bridge 25 Replacement 480,000 26 (Base Construction Allocation - 27 $400,000) 28 (Land Allocation - $20,000) 29 (Design and Contingencies - $60,000) 30 (7) Knox Township, T-600, Licking Creek 19970S0186B0698 - 129 -
1 Bridge over Licking Creek, Bridge 2 Replacement 445,000 3 (Base Construction Allocation - 4 $350,000) 5 (Land Allocation - $15,000) 6 (Design and Contingencies - $80,000) 7 (8) Madison Township, T-460, Red Bank 8 Creek Bridge over Tributary of Red Bank 9 Creek, Bridge Replacement 390,000 10 (Base Construction Allocation - 11 $300,000) 12 (Land Allocation - $20,000) 13 (Design and Contingencies - $70,000) 14 (9) Porter Township, T-462, Fiddlers Run 15 Bridge over Fiddlers Run, Bridge 16 Replacement 390,000 17 (Base Construction Allocation - 18 $300,000) 19 (Land Allocation - $10,000) 20 (Design and Contingencies - $80,000) 21 (10) Porter Township, T-472, Leatherwood 22 Creek Bridge over Leatherwood Creek, 23 Bridge Replacement 455,000 24 (Base Construction Allocation - 25 $375,000) 26 (Land Allocation - $20,000) 27 (Design and Contingencies - $60,000) 28 (11) Porter Township, T-750, Leisure Run 29 Bridge over Leisure Run, Bridge 30 Replacement 390,000 19970S0186B0698 - 130 -
1 (Base Construction Allocation - 2 $300,000) 3 (Land Allocation - $10,000) 4 (Design and Contingencies - $80,000) 5 (12) Red Bank Township, T-840, Beaver 6 Creek Bridge over Beaver Creek, Bridge 7 Replacement 420,000 8 (Base Construction Allocation - 9 $350,000) 10 (Land Allocation - $15,000) 11 (Design and Contingencies - $55,000) 12 (13) Red Bank Township, T-508, County 13 Bridge No.46, Pine Creek Bridge over 14 Pine Creek, Bridge Replacement 378,000 15 (Base Construction Allocation - 16 $300,000) 17 (Land Allocation - $8,000) 18 (Design and Contingencies - $70,000) 19 (14) Richland Township, T-382, Turkey Run 20 Bridge over Turkey Run, Bridge 21 Replacement 360,000 22 (Base Construction Allocation - 23 $300,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $50,000) 26 (15) Richland Township, T-382, Turkey Run 27 Bridge over Turkey Run, Bridge 28 Replacement 360,000 29 (Base Construction Allocation - 30 $300,000) 19970S0186B0698 - 131 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $50,000) 3 (16) Sligo Borough, Madison Street Bridge 4 over Little Licking Creek, Bridge 5 Replacement 445,000 6 (Base Construction Allocation - 7 $350,000) 8 (Land Allocation - $15,000) 9 (Design and Contingencies - $80,000) 10 (17) Beaver Township, T-332 over Beaver <-- 11 Creek, Bridge Replacement 400,000 12 (Base Construction Allocation - 13 $275,000) 14 (Land Allocation - $50,000) 15 (Design and Contingencies - $75,000) 16 (17) BEAVER TOWNSHIP, T-332, BRIDGE NO.17 <-- 17 OVER BEAVER CREEK, BRIDGE REPLACEMENT 560,000 18 (BASE CONSTRUCTION ALLOCATION - 19 $400,000) 20 (LAND ALLOCATION - $10,000) 21 (DESIGN AND CONTINGENCIES - $150,000) 22 (18) Beaver Township, T-385 over Canoe 23 Creek, Bridge Replacement 490,000 24 (Base Construction Allocation - 25 $320,000) 26 (Land Allocation - $80,000) 27 (Design and Contingencies - $90,000) 28 (19) Highland Township, T-573 over Toby 29 Creek, Bridge Replacement 500,000 30 (Base Construction Allocation - 19970S0186B0698 - 132 -
1 $360,000) 2 (Land Allocation - $40,000) 3 (Design and Contingencies - $100,000) 4 (20) Knox Township, T-850 over Step Creek, 5 Bridge Replacement 240,000 6 (Base Construction Allocation - 7 $180,000) 8 (Land Allocation - $20,000) 9 (Design and Contingencies - $40,000) 10 (21) Perry Township, T-301, Bridge 11 Replacement 200,000 12 (Base Construction Allocation - 13 $130,000) 14 (Land Allocation - $30,000) 15 (Design and Contingencies - $40,000) 16 (22) Millcreek Township, T-564 over Little 17 Mill Creek, Bridge Replacement 480,000 18 (Base Construction Allocation - 19 $400,000) 20 (Land Allocation - $20,000) 21 (Design and Contingencies - $60,000) 22 (23) Paint Township, T-578 over Step 23 Creek, Bridge Replacement 500,000 24 (Base Construction Allocation - 25 $400,000) 26 (Land Allocation - $20,000) 27 (Design and Contingencies - $80,000) 28 (24) Monroe Township, T-486, County Bridge 29 No.22 over Piney Creek, Bridge 30 Replacement 480,000 19970S0186B0698 - 133 -
1 (Base Construction Allocation - 2 $400,000) 3 (Land Allocation - $10,000) 4 (Design and Contingencies - $70,000) 5 (25) Clarion Township, T-532 over Brush 6 Run, Bridge Replacement 245,000 7 (Base Construction Allocation - 8 $200,000) 9 (Land Allocation - $10,000) 10 (Design and Contingencies - $35,000) 11 (26) Clarion Township, T-561 over Jones 12 Run, Bridge Replacement 245,000 13 (Base Construction Allocation - 14 $200,000) 15 (Land Allocation - $10,000) 16 (Design and Contingencies - $35,000) 17 (27) Elk Township, T-582 over Mahles Run, 18 Bridge Replacement 245,000 19 (Base Construction Allocation - 20 $200,000) 21 (Land Allocation - $10,000) 22 (Design and Contingencies - $35,000) 23 (28) Farmington Township, T-609 over Engle 24 Run, Bridge Replacement 245,000 25 (Base Construction Allocation - 26 $200,000) 27 (Land Allocation - $10,000) 28 (Design and Contingencies - $35,000) 29 (29) Paint Township, T-577 over Toby 30 Creek, Bridge Replacement 106,000 19970S0186B0698 - 134 -
1 (Base Construction Allocation - 2 $100,000) 3 (Land Allocation - $1,000) 4 (Design and Contingencies - $5,000) 5 (30) Paint Township, T-576 over Toby 6 Creek, Bridge Replacement 106,000 7 (Base Construction Allocation - 8 $100,000) 9 (Land Allocation - $1,000) 10 (Design and Contingencies - $5,000) 11 (31) Beaver Township, T-405 over Canoe 12 Creek, Bridge Replacement 106,000 13 (Base Construction Allocation - 14 $100,000) 15 (Land Allocation - $1,000) 16 (Design and Contingencies - $5,000) 17 (32) Beaver Township, T-411 over Boyd Run, 18 Bridge Replacement 106,000 19 (Base Construction Allocation - 20 $100,000) 21 (Land Allocation - $1,000) 22 (Design and Contingencies - $5,000) 23 (33) Elk Township, T-424 over Deer Creek, 24 Bridge Replacement 250,000 25 (Base Construction Allocation - 26 $200,000) 27 (Land Allocation - $10,000) 28 (Design and Contingencies - $40,000) 29 (34) Highland Township, T-577, Bridge over 30 Toby Creek, Bridge Replacement 518,000 19970S0186B0698 - 135 -
1 (Base Construction Allocation - 2 $380,000) 3 (Land Allocation - $8,000) 4 (Design and Contingencies - $130,000) 5 (35) Beaver Township, T-423, Bridge over 6 Canoe Creek, Bridge Replacement 510,000 7 (Base Construction Allocation - 8 $400,000) 9 (Land Allocation - $10,000) 10 (Design and Contingencies - $100,000) 11 (36) Elk Township, T-418, Bridge over Deer 12 Creek, Bridge Replacement 380,000 13 (Base Construction Allocation - 14 $300,000) 15 (Land Allocation - $10,000) 16 (Design and Contingencies - $70,000) 17 (37) Paint Township, T-582, Bridge over 18 Little Paint Creek, Bridge Replacement 424,000 19 (Base Construction Allocation - 20 $350,000) 21 (Land Allocation - $9,000) 22 (Design and Contingencies - $65,000) 23 (38) ASHLAND TOWNSHIP, T-863, BRIDGE OVER <-- 24 LITTLE CANOE CREEK, BRIDGE REPLACEMENT 330,000 25 (BASE CONSTRUCTION ALLOCATION - 26 $200,000) 27 (LAND ALLOCATION - $10,000) 28 (DESIGN AND CONTINGENCIES - $120,000) 29 (39) BEAVER TOWNSHIP, T-325, SCHETTLER 30 ROAD BRIDGE OVER CANOE CREEK, BRIDGE 19970S0186B0698 - 136 -
1 REPLACEMENT 395,000 2 (BASE CONSTRUCTION ALLOCATION - 3 $250,000) 4 (LAND ALLOCATION - $15,000) 5 (DESIGN AND CONTINGENCIES - $130,000) 6 (40) MADISON TOWNSHIP, T-442, BRIDGE NO.34 7 OVER WILDCAT RUN, BRIDGE REPLACEMENT 425,000 8 (BASE CONSTRUCTION ALLOCATION - 9 $275,000) 10 (LAND ALLOCATION - $10,000) 11 (DESIGN AND CONTINGENCIES - $140,000) 12 (41) MADISON TOWNSHIP, T-689, BRIDGE NO.33 13 OVER WILDCAT RUN, BRIDGE REPLACEMENT 460,000 14 (BASE CONSTRUCTION ALLOCATION - 15 $300,000) 16 (LAND ALLOCATION - $10,000) 17 (DESIGN AND CONTINGENCIES - $150,000) 18 (42) MADISON TOWNSHIP, T-880, BRIDGE 19 NO.2050 OVER TURKEY RUN, BRIDGE 20 REPLACEMENT 330,000 21 (BASE CONSTRUCTION ALLOCATION - 22 $200,000) 23 (LAND ALLOCATION - $10,000) 24 (DESIGN AND CONTINGENCIES - $120,000) 25 (b) State Bridges 26 (1) SR 0058, Callensburg Bridge over 27 Clarion River, Licking Township, Bridge 28 Painting 365,000 29 (Base Construction Allocation - 30 $350,000) 19970S0186B0698 - 137 -
1 (Design and Contingencies - $15,000) 2 (2) SR 0080, Beaver Creek Eastbound Bridge 3 over Beaver Creek, Beaver Township, 4 Bridge Painting 390,000 5 (Base Construction Allocation - 6 $375,000) 7 (Design and Contingencies - $15,000) 8 (3) SR 0080, Beaver Creek Westbound Bridge 9 over Beaver Creek, Beaver Township, 10 Bridge Painting 390,000 11 (Base Construction Allocation - 12 $375,000) 13 (Design and Contingencies - $15,000) 14 (4) SR 0080, Canoe Creek Eastbound Bridge 15 over Canoe Creek, Beaver Township, 16 Bridge Painting 1,230,000 17 (Base Construction Allocation - 18 $1,200,000) 19 (Design and Contingencies - $30,000) 20 (5) SR 0080, Canoe Creek Westbound Bridge 21 over Canoe Creek, Beaver Township, 22 Bridge Painting 1,290,000 23 (Base Construction Allocation - 24 $1,260,000) 25 (Design and Contingencies - $30,000) 26 (6) SR 0080, TR 558 Bridge over I-80, 27 Clarion Township, Bridge Painting 195,000 28 (Base Construction Allocation - 29 $180,000) 30 (Design and Contingencies - $15,000) 19970S0186B0698 - 138 -
1 (7) SR 0322, Exit 11 Bridge over I-80, 2 Clarion Township, Clarion Bridge 3 Painting 205,000 4 (Base Construction Allocation - 5 $190,000) 6 (Design and Contingencies - $15,000) 7 (8) SR 0536, Mayport Bridge over Redbank 8 Creek, Red Bank Township, Bridge 9 Painting 215,000 10 (Base Construction Allocation - 11 $200,000) 12 (Design and Contingencies - $15,000) 13 (9) SR 1009, Brush Creek Bridge over Brush 14 Creek, Clarion Township, Bridge 15 Painting 70,000 16 (Base Construction Allocation - 17 $55,000) 18 (Design and Contingencies - $15,000) 19 (10) SR 2001, Piney Creek Bridge over 20 Piney Creek, Limestone Township, Bridge 21 Painting 85,000 22 (Base Construction Allocation - 23 $70,000) 24 (Design and Contingencies - $15,000) 25 (11) SR 2001, Little Piney Creek Bridge 26 over Little Piney Creek, Limestone 27 Township, Bridge Painting 70,000 28 (Base Construction Allocation - 29 $55,000) 30 (Design and Contingencies - $15,000) 19970S0186B0698 - 139 -
1 (12) SR 2005, Glade Run Bridge over Glade 2 Run, Limestone Township, Bridge 3 Painting 60,000 4 (Base Construction Allocation - 5 $45,000) 6 (Design and Contingencies - $15,000) 7 (13) SR 2007, Licking Creek Bridge over 8 Licking Creek, Monroe Township, Bridge 9 Painting 75,000 10 (Base Construction Allocation - 11 $60,000) 12 (Design and Contingencies - $15,000) 13 (14) SR 2009, Lawsonham Bridge over 14 Redbank Creek, Madison Township, Bridge 15 Painting 195,000 16 (Base Construction Allocation - 17 $180,000) 18 (Design and Contingencies - $15,000) 19 (15) SR 2009, Wildcat Run Bridge over 20 Wildcat Run, Madison Township, Bridge 21 Painting 85,000 22 (Base Construction Allocation - 23 $70,000) 24 (Design and Contingencies - $15,000) 25 (16) SR 2015, Little Piney Creek Bridge 26 over Little Piney Creek, Limestone 27 Township, Bridge Painting 60,000 28 (Base Construction Allocation - 29 $45,000) 30 (Design and Contingencies - $15,000) 19970S0186B0698 - 140 -
1 (17) SR 3020, Alum Rock Bridge over Turkey 2 Run, Richland Township, Bridge 3 Painting 75,000 4 (Base Construction Allocation - 5 $60,000) 6 (Design and Contingencies - $15,000) 7 (18) SR 4003, Turkey Run Bridge over 8 Turkey Run, Richland Township, Bridge 9 Painting 65,000 10 (Base Construction Allocation - 11 $50,000) 12 (Design and Contingencies - $15,000) 13 (19) SR 4005, Canoe Creek Bridge over 14 Canoe Creek, Beaver Township, Bridge 15 Painting 70,000 16 (Base Construction Allocation - 17 $55,000) 18 (Design and Contingencies - $15,000) 19 (20) SR 0208, Conrail Overpass, Elk 20 Township, Bridge Removal 120,000 21 (Base Construction Allocation - 22 $80,000) 23 (Land Allocation - $10,000) 24 (Design and Contingencies - $30,000) 25 (21) SR 0322, Conrail Overpass, Elk 26 Township, Bridge Removal 250,000 27 (Base Construction Allocation - 28 $200,000) 29 (Land Allocation - $10,000) 30 (Design and Contingencies - $40,000) 19970S0186B0698 - 141 -
1 (22) SR 1011, Lake Erie, Franklin and 2 Clarion Railroad Overpass, Clarion 3 Township, Bridge Removal 12,000 4 (Base Construction Allocation - 5 $10,000) 6 (Design and Contingencies - $2,000) 7 (23) SR 0066, Bridge over Piney Creek, 8 Limestone Township, Bridge Replacement 650,000 9 (Base Construction Allocation - 10 $500,000) 11 (Land Allocation - $20,000) 12 (Design and Contingencies - $130,000) 13 (24) SR 0066, Bridge over Little Piney 14 Creek, Limestone Township, Bridge 15 Replacement 600,000 16 (Base Construction Allocation - 17 $450,000) 18 (Land Allocation - $20,000) 19 (Design and Contingencies - $130,000) 20 (25) SR 0068, Bridge over Brush Run, 21 Monroe Township, Bridge Replacement 650,000 22 (Base Construction Allocation - 23 $500,000) 24 (Land Allocation - $20,000) 25 (Design and Contingencies - $130,000) 26 (26) SR 0208, Bridge over Canoe Creek, 27 Beaver Township, Bridge Replacement 550,000 28 (Base Construction Allocation - 29 $400,000) 30 (Land Allocation - $20,000) 19970S0186B0698 - 142 -
1 (Design and Contingencies - $130,000) 2 (27) SR 2001, Bridge over Little Piney 3 Creek, Limestone Township, Bridge 4 Replacement 490,000 5 (Base Construction Allocation - 6 $350,000) 7 (Land Allocation - $20,000) 8 (Design and Contingencies - $120,000) 9 (28) SR 0208, SR 0208 over Deer Creek, Elk 10 Township, Bridge Replacement 505,000 11 (Base Construction Allocation - 12 $450,000) 13 (Land Allocation - $5,000) 14 (Design and Contingencies - $50,000) 15 (29) SR 2007, SR 2007 over Deer Creek, 16 Beaver Township, Bridge Replacement 455,000 17 (Base Construction Allocation - 18 $400,000) 19 (Land Allocation - $5,000) 20 (Design and Contingencies - $50,000) 21 (30) SR 4005, SR 4005 over Canoe Creek, 22 Beaver Township, Bridge Replacement 405,000 23 (Base Construction Allocation - 24 $350,000) 25 (Land Allocation - $5,000) 26 (Design and Contingencies - $50,000) 27 (31) SR 4008, SR 4008 over Paint Creek, 28 Knox Township, Bridge Replacement 505,000 29 (Base Construction Allocation - 30 $450,000) 19970S0186B0698 - 143 -
1 (Land Allocation - $5,000) 2 (Design and Contingencies - $50,000) 3 Section 21. Clearfield County. 4 (a) Local Bridges 5 (1) Knox Township, T-565 Bridge over Potts 6 Run, Bridge Replacement 510,000 7 (Base Construction Allocation - 8 $350,000) 9 (Land Allocation - $10,000) 10 (Design and Contingencies - $150,000) 11 (2) Houtzdale Borough, McAteer Street 12 Bridge, Bridge Replacement 430,000 13 (Base Construction Allocation - 14 $270,000) 15 (Land Allocation - $20,000) 16 (Design and Contingencies - $140,000) 17 (3) Penn Township, T-461 over Bell Run, 18 Bridge Replacement 106,000 19 (Base Construction Allocation - 20 $100,000) 21 (Land Allocation - $1,000) 22 (Design and Contingencies - $5,000) 23 (b) State Bridges 24 (1) SR 0879, Bridge over US 322 near 25 Clearfield Mall, Lawrence Township, 26 Bridge Painting 644,000 27 (Base Construction Allocation - 28 $614,000) 29 (Design and Contingencies - $30,000) 30 (2) SR 0729, Bridge over Muddy Run, 19970S0186B0698 - 144 -
1 Beccaria Township, Bridge Painting 35,000 2 (Base Construction Allocation - 3 $30,000) 4 (Design and Contingencies - $5,000) 5 (3) SR 0879, Bridge over Susquehanna 6 River, Lawrence Township, Bridge 7 Painting 183,000 8 (Base Construction Allocation - 9 $163,000) 10 (Design and Contingencies - $20,000) 11 (4) SR 0970, Bridge over Moshannon Creek, 12 Osceola Mills, Bridge Painting 145,000 13 (Base Construction Allocation - 14 $120,000) 15 (Design and Contingencies - $25,000) 16 (5) SR 0970, Bridge over Susquehanna 17 River, Village of Shawville, Bridge 18 Painting 163,000 19 (Base Construction Allocation - 20 $143,000) 21 (Design and Contingencies - $20,000) 22 (6) SR 1009, Bridge over Alder Run, Morris 23 Township, Bridge Painting 18,000 24 (Base Construction Allocation - 25 $15,000) 26 (Design and Contingencies - $3,000) 27 (7) SR 1014, Bridge over Alder Run, Graham 28 Township, Bridge Painting 18,000 29 (Base Construction Allocation - 30 $15,000) 19970S0186B0698 - 145 -
1 (Design and Contingencies - $3,000) 2 (8) SR 2010, Bridge over Beaver Run, 3 Woodward Township, Bridge Painting 18,000 4 (Base Construction Allocation - 5 $15,000) 6 (Design and Contingencies - $3,000) 7 (9) SR 2024, Bridge over Conrail, Pike 8 Township, Bridge Painting 28,000 9 (Base Construction Allocation - 10 $24,000) 11 (Design and Contingencies - $4,000) 12 (10) SR 3001, Bridge over Chest Creek, 13 Mahaffey Borough, Bridge Replacement 1,750,000 14 (Base Construction Allocation - 15 $1,300,000) 16 (Land Allocation - $150,000) 17 (Design and Contingencies - $300,000) 18 (11) SR 3012, Bridge over Matthews Run, 19 Beccaria Township, Bridge Painting 18,000 20 (Base Construction Allocation - 21 $15,000) 22 (Design and Contingencies - $3,000) 23 (12) SR 3012, Bridge over Clearfield 24 Creek, Beccaria Township, Bridge 25 Painting 100,000 26 (Base Construction Allocation - 27 $90,000) 28 (Design and Contingencies - $10,000) 29 (13) SR 0219, SR 0219 over Bear Run, Bell 30 Township, Bridge Replacement 505,000 19970S0186B0698 - 146 -
1 (Base Construction Allocation - 2 $450,000) 3 (Land Allocation - $5,000) 4 (Design and Contingencies - $50,000) 5 (14) SR 2014, BRIDGE OVER COAL RUN, <-- 6 DECATUR TOWNSHIP, BRIDGE REPLACEMENT 692,000 7 (BASE CONSTRUCTION ALLOCATION - 8 $512,000) 9 (LAND ALLOCATION - $30,000) 10 (DESIGN AND CONTINGENCIES - $150,000) 11 (15) SR 3012, BRIDGE OVER CLEARFIELD 12 CREEK, BECCARIA TOWNSHIP, BRIDGE 13 PAINTING 18,000 14 (BASE CONSTRUCTION ALLOCATION - 15 $15,000) 16 (DESIGN AND CONTINGENCIES - $3,000) 17 Section 22. Clinton County. 18 (a) Local Bridges 19 (1) Mill Hall Borough, Church Street over 20 Fishing Creek, Bridge Rehabilitation 5,000 21 (Base Construction Allocation - $4,000) 22 (Design and Contingencies - $1,000) 23 (b) State Bridges 24 (1) SR 0044, Bridge over SR 0220, 1 Mile 25 Northeast of Avis, Pine Creek Township, 26 Bridge Painting 580,000 27 (Base Construction Allocation - 28 $525,000) 29 (Design and Contingencies - $55,000) 30 (2) SR 0080, Lamar Interchange (Two 19970S0186B0698 - 147 -
1 Bridges) over PA 64 at Exit 25, Porter 2 Township, Bridge Rehabilitation 4,100,000 3 (Base Construction Allocation - 4 $3,400,000) 5 (Design and Contingencies - $700,000) 6 (3) SR 0144, Bridge over Kettle Creek, 1 7 Mile East of Hammersley Fork, Leidy 8 Township, Bridge Painting 660,000 9 (Base Construction Allocation - 10 $600,000) 11 (Design and Contingencies - $60,000) 12 Section 23. Columbia County. 13 (a) Local Bridges (Reserved) 14 (b) State Bridges 15 (1) SR 0044, Chillisquaque Creek Bridge 16 over Chillisquaque Creek, 3 Miles 17 Northwest of Jerseytown, Bridge 18 Replacement 477,000 19 (Base Construction Allocation - 20 $382,000) 21 (Land Allocation - $24,000) 22 (Design and Contingencies - $71,000) 23 (2) SR 0093, Bridge over North Branch of 24 Briar Creek, Bridge Replacement 350,000 25 (Base Construction Allocation - 26 $275,000) 27 (Land Allocation - $15,000) 28 (Design and Contingencies - $60,000) 29 (3) SR 0093, Briar Creek Bridge over Briar 30 Creek, 3 Miles West of Berwick, Bridge 19970S0186B0698 - 148 -
1 Replacement 392,000 2 (Base Construction Allocation - 3 $315,000) 4 (Land Allocation - $18,000) 5 (Design and Contingencies - $59,000) 6 (4) SR 0239, West Creek Bridge over West 7 Creek, Southeast of Benton and 8 Sugarloaf Townships, Bridge 9 Replacement 670,000 10 (Base Construction Allocation - 11 $536,000) 12 (Land Allocation - $34,000) 13 (Design and Contingencies - $100,000) 14 (5) SR 0442, West Branch Run Bridge over 15 West Branch Run, 1.5 Miles North of 16 Iola, Bridge Replacement 206,000 17 (Base Construction Allocation - 18 $165,000) 19 (Land Allocation - $10,000) 20 (Design and Contingencies - $31,000) 21 (6) SR 1004, Erie-Lackawanna Railroad 22 Bridge, Viaduct over Conrail, South 23 Centre Township, Bridge Replacement 1,900,000 24 (Base Construction Allocation - 25 $1,600,000) 26 (Land Allocation - $110,000) 27 (Design and Contingencies - $190,000) 28 (7) SR 1019, Briar Creek Bridge over Briar 29 Creek, Briar Creek Township, Bridge 30 Replacement 404,000 19970S0186B0698 - 149 -
1 (Base Construction Allocation - 2 $323,000) 3 (Land Allocation - $20,000) 4 (Design and Contingencies - $61,000) 5 (8) SR 4012, Little Hemlock Creek Bridge 6 over Little Hemlock Creek, 10 Miles 7 Southeast of Jerseytown, Bridge 8 Replacement 284,000 9 (Base Construction Allocation - 10 $227,000) 11 (Land Allocation - $14,000) 12 (Design and Contingencies - $43,000) 13 (9) SR 4037, Mud Run Bridge over Mud Run, 14 5 Miles Northwest of Millville Borough, 15 Bridge Replacement 307,000 16 (Base Construction Allocation - 17 $246,000) 18 (Land Allocation - $15,000) 19 (Design and Contingencies - $46,000) 20 (10) SR 0011, Bridge over Fishing Creek, 21 Bridge Painting 530,000 22 (Base Construction Allocation - 23 $520,000) 24 (Design and Contingencies - $10,000) 25 (11) SR 1022, Bridge over Fishing Creek, 26 Bridge Painting 380,000 27 (Base Construction Allocation - 28 $370,000) 29 (Design and Contingencies - $10,000) 30 (12) SR 1022, Bridge over Old Channel, 19970S0186B0698 - 150 -
1 Bridge Painting 125,000 2 (Base Construction Allocation - 3 $115,000) 4 (Design and Contingencies - $10,000) 5 (13) SR 4009, Bridge over Fishing Creek, 6 Bridge Painting 315,000 7 (Base Construction Allocation - 8 $305,000) 9 (Design and Contingencies - $10,000) 10 (14) SR 0042, SR 0042 over Roaring Creek, 11 Conyngham Township, Bridge Replacement 457,000 12 (Base Construction Allocation - 13 $366,000) 14 (Land Allocation - $23,000) 15 (Design and Contingencies - $68,000) 16 (15) SR 0239, SR 0239 over West Creek, 17 Benton Township, Bridge Replacement 760,000 18 (Base Construction Allocation - 19 $560,000) 20 (Land Allocation - $35,000) 21 (Design and Contingencies - $165,000) 22 (16) SR 0254, SR 0254 over Little Fishing 23 Creek, Millville Borough, Bridge 24 Replacement 1,020,000 25 (Base Construction Allocation - 26 $816,000) 27 (Land Allocation - $51,000) 28 (Design and Contingencies - $153,000) 29 (17) SR 0339, SR 0339 over Beaver Run, 30 Beaver Township, Bridge Replacement 320,000 19970S0186B0698 - 151 -
1 (Base Construction Allocation - 2 $256,000) 3 (Land Allocation - $16,000) 4 (Design and Contingencies - $48,000) 5 (18) SR 0487, SR 0487 over Stony Brook, 6 Orange Township, Bridge Replacement 380,000 7 (Base Construction Allocation - 8 $304,000) 9 (Land Allocation - $19,000) 10 (Design and Contingencies - $57,000) 11 (19) SR 1014, SR 1014 over Little Briar 12 Creek, Briar Creek Township, Bridge 13 Replacement 415,000 14 (Base Construction Allocation - 15 $332,000) 16 (Land Allocation - $21,000) 17 (Design and Contingencies - $62,000) 18 (20) SR 1023, SR 1023 over East Briar 19 Creek, Briar Creek Township, Bridge 20 Replacement 520,000 21 (Base Construction Allocation - 22 $466,000) 23 (Land Allocation - $29,000) 24 (Design and Contingencies - $25,000) 25 (21) SR 2003, SR 2003 over Tributary of 26 Roaring Creek, Roaring Creek Township, 27 Bridge Replacement 171,000 28 (Base Construction Allocation - 29 $136,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 152 -
1 (Design and Contingencies - $25,000) 2 (22) SR 2003, SR 2003 over Tributary of 3 Roaring Creek, Locust Township, Bridge 4 Replacement 245,000 5 (Base Construction Allocation - 6 $196,000) 7 (Land Allocation - $12,000) 8 (Design and Contingencies - $37,000) 9 (23) SR 2009, SR 2009 over Catawissa 10 Creek, Main Township, Bridge 11 Replacement 436,000 12 (Base Construction Allocation - 13 $349,000) 14 (Land Allocation - $22,000) 15 (Design and Contingencies - $65,000) 16 (24) SR 4009, SR 4009 over Little Fishing 17 Creek, Mt. Pleasant Township, Bridge 18 Replacement 1,232,000 19 (Base Construction Allocation - 20 $986,000) 21 (Land Allocation - $61,000) 22 (Design and Contingencies - $185,000) 23 (25) SR 4033, SR 4033 over Wolfhouse Run, 24 Pine Township, Bridge Replacement 252,000 25 (Base Construction Allocation - 26 $202,000) 27 (Land Allocation - $12,000) 28 (Design and Contingencies - $38,000) 29 (26) SR 4045, SR 4045 over Green Creek, 30 Greenwood Township, Bridge Replacement 435,000 19970S0186B0698 - 153 -
1 (Base Construction Allocation - 2 $348,000) 3 (Land Allocation - $22,000) 4 (Design and Contingencies - $65,000) 5 (27) SR 4049, SR 4049 over Coles Creek, 6 Sugarloaf Township, Bridge Replacement 1,095,000 7 (Base Construction Allocation - 8 $876,000) 9 (Land Allocation - $55,000) 10 (Design and Contingencies - $164,000) 11 Section 24. Crawford County. 12 (a) Local Bridges 13 (1) Fairfield Township, T-636 over Branch 14 of French Creek, Bridge Replacement 108,000 15 (Base Construction Allocation - 16 $100,000) 17 (Land Allocation - $1,000) 18 (Design and Contingencies - $7,000) 19 (2) Fairfield Township, T-321 Bridge No.1 20 over Branch of French Creek, Bridge 21 Replacement 106,000 22 (Base Construction Allocation - 23 $100,000) 24 (Land Allocation - $1,000) 25 (Design and Contingencies - $5,000) 26 (3) Fairfield Township, T-321 Bridge No.2 27 over Branch of French Creek, Bridge 28 Replacement 106,000 29 (Base Construction Allocation - 30 $100,000) 19970S0186B0698 - 154 -
1 (Land Allocation - $1,000) 2 (Design and Contingencies - $5,000) 3 (4) Spring Township, T-747 over Branch of 4 Conneaut Creek, Bridge Replacement 126,000 5 (Base Construction Allocation - 6 $120,000) 7 (Land Allocation - $1,000) 8 (Design and Contingencies - $5,000) 9 (5) Wayne Township, T-347 over Branch of 10 Powdermill Run, Bridge Replacement 106,000 11 (Base Construction Allocation - 12 $100,000) 13 (Land Allocation - $1,000) 14 (Design and Contingencies - $5,000) 15 (6) Wayne Township, T-457 over Tributary 16 of Lake Creek, Bridge Replacement 106,000 17 (Base Construction Allocation - 18 $100,000) 19 (Land Allocation - $1,000) 20 (Design and Contingencies - $5,000) 21 (b) State Bridges 22 (1) SR 0006, SR 0006 over Padan Creek, 23 Conneaut Township, Bridge Replacement 1,004,000 24 (Base Construction Allocation - 25 $784,000) 26 (Land Allocation - $20,000) 27 (Design and Contingencies - $200,000) 28 (2) SR 0006, SR 0006 over French Creek, 29 Woodcock Township, Bridge Replacement 2,325,000 30 (Base Construction Allocation - 19970S0186B0698 - 155 -
1 $1,840,000) 2 (Land Allocation - $20,000) 3 (Design and Contingencies - $465,000) 4 (3) SR 0079, SR 0079 under Maple Drive, 5 Hayfield Township, Bridge Replacement 2,401,000 6 (Base Construction Allocation - 7 $1,901,000) 8 (Land Allocation - $20,000) 9 (Design and Contingencies - $480,000) 10 (4) SR 0089, SR 0089 over Shirley Run, 11 Rome Township, Bridge Replacement 510,000 12 (Base Construction Allocation - 13 $420,000) 14 (Land Allocation - $20,000) 15 (Design and Contingencies - $70,000) 16 (5) SR 0098, SR 0098 over Van Horne Run, 17 Vernon Township, Bridge Replacement 320,000 18 (Base Construction Allocation - 19 $260,000) 20 (Land Allocation - $10,000) 21 (Design and Contingencies - $50,000) 22 (6) SR 0099, SR 0099 over Little 23 Conneauttee Creek, Cambridge Township, 24 Bridge Replacement 950,000 25 (Base Construction Allocation - 26 $700,000) 27 (Land Allocation - $50,000) 28 (Design and Contingencies - $200,000) 29 (7) SR 0099, SR 0099 over Conneaut Creek, 30 Cambridge Township, Bridge Replacement 600,000 19970S0186B0698 - 156 -
1 (Base Construction Allocation - 2 $500,000) 3 (Land Allocation - $30,000) 4 (Design and Contingencies - $70,000) 5 (8) SR 0198, SR 0198 over Carr Run, 6 Woodcock Township, Bridge Replacement 260,000 7 (Base Construction Allocation - 8 $200,000) 9 (Land Allocation - $20,000) 10 (Design and Contingencies - $40,000) 11 (9) SR 0285, SR 0285 over Bennett Run, 12 North Shenango Township, Bridge 13 Replacement 750,000 14 (Base Construction Allocation - 15 $650,000) 16 (Land Allocation - $20,000) 17 (Design and Contingencies - $80,000) 18 (10) SR 1002, SR 1002 over Acker Run, 19 Venango Township, Bridge Replacement 370,000 20 (Base Construction Allocation - 21 $300,000) 22 (Land Allocation - $20,000) 23 (Design and Contingencies - $50,000) 24 (11) SR 1024, SR 1024 over Britton Run, 25 Sparta Township, Bridge Replacement 340,000 26 (Base Construction Allocation - 27 $250,000) 28 (Land Allocation - $20,000) 29 (Design and Contingencies - $70,000) 30 (12) SR 2005, SR 2005 over French Creek, 19970S0186B0698 - 157 -
1 East Fairfield Township, Bridge 2 Replacement 1,300,000 3 (Base Construction Allocation - 4 $1,130,000) 5 (Land Allocation - $20,000) 6 (Design and Contingencies - $150,000) 7 (13) SR 2010, SR 2010 over Little Sugar 8 Creek, Wayne Township, Bridge 9 Replacement 260,000 10 (Base Construction Allocation - 11 $200,000) 12 (Land Allocation - $20,000) 13 (Design and Contingencies - $40,000) 14 (14) SR 3016, SR 3016 over B&LE Railroad, 15 Summit Township, Bridge Replacement 1,150,000 16 (Base Construction Allocation - 17 $1,000,000) 18 (Land Allocation - $30,000) 19 (Design and Contingencies - $120,000) 20 (15) SR 0018, SR 0018 Bridge over 21 Tributary of Conneaut Creek, Summit 22 Township, Bridge Rehabilitation 115,000 23 (Base Construction Allocation - 24 $100,000) 25 (Design and Contingencies - $15,000) 26 (16) SR 0098, SR 0098 Bridge over 27 Tributary of Cussewago Creek, Hayfield 28 Township, Bridge Rehabilitation 110,000 29 (Base Construction Allocation - 30 $100,000) 19970S0186B0698 - 158 -
1 (Design and Contingencies - $10,000) 2 (17) SR 2003, Mercer Pike Bridge over 3 Conneaut Creek Outlet, Union Township, 4 Bridge Replacement 600,000 5 (Base Construction Allocation - 6 $520,000) 7 (Land Allocation - $30,000) 8 (Design and Contingencies - $50,000) 9 Section 25. (Reserved). 10 Section 26. Dauphin County. 11 (a) Local Bridges 12 (1) City of Harrisburg, Mulberry Street 13 Ramp to Cameron Street, Bridge 14 Rehabilitation 108,000 15 (Base Construction Allocation - 16 $73,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $ 25,000) 19 (2) City of Harrisburg, Maclay Street 20 Bridge over Railroad, Bridge 21 Rehabilitation 218,000 22 (Base Construction Allocation - 23 $183,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $25,000) 26 (3) Mifflin Township, T-631, Reitz Road 27 Bridge over Little Wiconisco Creek, 28 County Bridge No.24, Bridge 29 Replacement 290,000 30 (Base Construction Allocation - 19970S0186B0698 - 159 -
1 $200,000) 2 (Land Allocation - $10,000) 3 (Design and Contingencies - $80,000) 4 (4) Mifflin Township, T-556, Kessler Road 5 Bridge over Little Wiconisco Creek, 6 Bridge Replacement 235,000 7 (Base Construction Allocation - 8 $150,000) 9 (Land Allocation - $10,000) 10 (Design and Contingencies - $75,000) 11 (5) Washington Township, Bolts Road Bridge 12 over Wiconisco Creek, Bridge 13 Rehabilitation 469,000 14 (Base Construction Allocation - 15 $374,000) 16 (Land Allocation - $10,000) 17 (Design and Contingencies - $85,000) 18 (6) Wayne Township, T-496, Lebo Road 19 Bridge over Powell Creek, Bridge 20 Rehabilitation 263,000 21 (Base Construction Allocation - 22 $168,000) 23 (Land Allocation - $10,000) 24 (Design and Contingencies - $85,000) 25 (7) Conewago Township, T-602 and T-749 26 over Conewago Creek, Bridge 27 Replacement 722,000 28 (Base Construction Allocation - 29 $556,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 160 -
1 (Design and Contingencies - $156,000) 2 (8) Halifax Township, T-454 over Armstrong 3 Creek, Bridge Replacement 480,000 4 (Base Construction Allocation - 5 $367,000) 6 (Land Allocation - $10,000) 7 (Design and Contingencies - $103,000) 8 (9) Jackson Township, T-544 over Armstrong 9 Creek, Bridge Replacement 379,000 10 (Base Construction Allocation - 11 $288,000) 12 (Land Allocation - $10,000) 13 (Design and Contingencies - $81,000) 14 (10) Jefferson Township, T-534 over Powell 15 Creek, Bridge Replacement 397,000 16 (Base Construction Allocation - 17 $302,000) 18 (Land Allocation - $10,000) 19 (Design and Contingencies - $85,000) 20 (11) Upper Paxton Township, T-460 over 21 Wiconisco Creek, Bridge Replacement 427,000 22 (Base Construction Allocation - 23 $326,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $91,000) 26 (12) Washington Township, T-595 over 27 Wiconisco Creek, Bridge Replacement 669,000 28 (Base Construction Allocation - 29 $515,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 161 -
1 (Design and Contingencies - $144,000) 2 (13) Washington Township, T-462 over 3 Wiconisco Creek, Bridge Replacement 668,000 4 (Base Construction Allocation - 5 $514,000) 6 (Land Allocation - $10,000) 7 (Design and Contingencies - $144,000) 8 (14) Wayne Township, T-448 over Powell 9 Creek, Bridge Replacement 438,000 10 (Base Construction Allocation - 11 $334,000) 12 (Land Allocation (Design and <-- 13 Contingencies 14 - $94,000) 15 (LAND ALLOCATION - $10,000) <-- 16 (DESIGN AND CONTINGENCIES - $94,000) 17 (b) State Bridges (Reserved) 18 Section 27. Delaware County. 19 (a) Local Bridges 20 (1) City of Chester, West 7th Street, 21 County Bridge No.186 over Chester 22 Creek, Bridge Replacement 1,630,000 23 (Base Construction Allocation - 24 $1,470,000) 25 (Land Allocation - $10,000) 26 (Design and Contingencies - $150,000) 27 (b) State Bridges 28 (1) SR 0030, Pedestrian Tunnel under SR 29 0030 and Ithan Avenue at Villanova 30 University, Radnor Township, Pedestrian 19970S0186B0698 - 162 -
1 Facilities 7,360,000 2 (Base Construction Allocation - 3 $6,500,000) 4 (Land Allocation - $650,000) 5 (Design and Contingencies - $210,000) 6 (2) SR 1015, Darby-Paoli Road Bridge over 7 Branch of Little Darby Creek, Radnor 8 Township, Bridge Replacement 1,000,000 9 (Base Construction Allocation - 10 $760,000) 11 (Land Allocation - $40,000) 12 (Design and Contingencies - $200,000) 13 (3) SR 0291, 4th Street Bridge over Ridley 14 Creek, Chester Township, Bridge 15 Painting 291,000 16 (Base Construction Allocation - 17 $253,000) 18 (Design and Contingencies - $38,000) 19 (4) SR 0291, Essington Avenue Bridge over 20 Darby Creek, Ridley Township, Bridge 21 Painting 546,000 22 (Base Construction Allocation - 23 $487,000) 24 (Design and Contingencies - $59,000) 25 (5) SR 1019, Conestoga Road Bridge over 26 PennDOT Railroad Right-of-Way, Radnor 27 Township, Bridge Removal 125,000 28 (Base Construction Allocation - 29 $100,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 163 -
1 (Design and Contingencies - $15,000) 2 (6) SR 3019, Rosevally Road Bridge over 3 SEPTA, Upper Providence Township, 4 Bridge Replacement 875,000 5 (Base Construction Allocation - 6 $700,000) 7 (Land Allocation - $100,000) 8 (Design and Contingencies - $75,000) 9 Section 28. Elk County. 10 (a) Local Bridges 11 (1) Village of Wilcox, T-631, Bridge over 12 Clarion River, Bridge Replacement 1,100,000 13 (Base Construction Allocation - 14 $850,000) 15 (Land Allocation - $50,000) 16 (Design and Contingencies - $200,000) 17 (b) State Bridges (Reserved) 18 Section 29. Erie County. 19 (a) Local Bridges 20 (1) Girard Township, Beckman Bridge over 21 I-90, Bridge Painting 200,000 22 (Base Construction Allocation - 23 $200,000) 24 (2) Millcreek Township, T-707, Zimmerly 25 Road Bridge over I-79, New 2-Lane 26 Bridge Construction, New Bridge 2,150,000 27 (Base Construction Allocation - 28 $1,900,000) 29 (Land Allocation - $50,000) 30 (Design and Contingencies - $200,000) 19970S0186B0698 - 164 -
1 (3) City of Erie, Norman Way, Bridge over 2 Millcreek, Bridge Rehabilitation 225,000 3 (Base Construction Allocation - 4 $200,000) 5 (Design and Contingencies - $25,000) 6 (4) City of Erie, McBride Viaduct-East 7 Avenue, Bridge over Railroad Lines, 8 Bridge Rehabilitation 1,340,000 9 (Base Construction Allocation - 10 $1,300,000) 11 (Design and Contingencies - $40,000) 12 (5) City of Erie, Kahkwa Bridge over 13 Ravine Drive, Bridge Rehabilitation 60,000 14 (Base Construction Allocation - 15 $50,000) 16 (Design and Contingencies - $10,000) 17 (6) Greenfield Township, T-974, Old Route 18 89 Bridge over West Branch of French 19 Creek Tributary, Bridge Replacement 350,000 20 (Base Construction Allocation - 21 $300,000) 22 (Land Allocation - $10,000) 23 (Design and Contingencies - $40,000) 24 (7) Franklin Township, T-479 T-424, Bridge <-- 25 No.1 over Falk Run, Bridge Replacement 350,000 26 (Base Construction Allocation - 27 $300,000) 28 (Land Allocation - $10,000) 29 (Design and Contingencies - $40,000) 30 (8) Franklin Township, T-479 T-424, Bridge <-- 19970S0186B0698 - 165 -
1 No.2 over Falk Run, Bridge Replacement 350,000 2 (Base Construction Allocation - 3 $300,000) 4 (Land Allocation - $10,000) 5 (Design and Contingencies - $40,000) 6 (9) Franklin Township, T-424, Falls Road <-- 7 Bridge over Falk Run, Bridge 8 Replacement 300,000 9 (Base Construction Allocation - 10 $250,000) 11 (Land Allocation - $10,000) 12 (Design and Contingencies - $40,000) 13 (10) (9) Millcreek Township, T-707, 14 Zimmerly Road Bridge over I-79, Two- 15 Lane Bridge Construction 2,150,000 16 (Base Construction Allocation - 17 $1,900,000) 18 (Land Allocation - $50,000) 19 (Design and Contingencies - $200,000) 20 (b) State Bridges 21 (1) SR 0005, SR 0005 over Scott Run, 22 Harborcreek Township, Bridge 23 Replacement 140,000 24 (Base Construction Allocation - 25 $100,000) 26 (Land Allocation - $10,000) 27 (Design and Contingencies - $30,000) 28 (2) SR 0006, SR 0006 over French Creek, Le 29 Boeuf Township, Bridge Replacement 700,000 30 (Base Construction Allocation - 19970S0186B0698 - 166 -
1 $600,000) 2 (Land Allocation - $20,000) 3 (Design and Contingencies - $80,000) 4 (3) SR 0019, SR 0019 over LeBoeuf Creek, 5 Waterford Township, Bridge Replacement 950,000 6 (Base Construction Allocation - 7 $840,000) 8 (Land Allocation - $30,000) 9 (Design and Contingencies - $80,000) 10 (4) SR 0020, SR 0020 over I-79, City of 11 Erie, Bridge Replacement 2,000,000 12 (Base Construction Allocation - 13 $1,770,000) 14 (Land Allocation - $30,000) 15 (Design and Contingencies - $200,000) 16 (5) SR 0089, SR 0089 over Sixteen Mile 17 Creek, North East Township, Bridge 18 Replacement 490,000 19 (Base Construction Allocation - 20 $400,000) 21 (Land Allocation - $20,000) 22 (Design and Contingencies - $70,000) 23 (6) SR 0090, SR 0090 over Crooked Creek, 24 Girard Township, Bridge Replacement 1,420,000 25 (Base Construction Allocation - 26 $1,330,000) 27 (Land Allocation - $30,000) 28 (Design and Contingencies - $60,000) 29 (7) SR 0090, SR 0090 under Cherry Street, 30 Summit Township, Bridge Replacement 1,600,000 19970S0186B0698 - 167 -
1 (Base Construction Allocation - 2 $1,410,000) 3 (Land Allocation - $40,000) 4 (Design and Contingencies - $150,000) 5 (8) SR 0090, SR 0090 under Clark Road, 6 Harborcreek Township, Bridge 7 Replacement 2,100,000 8 (Base Construction Allocation - 9 $1,880,000) 10 (Land Allocation - $40,000) 11 (Design and Contingencies - $180,000) 12 (9) SR 0098, SR 0098 over Cussewago Creek, 13 Elk Creek Township, Bridge Replacement 400,000 14 (Base Construction Allocation - 15 $300,000) 16 (Land Allocation - $20,000) 17 (Design and Contingencies - $80,000) 18 (10) SR 0474, SR 0474 over Dean Run, 19 Venango Township, Bridge Replacement 200,000 20 (Base Construction Allocation - 21 $160,000) 22 (Land Allocation - $10,000) 23 (Design and Contingencies - $30,000) 24 (11) SR 1001, SR 1001 over Conrail, 25 Millcreek Township, Bridge Replacement 720,000 26 (Base Construction Allocation - 27 $600,000) 28 (Land Allocation - $20,000) 29 (Design and Contingencies - $100,000) 30 (12) SR 1011, SR 1011 over Alder Brook, 19970S0186B0698 - 168 -
1 Venango Township, Bridge Replacement 470,000 2 (Base Construction Allocation - 3 $400,000) 4 (Land Allocation - $10,000) 5 (Design and Contingencies - $60,000) 6 (13) SR 1013, SR 1013 over I-90, North 7 East Township, Bridge Replacement 1,220,000 8 (Base Construction Allocation - 9 $1,100,000) 10 (Land Allocation - $20,000) 11 (Design and Contingencies - $100,000) 12 (14) SR 3001, SR 3001 over Conneaut Creek, 13 Conneaut Township, Bridge Replacement 1,020,000 14 (Base Construction Allocation - 15 $900,000) 16 (Land Allocation - $20,000) 17 (Design and Contingencies - $100,000) 18 (15) SR 3003, SR 3003 over West Branch 19 Conneaut Creek, Conneaut Township, 20 Bridge Replacement 630,000 21 (Base Construction Allocation - 22 $550,000) 23 (Land Allocation - $20,000) 24 (Design and Contingencies - $60,000) 25 (16) SR 3014, SR 3014 over Trout Run, 26 Waterford Borough, Bridge Replacement 370,000 27 (Base Construction Allocation - 28 $300,000) 29 (Land Allocation - $20,000) 30 (Design and Contingencies - $50,000) 19970S0186B0698 - 169 -
1 (17) SR 4007, SR 4007 over I-90, Fairview 2 Township, Bridge Replacement 1,920,000 3 (Base Construction Allocation - 4 $1,800,000) 5 (Land Allocation - $20,000) 6 (Design and Contingencies - $100,000) 7 Section 30. Fayette County. 8 (a) Local Bridges 9 (1) Brownsville Township, Lynn Run Road 10 Bridge over Redstone Creek, Bridge 11 Replacement 200,000 12 (Base Construction Allocation - 13 $130,000) 14 (Land Allocation - $10,000) 15 (Design and Contingencies - $60,000) 16 (2) Dunbar Township, Falls Avenue Bridge 17 over Possum Run, Bridge Replacement 450,000 18 (Base Construction Allocation - 19 $350,000) 20 (Land Allocation - $15,000) 21 (Design and Contingencies - $85,000) 22 (3) Georges Township, County Bridge No.162 23 over Mountain Creek, Bridge 24 Replacement 370,000 <-- 25 (Base Construction Allocation - 26 $300,000) 27 (Land Allocation - $5,000) 28 (Design and Contingencies - $65,000) 29 REPLACEMENT 640,000 <-- 30 (BASE CONSTRUCTION ALLOCATION - 19970S0186B0698 - 170 -
1 $425,000) 2 (LAND ALLOCATION - $40,000) 3 (DESIGN AND CONTINGENCIES - $175,000) 4 (4) German Township, Footedale Bridge 5 No.66 over Dunlap Creek, Bridge 6 Replacement 415,000 <-- 7 (Base Construction Allocation - 8 $330,000) 9 (Land Allocation - $10,000) 10 (Design and Contingencies - $75,000) 11 REPLACEMENT 498,000 <-- 12 (BASE CONSTRUCTION ALLOCATION - 13 $313,000) 14 (LAND ALLOCATION - $35,000) 15 (DESIGN AND CONTINGENCIES - $150,000) 16 (5) German Township, County Bridge No.54 17 over Browns Run, Bridge Replacement 430,000 <-- 18 (Base Construction Allocation - 19 $355,000) 20 (Land Allocation - $5,000) 21 (Design and Contingencies - $70,000) 22 OVER BROWNS RUN, BRIDGE REPLACEMENT 793,000 <-- 23 (BASE CONSTRUCTION ALLOCATION - 24 $563,000) 25 (LAND ALLOCATION - $50,000) 26 (DESIGN AND CONTINGENCIES - $180,000) 27 (6) German Township, Leckrone Bridge No.54 28 over Browns Run, Bridge Replacement 430,000 29 (Base Construction Allocation - 30 $350,000) 19970S0186B0698 - 171 -
1 (Land Allocation - $5,000) 2 (Design and Contingencies - $75,000) 3 (7) Menallen Township, T-509, Bridge over 4 Branch of Dunlap Creek, Bridge 5 Replacement 165,000 6 (Base Construction Allocation - 7 $110,000) 8 (Land Allocation - $5,000) 9 (Design and Contingencies - $50,000) 10 (8) Menallen Township, Fan Hallow Road 11 Bridge over Fans Run, Bridge 12 Replacement 145,000 13 (Base Construction Allocation - 14 $90,000) 15 (Land Allocation - $5,000) 16 (Design and Contingencies - $50,000) 17 (9) Menallen and North Union Townships, 18 Fan Hollow Bridge No.184 over Jennings 19 Run, Bridge Replacement 440,000 20 (Base Construction Allocation - 21 $350,000) 22 (Land Allocation - $10,000) 23 (Design and Contingencies - $80,000) 24 (10) Nicholson Township, County Bridge 25 No.29 over York Run, Bridge 26 Replacement 360,000 <-- 27 (Base Construction Allocation - 28 $295,000) 29 (Land Allocation - $5,000) 30 (Design and Contingencies - $60,000) 19970S0186B0698 - 172 -
1 REPLACEMENT 535,000 <-- 2 (BASE CONSTRUCTION ALLOCATION - 3 $350,000) 4 (LAND ALLOCATION - $35,000) 5 (DESIGN AND CONTINGENCIES - $150,000) 6 (11) Redstone Township, Merrittstown 7 Bridge No.147 over Dunlap Creek, Bridge 8 Replacement 435,000 9 (Base Construction Allocation - 10 $350,000) 11 (Land Allocation - $10,000) 12 (Design and Contingencies - $75,000) 13 (12) South Union Township, Leith Bridge <-- 14 No.41 over Redstone Creek, Bridge 15 Replacement 450,000 16 (Base Construction Allocation - 17 $360,000) 18 (Land Allocation - $10,000) 19 (Design and Contingencies - $80,000) 20 (13) Steward Township, Meadow Run Bridge 21 No.82 over Meadow Run, Bridge 22 Replacement 450,000 23 (Base Construction Allocation - 24 $360,000) 25 (Land Allocation - $10,000) 26 (Design and Contingencies - $80,000) 27 (12) SOUTH UNION TOWNSHIP, T-479, LEITH <-- 28 BRIDGE NO.41 OVER REDSTONE CREEK, 29 BRIDGE REPLACEMENT 690,000 30 (BASE CONSTRUCTION ALLOCATION - 19970S0186B0698 - 173 -
1 $475,000) 2 (LAND ALLOCATION - $40,000) 3 (DESIGN AND CONTINGENCIES - $175,000) 4 (13) STEWARD TOWNSHIP, T-798, MEADOW RUN 5 BRIDGE NO.82 OVER MEADOW RUN, BRIDGE 6 REPLACEMENT 825,000 7 (BASE CONSTRUCTION ALLOCATION - 8 $575,000) 9 (LAND ALLOCATION - $55,000) 10 (DESIGN AND CONTINGENCIES - $195,000) 11 (14) Springhill Township, T-335, County 12 Bridge No.92 over York Run, Bridge 13 Replacement 1,438,000 14 (Base Construction Allocation - 15 $1,113,000) 16 (Land Allocation - $75,000) 17 (Design and Contingencies - $250,000) 18 (15) Springfield Township, T-593, County 19 Bridge No.111 over Mill Run, Bridge 20 Replacement 320,000 21 (Base Construction Allocation - 22 $225,000) 23 (Land Allocation - $20,000) 24 (Design and Contingencies - $75,000) 25 (16) North Union Township, T-535 over 26 Redstone Creek, Bridge Replacement 825,000 27 (Base Construction Allocation - 28 $625,000) 29 (Land Allocation - $25,000) 30 (Design and Contingencies - $175,000) 19970S0186B0698 - 174 -
1 (17) North Union Township, T-557 over 2 Redstone Creek, Bridge Replacement 450,000 3 (Base Construction Allocation - 4 $275,000) 5 (Land Allocation - $50,000) 6 (Design and Contingencies - $125,000) 7 (18) GEORGES TOWNSHIP, T-387, COUNTY <-- 8 BRIDGE NO.102 OVER YORK RUN, BRIDGE 9 REHABILITATION 320,000 10 (BASE CONSTRUCTION ALLOCATION - 11 $225,000) 12 (LAND ALLOCATION - $20,000) 13 (DESIGN AND CONTINGENCIES - $75,000) 14 (19) SOUTH UNION TOWNSHIP, T-459, TOWNSHIP 15 BRIDGE NO.1 OVER LICK RUN, BRIDGE 16 REPLACEMENT 280,000 17 (BASE CONSTRUCTION ALLOCATION - 18 $175,000) 19 (LAND ALLOCATION - $25,000) 20 (DESIGN AND CONTINGENCIES - $80,000) 21 (20) STEWART TOWNSHIP, T-415, COUNTY 22 BRIDGE NO.63 OVER MEADOW RUN, BRIDGE 23 REPLACEMENT 1,005,000 24 (BASE CONSTRUCTION ALLOCATION - 25 $775,000) 26 (LAND ALLOCATION - $50,000) 27 (DESIGN AND CONTINGENCIES - $180,000) 28 (21) GERMAN TOWNSHIP, COUNTY BRIDGE NO.54 29 OVER BROWNS RUN AT LEITH COMMUNITY, 30 BRIDGE REPLACEMENT 430,000 19970S0186B0698 - 175 -
1 (BASE CONSTRUCTION ALLOCATION - 2 $350,000) 3 (LAND ALLOCATION - $5,000) 4 (DESIGN AND CONTINGENCIES - $75,000) 5 (b) State Bridges 6 (1) SR 0021, Masontown Bridge over 7 Monongahela River, Railroad and Private 8 Road, German Township, Bridge Painting 1,500,000 9 (Base Construction Allocation - 10 $1,500,000) 11 (2) SR 0031, Jacobs Creek Bridge over 12 Branch of Jacobs Creek, Bullskin 13 Township, Bridge Replacement 290,000 14 (Base Construction Allocation - 15 $180,000) 16 (Land Allocation - $35,000) 17 (Design and Contingencies - $75,000) 18 (3) SR 0119, Memorial Bridge over 19 Youghiogheny River, Connellsville 20 Borough, Bridge Painting 100,000 21 (Base Construction Allocation - 22 $100,000) 23 (4) SR 0201, Furnace Run Bridge over 24 Furnace Run, Franklin Township, Bridge 25 Replacement 445,000 26 (Base Construction Allocation - 27 $245,000) 28 (Land Allocation - $25,000) 29 (Design and Contingencies - $175,000) 30 (5) SR 0711, Crawford Avenue Bridge over 19970S0186B0698 - 176 -
1 Youghiogheny River, Connellsville 2 Borough, Bridge Painting 100,000 3 (Base Construction Allocation - 4 $100,000) 5 (6) SR 0982, Jacobs Creek Bridge over 6 Branch of Jacobs Creek, Bullskin 7 Township, Bridge Replacement 335,000 8 (Base Construction Allocation - 9 $225,000) 10 (Land Allocation - $35,000) 11 (Design and Contingencies - $75,000) 12 (7) SR 0982, Bridge over Mounts Creek, 13 Bullskin Township, Bridge Painting 105,000 14 (Base Construction Allocation - 15 $105,000) 16 (8) SR 1051, Mounts Creek Bridge over 17 Mounts Creek, Bullskin Township, Bridge 18 Replacement 436,000 19 (Base Construction Allocation - 20 $236,000) 21 (Land Allocation - $25,000) 22 (Design and Contingencies - $175,000) 23 (9) SR 3013, Browns Run Bridge over Browns 24 Run, German Township, Bridge 25 Replacement 631,000 26 (Base Construction Allocation - 27 $431,000) 28 (Land Allocation - $25,000) 29 (Design and Contingencies - $175,000) 30 (10) SR 3015, Muddy Run Bridge over Muddy 19970S0186B0698 - 177 -
1 Run, Georges Township, Bridge Painting 33,000 2 (Base Construction Allocation - 3 $33,000) 4 (11) SR 4038, Washington Run Bridge over 5 Washington Run, Perry Township, Bridge 6 Replacement 640,000 7 (Base Construction Allocation - 8 $440,000) 9 (Land Allocation - $25,000) 10 (Design and Contingencies - $175,000) 11 (12) SR 0381, SR 0381 over Stoney Run, 12 Wharton Township, Bridge Replacement 663,000 13 (Base Construction Allocation - 14 $463,000) 15 (Land Allocation - $50,000) 16 (Design and Contingencies - $150,000) 17 (13) SR 0819, SR 0819 over Branch of 18 Jacobs Creek, Lower Tyrone Township, 19 Bridge Replacement 240,000 20 (Base Construction Allocation - 21 $125,000) 22 (Land Allocation - $15,000) 23 (Design and Contingencies - $100,000) 24 (14) SR 1021, SR 1021 over Breakneck Run, 25 Bullskin Township, Bridge Replacement 650,000 26 (Base Construction Allocation - 27 $475,000) 28 (Land Allocation - $50,000) 29 (Design and Contingencies - $125,000) 30 (15) SR 1031, SR 1031 over Galley Run, 19970S0186B0698 - 178 -
1 Upper Tyrone Township, Bridge 2 Replacement 475,000 3 (Base Construction Allocation - 4 $325,000) 5 (Land Allocation - $25,000) 6 (Design and Contingencies - $125,000) 7 (16) SR 1031, SR 1031 over Branch of 8 Galley Run, Upper Tyrone Township, 9 Bridge Replacement 613,000 10 (Base Construction Allocation - 11 $413,000) 12 (Land Allocation - $50,000) 13 (Design and Contingencies - $150,000) 14 (17) SR 1044, SR 1044 over Branch of 15 Mounts Creek, Bullskin Township, Bridge 16 Replacement 350,000 17 (Base Construction Allocation - 18 $200,000) 19 (Land Allocation - $25,000) 20 (Design and Contingencies - $125,000) 21 (18) SR 2003, SR 2003 over Chaney Run, 22 Wharton Township, Bridge Replacement 290,000 23 (Base Construction Allocation - 24 $175,000) 25 (Land Allocation - $15,000) 26 (Design and Contingencies - $100,000) 27 (19) SR 3003, SR 3003 at Nicholson 28 Township Border, Springhill Township, 29 Bridge Replacement 1,400,000 30 (Base Construction Allocation - 19970S0186B0698 - 179 -
1 $1,125,000) 2 (Land Allocation - $75,000) 3 (Design and Contingencies - $200,000) 4 (20) SR 3003, SR 3003 over Georges Creek, 5 Springhill Township, Bridge 6 Replacement 1,450,000 7 (Base Construction Allocation - 8 $1,150,000) 9 (Land Allocation - $75,000) 10 (Design and Contingencies - $225,000) 11 (21) SR 3003, SR 3003 Nicholson Township 12 over Georges Creek, Springhill 13 Township, Bridge Replacement 1,200,000 14 (Base Construction Allocation - 15 $975,000) 16 (Land Allocation - $50,000) 17 (Design and Contingencies - $175,000) 18 (22) SR 3009, SR 3009 over Georges Creek, 19 Springhill Township, Bridge 20 Replacement 863,000 21 (Base Construction Allocation - 22 $688,000) 23 (Land Allocation - $25,000) 24 (Design and Contingencies - $150,000) 25 (23) SR 3013, SR 3013 over Middle Run, 26 German Township, Bridge Replacement 900,000 27 (Base Construction Allocation - 28 $650,000) 29 (Land Allocation - $75,000) 30 (Design and Contingencies - $175,000) 19970S0186B0698 - 180 -
1 (24) SR 4027, SR 4027 over Little Redstone 2 Creek, Jefferson Township, Bridge 3 Replacement 538,000 4 (Base Construction Allocation - 5 $338,000) 6 (Land Allocation - $50,000) 7 (Design and Contingencies - $150,000) 8 (25) SR 4044, SR 4044 over Downers Run, 9 Washington Township, Bridge 10 Replacement 800,000 11 (Base Construction Allocation - 12 $575,000) 13 (Land Allocation - $50,000) 14 (Design and Contingencies - $175,000) 15 (26) SR 4046, SR 4046 over Lutz Run and 16 Abandoned Railroad, Washington 17 Township, Bridge Replacement 1,400,000 18 (Base Construction Allocation - 19 $1,075,000) 20 (Land Allocation - $75,000) 21 (Design and Contingencies - $250,000) 22 (27) SR 1045, BRIDGE OVER BRANCH OF <-- 23 DICKERSON RUN, VANDERBILT BOROUGH, 24 BRIDGE REPLACEMENT 330,000 25 (BASE CONSTRUCTION ALLOCATION - 26 $225,000) 27 (LAND ALLOCATION - $5,000) 28 (DESIGN AND CONTINGENCIES - $100,000 29 (28) SR 0201, BRIDGE OVER VIRGIN RUN, 30 FRANKLIN TOWNSHIP, BRIDGE REPLACEMENT 330,000 19970S0186B0698 - 181 -
1 (BASE CONSTRUCTION ALLOCATION - 2 $225,000) 3 (LAND ALLOCATION - $5,000) 4 (DESIGN AND CONTINGENCIES - $100,000 5 (29) SR 4016, BRIDGE OVER REDSTONE CREEK, 6 REDSTONE TOWNSHIP, BRIDGE REPLACEMENT 1,030,000 7 (BASE CONSTRUCTION ALLOCATION - 8 $830,000) 9 (LAND ALLOCATION - $$25,000) 10 (DESIGN AND CONTINGENCIES - $175,000) 11 (30) SR 1021, BRIDGE OVER BREAKNECK RUN, 12 BULLSKIN TOWNSHIP, BRIDGE REPLACEMENT 505,000 13 (BASE CONSTRUCTION ALLOCATION - 14 $325,000) 15 (LAND ALLOCATION - $5,000) 16 (DESIGN AND CONTINGENCIES - $175,000) 17 (31) SR 1031, BRIDGE OVER BRANCH OF GALLEY 18 RUN, UPPER TYRONE TOWNSHIP, BRIDGE 19 REPLACEMENT 465,000 20 (BASE CONSTRUCTION ALLOCATION - 21 $300,000 22 (LAND ALLOCATION - $15,000) 23 (DESIGN AND CONTINGENCIES - $150,000) 24 (32) SR 3003, BRIDGE OVER GEORGES CREEK, 25 SPRINGHILL/NICHOLSON TOWNSHIP, BRIDGE 26 REPLACEMENT 785,000 27 (BASE CONSTRUCTION ALLOCATION - 28 $600,000) 29 (LAND ALLOCATION - $10,000) 30 (DESIGN AND CONTINGENCIES - $175,000) 19970S0186B0698 - 182 -
1 (33) SR 3003, BRIDGE OVER GEORGES CREEK, 2 SPRINGHILL/NICHOLSON TOWNSHIP, BRIDGE 3 REPLACEMENT 885,000 4 (BASE CONSTRUCTION ALLOCATION - 5 $700,000) 6 (LAND ALLOCATION - $10,000) 7 (DESIGN AND CONTINGENCIES -$175,000) 8 (34) SR 4027, BRIDGE OVER LITTLE REDSTONE 9 CREEK, JEFFERSON TOWNSHIP, BRIDGE 10 REPLACEMENT 355,000 11 (BASE CONSTRUCTION ALLOCATION - 12 $250,000) 13 (LAND ALLOCATION - $5,000) 14 (DESIGN AND CONTINGENCIES - $100,000) 15 (35) SR 3007, BRIDGE OVER GEORGES CREEK, 16 GEORGES TOWNSHIP, BRIDGE REPLACEMENT 700,000 17 (BASE CONSTRUCTION ALLOCATION - 18 $500,000) 19 (LAND ALLOCATION - $25,000) 20 (DESIGN AND CONTINGENCIES - $175,000) 21 (36) SR 0031, JACOBS CREEK BRIDGE OVER 22 JACOBS CREEK, BULLSKIN TOWNSHIP, 23 FAYETTE COUNTY, AND MT. PLEASANT 24 TOWNSHIP, WESTMORELAND COUNTY, BRIDGE 25 REPLACEMENT 715,000 26 (BASE CONSTRUCTION ALLOCATION - 27 $500,000) 28 (LAND ALLOCATION - $40,000) 29 (DESIGN AND CONTINGENCIES - $175,000) 30 Section 31. Forest County. 19970S0186B0698 - 183 -
1 (a) Local Bridges (Reserved) 2 (b) State Bridges 3 (1) SR 0227, SR 0227 over West Hickory 4 Creek, Harmony Township, Bridge 5 Replacement 480,000 6 (Base Construction Allocation - 7 $400,000) 8 (Land Allocation - $20,000) 9 (Design and Contingencies - $60,000) 10 (2) SR 3001, SR 3001 over Little Tionesta 11 Creek, Tionesta Township, Bridge 12 Replacement 400,000 13 (Base Construction Allocation - 14 $310,000) 15 (Land Allocation - $10,000) 16 (Design and Contingencies - $80,000) 17 (3) SR 3004, SR 3004 over Little Hickory 18 Creek, Hickory Township, Bridge 19 Replacement 390,000 20 (Base Construction Allocation - 21 $300,000) 22 (Land Allocation - $30,000) 23 (Design and Contingencies - $60,000) 24 (4) SR 3004, SR 3004 over Piney Run, Green 25 Township, Bridge Replacement 390,000 26 (Base Construction Allocation - 27 $300,000) 28 (Land Allocation - $10,000) 29 (Design and Contingencies - $80,000) 30 (5) SR 3001, Red Brush Road Bridge over 19970S0186B0698 - 184 -
1 Little Tionesta Creek, Tionesta 2 Township, Bridge Rehabilitation 605,000 3 (Base Construction Allocation - 4 $550,000) 5 (Design and Contingencies - $55,000) 6 Section 32. Franklin County. 7 (a) Local Bridges (Reserved) 8 (b) State Bridges 9 (1) SR 3012, Social Island Road Bridge 10 over Conococheague Creek, Hamilton 11 Township, Bridge Replacement 786,000 12 (Base Construction Allocation - 13 $636,000) 14 (Land Allocation - $95,000) 15 (Design and Contingencies - $55,000) 16 (2) SR 4010, Edenville Road Bridge over 17 Wilson Run, St. Thomas Township, Bridge 18 Replacement 335,000 19 (Base Construction Allocation - 20 $225,000) 21 (Land Allocation - $10,000) 22 (Design and Contingencies - $100,000) 23 (3) SR 4009, over Wilson Run, St. Thomas 24 Township, Bridge Replacement 750,000 25 (Base Construction Allocation - 26 $500,000) 27 (Land Allocation - $50,000) 28 (Design and Contingencies - $200,000) 29 Section 33. (Reserved). 30 Section 34. Greene County. 19970S0186B0698 - 185 -
1 (a) Local Bridges 2 (1) Morgan Township, County Bridge No.89 3 over Browns Run, Bridge Replacement 286,000 4 (Base Construction Allocation - 5 $166,000) 6 (Land Allocation - $20,000) 7 (Design and Contingencies - $100,000) 8 (2) Morgan Township, County Bridge No.90 9 over Browns Run, Bridge Replacement 282,000 10 (Base Construction Allocation - 11 $162,000) 12 (Land Allocation - $20,000) 13 (Design and Contingencies - $100,000) 14 (3) Morgan Township, County Bridge No.91 15 over Browns Run, Bridge Replacement 273,000 16 (Base Construction Allocation - 17 $153,000) 18 (Land Allocation - $20,000) 19 (Design and Contingencies - $100,000) 20 (4) Cumberland Township, T-517, County 21 Bridge No.4, Ullery Road over Goose 22 Run, Bridge Replacement 360,000 23 (Base Construction Allocation - 24 $200,000) 25 (Land Allocation - $10,000) 26 (Design and Contingencies - $150,000) 27 (5) Cumberland Township, T-634, County 28 Bridge No.15, Coal Hill Road over Muddy 29 Creek, Bridge Replacement 410,000 30 (Base Construction Allocation - 19970S0186B0698 - 186 -
1 $240,000) 2 (Land Allocation - $10,000) 3 (Design and Contingencies - $160,000) 4 (6) Greene Township, T-411, County Bridge 5 No.20 over Whitely Creek, Bridge 6 Replacement 490,000 <-- 7 (Base Construction Allocation - 8 $300,000) 9 (Land Allocation - $15,000) 10 (Design and Contingencies - $175,000) 11 REPLACEMENT 1,075,000 <-- 12 (BASE CONSTRUCTION ALLOCATION - 13 $900,000) 14 (LAND ALLOCATION - $25,000) 15 (DESIGN AND CONTINGENCIES - $150,000) 16 (7) Gray Township, T-392, County Bridge 17 No.63 over Grays Creek, Bridge 18 Replacement 380,000 19 (Base Construction Allocation - 20 $220,000) 21 (Land Allocation - $10,000) 22 (Design and Contingencies - $150,000) 23 (8) Washington Township, T-550, County 24 Bridge No.97 over Craynes Run, Bridge 25 Replacement 360,000 26 (Base Construction Allocation - 27 $200,000) 28 (Land Allocation - $10,000) 29 (Design and Contingencies - $150,000) 30 (9) Morris Township, T-629, County Bridge 19970S0186B0698 - 187 -
1 No.73 over Bates Fork Creek, Bridge 2 Replacement 490,000 3 (Base Construction Allocation - 4 $350,000) 5 (Land Allocation - $15,000) 6 (Design and Contingencies - $125,000) 7 (10) Cumberland Township, T-660, County 8 Bridge No.13 over Muddy Creek, Bridge 9 Replacement 565,000 10 (Base Construction Allocation - 11 $400,000) 12 (Land Allocation - 15,000) 13 (Design and Contingencies - $150,000) 14 (11) Aleppo Township, T-304, County Bridge 15 No.108 over Branch of Harts Run, Bridge 16 Replacement 575,000 17 (Base Construction Allocation - 18 $425,000) 19 (Land Allocation - $25,000) 20 (Design and Contingencies - $125,000) 21 (12) FRANKLIN TOWNSHIP, T-511, BRIDGE <-- 22 NO.30 OVER SMITH CREEK, BRIDGE 23 REPLACEMENT 625,000 24 (BASE CONSTRUCTION ALLOCATION - 25 $475,000) 26 (LAND ALLOCATION - $25,000) 27 (DESIGN AND CONTINGENCIES - $125,000) 28 (13) MORGAN TOWNSHIP, T-659, BRIDGE NO.87 29 OVER TEN MILE CREEK, BRIDGE 30 REPLACEMENT 1,275,000 19970S0186B0698 - 188 -
1 (BASE CONSTRUCTION ALLOCATION - 2 $1,100,000) 3 (LAND ALLOCATION - $25,000) 4 (DESIGN AND CONTINGENCIES - $150,000) 5 (14) RICHHILL TOWNSHIP, T-356, BRIDGE 6 NO.57 OVER NORTH FORK OF WHEELING 7 CREEK, BRIDGE REPLACEMENT 765,000 8 (BASE CONSTRUCTION ALLOCATION - 9 $625,000) 10 (LAND ALLOCATION - $15,000) 11 (DESIGN AND CONTINGENCIES - $125,000) 12 (15) JACKSON TOWNSHIP, T-381, BRIDGE 13 NO.109 OVER JOB CREEK, BRIDGE 14 REPLACEMENT 465,000 15 (BASE CONSTRUCTION ALLOCATION - 16 $325,000) 17 (LAND ALLOCATION - $15,000) 18 (DESIGN AND CONTINGENCIES - $125,000) 19 (b) State Bridges 20 (1) SR 0018, Bridge over South Fork of Ten 21 Mile Creek, Franklin Township, Bridge 22 Rehabilitation 320,000 23 (Base Construction Allocation - 24 $280,000) 25 (Design and Contingencies - $40,000) 26 (2) SR 0018, Bates Creek Bridge over Bates 27 Fork and Browns Creeks, Washington 28 Township, Bridge Replacement 650,000 29 (Base Construction Allocation - 30 $450,000) 19970S0186B0698 - 189 -
1 (Land Allocation - $25,000) 2 (Design and Contingencies - $175,000) 3 (3) SR 0021, Grinnage Run Bridge over 4 Grinnage Run, Gray Township, Bridge 5 Replacement 453,000 6 (Base Construction Allocation - 7 $253,000) 8 (Land Allocation - $25,000) 9 (Design and Contingencies - $175,000) 10 (4) SR 0079, I-79 Bridge over T-631, 11 Washington Township, Bridge 12 Replacement 980,000 13 (Base Construction Allocation - 14 $740,000) 15 (Land Allocation - $40,000) 16 (Design and Contingencies - $200,000) 17 (5) SR 0079, I-79 Bridge over T-631, 18 Washington Township, Bridge 19 Rehabilitation 945,000 20 (Base Construction Allocation - 21 $705,000) 22 (Land Allocation - $40,000) 23 (Design and Contingencies - $200,000) 24 (6) SR 0079, I-79 Bridge over PA 221, 25 Washington Township, Bridge 26 Replacement 2,074,000 27 (Base Construction Allocation - 28 $1,784,000) 29 (Land Allocation - $40,000) 30 (Design and Contingencies - $250,000) 19970S0186B0698 - 190 -
1 (7) SR 0079, I-79 Bridge No.2 over PA 221, 2 Washington Township, Bridge 3 Replacement 2,074,000 4 (Base Construction Allocation - 5 $1,784,000) 6 (Land Allocation - $40,000) 7 (Design and Contingencies - $250,000) 8 (8) SR 0079, I-79 Bridge over T-512, 9 Washington Township, Bridge 10 Rehabilitation 980,000 11 (Base Construction Allocation - 12 $740,000) 13 (Land Allocation - $40,000) 14 (Design and Contingencies - $200,000) 15 (9) SR 0079, I-79 Bridge No.2 over T-512, 16 Washington Township, Bridge 17 Replacement 1,020,000 18 (Base Construction Allocation - 19 $780,000) 20 (Land Allocation - $40,000) 21 (Design and Contingencies - $200,000) 22 (10) SR 0088, Albert Gallatin Bridge over 23 Monongahela River, Dunkard Township, 24 Bridge Painting 1,500,000 25 (Base Construction Allocation - 26 $1,500,000) 27 (11) SR 0088, Point Marion Bridge over 28 Monongahela River, Dunkard Township, 29 Bridge Replacement 6,200,000 30 (Base Construction Allocation - 19970S0186B0698 - 191 -
1 $5,500,000) 2 (Land Allocation - $200,000) 3 (Design and Contingencies - $500,000) 4 (12) SR 0218, Roberts Run Bridge No.2 over 5 Roberts Run, Wayne Township, Bridge 6 Replacement 768,000 7 (Base Construction Allocation - 8 $568,000) 9 (Land Allocation - $25,000) 10 (Design and Contingencies - $175,000) 11 (13) SR 2003, Bridge over Branch of 12 Dunkard Creek, Perry Township, Bridge 13 Replacement 625,000 14 (Base Construction Allocation - 15 $400,000) 16 (Land Allocation - $25,000) 17 (Design and Contingencies - $200,000) 18 (14) SR 3007, Bridge over Branch of 19 Wheeling Creek, Richill Township, 20 Bridge Replacement 375,000 21 (Base Construction Allocation - 22 $175,000) 23 (Land Allocation - $25,000) 24 (Design and Contingencies - $175,000) 25 Section 35. Huntingdon County. 26 (a) Local Bridges 27 (1) Mill Creek Borough, Main Street Bridge 28 over Mill Creek, Bridge Rehabilitation 30,000 29 (Base Construction Allocation - 30 $30,000) 19970S0186B0698 - 192 -
1 (2) Juniata Township, T-428, Corbin Bridge 2 over Raystown Branch of Juniata River, 3 Bridge Replacement 920,000 4 (Base Construction Allocation - 5 $920,000) 6 (3) Springfield Township, T-313, Walnut 7 Grove Bridge, County Bridge No.2 over 8 Sideling Hill Creek, Bridge 9 Replacement 975,000 10 (Base Construction Allocation - 11 $800,000) 12 (Land Allocation - $25,000) 13 (Design and Contingencies - $150,000) 14 (b) State Bridges (Reserved) 15 Section 36. Indiana County. 16 (a) Local Bridges 17 (1) Banks Township, T-974, County Bridge 18 No.13, Bear Run Bridge over Bear Run, 19 Bridge Replacement 500,000 20 (Base Construction Allocation - 21 $400,000) 22 (Land Allocation - $20,000) 23 (Design and Contingencies - $80,000) 24 (2) Blacklick Township, T-574, Muddy Run 25 Bridge over Muddy Run, Bridge 26 Replacement 380,000 27 (Base Construction Allocation - 28 $300,000) 29 (Land Allocation - $10,000) 30 (Design and Contingencies - $70,000) 19970S0186B0698 - 193 -
1 (3) Cherryhill Township, T-686, County 2 Bridge No.65, Grace Church Bridge over 3 Two Lick Creek, Bridge Replacement 600,000 4 (Base Construction Allocation - 5 $500,000) 6 (Land Allocation - $20,000) 7 (Design and Contingencies - $80,000) 8 (4) Cherryhill Township, T-978, Allen 9 Bridge over Two Lick Reservoir, Bridge 10 Rehabilitation 264,000 11 (Base Construction Allocation - 12 $200,000) 13 (Land Allocation - $10,000) 14 (Design and Contingencies - $54,000) 15 (5) Rayne Township, T-760, County Bridge 16 No.23-A, Chambersville Bridge over 17 Crooked Creek, Bridge Rehabilitation 190,000 18 (Base Construction Allocation - 19 $150,000) 20 (Land Allocation - $10,000) 21 (Design and Contingencies - $30,000) 22 (6) Grant Township, T-820 over Crooked 23 Run, Bridge Replacement 245,000 24 (Base Construction Allocation - 25 $200,000) 26 (Land Allocation - $10,000) 27 (Design and Contingencies - $35,000) 28 (b) State Bridges 29 (1) SR 0022, Chestnut Ridge Bridge over SR 30 0119, Burrell Township, Bridge 19970S0186B0698 - 194 -
1 Painting 90,000 2 (Base Construction Allocation - 3 $75,000) 4 (Design and Contingencies - $15,000) 5 (2) SR 0022, Armagh Bridge over SR 0056, 6 West Wheatfield Township, Bridge 7 Painting 145,000 8 (Base Construction Allocation - 9 $130,000) 10 (Design and Contingencies - $15,000) 11 (3) SR 0119, Blacklick Bridge over 12 Blacklick Creek, Burrell Township, 13 Bridge Painting 280,000 14 (Base Construction Allocation - 15 $265,000) 16 (Design and Contingencies - $15,000) 17 (4) SR 0119, Bypass Steel Bridge No.1 over 18 Wayne Avenue Ramps, White Township, 19 Bridge Painting 170,000 20 (Base Construction Allocation - 21 $155,000) 22 (Design and Contingencies - $15,000) 23 (5) SR 0119, Bypass Steel Bridge No.2 over 24 Wayne Avenue Ramps, White Township, 25 Bridge Painting 170,000 26 (Base Construction Allocation - 27 $155,000) 28 (Design and Contingencies - $15,000) 29 (6) SR 0119, Bypass Steel Bridge No.3 over 30 SR 0422, White Township, Bridge 19970S0186B0698 - 195 -
1 Painting 240,000 2 (Base Construction Allocation - 3 $225,000) 4 (Design and Contingencies - $15,000) 5 (7) SR 0119, Bypass Steel Bridge No.4 over 6 SR 0422, White Township, Bridge 7 Painting 240,000 8 (Base Construction Allocation - 9 $225,000) 10 (Design and Contingencies - $15,000) 11 (8) SR 0119, Bypass Steel Bridge No.5 over 12 SR 0954, White Township, Bridge 13 Painting 195,000 14 (Base Construction Allocation - 15 $180,000) 16 (Design and Contingencies - $15,000) 17 (9) SR 0119, Bypass Steel Bridge No.6 over 18 SR 0954, White Township, Bridge 19 Painting 175,000 20 (Base Construction Allocation - 21 $160,000) 22 (Design and Contingencies - $15,000) 23 (10) SR 0119, Bypass Steel Bridge No.7 24 over SR 0286, White Township, Bridge 25 Painting 235,000 26 (Base Construction Allocation - 27 $220,000) 28 (Design and Contingencies - $15,000) 29 (11) SR 0119, Bypass Steel Bridge No.8 30 over SR 0286, White Township, Bridge 19970S0186B0698 - 196 -
1 Painting 215,000 2 (Base Construction Allocation - 3 $200,000) 4 (Design and Contingencies - $15,000) 5 (12) SR 0119, Bypass Steel Bridge No.9 6 over SR 1003, White Township, Bridge 7 Painting 200,000 8 (Base Construction Allocation - 9 $185,000) 10 (Design and Contingencies - $15,000) 11 (13) SR 0119, Bypass Steel Bridge No.10 12 over SR 1003, White Township, Bridge 13 Painting 175,000 14 (Base Construction Allocation - 15 $160,000) 16 (Design and Contingencies - $15,000) 17 (14) SR 0119, Bypass Steel Bridge No.11 18 over SR 0110, White Township, Bridge 19 Painting 125,000 20 (Base Construction Allocation - 21 $110,000) 22 (Design and Contingencies - $15,000) 23 (15) SR 0119, Bypass Steel Bridge No.12 24 over SR 0110, White Township, Bridge 25 Painting 125,000 26 (Base Construction Allocation - 27 $110,000) 28 (Design and Contingencies - $15,000) 29 (16) SR 0217, Torrance Bridge over 30 Conemaugh River, Burrell Township, 19970S0186B0698 - 197 -
1 Bridge Painting 435,000 2 (Base Construction Allocation - 3 $420,000) 4 (Design and Contingencies - $15,000) 5 (17) SR 0217, Blacklick Creek Bridge over 6 Blacklick Creek, Burrell Township, 7 Bridge Painting 400,000 8 (Base Construction Allocation - 9 $385,000) 10 (Design and Contingencies - $15,000) 11 (18) SR 0259, Heshbon Bridge over 12 Blacklick Creek, West Wheatfield 13 Township, Bridge Painting 200,000 14 (Base Construction Allocation - 15 $185,000) 16 (Design and Contingencies - $15,000) 17 (19) SR 0286, Clymer Bridge over Twolick 18 Creek, Clymer Borough, Bridge Painting 175,000 19 (Base Construction Allocation - 20 $160,000) 21 (Design and Contingencies - $15,000) 22 (20) SR 0422, Twolick Eastbound Bridge 23 over Twolick Creek, White Township, 24 Bridge Painting 360,000 25 (Base Construction Allocation - 26 $345,000) 27 (Design and Contingencies - $15,000) 28 (21) SR 0422, Twolick Westbound Bridge 29 over Twolick Creek, White Township, 30 Bridge Painting 360,000 19970S0186B0698 - 198 -
1 (Base Construction Allocation - 2 $345,000) 3 (Design and Contingencies - $15,000) 4 (22) SR 0422, Penn Run Exit Bridge 5 Eastbound over TR 840, White Township, 6 Bridge Painting 190,000 7 (Base Construction Allocation - 8 $175,000) 9 (Design and Contingencies - $15,000) 10 (23) SR 0422, Penn Run Exit Bridge 11 Westbound over TR 840, White Township, 12 Bridge Painting 190,000 13 (Base Construction Allocation - 14 $175,000) 15 (Design and Contingencies - $15,000) 16 (24) SR 0580, Cush Cushion Creek Bridge 17 over Cush Cushion Creek, Green 18 Township, Bridge Painting 85,000 19 (Base Construction Allocation - 20 $70,000) 21 (Design and Contingencies - $15,000) 22 (25) SR 0954, Yellow Creek Bridge over 23 Yellow Creek, White Township, Bridge 24 Painting 125,000 25 (Base Construction Allocation - 26 $110,000) 27 (Design and Contingencies - $15,000) 28 (26) SR 0954, Creekside Bridge over 29 Crooked Creek, White Township, Bridge 30 Painting 125,000 19970S0186B0698 - 199 -
1 (Base Construction Allocation - 2 $110,000) 3 (Design and Contingencies - $15,000) 4 (27) SR 0954, South Branch Bridge over 5 South Branch of Plum Creek, Washington 6 Township, Bridge Painting 75,000 7 (Base Construction Allocation - 8 $60,000) 9 (Design and Contingencies - $15,000) 10 (28) SR 1004, Philadelphia Street Exit 11 Bridge over SR 0119, White Township, 12 Bridge Painting 235,000 13 (Base Construction Allocation - 14 $220,000) 15 (Design and Contingencies - $15,000) 16 (29) SR 1006, Jimmy Stewart Airport Bridge 17 over SR 0119, White Township, Bridge 18 Painting 245,000 19 (Base Construction Allocation - 20 $230,000) 21 (Design and Contingencies - $15,000) 22 (30) SR 1007, Tanoma Bridge over Crooked 23 Creek, Rayne Township, Bridge Painting 75,000 24 (Base Construction Allocation - 25 $60,000) 26 (Design and Contingencies - $15,000) 27 (31) SR 1014, Diamondville Bridge over 28 North Branch of Twolick Creek, Green 29 Township, Bridge Painting 75,000 30 (Base Construction Allocation - 19970S0186B0698 - 200 -
1 $60,000) 2 (Design and Contingencies - $15,000) 3 (32) SR 1017, Pine Flats Bridge over South 4 Branch of Twolick Creek, Green 5 Township, Bridge Painting 95,000 6 (Base Construction Allocation - 7 $80,000) 8 (Design and Contingencies - $15,000) 9 (33) SR 1033, Gypsy Bridge over Cush 10 Creek, Montgomery Township, Bridge 11 Painting 85,000 12 (Base Construction Allocation - 13 $70,000) 14 (Design and Contingencies - $15,000) 15 (34) SR 1034, Lower Wilgus Bridge over 16 Branch of Cush Creek, Montgomery 17 Township, Bridge Painting 55,000 18 (Base Construction Allocation - 19 $40,000) 20 (Design and Contingencies - $15,000) 21 (35) SR 1038, Crooked Run Bridge over 22 Crooked Run, East Mahoning Township, 23 Bridge Painting 60,000 24 (Base Construction Allocation - 25 $45,000) 26 (Design and Contingencies - $15,000) 27 (36) SR 1045, Broadhead Run Bridge over 28 Broadhead Run, Canoe Township, Bridge 29 Painting 70,000 30 (Base Construction Allocation - 19970S0186B0698 - 201 -
1 $55,000) 2 (Design and Contingencies - $15,000) 3 (37) SR 1045, Juneau Bridge over Canoe 4 Creek, Canoe Township, Bridge Painting 75,000 5 (Base Construction Allocation - 6 $60,000) 7 (Design and Contingencies - $15,000) 8 (38) SR 1046, Straight Run Bridge over 9 Straight Run, Banks Township, Bridge 10 Painting 80,000 11 (Base Construction Allocation - 12 $65,000) 13 (Design and Contingencies - $15,000) 14 (39) SR 2019, Tearing Run Bridge No.1 over 15 Tearing Run, Center Township, Bridge 16 Painting 55,000 17 (Base Construction Allocation - 18 $40,000) 19 (Design and Contingencies - $15,000) 20 (40) SR 2019, Tearing Run Bridge No.2 over 21 Tearing Run, Center Township, Bridge 22 Painting 65,000 23 (Base Construction Allocation - 24 $50,000) 25 (Design and Contingencies - $15,000) 26 (41) SR 3003, Tunnelton Bridge over 27 Conemaugh River, Conemaugh Township, 28 Bridge Painting 525,000 29 (Base Construction Allocation - 30 $510,000) 19970S0186B0698 - 202 -
1 (Design and Contingencies - $15,000) 2 (42) SR 3007, Clarksburg Bridge over 3 Blacklegs Creek, Conemaugh Township, 4 Bridge Painting 105,000 5 (Base Construction Allocation - 6 $90,000) 7 (Design and Contingencies - $15,000) 8 (43) SR 3011, Blacklick Creek Bridge No.1 9 over Blacklick Creek, Brush Valley 10 Township, Bridge Painting 405,000 11 (Base Construction Allocation - 12 $390,000) 13 (Design and Contingencies - $15,000) 14 (44) SR 3011, Blacklick Creek Bridge No.2 15 over Blacklick Creek, Blacklick 16 Township, Bridge Painting 405,000 17 (Base Construction Allocation - 18 $390,000) 19 (Design and Contingencies - $15,000) 20 (45) SR 3013, Muddy Run Bridge over Muddy 21 Run, Blacklick Township, Bridge 22 Painting 65,000 23 (Base Construction Allocation - 24 $50,000) 25 (Design and Contingencies - $15,000) 26 (46) SR 3016, Homer City Bridge over 27 Twolick Creek, Homer City Borough, 28 Bridge Painting 125,000 29 (Base Construction Allocation - 30 $110,000) 19970S0186B0698 - 203 -
1 (Design and Contingencies - $15,000) 2 (47) SR 3031, Blacklegs Run Bridge over 3 Blacklegs Run, Young Township, Bridge 4 Painting 65,000 5 (Base Construction Allocation - 6 $50,000) 7 (Design and Contingencies - $15,000) 8 (48) SR 3037, Walker Run Bridge over 9 Walker Run, Armstrong Township, Bridge 10 Painting 55,000 11 (Base Construction Allocation - 12 $40,000) 13 (Design and Contingencies - $15,000) 14 (49) SR 3039, Anthony Run Bridge over 15 Anthony Run, Armstrong Township, Bridge 16 Painting 55,000 17 (Base Construction Allocation - 18 $40,000) 19 (Design and Contingencies - $15,000) 20 (50) SR 4001, Fisher Siding Bridge over 21 Crooked Creek, Armstrong Township, 22 Bridge Painting 110,000 23 (Base Construction Allocation - 24 $95,000) 25 (Design and Contingencies - $15,000) 26 (51) SR 4001, Five Points Bridge over 27 South Branch of Plum Creek, Washington 28 Township, Bridge Painting 100,000 29 (Base Construction Allocation - 30 $85,000) 19970S0186B0698 - 204 -
1 (Design and Contingencies - $15,000) 2 (52) SR 4006, Reddings Run Bridge over 3 Reddings Run, Washington Township, 4 Bridge Painting 55,000 5 (Base Construction Allocation - 6 $40,000) 7 (Design and Contingencies - $15,000) 8 (53) SR 4008, Kimmel Station Bridge No.1 9 over Branch of Crooked Creek, Rayne 10 Township, Bridge Painting 50,000 11 (Base Construction Allocation - 12 $35,000) 13 (Design and Contingencies - $15,000) 14 (54) SR 4008, Kimmel Station Bridge No.2 15 over Branch of Crooked Creek, Rayne 16 Township, Bridge Painting 50,000 17 (Base Construction Allocation - 18 $35,000) 19 (Design and Contingencies - $15,000) 20 (55) SR 4035, Plumville Bridge over Plum 21 Creek, Plumville Borough, Bridge 22 Painting 75,000 23 (Base Construction Allocation - 24 $60,000) 25 (Design and Contingencies - $15,000) 26 (56) SR 0056, Seward Conrail Overpass, 27 East Wheatfield Township, Bridge 28 Replacement 2,570,000 29 (Base Construction Allocation - 30 $2,080,000) 19970S0186B0698 - 205 -
1 (Land Allocation - $150,000) 2 (Design and Contingencies - $340,000) 3 Section 37. Jefferson County. 4 (a) Local Bridges 5 (1) Summerville Borough, County Bridge 40- 6 A, Anderson Road Bridge over Runaway 7 Run, Bridge Rehabilitation 415,000 8 (Base Construction Allocation - 9 $345,000) 10 (Land Allocation - $10,000) 11 (Design and Contingencies - $60,000) 12 (2) Sykesville Borough, Station Street 13 Bridge over Stump Creek, Bridge 14 Replacement 570,000 15 (Base Construction Allocation - 16 $500,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $60,000) 19 (3) Eldred Township, T-346 over Mill 20 Creek, Bridge Replacement 420,000 21 (Base Construction Allocation - 22 $330,000) 23 (Land Allocation - $10,000) 24 (Design and Contingencies - $80,000) 25 (4) Eldred Township, T-353 over Mill Run, 26 Bridge Replacement 245,000 27 (Base Construction Allocation - 28 $200,000) 29 (Land Allocation - $10,000) 30 (Design and Contingencies - $35,000) 19970S0186B0698 - 206 -
1 (5) Oliver Township, T-718 over Little 2 Sandy Creek, Bridge Replacement 490,000 3 (Base Construction Allocation - 4 $400,000) 5 (Land Allocation - $10,000) 6 (Design and Contingencies - $80,000) 7 (6) Union Township, T-320 over Little Mill 8 Creek, Bridge Replacement 245,000 9 (Base Construction Allocation - 10 $200,000) 11 (Land Allocation - $10,000) 12 (Design and Contingencies - $35,000) 13 (7) Union Township, T-321 over Runaway 14 Run, Bridge Replacement 145,000 15 (Base Construction Allocation - 16 $100,000) 17 (Land Allocation - $5,000) 18 (Design and Contingencies - $40,000) 19 (8) Young Township, T-632, BRIDGE NO.JC-36 <-- 20 over Saw Mill Run, Bridge Replacement 310,000 <-- 21 (Base Construction Allocation - 22 $250,000) 23 (Land Allocation - $10,000) 24 (Design and Contingencies - $50,000) 25 RUN, BRIDGE REPLACEMENT 330,000 <-- 26 (BASE CONSTRUCTION ALLOCATION - 27 $270,000) 28 (DESIGN AND CONTINGENCIES - $60,000) 29 (b) State Bridges 30 (1) SR 3033, T-830, Knox No.1 Bridge over 19970S0186B0698 - 207 -
1 Swamp Run, Knox Township, Bridge 2 Replacement 446,000 3 (Base Construction Allocation - 4 $376,000) 5 (Land Allocation - $10,000) 6 (Design and Contingencies - $60,000) 7 (2) SR 0036, Sawmill Run Bridge over 8 Sawmill Run, Punxsutawney Borough, 9 Bridge Painting 60,000 10 (Base Construction Allocation - 11 $45,000) 12 (Design and Contingencies - $15,000) 13 (3) SR 0119, Punxsutawney Bridge over 14 Mahoning Creek, Punxsutawney Borough, 15 Bridge Painting 250,000 16 (Base Construction Allocation - 17 $235,000) 18 (Design and Contingencies - $15,000) 19 (4) SR 0410, Beaver Run Bridge over Beaver 20 Run, Henderson Township, Bridge 21 Painting 55,000 22 (Base Construction Allocation - 23 $40,000) 24 (Design and Contingencies - $15,000) 25 (5) SR 0830, Falls Creek Bridge over Falls 26 Creek, Falls Creek Township, Bridge 27 Painting 80,000 28 (Base Construction Allocation - 29 $65,000) 30 (Design and Contingencies - $15,000) 19970S0186B0698 - 208 -
1 (6) SR 0949, Corsica Exit Bridge over I- 2 80, Union Township, Bridge Painting 205,000 3 (Base Construction Allocation - 4 $190,000) 5 (Design and Contingencies - $15,000) 6 (7) SR 1009, Kyle's Run Bridge over Kyle's 7 Run, Washington Township, Bridge 8 Painting 60,000 9 (Base Construction Allocation - 10 $45,000) 11 (Design and Contingencies - $15,000) 12 (8) SR 1027, Egypt Bridge over North Fork 13 Creek, Rock Township, Bridge Painting 125,000 14 (Base Construction Allocation - 15 $110,000) 16 (Design and Contingencies - $15,000) 17 (9) SR 2007, Clover Run Bridge over Clover 18 Run, Gaskill Township, Bridge Painting 95,000 19 (Base Construction Allocation - 20 $80,000) 21 (Design and Contingencies - $15,000) 22 (10) SR 2008, Stump Creek Bridge over 23 Stump Creek, Henderson Township, Bridge 24 Painting 100,000 25 (Base Construction Allocation - 26 $85,000) 27 (Design and Contingencies - $15,000) 28 (11) SR 2023, Anita Bridge over Elk Run, 29 McCalmont Township, Bridge Painting 60,000 30 (Base Construction Allocation - 19970S0186B0698 - 209 -
1 $45,000) 2 (Design and Contingencies - $15,000) 3 (12) SR 2023, Charcoal Plant Bridge over 4 Sandy Lick Creek, Pine Creek Township, 5 Bridge Painting 125,000 6 (Base Construction Allocation - 7 $110,000) 8 (Design and Contingencies - $15,000) 9 (13) SR 3003, Baxter Bridge over Redbank 10 Creek, Clover Township, Bridge 11 Painting 235,000 12 (Base Construction Allocation - 13 $220,000) 14 (Design and Contingencies - $15,000) 15 (14) SR 4006, North Fork Creek Bridge over 16 North Fork Creek, Warsaw Township, 17 Bridge Painting 110,000 18 (Base Construction Allocation - 19 $95,000) 20 (Design and Contingencies - $15,000) 21 (15) SR 0310, Bridge over Branch of Trout 22 Run, Winslow Township, Bridge 23 Replacement 490,000 24 (Base Construction Allocation - 25 $350,000) 26 (Land Allocation - $20,000) 27 (Design and Contingencies - $120,000) 28 (16) SR 3018, Bridge over Little Sandy 29 Creek, Limestone Township, Bridge 30 Replacement 670,000 19970S0186B0698 - 210 -
1 (Base Construction Allocation - 2 $500,000) 3 (Land Allocation - $20,000) 4 (Design and Contingencies - $150,000) 5 Section 38. Juniata County. 6 (a) Local Bridges 7 (1) Fayette Township, T-558 over West 8 Branch of Cocolamus Creek, Bridge 9 Rehabilitation 21,000 10 (Base Construction Allocation - 11 $18,000) 12 (Design and Contingencies - $3,000) 13 (2) Fayette Township, T-602 over Little 14 Lost Creek, Bridge Rehabilitation 19,000 15 (Base Construction Allocation - 16 $17,000) 17 (Design and Contingencies - $2,000) 18 (b) State Bridges 19 (1) SR 0850, Laurel Run Bridge over Laurel 20 Run, Village of Honey Grove, Tuscarora 21 Township, Bridge Replacement 670,000 22 (Base Construction Allocation - 23 $500,000) 24 (Land Allocation - $20,000) 25 (Design and Contingencies - $150,000) 26 (2) SR 0850, Bridge over Tuscarora Creek, 27 Tuscarora Township, Bridge 28 Rehabilitation 155,000 29 (Base Construction Allocation - 30 $150,000) 19970S0186B0698 - 211 -
1 (Design and Contingencies - $5,000) 2 (3) SR 0850, Bridge over Tuscarora Creek, 3 Tuscarora Township, Bridge Replacement 1,420,000 4 (Base Construction Allocation - 5 $1,280,000) 6 (Land Allocation - $40,000) 7 (Design and Contingencies - $100,000) 8 Section 39. Lackawanna County. 9 (a) Local Bridges 10 (1) Mayfield Borough, Poplar Street Bridge 11 No.1 at Junction of South Washington 12 Avenue, Bridge Rehabilitation 150,000 13 (Base Construction Allocation - 14 $130,000) 15 (Design and Contingencies - $20,000) 16 (b) State Bridges 17 (1) SR 1016, Hill Street Bridge over 18 Lackawanna River, Jessup and Blakely 19 Boroughs, Bridge Deck Rehabilitation 890,000 20 (Base Construction Allocation - 21 $800,000) 22 (Land Allocation - $10,000) 23 (Design and Contingencies - $80,000) 24 (2) SR 3011, Keyser Avenue Bridge over 25 Lindy Creek, City of Scranton, Bridge 26 Replacement 185,000 27 (Base Construction Allocation - 28 $100,000) 29 (Land Allocation - $10,000) 30 (Design and Contingencies - $75,000) 19970S0186B0698 - 212 -
1 (3) SR 0171, Bridge over Elk Creek at 2 Junction of SR 1011, Fell Township, 3 Bridge Replacement 660,000 4 (Base Construction Allocation - 5 $520,000) 6 (Land Allocation - $10,000) 7 (Design and Contingencies - $130,000) 8 (4) SR 0247, Bridge over South Branch of 9 Tunkhannock Creek, North of TR 438, 10 Scott Township, Bridge Replacement 426,000 11 (Base Construction Allocation - 12 $330,000) 13 (Land Allocation - $10,000) 14 (Design and Contingencies - $86,000) 15 (5) SR 2003, Bridge over Wallenpaupack 16 Creek, North of TR 348, Jefferson 17 Township, Bridge Replacement 355,000 18 (Base Construction Allocation - 19 $275,000) 20 (Land Allocation - $10,000) 21 (Design and Contingencies - $70,000) 22 (6) SR 3013, Main Street Bridge, Old Forge 23 Borough, Bridge Painting 660,000 24 (Base Construction Allocation - 25 $600,000) 26 (Design and Contingencies - $60,000) 27 (7) State Bridges, Countywide Bridge Zone 28 Painting, Bridge Painting 370,000 29 (Base Construction Allocation - 30 $350,000) 19970S0186B0698 - 213 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $10,000) 3 (8) SR 1013, Bridge over Elm Brook, 0.7 4 Mile North of SR 1006, Scott Township, 5 Bridge Replacement 240,000 6 (Base Construction Allocation - 7 $200,000) 8 (Land Allocation - $10,000) 9 (Design and Contingencies - $30,000) 10 (9) SR 0524, Kennedy Creek Bridge, 0.5 11 Mile East of TR 407, North Abington 12 Township, Bridge Replacement 330,000 13 (Base Construction Allocation - 14 $280,000) 15 (Land Allocation - $10,000) 16 (Design and Contingencies - $40,000) 17 (10) SR 0011, Roaring Brook Retaining 18 Wall, Spruce Street Complex, City of 19 Scranton, Bridge Replacement 1,320,000 20 (Base Construction Allocation - 21 $1,160,000) 22 (Land Allocation - $10,000) 23 (Design and Contingencies - $150,000) 24 Section 40. Lancaster County. 25 (a) Local Bridges 26 (1) Manor Township, T-599, West Roseville 27 Road Bridge over Little Conestoga 28 Creek, Bridge Replacement 375,000 29 (Base Construction Allocation - 30 $286,000) 19970S0186B0698 - 214 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $150,000) 3 (2) Mt. Joy Township, T-350, Risser Mill 4 Bridge over Tributary of Little 5 Chickies Creek, Bridge Rehabilitation 550,000 6 (Base Construction Allocation - 7 $400,000) 8 (Design and Contingencies - $150,000) 9 (3) Pequea Township, Silver Mine Road at 10 Burnt Mills, Bridge Replacement 100,000 11 (Base Construction Allocation - 12 $90,000) 13 (Design and Contingencies - $10,000) 14 (4) EAST HEMPFIELD AND MANHEIM TOWNSHIPS, <-- 15 SHREINER STATION ROAD BRIDGE OVER 16 CONESTOGA CREEK, BRIDGE REPLACEMENT 477,000 17 (BASE CONSTRUCTION ALLOCATION - 18 $377,000) 19 (LAND ALLOCATION - $20,000) 20 (DESIGN AND CONTINGENCIES - $80,000) 21 (b) State Bridges 22 (1) SR 1024, Bridge over Little Cocalico 23 Creek, East Cocalico Township, Bridge 24 Replacement 675,000 25 (Base Construction Allocation - 26 $550,000) 27 (Land Allocation - $25,000) 28 (Design and Contingencies - $100,000) 29 Section 41. Lawrence County. 30 (a) Local Bridges 19970S0186B0698 - 215 -
1 (1) City of New Castle, Willard Avenue 2 Bridge over Tributary of Shenango 3 River, Bridge Replacement 210,000 4 (Base Construction Allocation - 5 $150,000) 6 (Land Allocation - $20,000) 7 (Design and Contingencies - $40,000) 8 (2) Wampum Borough, Main Street Bridge 9 over Eckles Run, Bridge Rehabilitation 190,000 10 (Base Construction Allocation - 11 $150,000) 12 (Design and Contingencies - $40,000) 13 (b) State Bridges 14 (1) SR 0018, Mahoning Avenue Viaduct over 15 Shenango River and Railroad, City of 16 New Castle, Bridge Replacement 9,320,000 17 (Base Construction Allocation - 18 $9,000,000) 19 (Land Allocation - $20,000) 20 (Design and Contingencies - $300,000) 21 (2) SR 0018, Liberty Street Bridge over 22 Hickory Run, New Castle City, Bridge 23 Rehabilitation 450,000 24 (Base Construction Allocation - 25 $300,000) 26 (Land Allocation - $50,000) 27 (Design and Contingencies - $100,000) 28 (3) SR 0060, SR 0060 Southbound over SR 29 4004, Neshannock Township, Bridge 30 Replacement 350,000 19970S0186B0698 - 216 -
1 (Base Construction Allocation - 2 $200,000) 3 (Land Allocation - $50,000) 4 (Design and Contingencies - $100,000) 5 (4) SR 0065, Ellwood Road Bridge over B&O 6 Railroad, Shenango Township, Bridge 7 Replacement 400,000 8 (Base Construction Allocation - 9 $250,000) 10 (Land Allocation - $50,000) 11 (Design and Contingencies - $100,000) 12 (5) SR 0488, Portersville Road Bridge over 13 Morrison Run, Perry Township, Bridge 14 Replacement 250,000 15 (Base Construction Allocation - 16 $100,000) 17 (Land Allocation - $50,000) 18 (Design and Contingencies - $100,000) 19 (6) SR 0488, Portersville Road Bridge over 20 Morrison Run, Perry Township, Bridge 21 Replacement 250,000 22 (Base Construction Allocation - 23 $100,000) 24 (Land Allocation - $50,000) 25 (Design and Contingencies - $100,000) 26 (7) SR 3001, South Main Street Bridge over 27 Bessemer Haul Road, Bessemer Borough, 28 Bridge Rehabilitation 950,000 29 (Base Construction Allocation - 30 $800,000) 19970S0186B0698 - 217 -
1 (Design and Contingencies - $150,000) 2 (8) SR 4004, Union and Neshannock 3 Townships, Bridge Rehabilitation 800,000 4 (Base Construction Allocation - 5 $700,000) 6 (Design and Contingencies - $100,000) 7 (9) SR 0060, Beaver Valley Expansion 8 Bridge over SR 4005, Neshannock 9 Township, Bridge Rehabilitation 650,000 10 (Base Construction Allocation - 11 $500,000) 12 (Design and Contingencies - $150,000) 13 (10) SR 0060, Beaver Valley Extension 14 Bridge over SR 4005, Neshannock 15 Township, Bridge Rehabilitation 127,000 16 (Base Construction Allocation - 17 $116,000) 18 (Design and Contingencies - $11,000) 19 (11) SR 0081, US 224 State Street Bridge 20 over SR 0422 and Ramp K, Union 21 Township, Bridge Rehabilitation 706,000 22 (Base Construction Allocation - 23 $644,000) 24 (Design and Contingencies - $62,000) 25 (12) SR 0422, Westbound Bridge over Beaver 26 River, Railroad and Local Street, 27 Taylor Township, Bridge Rehabilitation 6,841,000 28 (Base Construction Allocation - 29 $6,741,000) 30 (Design and Contingencies - $100,000) 19970S0186B0698 - 218 -
1 (13) SR 0422, Eastbound Bridge over Beaver 2 River, Railroad and Local Street, 3 Taylor Township, Bridge Replacement 6,963,000 4 (Base Construction Allocation - 5 $6,863,000) 6 (Design and Contingencies - $100,000) 7 (14) SR 0422, Bridge over Business US 422, 8 Union Township, Bridge Rehabilitation 1,379,000 9 (Base Construction Allocation - 10 $1,254,000) 11 (Design and Contingencies - $125,000) 12 (15) SR 0422, Ben Franklin Highway Bridge 13 over Business US 422, Union Township, 14 Bridge Rehabilitation 436,000 15 (Base Construction Allocation - 16 $398,000) 17 (Design and Contingencies - $38,000) 18 (16) SR 0551, Main Street Bridge over 19 Beaver Creek, Little Beaver Township, 20 Bridge Replacement 624,000 21 (Base Construction Allocation - 22 $524,000) 23 (Design and Contingencies - $100,000) 24 (17) SR 2020, Pleasant Road Bridge over 25 Camp Run, Perry Township, Bridge 26 Replacement 400,000 27 (Base Construction Allocation - 28 $300,000) 29 (Design and Contingencies - $100,000) 30 (18) SR 3002, Beaver Dam Road Bridge over 19970S0186B0698 - 219 -
1 Honey Creek, Little Beaver Township, 2 Bridge Painting 30,000 3 (Base Construction Allocation - 4 $25,000) 5 (Design and Contingencies - $5,000) 6 (19) SR 3004, Wallace Road Bridge over 7 Sugar Creek, North Beaver Township, 8 Bridge Replacement 130,000 9 (Base Construction Allocation - 10 $120,000) 11 (Design and Contingencies - $10,000) 12 (20) SR 3004, Wallace Road Bridge over 13 Branch of Honey Creek, North Beaver 14 Township, Bridge Painting 30,000 15 (Base Construction Allocation - 16 $25,000) 17 (Design and Contingencies - $5,000) 18 (21) SR 3004, Wallace Road Bridge over 19 Branch of Honey Creek, North Beaver 20 Township, Bridge Painting 325,000 21 (Base Construction Allocation - 22 $300,000) 23 (Design and Contingencies - $25,000) 24 (22) SR 4006, Coffee Run Bridge over 25 Coffee Run, Mahoning Township, Bridge 26 Replacement 335,000 27 (Base Construction Allocation - 28 $270,000) 29 (Land Allocation - $15,000) 30 (Design and Contingencies - $50,000) 19970S0186B0698 - 220 -
1 (23) SR 0224, Bridge over Conrail, 2 Mahoning Township, Bridge Replacement 2,000,000 3 (Base Construction Allocation - 4 $1,700,000) 5 (Land Allocation - $100,000) 6 (Design and Contingencies - $200,000) 7 Section 42. Lebanon County. 8 (a) Local Bridges 9 (1) Union Township, T-617, Green Point 10 School House Bridge over Trout Run, 11 Bridge Replacement 255,000 12 (Base Construction Allocation - 13 $170,000) 14 (Land Allocation - $10,000) 15 (Design and Contingencies - $75,000) 16 (2) Bethel Township, Market Drive, T-545 17 over Beach Run, Bridge Replacement 30,000 18 (Base Construction Allocation - 19 $20,000) 20 (Design and Contingencies - $10,000) 21 (3) South Londonderry Township, Patrick 22 Road, T-331 over Tributary of Little 23 Conewago Creek, Bridge Rehabilitation 5,000 24 (Base Construction Allocation - $4,000) 25 (Design and Contingencies - $1,000) 26 (4) South Londonderry Township, Eckert 27 Road, T-304 over Little Conewago Creek, 28 Bridge Rehabilitation 5,000 29 (Base Construction Allocation - $4,000) 30 (Design and Contingencies - $1,000) 19970S0186B0698 - 221 -
1 (5) South Londonderry Township, Risser 2 Road, T-300 over Conewago Creek, Bridge 3 Rehabilitation 4,000 4 (Base Construction Allocation - $3,000) 5 (Design and Contingencies - $1,000) 6 (6) South Londonderry Township, Long Road, 7 T-304 over Tributary of Conewago Creek, 8 Bridge Rehabilitation 4,000 9 (Base Construction Allocation - $3,000) 10 (Design and Contingencies - $1,000) 11 (7) South Londonderry Township, Eckert 12 Road, T-304 over Tributary of Little 13 Conewago Creek, Bridge Rehabilitation 5,000 14 (Base Construction Allocation - $4,000) 15 (Design and Contingencies - $1,000) 16 (8) South Londonderry Township, Church 17 Road, T-303 over Unnamed Creek, Bridge 18 Rehabilitation 3,000 19 (Base Construction Allocation - $2,000) 20 (Design and Contingencies - $1,000) 21 (9) South Londonderry Township, Patrick 22 Road, T-331 over Tributary of Little 23 Conewago Creek, Bridge Rehabilitation 4,000 24 (Base Construction Allocation - $3,000) 25 (Design and Contingencies - $1,000) 26 (10) South Londonderry Township, Hinkle 27 Road, T-433 over Killinger Creek, 28 Bridge Rehabilitation 4,000 29 (Base Construction Allocation - $3,000) 30 (Design and Contingencies - $1,000) 19970S0186B0698 - 222 -
1 (11) South Londonderry Township, Brandt 2 Road, T-346 over Killinger Creek, 3 Bridge Rehabilitation 3,000 4 (Base Construction Allocation - $2,000) 5 (Design and Contingencies - $1,000) 6 (12) Union Township, Green Point School 7 House Road, T-617 over Trout Run, 8 Bridge Replacement 90,000 9 (Base Construction Allocation - 10 $70,000) 11 (Design and Contingencies - $20,000) 12 (b) State Bridges (Reserved) 13 Section 43. Lehigh County. 14 (a) Local Bridges (Reserved) 15 (b) State Bridges 16 (1) SR 4007, Schlicher's Bridge over 17 Jordan Creek, North Whitehall Township, 18 Bridge Replacement 875,000 19 (Base Construction Allocation - 20 $560,000) 21 (Land Allocation - $145,000) 22 (Design and Contingencies - $170,000) 23 (2) SR 3011, Farmington Road over 24 Tributary of Schaffer Run, Upper 25 Macungie Township, Bridge 26 Rehabilitation 330,000 27 (Base Construction Allocation - 28 $175,000) 29 (Land Allocation - $55,000) 30 (Design and Contingencies - $100,000) 19970S0186B0698 - 223 -
1 (3) SR 1027, Cold Springs Road over Spring 2 Creek, Whitehall Township, Bridge 3 Replacement 2,550,000 4 (Base Construction Allocation - 5 $1,640,000) 6 (Land Allocation - $420,000) 7 (Design and Contingencies - $490,000) 8 Section 44. Luzerne County. 9 (a) Local Bridges 10 (1) Ashley Borough, Ashley Street Bridge, 11 Bridge Removal 260,000 12 (Base Construction Allocation - 13 $200,000) 14 (Land Allocation - $5,000) 15 (Design and Contingencies - $55,000) 16 (2) Franklin Township, T-784, Bridge over 17 Sutton Creek, Bridge Replacement 320,000 18 (Base Construction Allocation - 19 $250,000) 20 (Land Allocation - $15,000) 21 (Design and Contingencies - $55,000) 22 (3) Black Creek Township, T-309 over Falls 23 Run Creek, Bridge Replacement 395,000 24 (Base Construction Allocation - 25 $265,000) 26 (Land Allocation - $5,000) 27 (Design and Contingencies - $125,000) 28 (4) Black Creek Township, T-314 over 29 Branch of Black Creek, Bridge 30 Replacement 440,000 19970S0186B0698 - 224 -
1 (Base Construction Allocation - 2 $310,000) 3 (Land Allocation - $5,000) 4 (Design and Contingencies - $125,000) 5 (5) Butler Township, T-356 over Nescopeck 6 Creek, Bridge Replacement 405,000 7 (Base Construction Allocation - 8 $275,000) 9 (Land Allocation - $5,000) 10 (Design and Contingencies - $125,000) 11 (6) City of Wilkes-Barre, Division Street 12 over Solomon's Creek, Bridge 13 Replacement 955,000 14 (Base Construction Allocation - 15 $800,000) 16 (Land Allocation - $5,000) 17 (Design and Contingencies - $150,000) 18 (7) Dallas Township, County Road No.12 19 over Toby's Creek, Bridge Replacement 405,000 20 (Base Construction Allocation - 21 $275,000) 22 (Land Allocation - $5,000) 23 (Design and Contingencies - $125,000) 24 (8) Dennison Township, County Road No.41 25 over Nescopeck Creek, Bridge 26 Replacement 405,000 27 (Base Construction Allocation - 28 $275,000) 29 (Land Allocation - $5,000) 30 (Design and Contingencies - $125,000) 19970S0186B0698 - 225 -
1 (9) Dorrance Township, County Road No.30 2 over Wapwallopen Creek, Bridge 3 Replacement 405,000 4 (Base Construction Allocation - 5 $275,000) 6 (Land Allocation - $5,000) 7 (Design and Contingencies - $125,000) 8 (10) Fairmount Township, T-563 over Maple 9 Run Creek, Bridge Replacement 395,000 10 (Base Construction Allocation - 11 $265,000) 12 (Land Allocation - $5,000) 13 (Design and Contingencies - $125,000) 14 (11) Franklin Township, T-782 over Sutton 15 Creek, Bridge Replacement 405,000 16 (Base Construction Allocation - 17 $275,000) 18 (Land Allocation - $5,000) 19 (Design and Contingencies - $125,000) 20 (12) Hunlock Township, T-534 over Hunlock 21 Creek, Bridge Replacement 405,000 22 (Base Construction Allocation - 23 $275,000) 24 (Land Allocation - $5,000) 25 (Design and Contingencies - $125,000) 26 (13) Jackson Township, County Road No.16 27 over Toby's Creek, Bridge Replacement 350,000 28 (Base Construction Allocation - 29 $225,000) 30 (Land Allocation - $5,000) 19970S0186B0698 - 226 -
1 (Design and Contingencies - $120,000) 2 (14) Jackson Township, County Road No.16 3 over Toby's Creek, Bridge Replacement 370,000 4 (Base Construction Allocation - 5 $240,000) 6 (Land Allocation - $5,000) 7 (Design and Contingencies - $125,000) 8 (15) Jackson Township, T-605 over Branch 9 of Harvey's Creek, Bridge Replacement 395,000 10 (Base Construction Allocation - 11 $265,000) 12 (Land Allocation - $5,000) 13 (Design and Contingencies - $125,000) 14 (16) Jackson Township, County Road No.13 15 over Toby's Creek, Bridge Replacement 395,000 16 (Base Construction Allocation - 17 $265,000) 18 (Land Allocation - $5,000) 19 (Design and Contingencies - $125,000) 20 (17) Lake Township, T-796 over Beaver Run 21 Creek, Bridge Replacement 410,000 22 (Base Construction Allocation - 23 $280,000) 24 (Land Allocation - $5,000) 25 (Design and Contingencies - $125,000) 26 (18) Lake Township, T-779 over Bryant Pond 27 Outlet, Bridge Replacement 430,000 28 (Base Construction Allocation - 29 $300,000) 30 (Land Allocation - $5,000) 19970S0186B0698 - 227 -
1 (Design and Contingencies - $125,000) 2 (19) Nescopeck Township, T-381 over Branch 3 of Nescopeck Creek, Bridge Replacement 410,000 4 (Base Construction Allocation - 5 $280,000) 6 (Land Allocation - $5,000) 7 (Design and Contingencies - $125,000) 8 (20) Ross Township, T-680 over Huntingdon 9 Creek, Bridge Replacement 410,000 10 (Base Construction Allocation - 11 $280,000) 12 (Land Allocation - $5,000) 13 (Design and Contingencies - $125,000) 14 (21) Ross Township, T-571 over Outlet 15 North Pond, Bridge Replacement 420,000 16 (Base Construction Allocation - 17 $290,000) 18 (Land Allocation - $5,000) 19 (Design and Contingencies - $125,000) 20 (22) Ross Township, T-575 over Huntingdon 21 Creek, Bridge Replacement 455,000 22 (Base Construction Allocation - 23 $325,000) 24 (Land Allocation - $5,000) 25 (Design and Contingencies - $125,000) 26 (23) Ross Township, County Road No.2 over 27 Marsh Creek, Bridge Replacement 440,000 28 (Base Construction Allocation - 29 $310,000) 30 (Land Allocation - $5,000) 19970S0186B0698 - 228 -
1 (Design and Contingencies - $125,000) 2 (24) Sugarloaf Township, T-332 over Branch 3 of Nescopeck Creek, Bridge Replacement 430,000 4 (Base Construction Allocation - 5 $300,000) 6 (Land Allocation - $5,000) 7 (Design and Contingencies - $125,000) 8 (25) Plymouth Township, T-497 over Mud 9 Pond Inlet, Bridge Replacement 405,000 10 (Base Construction Allocation - 11 $275,000) 12 (26) Slocum Township, T-454 over Black 13 Creek, Bridge Replacement 395,000 14 (Base Construction Allocation - 15 $265,000) 16 (Land Allocation - $5,000) 17 (Design and Contingencies - $125,000) 18 (27) Wright Township, County Road No.21 19 over Wapwallopen Creek, Bridge 20 Replacement 395,000 21 (Base Construction Allocation - 22 $265,000) 23 (Land Allocation - $5,000) 24 (Design and Contingencies - $125,000) 25 (28) City of Wilkes-Barre, Stanton Street, 26 Bowman Spring Run Bridge, Intersection 27 of Empire Street, Bridge Replacement 170,000 28 (Base Construction Allocation - 29 $140,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 229 -
1 (Design and Contingencies - $20,000) 2 (29) BOROUGH OF LARKSVILLE, NESBITT STREET <-- 3 BRIDGE, BRIDGE REPLACEMENT 109,000 4 (BASE CONSTRUCTION ALLOCATION - 5 $95,000) 6 (DESIGN AND CONTINGENCIES - $14,000) 7 (b) State Bridges 8 (1) SR 0011, Erie-Lackawanna Railroad 9 Bridge over Erie-Lackawanna Railroad, 10 Plymouth Township, Bridge Removal 185,000 11 (Base Construction Allocation - 12 $150,000) 13 (Land Allocation - $10,000) 14 (Design and Contingencies - $25,000) 15 (2) SR 1030, Harvey's Lake Bridge at 16 Junction of SR 1053, Lake Township, 17 Bridge Replacement 460,000 18 (Base Construction Allocation - 19 $350,000) 20 (Land Allocation - $20,000) 21 (Design and Contingencies - $90,000) 22 (3) SR 3007, Bridge over Wapwallopen 23 Creek, South of SR 3010, Dorrance 24 Township, Bridge Replacement 530,000 25 (Base Construction Allocation - 26 $420,000) 27 (Land Allocation - $10,000) 28 (Design and Contingencies - $100,000) 29 (4) State Bridges, Countywide Bridge Zone 30 Painting, Bridge Painting 370,000 19970S0186B0698 - 230 -
1 (Base Construction Allocation - 2 $350,000) 3 (Land Allocation - $10,000) 4 (Design and Contingencies - $10,000) 5 (5) SR 3038, Black Creek Stone Arch 6 Bridge, 0.1 Mile North of SR 3018, 7 Black Creek Township, Bridge 8 Replacement 240,000 9 (Base Construction Allocation - 10 $200,000) 11 (Land Allocation - $10,000) 12 (Design and Contingencies - $30,000) 13 (6) SR 1034, Pikes Creek Bridge, 132 Feet 14 East of TR 11, Lake Township, Bridge 15 Replacement 180,000 16 (Base Construction Allocation - 17 $150,000) 18 (Land Allocation - $10,000) 19 (Design and Contingencies - $20,000) 20 (7) SR 2041, Wright Creek Bridge, 2 Miles 21 North of TR 940, Dennison Township, 22 Bridge Replacement 400,000 23 (Base Construction Allocation - 24 $340,000) 25 (Land Allocation - $10,000) 26 (Design and Contingencies - $50,000) 27 Section 45. Lycoming County. 28 (a) Local Bridges 29 (1) Mifflin Township, T-651 over Larry's 30 Creek, Bridge Replacement 528,000 19970S0186B0698 - 231 -
1 (Base Construction Allocation - 2 $438,000) 3 (Land Allocation - $20,000) 4 (Design and Contingencies - $70,000) 5 (2) McIntyre Township, T-667, Rolston 6 Bridge over Lycoming Creek, Bridge 7 Replacement 1,620,000 8 (Base Construction Allocation - 9 $1,400,000) 10 (Land Allocation - $20,000) 11 (Design and Contingencies - $200,000) 12 (3) FRANKLIN TOWNSHIP, T-710, BRIDGE OVER <-- 13 BEAVER RUN, BRIDGE REPLACEMENT 265,000 14 (BASE CONSTRUCTION ALLOCATION - 15 $212,000) 16 (LAND ALLOCATION - $40,000) 17 (DESIGN AND CONTINGENCIES - $13,000) 18 (4) PIATT TOWNSHIP, T-365, BRIDGE OVER 19 LARRY'S CREEK, BRIDGE REPLACEMENT 1,251,000 20 (BASE CONSTRUCTION ALLOCATION - 21 $1,039,000) 22 (LAND ALLOCATION - $30,000) 23 (DESIGN AND CONTINGENCIES - $182,000) 24 (5) MCINTYRE TOWNSHIP, T-673, BRIDGE OVER 25 LYCOMING CREEK, BRIDGE REPLACEMENT 902,000 26 (BASE CONSTRUCTION ALLOCATION - 27 $744,000) 28 (LAND ALLOCATION - $23,000) 29 (DESIGN AND CONTINGENCIES - $135,000) 30 (6) SHREWSBURY TOWNSHIP, T-686, BRIDGE 19970S0186B0698 - 232 -
1 OVER ROCK RUN, BRIDGE REPLACEMENT 288,000 2 (BASE CONSTRUCTION ALLOCATION - 3 $238,000) 4 (LAND ALLOCATION - $7,000) 5 (DESIGN AND CONTINGENCIES - $43,000) 6 (7) PIATT TOWNSHIP, T-343, BRIDGE OVER 7 PINE RUN, BRIDGE REPLACEMENT 353,000 8 (BASE CONSTRUCTION ALLOCATION - 9 $291,000) 10 (LAND ALLOCATION - $9,000) 11 (DESIGN AND CONTINGENCIES - $53,000) 12 (8) WASHINGTON TOWNSHIP, T-397, BRIDGE 13 OVER DEER HOLE CREEK, BRIDGE 14 REPLACEMENT 517,000 15 (BASE CONSTRUCTION ALLOCATION - 16 $426,000) 17 (LAND ALLOCATION - $13,000) 18 (DESIGN AND CONTINGENCIES - $78,000) 19 (9) SOUTH WILLIAMSPORT BOROUGH, EAST 20 CENTRAL AVENUE, BRIDGE OVER HAGERMANS 21 RUN, BRIDGE REPLACEMENT 519,000 22 (BASE CONSTRUCTION ALLOCATION - 23 $428,000) 24 (LAND ALLOCATION - $13,000) 25 (DESIGN AND CONTINGENCIES - $78,000) 26 (10) MORELAND TOWNSHIP, T-443, BRIDGE OVER 27 LITTLE MUNCY CREEK, BRIDGE REPLACEMENT 780,000 28 (BASE CONSTRUCTION ALLOCATION - 29 $630,000) 30 (LAND ALLOCATION - $20,000) 19970S0186B0698 - 233 -
1 (DESIGN AND CONTINGENCIES - $130,000) 2 (11) MUNCY CREEK TOWNSHIP, T-437, BRIDGE 3 OVER BRANCH OF MUNCY CREEK, BRIDGE 4 REPLACEMENT 335,000 5 (BASE CONSTRUCTION ALLOCATION - 6 $268,000) 7 (LAND ALLOCATION - $17,000) 8 (DESIGN AND CONTINGENCIES - $50,000) 9 (12) MUNCY CREEK TOWNSHIP, T-811, BRIDGE 10 OVER WOLF RUN, BRIDGE REPLACEMENT 150,000 11 (BASE CONSTRUCTION ALLOCATION - 12 $120,000) 13 (LAND ALLOCATION - $10,000) 14 (DESIGN AND CONTINGENCIES - $20,000) 15 (b) State Bridges 16 (1) SR 0220, Quenshukeny Run Bridge over 17 Quenshukeny Run, Village of Linden, 18 Bridge Replacement 395,000 19 (Base Construction Allocation - 20 $316,000) 21 (Land Allocation - $20,000) 22 (Design and Contingencies - $59,000) 23 (2) SR 0973, Bridge over Hoagland Run, 3 24 Miles West of Cogan Station, Bridge 25 Rehabilitation 195,000 26 (Base Construction Allocation - 27 $156,000) 28 (Land Allocation - $10,000) 29 (Design and Contingencies - $29,000) 30 (3) SR 1006, Wallis Run Bridge over Wallis 19970S0186B0698 - 234 -
1 Run, Cascade Township, Bridge 2 Replacement 65,000 3 (Base Construction Allocation - 4 $50,000) 5 (Land Allocation - $5,000) 6 (Design and Contingencies - $10,000) 7 (4) SR 2022, Mill Creek Bridge, North of 8 Montoursville, Bridge Replacement 668,000 9 (Base Construction Allocation - 10 $575,000) 11 (Land Allocation - $43,000) 12 (Design and Contingencies - $50,000) 13 (5) SR 2051, Wolf Run Bridge over Wolf 14 Run, South of SR 0220, Muncy Township, 15 Bridge Replacement 638,000 16 (Base Construction Allocation - 17 $510,000) 18 (Land Allocation - $32,000) 19 (Design and Contingencies - $96,000) 20 (6) SR 3024, Jobs Run Road Bridge over 21 Tributary of Larrys Creek, East of 22 Salladasburg, Bridge Replacement 108,000 23 (Base Construction Allocation - 24 $92,000) 25 (Land Allocation - $8,000) 26 (Design and Contingencies - $8,000) 27 (7) SR 3028, West 4th Street, Lycoming 28 Creek Bridge, City of Williamsport, 29 Bridge Rehabilitation 216,000 30 (Base Construction Allocation - 19970S0186B0698 - 235 -
1 $185,000) 2 (Land Allocation - $15,000) 3 (Design and Contingencies - $16,000) 4 (8) SR 0044, Bridge over Conrail, Bridge 5 Painting 210,000 6 (Base Construction Allocation - 7 $200,000) 8 (Design and Contingencies - $10,000) 9 (9) SR 0180, I-180 Eastbound Bridge over 10 Loyalsock Creek, Bridge Painting 135,000 11 (Base Construction Allocation - 12 $125,000) 13 (Design and Contingencies - $10,000) 14 (10) SR 0180, I-180 Westbound Bridge over 15 Loyalsock Creek, Bridge Painting 135,000 16 (Base Construction Allocation - 17 $125,000) 18 (Design and Contingencies - $10,000) 19 (11) SR 2014, Bridge over Lycoming Creek, 20 Bridge Painting 780,000 21 (Base Construction Allocation - 22 $770,000) 23 (Design and Contingencies - $10,000) 24 (12) SR 2061, Bridge over Little Muncy 25 Creek, Bridge Painting 80,000 26 (Base Construction Allocation - 27 $70,000) 28 (Design and Contingencies - $10,000) 29 (13) SR 0014, SR 0014 over Trout Run, 30 Lewis Township, Bridge Replacement 640,000 19970S0186B0698 - 236 -
1 (Base Construction Allocation - 2 $512,000) 3 (Land Allocation - $32,000) 4 (Design and Contingencies - $96,000) 5 (14) SR 0044, SR 0044 over Ramsey Run, 6 Cummings Township, Bridge Replacement 394,000 7 (Base Construction Allocation - 8 $315,000) 9 (Land Allocation - $20,000) 10 (Design and Contingencies - $59,000) 11 (15) SR 0044, SR 0044 over Pine Bottom 12 Run, Cummings Township, Bridge 13 Replacement 360,000 14 (Base Construction Allocation - 15 $288,000) 16 (Land Allocation - $18,000) 17 (Design and Contingencies - $54,000) 18 (16) SR 0118, SR 0118 over Big Run, 19 Franklin Township, Bridge Replacement 382,000 20 (Base Construction Allocation - 21 $307,000) 22 (Land Allocation - $19,000) 23 (Design and Contingencies - $56,000) 24 (17) SR 0284, SR 0284 over Blacks Creek, 25 Pine Township, Bridge Replacement 700,000 26 (Base Construction Allocation - 27 $570,000) 28 (Land Allocation - $30,000) 29 (Design and Contingencies - $100,000) 30 (18) SR 0405, SR 0405 over West Branch of 19970S0186B0698 - 237 -
1 Susquehanna River, Muncy Creek 2 Township, Bridge Replacement 24,924,000 3 (Base Construction Allocation - 4 $19,939,000) 5 (Land Allocation - $1,246,000) 6 (Design and Contingencies - $3,739,000) 7 (19) SR 0654, SR 0654 over Mosquito Creek, 8 Anthony Township, Bridge Replacement 674,000 9 (Base Construction Allocation - 10 $539,000) 11 (Land Allocation - $34,000) 12 (Design and Contingencies - $101,000) 13 (20) SR 0973, SR 0973 over Mud Run, 14 Mifflin Township, Bridge Replacement 294,000 15 (Base Construction Allocation - 16 $252,000) 17 (Land Allocation - $20,000) 18 (Design and Contingencies - $22,000) 19 (21) SR 1005, SR 1005 over Plunketts 20 Creek, Plunketts Creek Township, Bridge 21 Replacement 366,000 22 (Base Construction Allocation - 23 $293,000) 24 (Land Allocation - $18,000) 25 (Design and Contingencies - $55,000) 26 (22) SR 2061, SR 2061 over Sugar Run, 27 Moreland Township, Bridge Replacement 443,000 28 (Base Construction Allocation - 29 $354,000) 30 (Land Allocation - $22,000) 19970S0186B0698 - 238 -
1 (Design and Contingencies - $67,000) 2 (23) SR 2085, SR 2085 over Muncy Creek, 3 Penn Township, Bridge Replacement 1,050,000 4 (Base Construction Allocation - 5 $840,000) 6 (Land Allocation - $53,000) 7 (Design and Contingencies - $157,000) 8 (24) SR 0405, East Water Street over Glade 9 Run, Muncy Borough, Bridge Replacement 500,000 10 (Base Construction Allocation - 11 $350,000) 12 (Land Allocation - $50,000) 13 (Design and Contingencies - $100,000) 14 (25) SR 1003, Bridge over Wallis Run, 15 Gamble Township, Bridge Replacement 1,020,000 16 (Base Construction Allocation - 17 $820,000) 18 (Land Allocation - $50,000) 19 (Design and Contingencies - $150,000) 20 (26) SR 1003, Bridge over Salt Run, Gamble 21 Township, Bridge Replacement 390,000 22 (Base Construction Allocation - 23 $300,000) 24 (Land Allocation - $30,000) 25 (Design and Contingencies - $60,000) 26 (27) US 15, Bridge over 2nd Avenue, South 27 Williamsport Borough, Bridge 28 Replacement 1,550,000 29 (Base Construction Allocation - 30 $1,250,000) 19970S0186B0698 - 239 -
1 (Land Allocation - $50,000) 2 (Design and Contingencies - $250,000) 3 (28) SR 44, Bridge over Conrail, Nippenose 4 Township, Bridge Replacement 2,425,000 5 (Base Construction Allocation - 6 $2,000,000) 7 (Land Allocation - $100,000) 8 (Design and Contingencies - $325,000) 9 (29) US 220, Southbound Bridge over SR 10 3005, Jersey Shore Borough, Deck 11 Replacement 275,000 12 (Base Construction Allocation - 13 $225,000) 14 (Design and Contingencies - $50,000) 15 (30) US 220, Northbound Bridge over 16 Railroad, Porter Township, Bridge 17 Replacement 900,000 18 (Base Construction Allocation - 19 $750,000) 20 (Design and Contingencies - $150,000) 21 (31) US 220, Southbound Bridge over 22 Railroad, Porter Township, Bridge 23 Rehabilitation 900,000 24 (Base Construction Allocation - 25 $750,000) 26 (Design and Contingencies - $150,000) 27 (32) US 220, Northbound Bridge over SR 28 3005, Jersey Shore Borough, Bridge 29 Rehabilitation 275,000 30 (Base Construction Allocation - 19970S0186B0698 - 240 -
1 $225,000) 2 (Design and Contingencies - $50,000) 3 (33) US 220, Ramp on US 220, Jersey Shore 4 Borough, Deck Replacement 1,500,000 5 (Base Construction Allocation - 6 $1,250,000) 7 (Design and Contingencies - $250,000) 8 (34) US 220, Northbound Bridge over Ramp 9 A, Woodward Township, Bridge 10 Rehabilitation 550,000 11 (Base Construction Allocation - 12 $500,000) 13 (Design and Contingencies - $50,000) 14 (35) US 220, Northbound Bridge over T-331, 15 Woodward Township, Bridge 16 Rehabilitation 275,000 17 (Base Construction Allocation - 18 $250,000) 19 (Design and Contingencies - $25,000) 20 (36) US 220, Northbound Bridge over 21 Railroad, Woodward Township, Bridge 22 Rehabilitation 825,000 23 (Base Construction Allocation - 24 $750,000) 25 (Design and Contingencies - $75,000) 26 (37) US 220, Southbound Bridge over Ramp, 27 Woodward Township, Bridge 28 Rehabilitation 550,000 29 (Base Construction Allocation - 30 $500,000) 19970S0186B0698 - 241 -
1 (Design and Contingencies - $50,000) 2 (38) US 220, Southbound Bridge over T-331, 3 Woodward Township, Bridge 4 Rehabilitation 275,000 5 (Base Construction Allocation - 6 $250,000) 7 (Design and Contingencies - $25,000) 8 (39) US 220, Southbound Bridge over 9 Railroad, Woodward Township, Bridge 10 Rehabilitation 825,000 11 (Base Construction Allocation - 12 $750,000) 13 (Design and Contingencies - $75,000) 14 (40) US 220, Reach Road over US 220, City 15 of Williamsport, Deck Replacement 1,400,000 16 (Base Construction Allocation - 17 $1,250,000) 18 (Design and Contingencies - $150,000) 19 (41) US 220, Northbound Bridge over Arch 20 Street, City of Williamsport, Bridge 21 Rehabilitation 385,000 22 (Base Construction Allocation - 23 $350,000) 24 (Design and Contingencies - $35,000) 25 (42) US 220, Southbound Bridge over Arch 26 Street, City of Williamsport, Bridge 27 Rehabilitation 385,000 28 (Base Construction Allocation - 29 $350,000) 30 (Design and Contingencies - $35,000) 19970S0186B0698 - 242 -
1 (43) US 220, Northbound Bridge over 2 Lycoming Creek, City of Williamsport, 3 Bridge Rehabilitation 1,100,000 4 (Base Construction Allocation - 5 $1,000,000) 6 (Design and Contingencies - $100,000) 7 (44) I-180, Eastbound Bridge over Maynard 8 Street, City of Williamsport, Bridge 9 Widening and Deck Replacement 950,000 10 (Base Construction Allocation - 11 $800,000) 12 (Design and Contingencies - $150,000) 13 (45) I-180, Westbound Bridge over Maynard 14 Street, City of Williamsport, Bridge 15 Widening and Deck Replacement 950,000 16 (Base Construction Allocation - 17 $800,000) 18 (Design and Contingencies - $150,000) 19 (46) I-180, Eastbound and Westbound 20 Bridges over Railroad, City of 21 Williamsport, Bridge Widening and Deck 22 Replacement 900,000 23 (Base Construction Allocation - 24 $750,000) 25 (Design and Contingencies - $150,000) 26 (47) I-180, Eastbound Bridge over Hepburn 27 Street, City of Williamsport, Bridge 28 Widening and Deck Replacement 1,200,000 29 (Base Construction Allocation - 30 $1,000,000) 19970S0186B0698 - 243 -
1 (Design and Contingencies - $200,000) 2 (48) I-180, Westbound Bridge over Hepburn 3 Street, City of Williamsport, Bridge 4 Widening and Deck Replacement 1,200,000 5 (Base Construction Allocation - 6 $1,000,000) 7 (Design and Contingencies - $200,000) 8 (49) I-180, Eastbound Bridge over Basin 9 Street, City of Williamsport, Bridge 10 Rehabilitation 550,000 11 (Base Construction Allocation - 12 $500,000) 13 (Design and Contingencies - $50,000) 14 (50) I-180, Westbound Bridge over Basin 15 Street, City of Williamsport, Bridge 16 Rehabilitation 550,000 17 (Base Construction Allocation - 18 $500,000) 19 (Design and Contingencies - $50,000) 20 (51) I-180, Eastbound and Westbound 21 Bridges over Muncy Creek, Muncy Creek 22 Township, Bridge Rehabilitation 1,100,000 23 (Base Construction Allocation - 24 $1,000,000) 25 (Design and Contingencies - $100,000) 26 (52) I-180, Eastbound and Westbound 27 Bridges over PA 405, Muncy Creek 28 Township, Bridge Rehabilitation 1,100,000 29 (Base Construction Allocation - 30 $1,000,000) 19970S0186B0698 - 244 -
1 (Design and Contingencies - $100,000) 2 (53) I-180, Eastbound Bridge over SR 4024, 3 Muncy Creek Township, Bridge 4 Rehabilitation 550,000 5 (Base Construction Allocation - 6 $500,000) 7 (Design and Contingencies - $50,000) 8 (54) I-180, Eastbound and Westbound 9 Bridges over SR 2061, Muncy Creek 10 Township, Bridge Rehabilitation 660,000 11 (Base Construction Allocation - 12 $600,000) 13 (Design and Contingencies - $60,000) 14 (55) I-180, Eastbound and Westbound 15 Bridges over SR 2014, Muncy Creek 16 Township, Bridge Rehabilitation 660,000 17 (Base Construction Allocation - 18 $600,000) 19 (Design and Contingencies - $60,000) 20 Section 46. McKean County. 21 (a) Local Bridges 22 (1) Foster Township, T-359, Garlock Hollow 23 Bridge over Kendall Creek, Bridge 24 Replacement 580,000 25 (Base Construction Allocation - 26 $400,000) 27 (Land Allocation - $20,000) 28 (Design and Contingencies - $160,000) 29 (b) State Bridges 30 (1) SR 3009, Kinzua Creek Bridge over 19970S0186B0698 - 245 -
1 Kinzua Creek, Borough of Mt. Jewett, 2 Bridge Replacement 880,000 3 (Base Construction Allocation - 4 $700,000) 5 (Land Allocation - $30,000) 6 (Design and Contingencies - $150,000) 7 (2) SR 4005, Kendall Creek Bridge over 8 Kendall Creek, City of Bradford, Bridge 9 Replacement 800,000 10 (Base Construction Allocation - 11 $650,000) 12 (Land Allocation - $50,000) 13 (Design and Contingencies - $100,000) 14 Section 47. Mercer County. 15 (a) Local Bridges 16 (1) City of Sharon, Service Avenue Bridge 17 over Pine Run, Bridge Replacement 240,000 18 (Base Construction Allocation - 19 $210,000) 20 (Land Allocation - $5,000) 21 (Design and Contingencies - $25,000) 22 (2) City of Sharon, Wengler Avenue Bridge 23 over Pine Hollow Run, Bridge 24 Replacement 218,000 25 (Base Construction Allocation - 26 $193,000) 27 (Land Allocation - $5,000) 28 (Design and Contingencies - $20,000) 29 (3) Pine Township, T-355, Pinchlong Road 30 Bridge over Swamp Run, Bridge 19970S0186B0698 - 246 -
1 Replacement 203,000 2 (Base Construction Allocation - 3 $178,000) 4 (Land Allocation - $5,000) 5 (Design and Contingencies - $20,000) 6 (4) Pine Township, T-878, Diamond Road 7 Bridge over Wolf Creek, Bridge 8 Replacement 1,813,000 9 (Base Construction Allocation - 10 $1,668,000) 11 (Land Allocation - $60,000) 12 (Design and Contingencies - $85,000) 13 (5) Pine Township, T-413, Daugherty Road 14 Bridge over Wolf Run, Bridge 15 Replacement 407,000 16 (Base Construction Allocation - 17 $352,000) 18 (Land Allocation - $15,000) 19 (Design and Contingencies - $40,000) 20 (6) Shenango Township, T-955, Oak Hill 21 Road Bridge over Turkey Run, Bridge 22 Replacement 297,000 23 (Base Construction Allocation - 24 $257,000) 25 (Land Allocation - $10,000) 26 (Design and Contingencies - $30,000) 27 (7) Shenango Township, Heasley Road Bridge 28 over Tributary of Shenango River, 29 Bridge Replacement 173,000 30 (Base Construction Allocation - 19970S0186B0698 - 247 -
1 $155,000) 2 (Land Allocation - $3,000) 3 (Design and Contingencies - $15,000) 4 (8) Springfield Township, T-722, Spring 5 Road Bridge over Mill Run, Bridge 6 Replacement 230,000 7 (Base Construction Allocation - 8 $200,000) 9 (Land Allocation - $5,000) 10 (Design and Contingencies - $25,000) 11 (9) Worth Township, T-912, Jack Atwell 12 Road Bridge over Wolf Creek, Bridge 13 Replacement 297,000 14 (Base Construction Allocation - 15 $257,000) 16 (Land Allocation - $10,000) 17 (Design and Contingencies - $30,000) 18 (b) State Bridges 19 (1) SR 0058, SR 0058 over Sugar Creek, 20 Greene Township, Bridge Replacement 270,000 21 (Base Construction Allocation - 22 $200,000) 23 (Land Allocation - $20,000) 24 (Design and Contingencies - $50,00) 25 (2) SR 0058, SR 0058 over Tributary of 26 Shenango River, Greenville Borough, 27 Bridge Replacement 250,000 28 (Base Construction Allocation - 29 $200,000) 30 (Land Allocation - $20,000) 19970S0186B0698 - 248 -
1 (Design and Contingencies - $30,000) 2 (3) SR 0058, SR 0058 over I-79, Findley 3 Township, Bridge Replacement 1,630,000 4 (Base Construction Allocation - 5 $1,500,000) 6 (Land Allocation - $30,000) 7 (Design and Contingencies - $100,000) 8 (4) SR 0062, SR 0062 over Shenango 9 River/Riverside Drive, City of Sharon, 10 Bridge Replacement 2,780,000 11 (Base Construction Allocation - 12 $2,500,000) 13 (Land Allocation - $30,000) 14 (Design and Contingencies - $250,000) 15 (5) SR 0158, SR 0158 over Little 16 Neshannock Creek, Wilmington Township, 17 Bridge Replacement 770,000 18 (Base Construction Allocation - 19 $650,000) 20 (Land Allocation - $40,000) 21 (Design and Contingencies - $80,000) 22 (6) SR 0173, SR 0173 over Mill Creek, New 23 Lebanon Borough, Bridge Replacement 430,000 24 (Base Construction Allocation - 25 $350,000) 26 (Land Allocation - $20,000) 27 (Design and Contingencies - $60,000) 28 (7) SR 0208, SR 0208 over Wolf Creek, 29 Grove City Borough, Bridge Replacement 1,000,000 30 (Base Construction Allocation - 19970S0186B0698 - 249 -
1 $870,000) 2 (Land Allocation - $30,000) 3 (Design and Contingencies - $100,000) 4 (8) SR 0258, SR 0258 over Daley Run, 5 Jefferson Township, Bridge Replacement 430,000 6 (Base Construction Allocation - 7 $350,000) 8 (Land Allocation - $20,000) 9 (Design and Contingencies - $60,000) 10 (9) SR 0318, SR 0318 over Shenango 11 River/Street/Railroad, West Middlesex 12 Borough, Bridge Replacement 4,400,000 13 (Base Construction Allocation - 14 $3,700,000) 15 (Land Allocation - $100,000) 16 (Design and Contingencies - $600,000) 17 (10) SR 0518, SR 0518 over Pine Hollow 18 Run, City of Hermitage, Bridge 19 Replacement 410,000 20 (Base Construction Allocation - 21 $300,000) 22 (Land Allocation - $30,000) 23 (Design and Contingencies - $80,000) 24 (11) SR 0846, SR 0846 over Shenango 25 Reservoir, South Pymatuning Township, 26 Bridge Replacement 1,500,000 27 (Base Construction Allocation - 28 $1,340,000) 29 (Land Allocation - $10,000) 30 (Design and Contingencies - $150,000) 19970S0186B0698 - 250 -
1 (12) SR 2006, SR 2006 over I-79, 2 Springfield Township, Bridge 3 Replacement 1,100,000 4 (Base Construction Allocation - 5 $1,000,000) 6 (Land Allocation - $10,000) 7 (Design and Contingencies - $90,000) 8 (13) SR 2014, SR 2014 over Mill Creek, 9 Findley Township, Bridge Replacement 330,000 10 (Base Construction Allocation - 11 $240,000) 12 (Land Allocation - $20,000) 13 (Design and Contingencies - $70,000) 14 (14) SR 2025, SR 2025 over Lake Barmore 15 Outlet, Pine Township, Bridge 16 Replacement 300,000 17 (Base Construction Allocation - 18 $230,000) 19 (Land Allocation - $10,000) 20 (Design and Contingencies - $60,000) 21 (15) SR 3011, SR 3011 over I-80, Shenango 22 Township, Bridge Replacement 810,000 23 (Base Construction Allocation - 24 $700,000) 25 (Land Allocation - $10,000) 26 (Design and Contingencies - $100,000) 27 (16) SR 4014, SR 4014 over Shenango River, 28 Delaware Township, Bridge Replacement 920,000 29 (Base Construction Allocation - 30 $800,000) 19970S0186B0698 - 251 -
1 (Land Allocation - $20,000) 2 (Design and Contingencies - $100,000) 3 (17) SR 0518, PA 516 (Walnut Street) 4 Bridge over Pine Hollow Road, City of 5 Hermitage, Bridge Replacement 550,000 6 (Base Construction Allocation - 7 $500,000) 8 (Design and Contingencies - $50,000) 9 Section 48. Mifflin County. 10 (a) Local Bridges 11 (1) Oliver Township, T-803, Bridge over 12 Musser Run, Bridge Replacement 492,000 13 (Base Construction Allocation - 14 $390,000) 15 (Land Allocation - $2,000) 16 (Design and Contingencies - $100,000) 17 (2) Decatur Township, T-379, Bridge over 18 Meadow Creek, Bridge Replacement 370,000 19 (Base Construction Allocation - 20 $300,000) 21 (Land Allocation - $10,000) 22 (Design and Contingencies - $60,000) 23 (b) State Bridges 24 (1) SR 0022, Bridge over Kish Creek, 25 Lewistown Borough, Bridge Painting 800,000 26 (Base Construction Allocation - 27 $720,000) 28 (Design and Contingencies - $80,000) 29 (2) SR 3017, Bridge over Juniata River, 30 Wayne Township, Bridge Painting 935,000 19970S0186B0698 - 252 -
1 (Base Construction Allocation - 2 $850,000) 3 (Design and Contingencies - $85,000) 4 Section 49. Monroe County. 5 (a) Local Bridges 6 (1) Smithfield Township, T-522, Bridge <-- 7 over Marshalls Creek, Bridge 8 Replacement 134,000 9 (Base Construction Allocation - 10 $116,000) 11 (Land Allocation - $6,000) 12 (Design and Contingencies - $12,000) 13 (1) HAMILTON TOWNSHIP, T-202, BRIDGE OVER <-- 14 LAKE CREEK, BRIDGE REPLACEMENT 320,000 15 (BASE CONSTRUCTION ALLOCATION - 16 $270,000) 17 (LAND ALLOCATION - $10,000) 18 (DESIGN AND CONTINGENCIES - $40,000) 19 (2) STROUD TOWNSHIP, T-420, BRIDGE OVER 20 CHERRY CREEK, BRIDGE REPLACEMENT 360,000 21 (BASE CONSTRUCTION ALLOCATION - 22 $230,000) 23 (LAND ALLOCATION - $10,000) 24 (DESIGN AND CONTINGENCIES - $120,000) 25 (3) SMITHFIELD TOWNSHIP, T-539, BRIDGE 26 OVER MARSHALLS CREEK, BRIDGE 27 REHABILITATION 348,000 28 (BASE CONSTRUCTION ALLOCATION - 29 $288,000) 30 (LAND ALLOCATION - $10,000) 19970S0186B0698 - 253 -
1 (DESIGN AND CONTINGENCIES - $50,000) 2 (4) SMITHFIELD TOWNSHIP, T-522, BRIDGE 3 OVER MARSHALLS CREEK, BRIDGE 4 REPLACEMENT 134,000 5 (BASE CONSTRUCTION ALLOCATION - 6 $116,000) 7 (LAND ALLOCATION - $6,000) 8 (DESIGN AND CONTINGENCIES - $12,000) 9 (5) BARRETT TOWNSHIP, T-612, BRIDGE OVER 10 BRODHEAD CREEK, BRIDGE REPLACEMENT 174,000 11 (BASE CONSTRUCTION ALLOCATION - 12 $152,000) 13 (LAND ALLOCATION - $7,000) 14 (DESIGN AND CONTINGENCIES - $15,000) 15 (6) HAMILTON TOWNSHIP, T-414, COUNTY 16 BRIDGE NO. 7 OVER MCMICHAEL CREEK, 17 BRIDGE REPLACEMENT 1,070,000 18 (BASE CONSTRUCTION ALLOCATION - 19 $840,000) 20 (LAND ALLOCATION - $30,000) 21 (DESIGN AND CONTINGENCIES - $200,000) 22 (7) TUNKHANNOCK TOWNSHIP, T-633, BRIDGE 23 OVER TUNKHANNOCK CREEK, BRIDGE 24 REPLACEMENT 139,000 25 (BASE CONSTRUCTION ALLOCATION - 26 $121,000) 27 (LAND ALLOCATION - $6,000) 28 (DESIGN AND CONTINGENCIES - $12,000) 29 (8) HAMILTON TOWNSHIP, T-233, COUNTY 30 BRIDGE NO. 9 OVER MCMICHAEL CREEK, 19970S0186B0698 - 254 -
1 BRIDGE REPLACEMENT 665,000 2 (BASE CONSTRUCTION ALLOCATION - 3 $515,000) 4 (LAND ALLOCATION - $10,000) 5 (DESIGN AND CONTINGENCIES - $140,000) 6 (9) JACKSON TOWNSHIP, T-486, BRIDGE OVER 7 TROUT LAKE SPILLWAY, BRIDGE 8 REPLACEMENT 184,000 9 (BASE CONSTRUCTION ALLOCATION - 10 $160,000) 11 (LAND ALLOCATION - $8,000) 12 (DESIGN AND CONTINGENCIES - $16,000) 13 (10) HAMILTON TOWNSHIP, T-231, COUNTY 14 BRIDGE NO. 8 OVER APPENZELL CREEK, 15 BRIDGE REPLACEMENT 565,000 16 (BASE CONSTRUCTION ALLOCATION - 17 $415,000) 18 (LAND ALLOCATION - $10,000) 19 (DESIGN AND CONTINGENCIES - $140,000) 20 (11) COOLBAUGH TOWNSHIP, T-591, STEAMTOWN 21 RAILROAD BRIDGE, BRIDGE REPLACEMENT 1,031,000 22 (BASE CONSTRUCTION ALLOCATION - 23 $937,000) 24 (DESIGN AND CONTINGENCIES - $94,000) 25 (12) JACKSON TOWNSHIP, T-434, COUNTY 26 BRIDGE NO. 13 OVER APPENZELL CREEK, 27 BRIDGE REPLACEMENT 667,000 28 (BASE CONSTRUCTION ALLOCATION - 29 $525,000) 30 (LAND ALLOCATION - $12,000) 19970S0186B0698 - 255 -
1 (DESIGN AND CONTINGENCIES - $130,000) 2 (13) HAMILTON TOWNSHIP, T-237, COUNTY 3 BRIDGE NO. 12 OVER LAKE CREEK, BRIDGE 4 REPLACEMENT 430,000 5 (BASE CONSTRUCTION ALLOCATION - 6 $300,000) 7 (LAND ALLOCATION - $10,000) 8 (DESIGN AND CONTINGENCIES - $120,000) 9 (b) State Bridges 10 (1) SR 0447, SR 0447 over Broadhead Creek 11 and Railroad, Stroud Township, Bridge 12 Rehabilitation 1,395,000 13 (Base Construction Allocation - 14 $1,071,000) 15 (Design and Contingencies - $324,000) 16 (2) SR 3003, Silver Spring Boulevard over 17 Chapple Creek, Eldred Township, Bridge 18 Replacement 280,000 19 (Base Construction Allocation - 20 $130,000) 21 (Land Allocation - $50,000) 22 (Design and Contingencies - $100,000) 23 (3) SR 2012, SR 2012 over Broadhead Creek, 24 East Stroudsburg Borough, Bridge 25 Rehabilitation 1,500,000 26 (Base Construction Allocation - 27 $1,150,000) 28 (Design and Contingencies - $350,000) 29 (4) SR 0080, I-80 Westbound over 30 Tunkhannock Creek at County Line, 19970S0186B0698 - 256 -
1 Tobyhanna Township, Bridge 2 Rehabilitation 935,000 3 (Base Construction Allocation - 4 $720,000) 5 (Design and Contingencies - $215,000) 6 (5) SR 0080, I-80 Eastbound over 7 Tunkhannock Creek at County Line, 8 Tunkhannock Township, Bridge 9 Rehabilitation 935,000 10 (Base Construction Allocation - 11 $720,000) 12 (Design and Contingencies - $215,000) 13 (6) SR 4003, SR 4003 over Lehigh River at 14 Lackawanna County Line, Coolbaugh 15 Township, Bridge Rehabilitation 390,000 16 (Base Construction Allocation - 17 $295,000) 18 (Design and Contingencies - $95,000) 19 (7) Norristown Borough, Markley Street <-- 20 Bridge over Stoney Creek, Bridge 21 Replacement 1,250,000 22 (Base Construction Allocation - 23 $1,000,000) 24 (Land Allocation - $50,000) 25 (Design and Contingencies - $200,000) 26 (8) Norristown Borough, Markley Street 27 Bridge over Stoney Creek, Bridge 28 Rehabilitation 500,000 29 (Base Construction Allocation - 30 $400,000) 19970S0186B0698 - 257 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $90,000) 3 (9) Horsham Township, Davis Grove Road 4 over Park Creek, Bridge Replacement 300,000 5 (Base Construction Allocation - 6 $230,000) 7 (Land Allocation - $20,000) 8 (Design and Contingencies - $50,000) 9 (10) Franconia Township, Keller Creamery 10 Road over Indian Creek, Bridge 11 Replacement 320,000 12 (Base Construction Allocation - 13 $250,000) 14 (Land Allocation - $20,000) 15 (Design and Contingencies - $50,000) 16 (11) East Norriton Township, Germantown 17 Pike over Five Mile Run Creek, Bridge 18 Replacement 500,000 19 (Base Construction Allocation - 20 $430,000) 21 (Land Allocation - $20,000) 22 (Design and Contingencies - $50,000) 23 (12) Upper Hanover Township, Eleventh 24 Street over Macoby Creek, Bridge 25 Replacement 400,000 26 (Base Construction Allocation - 27 $340,000) 28 (Land Allocation - $20,000) 29 (Design and Contingencies - $40,000) 30 (13) Lower Merion Township, Black Rock 19970S0186B0698 - 258 -
1 Road over Mill Creek, Bridge 2 Replacement 350,000 3 (Base Construction Allocation - 4 $295,000) 5 (Land Allocation - $20,000) 6 (Design and Contingencies - $35,000) 7 (14) Lower Merion Township, Morris Road 8 over Mill Creek, Bridge Replacement 350,000 9 (Base Construction Allocation - 10 $285,000) 11 (Land Allocation - $20,000) 12 (Design and Contingencies - $45,000) 13 (15) Upper Merion Township, Conrail over 14 South Gulph Road, Bridge Replacement 4,500,000 15 (Base Construction Allocation - 16 $4,250,000) 17 (Land Allocation - $50,000) 18 (Design and Contingencies - $200,000) 19 (16) Trappe Borough, College Avenue over 20 Buckwalter Tributary, Bridge 21 Replacement 140,000 22 (Base Construction Allocation - 23 $120,000) 24 (Design and Contingencies - $20,000) 25 (7) SR 0033, NORTHBOUND BRIDGE OVER US 209 <-- 26 WESTBOUND, HAMILTON TOWNSHIP, BRIDGE 27 REHABILITATION 180,000 28 (BASE CONSTRUCTION ALLOCATION - 29 $180,000) 30 (8) SR 0191, STITES BRIDGE, STROUDSBURG 19970S0186B0698 - 259 -
1 TOWNSHIP, BRIDGE REHABILITATION 600,000 2 (BASE CONSTRUCTION ALLOCATION - 3 $500,000) 4 (DESIGN AND CONTINGENCIES - $100,000) 5 (9) SR 0209, BRIDGE OVER I-80, SMITHFIELD 6 TOWNSHIP, BRIDGE REHABILITATION 434,000 7 (BASE CONSTRUCTION ALLOCATION - 8 $334,000) 9 (DESIGN AND CONTINGENCIES - $100,000) 10 (10) SR 0402, RESSICA FALLS BRIDGE OVER 11 BIG BUSHKILL CREEK, MIDDLE SMITHFIELD 12 TOWNSHIP, BRIDGE REPLACEMENT 1,520,000 13 (BASE CONSTRUCTION ALLOCATION - 14 $1,060,000) 15 (LAND ALLOCATION - $60,000) 16 (DESIGN AND CONTINGENCIES - $400,000) 17 (11) SR 0423, WARNERTOWN BRIDGE OVER 18 TOBYHANNA CREEK, COOLBAUGH TOWNSHIP, 19 BRIDGE REHABILITATION 977,000 20 (BASE CONSTRUCTION ALLOCATION - 21 $600,000) 22 (LAND ALLOCATION - $27,000) 23 (DESIGN AND CONTINGENCIES - $350,000) 24 (12) SR 0940, POCONO SUMMIT BRIDGE OVER 25 CONRAIL, TOBYHANNA TOWNSHIP, BRIDGE 26 REHABILITATION 1,250,000 27 (BASE CONSTRUCTION ALLOCATION - 28 $1,000,000) 29 (LAND ALLOCATION - $50,000) 30 (DESIGN AND CONTINGENCIES - $200,000) 19970S0186B0698 - 260 -
1 (13) SR 1010, BRIDGE OVER STONY CREEK, 2 PRICE TOWNSHIP, BRIDGE REPLACEMENT 310,000 3 (BASE CONSTRUCTION ALLOCATION - 4 $200,000) 5 (LAND ALLOCATION - $10,000) 6 (DESIGN AND CONTINGENCIES - $100,000) 7 (14) SR 2003, BRIDGE OVER CHERRY CREEK, 8 HAMILTON TOWNSHIP, BRIDGE REPLACEMENT 205,000 9 (BASE CONSTRUCTION ALLOCATION - 10 $139,000) 11 (LAND ALLOCATION - $13,000) 12 (DESIGN AND CONTINGENCIES - $53,000) 13 (15) SR 2004, SAYLORSBURG BRIDGE OVER SR 14 0033, HAMILTON TOWNSHIP, BRIDGE 15 REHABILITATION 335,000 16 (BASE CONSTRUCTION ALLOCATION - 17 $304,000) 18 (DESIGN AND CONTINGENCIES - $31,000) 19 (16) SR 2017, BRIDGE OVER I-80 AT EXIT 51, 20 EAST STROUDSBURG BOROUGH, BRIDGE 21 REHABILITATION 689,000 22 (BASE CONSTRUCTION ALLOCATION - 23 $625,000) 24 (DESIGN AND CONTINGENCIES - $64,000) 25 (17) SR 2030, WATER GAP BRIDGE OVER US 26 209, SMITHFIELD TOWNSHIP, BRIDGE 27 REHABILITATION 1,390,000 28 (BASE CONSTRUCTION ALLOCATION - 29 $1,158,000) 30 (DESIGN AND CONTINGENCIES - $232,000) 19970S0186B0698 - 261 -
1 (18) SR 3011, BRIDGE OVER SUGAR HOLLOW 2 CREEK, CHESTNUTHILL TOWNSHIP, BRIDGE 3 REPLACEMENT 129,000 4 (BASE CONSTRUCTION ALLOCATION - 5 $117,000) 6 (DESIGN AND CONTINGENCIES - $12,000) 7 (19) SR 3016, BRIDGE OVER POHOPOCO CREEK, 8 CHESTNUTHILL TOWNSHIP, BRIDGE 9 REPLACEMENT 139,000 10 (BASE CONSTRUCTION ALLOCATION - 11 $121,000) 12 (LAND ALLOCATION - $6,000) 13 (DESIGN AND CONTINGENCIES - $12,000) 14 (20) SR 3018, BRIDGE NO.1 OVER KETTLE 15 CREEK, HAMILTON TOWNSHIP, BRIDGE 16 REPLACEMENT 80,000 17 (BASE CONSTRUCTION ALLOCATION - 18 $70,000) 19 (LAND ALLOCATION - $3,000) 20 (DESIGN AND CONTINGENCIES - $7,000) 21 (21) SR 3018, BRIDGE NO.2 OVER KETTLE 22 CREEK, HAMILTON TOWNSHIP, BRIDGE 23 REPLACEMENT 68,000 24 (BASE CONSTRUCTION ALLOCATION - 25 $59,000) 26 (LAND ALLOCATION - $3,000) 27 (DESIGN AND CONTINGENCIES - $6,000) 28 (22) SR 3022, BRIDGE OVER MCMICHAEL CREEK, 29 HAMILTON TOWNSHIP, BRIDGE REPLACEMENT 161,000 30 (BASE CONSTRUCTION ALLOCATION - 19970S0186B0698 - 262 -
1 $140,000) 2 (LAND ALLOCATION - $7,000) 3 (DESIGN AND CONTINGENCIES - $14,000) 4 (23) SR 4001, LONG POND BRIDGE OVER 5 TUNKHANNOCK CREEK, TUNKHANNOCK 6 TOWNSHIP, BRIDGE REPLACEMENT 1,454,000 7 (BASE CONSTRUCTION ALLOCATION - 8 $900,000) 9 (LAND ALLOCATION - $50,000) 10 (DESIGN AND CONTINGENCIES - $500,000) 11 (24) SR 4007, POCONO MANOR BRIDGE OVER E L 12 RAILROAD, BOROUGH OF MT. POCONO, BRIDGE 13 REPLACEMENT 1,185,000 14 (BASE CONSTRUCTION ALLOCATION - 15 $935,000) 16 (LAND ALLOCATION - $50,000) 17 (DESIGN AND CONTINGENCIES - $200,000) 18 Section 50. Montgomery County. 19 (a) Local Bridges 20 (1) Norristown Borough, Hospital Bridge 21 over Stony Creek, Bridge Replacement 412,000 22 (Base Construction Allocation - 23 $365,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $37,000) 26 (2) Trappe Borough, College Avenue Bridge 27 over Tributary of Perkiomen Creek, 28 Bridge Replacement 360,000 29 (Base Construction Allocation - 30 $300,000) 19970S0186B0698 - 263 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $50,000) 3 (3) Towamencin Township, Bustard Road 4 Bridge over Towamencin Creek, Bridge 5 Replacement 454,000 6 (Base Construction Allocation - 7 $400,000) 8 (Land Allocation - $10,000) 9 (Design and Contingencies - $44,000) 10 (4) Upper Hanover Township, T-444, 11 Treichler Road Bridge under Reading 12 Railroad, Bridge Removal 151,000 13 (Base Construction Allocation - 14 $126,000) 15 (Land Allocation - $5,000) 16 (Design and Contingencies - $20,000) 17 (5) Upper Providence Township, T-400, 18 Supio Road Bridge under Reading 19 Railroad, Bridge Removal 187,000 20 (Base Construction Allocation - 21 $157,000) 22 (Land Allocation - $5,000) 23 (Design and Contingencies - $25,000) 24 (6) Upper Salford Township, T-444, Bridge 25 over Abandoned Railroad, Bridge 26 Removal 1,175,000 27 (Base Construction Allocation - 28 $1,000,000) 29 (Land Allocation - $25,000) 30 (Design and Contingencies - $150,000) 19970S0186B0698 - 264 -
1 (7) Norristown Borough, Markley Street 2 Bridge over Stoney Creek, Bridge 3 Replacement 1,250,000 4 (Base Construction Allocation - 5 $1,000,000) 6 (Land Allocation - $50,000) 7 (Design and Contingencies - $200,000) 8 (8) Norristown Borough, Markley Street 9 Bridge over Stoney Creek, Bridge 10 Rehabilitation 500,000 11 (Base Construction Allocation - 12 $400,000) 13 (Land Allocation - $10,000) 14 (Design and Contingencies - $90,000) 15 (9) Horsham Township, Davis Grove Road 16 over Park Creek, Bridge Replacement 300,000 17 (Base Construction Allocation - 18 $230,000) 19 (Land Allocation - $20,000) 20 (Design and Contingencies - $50,000) 21 (10) Franconia Township, Keller Creamery 22 Road over Indian Creek, Bridge 23 Replacement 320,000 24 (Base Construction Allocation - 25 $250,000) 26 (Land Allocation - $20,000) 27 (Design and Contingencies - $50,000) 28 (11) East Norriton Township, Germantown 29 Pike over Five Mile Run Creek, Bridge 30 Replacement 500,000 19970S0186B0698 - 265 -
1 (Base Construction Allocation - 2 $430,000) 3 (Land Allocation - $20,000) 4 (Design and Contingencies - $50,000) 5 (12) Upper Hanover Township, Eleventh 6 Street over Macoby Creek, Bridge 7 Replacement 400,000 8 (Base Construction Allocation - 9 $340,000) 10 (Land Allocation - $20,000) 11 (Design and Contingencies - $40,000) 12 (13) Lower Merion Township, Black Rock 13 Road over Mill Creek, Bridge 14 Replacement 350,000 15 (Base Construction Allocation - 16 $295,000) 17 (Land Allocation - $20,000) 18 (Design and Contingencies - $35,000) 19 (14) Lower Merion Township, Morris Road 20 over Mill Creek, Bridge Replacement 350,000 21 (Base Construction Allocation - 22 $285,000) 23 (Land Allocation - $20,000) 24 (Design and Contingencies - $45,000) 25 (15) Upper Merion Township, Conrail over 26 South Gulph Road, Bridge Replacement 4,500,000 27 (Base Construction Allocation - 28 $4,250,000) 29 (Land Allocation - $50,000) 30 (Design and Contingencies - $200,000) 19970S0186B0698 - 266 -
1 (16) Trappe Borough, College Avenue over 2 Buckwalter Tributary, Bridge 3 Replacement 140,000 4 (Base Construction Allocation - 5 $120,000) 6 (Design and Contingencies - $20,000) 7 (b) State Bridges 8 (1) SR 2009, Byberry Road Bridge over 9 Southampton Creek, Upper Moreland 10 Township and Bryn Athyn Borough, 11 Historic Bridge Replacement 680,000 12 (Base Construction Allocation - 13 $500,000) 14 (Land Allocation - $20,000) 15 (Design and Contingencies - $160,000) 16 (2) SR 2018, Bethlehem Pike Bridge over 17 Branch of Wissahickon Creek, 18 Springfield Township, Bridge 19 Rehabilitation 525,000 20 (Base Construction Allocation - 21 $400,000) 22 (Land Allocation - $25,000) 23 (Design and Contingencies - $100,000) 24 (3) SR 4030, New Hanover Square Road 25 Bridge over West Swamp Creek (Two 26 Bridges), New Hanover Township, Bridge 27 Replacement 1,150,000 28 (Base Construction Allocation - 29 $900,000) 30 (Land Allocation - $50,000) 19970S0186B0698 - 267 -
1 (Design and Contingencies - $200,000) 2 (4) SR 0100, Extended, (Three Bridges), 3 High Street to Farmington Road, 4 Pottstown Borough and Upper Pottsgrove 5 Township, Bridge Rehabilitation 1,650,000 6 (Base Construction Allocation - 7 $1,500,000) 8 (Land Allocation - $50,000) 9 (Design and Contingencies - $100,000) 10 (5) SR 1017, Salfordville Road Bridge over 11 East Branch of Perkiomen Creek, Lower 12 Salford Township, Bridge Replacement 1,500,000 13 (Base Construction Allocation - 14 $1,250,000) 15 (Land Allocation - $50,000) 16 (Design and Contingencies - $200,000) 17 (6) SR 1024, Salford Station (Two Bridges) 18 over Perkiomen Creek, Upper Salford and 19 Lower Fredrick Townships, Bridge 20 Replacement 1,200,000 21 (Base Construction Allocation - 22 $1,000,000) 23 (Land Allocation - $50,000) 24 (Design and Contingencies - $150,000) 25 (7) SR 3020, Dannehower Bridge over River 26 and New US 202, Upper Merion Township, 27 Bridgeport and Norristown Boroughs, 28 Bridge Painting 872,000 29 (Base Construction Allocation - 30 $802,000) 19970S0186B0698 - 268 -
1 (Design and Contingencies - $70,000) 2 (8) SR 3039, South Gulph Road Overpass 3 under Conrail, Upper Merion Township, 4 Bridge Replacement 1,500,000 5 (Base Construction Allocation - 6 $1,300,000) 7 (Land Allocation - $50,000) 8 (Design and Contingencies - $150,000) 9 (9) SR 4003, Black Rock Road Bridge over 10 Abandoned Reading Track, Upper 11 Providence Township, Bridge Removal 205,000 12 (Base Construction Allocation - 13 $175,000) 14 (Land Allocation - $10,000) 15 (Design and Contingencies - $20,000) 16 (10) SR 4012, Graterford Road Bridge over 17 Perkiomen Creek, Skippack and Perkiomen 18 Townships, Bridge Replacement 1,475,000 19 (Base Construction Allocation - 20 $1,300,000) 21 (Land Allocation - $50,000) 22 (Design and Contingencies - $125,000) 23 (11) SR 4031, Ridge Pike Bridge over 24 Manatawny Creek, Pottstown Borough, 25 Bridge Replacement 2,053,000 26 (Base Construction Allocation - 27 $1,935,000) 28 (Land Allocation - $45,000) 29 (Design and Contingencies - $73,000) 30 Section 51. Montour County. 19970S0186B0698 - 269 -
1 (a) Local Bridges 2 (1) Derry Township, T-407, County Bridge 3 No.13 over West Branch of Chillisquaque 4 Creek near Washingtonville Borough, 5 Bridge Replacement 350,000 6 (Base Construction Allocation - 7 $265,000) 8 (Land Allocation - $35,000) 9 (Design and Contingencies - $50,000) 10 (b) State Bridges 11 (1) SR 1004, Bridge over Chillisquaque 12 Creek, North of Washingtonville 13 Borough, Bridge Replacement 620,000 14 (Base Construction Allocation - 15 $500,000) 16 (Land Allocation - $40,000) 17 (Design and Contingencies - $80,000) 18 (2) SR 1006, Bridge over Branch of 19 Chillisquaque Creek, 3 Miles Northwest 20 of Washingtonville Borough, Bridge 21 Replacement 510,000 22 (Base Construction Allocation - 23 $410,000) 24 (Land Allocation - $25,000) 25 (Design and Contingencies - $80,000) 26 (3) SR 3004, Bridge over Beaver Run, 2 27 Miles West of Moresburg, Bridge 28 Replacement 285,000 29 (Base Construction Allocation - 30 $227,000) 19970S0186B0698 - 270 -
1 (Land Allocation - $14,000) 2 (Design and Contingencies - $44,000) 3 (4) SR 4001, Bridge over Chillisquaque 4 Creek, Anthony Township, Bridge 5 Replacement 458,000 6 (Base Construction Allocation - 7 $366,000) 8 (Land Allocation - $23,000) 9 (Design and Contingencies - $69,000) 10 (5) SR 0011, SR 0011 over Sechler Run, 11 Mahoning Township, Bridge Replacement 582,000 12 (Base Construction Allocation - 13 $466,000) 14 (Land Allocation - $29,000) 15 (Design and Contingencies - $87,000) 16 (6) SR 0054, SR 0054 over Chillisquaque 17 Creek, Anthony Township, Bridge 18 Replacement 547,000 19 (Base Construction Allocation - 20 $438,000) 21 (Land Allocation - $27,000) 22 (Design and Contingencies - $82,000) 23 (7) SR 0642, SR 0642 over Mahoning Creek, 24 West Hemlock Township, Bridge 25 Replacement 213,000 26 (Base Construction Allocation - 27 $170,000) 28 (Land Allocation - $11,000) 29 (Design and Contingencies - $32,000) 30 (8) SR 1009, SR 1009 over Branch of Lowry 19970S0186B0698 - 271 -
1 Run, Anthony Township, Bridge 2 Replacement 431,000 3 (Base Construction Allocation - 4 $345,000) 5 (Land Allocation - $21,000) 6 (Design and Contingencies - $65,000) 7 (9) SR 1011, SR 1011 over Tributary of 8 Chillisquaque Creek, Anthony Township, 9 Bridge Replacement 212,000 10 (Base Construction Allocation - 11 $170,000) 12 (Land Allocation - $11,000) 13 (Design and Contingencies - $31,000) 14 Section 52. Northampton County. 15 (a) Local Bridges 16 (1) Lehigh Township, Indiantrail Road 17 Bridge over Indian Creek, Bridge 18 Painting 16,000 19 (Base Construction Allocation - 20 $14,000) 21 (Design and Contingencies - $2,000) 22 (2) Lehigh Township, T-548, Bridge over 23 Bertsch Creek, Bridge Replacement 400,000 24 (Base Construction Allocation - 25 $300,000) 26 (Land Allocation - $20,000) 27 (Design and Contingencies - $80,000) 28 (3) Lehigh Township, Wood Drive Bridge, 29 Bridge Replacement 65,000 30 (Base Construction Allocation - 19970S0186B0698 - 272 -
1 $41,000) 2 (Land Allocation - $4,000) 3 (Design and Contingencies - $20,000) 4 (4) Freemansburg Borough, LVRR Bridge over 5 Main Street, Bridge Removal 898,000 6 (Base Construction Allocation - 7 $694,000) 8 (Land Allocation - $100,000) 9 (Design and Contingencies - $104,000) 10 (5) CITY OF BETHLEHEM, COUNTY BRIDGE <-- 11 NO.88, BRIDGE OVER MONOCACY CREEK, 12 BRIDGE REHABILITATION 275,000 13 (BASE CONSTRUCTION ALLOCATION - 14 $250,000) 15 (DESIGN AND CONTINGENCIES - $25,000) 16 (b) State Bridges 17 (1) SR 2017, Tatamy Road over Tributary of 18 Bushkill Creek, Palmer Township, Bridge 19 Rehabilitation 240,000 20 (Base Construction Allocation - 21 $100,000) 22 (Land Allocation - $40,000) 23 (Design and Contingencies - $100,000) 24 (2) SR 4020, Maple Drive over Tributary of 25 Bertsch Creek, Lehigh Township, Bridge 26 Rehabilitation 465,000 27 (Base Construction Allocation - 28 $275,000) 29 (Land Allocation - $80,000) 30 (Design and Contingencies - $110,000) 19970S0186B0698 - 273 -
1 Section 53. Northumberland County. 2 (a) Local Bridges 3 (1) Borough of Milton, Ridge Avenue over 4 Limestone Run, Bridge Replacement 520,000 5 (Base Construction Allocation - 6 $380,000) 7 (Land Allocation - $20,000) 8 (Design and Contingencies - $120,000) 9 (2) Lewis Township, T-631, Old State Road 10 Bridge over Branch of Beaver Run, 11 Bridge Replacement 220,000 12 (Base Construction Allocation - 13 $200,000) 14 (Design and Contingencies - $20,000) 15 (b) State Bridges 16 (1) SR 0642, Chillisquaque Creek Bridge 17 over Chillisquaque Creek, 0.5 Mile East 18 of Pottsgrove, Bridge Deck Replacement 1,184,000 19 (Base Construction Allocation - 20 $947,000) 21 (Land Allocation - $59,000) 22 (Design and Contingencies - $178,000) 23 (2) SR 1005, Delaware Run Bridge over 24 Delaware Run, 3 Miles North of 25 Watsontown Borough, Bridge Replacement 509,000 26 (Base Construction Allocation - 27 $408,000) 28 (Land Allocation - $25,000) 29 (Design and Contingencies - $76,000) 30 (3) SR 0045, Bridge over Chillisquaque 19970S0186B0698 - 274 -
1 Creek, East of SR 0147, Bridge 2 Painting 260,000 3 (Base Construction Allocation - 4 $250,000) 5 (Design and Contingencies - $10,000) 6 (4) SR 0054, SR 0054 over North Branch of 7 Shamokin Creek, Mt. Carmel Township, 8 Bridge Replacement 721,000 9 (Base Construction Allocation - 10 $577,000) 11 (Land Allocation - $36,000) 12 (Design and Contingencies - $108,000) 13 (5) SR 2001, SR 2001 over Little Roaring 14 Creek, Rush Township, Bridge 15 Replacement 415,000 16 (Base Construction Allocation - 17 $335,000) 18 (Land Allocation - $20,000) 19 (Design and Contingencies - $60,000) 20 (6) SR 2023, SR 2023 over Conrail, Mt. 21 Carmel Township, Bridge Replacement 1,275,000 22 (Base Construction Allocation - 23 $1,020,000) 24 (Land Allocation - $64,000) 25 (Design and Contingencies - $191,000) 26 (7) SR 4013, SR 4013 over Plum Creek, 27 Rockefeller Township, Bridge 28 Replacement 361,000 29 (Base Construction Allocation - 30 $289,000) 19970S0186B0698 - 275 -
1 (Land Allocation - $18,000) 2 (Design and Contingencies - $54,000) 3 Section 54. Perry County. 4 (a) Local Bridges 5 (1) Tyrone Township, County Bridge No.4, 6 Rices Bridge over Shermans Creek, 7 Covered Bridge Replacement 768,000 8 (Base Construction Allocation - 9 $552,000) 10 (Land Allocation - $77,000) 11 (Design and Contingencies - $139,000) 12 (2) Northeast Madison Township, T-403 over 13 Bixler Run, Bridge Replacement 585,000 14 (Base Construction Allocation - 15 $400,000) 16 (Land Allocation - $10,000) 17 (Design and Contingencies - $175,000) 18 (3) Tyrone Township, Rices Bridge (County 19 Bridge No.4) over Shermans Creek, 20 Bridge Replacement 768,000 21 (Base Construction Allocation - 22 $552,000) 23 (Land Allocation - $77,000) 24 (Design and Contingencies - $139,000) 25 (b) State Bridges 26 (1) SR 4006, Raccoon Creek Bridge over 27 Raccoon Creek, Tuscarora Township, 28 Bridge Replacement 466,000 29 (Base Construction Allocation - 30 $288,000) 19970S0186B0698 - 276 -
1 (Land Allocation - $20,000) 2 (Design and Contingencies - $158,000) 3 (2) SR 3002, Horse Valley Road Bridges 4 (Two Bridges) over Horse Valley Run, 5 Toboyne Township, Bridge Replacement 725,000 6 (Base Construction Allocation - 7 $700,000) 8 (Land Allocation - $5,000) 9 (Design and Contingencies - $20,000) 10 Section 55. Philadelphia County. 11 (a) Local Bridges 12 (1) City of Philadelphia, Byberry Road 13 Bridge over Conrail, Temporary Bridge 14 Construction 511,000 15 (Base Construction Allocation - 16 $390,000) 17 (Land Allocation - $51,000) 18 (Design and Contingencies - $70,000) 19 (2) City of Philadelphia, Wyoming Avenue 20 Bridge over Former Course Frankford 21 Creek, West of Castor Avenue, Bridge 22 Replacement 1,300,000 23 (Base Construction Allocation - 24 $1,200,000) 25 (Design and Contingencies - $100,000) 26 (3) City of Philadelphia, Chelten Avenue 27 Bridge over SEPTA, West of Wayne 28 Avenue, Bridge Replacement 2,300,000 29 (Base Construction Allocation - 30 $2,100,000) 19970S0186B0698 - 277 -
1 (Design and Contingencies - $200,000) 2 (4) City of Philadelphia, Fisher's Lane 3 Bridge over Tacony Creek, West of 4 Ramona Avenue, Bridge Replacement 1,625,000 5 (Base Construction Allocation - 6 $1,400,000) 7 (Design and Contingencies - $225,000) 8 (5) City of Philadelphia, Kingsessing 9 Avenue Bridge over SEPTA, Bridge 10 Replacement 2,550,000 11 (Base Construction Allocation - 12 $2,200,000) 13 (Land Allocation - $100,000) 14 (Design and Contingencies - $250,000) 15 (6) City of Philadelphia, Montgomery 16 Bridge over Amtrak, Bridge Replacement 5,275,000 17 (Base Construction Allocation - 18 $4,750,000) 19 (Land Allocation - $125,000) 20 (Design and Contingencies - $400,000) 21 (7) City of Philadelphia, Thomas Avenue 22 Bridge over SEPTA, Bridge Replacement 3,150,000 23 (Base Construction Allocation - 24 $2,750,000) 25 (Land Allocation - $100,000) 26 (Design and Contingencies - $300,000) 27 (8) City of Philadelphia, Sedgley Avenue 28 Bridge over Conrail, Bridge 29 Replacement 1,000,000 30 (Base Construction Allocation - 19970S0186B0698 - 278 -
1 $800,000) 2 (Land Allocation - $100,000) 3 (Design and Contingencies - $100,000) 4 (9) City of Philadelphia, Lexington Avenue 5 Bridge over Conrail, Bridge 6 Replacement 420,000 7 (Base Construction Allocation - 8 $360,000) 9 (Land Allocation - $20,000) 10 (Design and Contingencies - $40,000) 11 (10) City of Philadelphia, Greenland 12 Bridge over Conrail and I-76, Bridge 13 Replacement 1,350,000 14 (Base Construction Allocation - 15 $1,100,000) 16 (Land Allocation - $100,000) 17 (Design and Contingencies - $150,000) 18 (11) City of Philadelphia, Glenwood Drive 19 Bridge over Conrail, Bridge 20 Replacement 1,450,000 21 (Base Construction Allocation - 22 $1,200,000) 23 (Land Allocation - $100,000) 24 (Design and Contingencies - $150,000) 25 (12) City of Philadelphia, Second Street 26 Bridge over Conrail, Bridge 27 Replacement 740,000 28 (Base Construction Allocation - 29 $650,000) 30 (Land Allocation - $20,000) 19970S0186B0698 - 279 -
1 (Design and Contingencies - $70,000) 2 (13) City of Philadelphia, Cambria Street 3 Bridge over Conrail, Bridge 4 Replacement 2,750,000 5 (Base Construction Allocation - 6 $2,400,000) 7 (Land Allocation - $100,000) 8 (Design and Contingencies - $250,000) 9 (b) State Bridges 10 (1) SR 4007, Germantown Avenue Bridge, 11 Conrail Overpass, City of Philadelphia, 12 Bridge Removal 125,000 13 (Base Construction Allocation - 14 $100,000) 15 (Land Allocation - $10,000) 16 (Design and Contingencies - $15,000) 17 (2) SR 0076, Schuylkill Expressway Bridge 18 over Schuylkill River, City of 19 Philadelphia, Bridge Painting 2,580,000 20 (Base Construction Allocation - 21 $2,390,000) 22 (Design and Contingencies - $190,000) 23 (3) SR 2003, 5th Street Bridge over 24 Amtrak, City of Philadelphia, Bridge 25 Replacement 2,400,000 26 (Base Construction Allocation - 27 $2,000,000) 28 (Land Allocation - $200,000) 29 (Design and Contingencies - $200,000) 30 (4) SR 3008, Chestnut Street Bridge over 19970S0186B0698 - 280 -
1 Schuylkill River, City of Philadelphia, 2 Bridge Painting 477,000 3 (Base Construction Allocation - 4 $426,000) 5 (Design and Contingencies - $51,000) 6 (5) SR 3037, JFK Boulevard Bridge over 7 Schuylkill River, City of Philadelphia, 8 Bridge Painting 857,000 9 (Base Construction Allocation - 10 $794,000) 11 (Design and Contingencies - $63,000) 12 (6) SR 0095, Delaware River Expressway 13 over Westmoreland and Tioga Streets, 14 City of Philadelphia, Bridge 15 Rehabilitation 4,450,000 16 (Base Construction Allocation - 17 $4,200,000) 18 (Land Allocation - $50,000) 19 (Design and Contingencies - $200,000) 20 Section 56. Pike County. 21 (a) Local Bridges (Reserved) 22 (b) State Bridges 23 (1) SR 0390, Bridge Kill Creek Bridge, 24 North of SR 3002, Green Township, 25 Bridge Replacement 430,000 26 (Base Construction Allocation - 27 $340,000) 28 (Land Allocation - $10,000) 29 (Design and Contingencies - $80,000) 30 (2) SR 2011, Bridge over Outlet to Sawkill 19970S0186B0698 - 281 -
1 Pond, South of TR 6, Dingman Township, 2 Bridge Replacement 355,000 3 (Base Construction Allocation - 4 $275,000) 5 (Land Allocation - $10,000) 6 (Design and Contingencies - $70,000) 7 (3) SR 0434, Shohola Bridge over Delaware 8 River, Shohola Township and New York 9 State Line, Bridge Painting 2,200,000 10 (Base Construction Allocation - 11 $2,000,000) 12 (Design and Contingencies - $200,000) 13 (4) State Bridges, Countywide Bridge Zone 14 Painting, Bridge Painting 370,000 15 (Base Construction Allocation - 16 $350,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $10,000) 19 Section 57. (Reserved). 20 Section 58. Schuylkill County. 21 (a) Local Bridges 22 (1) City of Pottsville, Washington Street 23 Bridge No.2 over Conrail and PA 61, 24 Bridge Replacement 2,225,000 25 (Base Construction Allocation - 26 $2,000,000) 27 (Land Allocation - $25,000) 28 (Design and Contingencies - $200,000) 29 (2) Pine Grove Township, Penn Central 30 Bridge over T-390, Bridge Removal 551,000 19970S0186B0698 - 282 -
1 (Base Construction Allocation - 2 $435,000) 3 (Land Allocation - $50,000) 4 (Design and Contingencies - $66,000) 5 (3) Rush Township, T-862, Bridge No.42 6 over Pine Creek, Bridge Replacement 139,000 7 (Base Construction Allocation - 8 $121,000) 9 (Land Allocation - $6,000) 10 (Design and Contingencies - $12,000) 11 (4) St. Clair Borough, Russell Street 12 Bridge over Mill Creek, Bridge 13 Replacement 223,000 14 (Base Construction Allocation - 15 $193,000) 16 (Land Allocation - $10,000) 17 (Design and Contingencies - $20,000) 18 (5) Upper Mahantongo Township, T-473, 19 Bridge over Mahantongo Creek, Bridge 20 Replacement 202,000 21 (Base Construction Allocation - 22 $175,000) 23 (Land Allocation - $9,000) 24 (Design and Contingencies - $18,000) 25 (6) EAST BRUNSWICK TOWNSHIP, T-753, BRIDGE <-- 26 OVER INDIAN RUN, BRIDGE REPLACEMENT 400,000 27 (BASE CONSTRUCTION ALLOCATION - 28 $290,000) 29 (LAND ALLOCATION - $10,000) 30 (DESIGN AND CONTINGENCIES - $100,000) 19970S0186B0698 - 283 -
1 (7) WEST BRUNSWICK TOWNSHIP, COUNTY BRIDGE 2 NO.94 OVER SCHUYLKILL RIVER, BRIDGE 3 REPLACEMENT 384,000 4 (BASE CONSTRUCTION ALLOCATION - 5 $384,000) 6 (8) TREMONT BOROUGH, MAPLE STREET BRIDGE 7 NO.22 OVER GOODSPRING CREEK, BRIDGE 8 REPLACEMENT 214,000 9 (BASE CONSTRUCTION ALLOCATION - 10 $178,000) 11 (DESIGN AND CONTINGENCIES - $36,000) 12 (9) GILBERTON BOROUGH, BRIDGE STREET 13 BRIDGE OVER MAHANOY CREEK, BRIDGE 14 REPLACEMENT 520,000 15 (BASE CONSTRUCTION ALLOCATION - 16 $400,000) 17 (LAND ALLOCATION - $20,000) 18 (DESIGN AND CONTINGENCIES - $100,000) 19 (10) PORTER TOWNSHIP, T-416, BRIDGE NO.79 20 OVER WICONISCO CREEK, BRIDGE 21 REPLACEMENT 287,000 22 (BASE CONSTRUCTION ALLOCATION - 23 $250,000) 24 (LAND ALLOCATION - $12,000) 25 (DESIGN AND CONTINGENCIES - $25,000) 26 (11) UNION TOWNSHIP, T-594, BRIDGE OVER 27 LITTLE CATAWISSA CREEK, BRIDGE 28 REPLACEMENT 296,000 29 (BASE CONSTRUCTION ALLOCATION - 30 $230,000) 19970S0186B0698 - 284 -
1 (LAND ALLOCATION - $5,000) 2 (DESIGN AND CONTINGENCIES - $61,000) 3 (12) DEER LAKE BOROUGH, DREHERSVILLE ROAD 4 BRIDGE OVER PINE CREEK, BRIDGE 5 REPLACEMENT 484,000 6 (BASE CONSTRUCTION ALLOCATION - 7 $324,000) 8 (LAND ALLOCATION - $10,000) 9 (DESIGN AND CONTINGENCIES - $150,000) 10 (13) PORT CARBON BOROUGH, MILL STREET 11 BRIDGE NO.106 OVER SCHUYLKILL RIVER, 12 BRIDGE REPLACEMENT 1,050,000 13 (BASE CONSTRUCTION ALLOCATION - 14 $750,000) 15 (LAND ALLOCATION - $50,000) 16 (DESIGN AND CONTINGENCIES - $250,000) 17 (14) HEGINS TOWNSHIP, T-478, BROAD STREET 18 BRIDGE OVER PINE CREEK, BRIDGE 19 REPLACEMENT 357,000 20 (BASE CONSTRUCTION ALLOCATION - 21 $290,000) 22 (LAND ALLOCATION - $5,000) 23 (DESIGN AND CONTINGENCIES - $62,000) 24 (15) FRACKVILLE BOROUGH, SPRING STREET 25 READING RAILROAD BRIDGE, BRIDGE 26 REMOVAL 112,000 27 (BASE CONSTRUCTION ALLOCATION - 28 $52,000) 29 (LAND ALLOCATION - $10,000) 30 (DESIGN AND CONTINGENCIES - $50,000) 19970S0186B0698 - 285 -
1 (16) ELDRED TOWNSHIP, T-383, BRIDGE OVER 2 MAHANTANGO CREEK, BRIDGE REPLACEMENT 121,000 3 (BASE CONSTRUCTION ALLOCATION - 4 $110,000) 5 (DESIGN AND CONTINGENCIES - $11,000) 6 (17) PORT CLINTON BOROUGH, BROAD STREET, 7 COUNTY BRIDGE NO.123 OVER SCHUYLKILL 8 RIVER, BRIDGE REPLACEMENT 828,000 9 (BASE CONSTRUCTION ALLOCATION - 10 $692,000) 11 (LAND ALLOCATION - $32,000) 12 (DESIGN AND CONTINGENCIES - $104,000) 13 (18) SOUTH MANHEIM TOWNSHIP, T-676 COUNTY 14 BRIDGE NO.112 OVER BEAR CREEK, BRIDGE 15 REPLACEMENT 470,000 16 (BASE CONSTRUCTION ALLOCATION - 17 $300,000) 18 (LAND ALLOCATION - $20,000) 19 (DESIGN AND CONTINGENCIES - $150,000) 20 (19) PORT CARBON BOROUGH, WASHINGTON 21 STREET BRIDGE OVER MILL CREEK, BRIDGE 22 REPLACEMENT 684,000 23 (BASE CONSTRUCTION ALLOCATION - 24 $564,000) 25 (LAND ALLOCATION - $20,000) 26 (DESIGN AND CONTINGENCIES - $100,000) 27 (20) CITY OF POTTSVILLE, WASHINGTON STREET 28 OVER CONRAIL AND SR 0061, BRIDGE 29 REHABILITATION 803,000 30 (BASE CONSTRUCTION ALLOCATION - 19970S0186B0698 - 286 -
1 $669,000) 2 (DESIGN AND CONTINGENCIES - $134,000) 3 (21) ST. CLAIR BOROUGH, RUSSELL STREET 4 BRIDGE OVER MILL CREEK, BRIDGE 5 REPLACEMENT 480,000 6 (BASE CONSTRUCTION ALLOCATION - 7 $350,000) 8 (LAND ALLOCATION - $10,000) 9 (DESIGN AND CONTINGENCIES - $120,000) 10 (22) NORTH UNION TOWNSHIP, T-455, BRIDGE 11 OVER TOMHICKEN CREEK, BRIDGE 12 REPLACEMENT 360,000 13 (BASE CONSTRUCTION ALLOCATION - 14 $250,000) 15 (LAND ALLOCATION - $10,000) 16 (DESIGN AND CONTINGENCIES - $100,000) 17 (23) WEST BRUNSWICK TOWNSHIP, T-723, 18 INDUSTRIAL ROAD OVER PINE CREEK, BRIDGE 19 REPLACEMENT 584,000 20 (BASE CONSTRUCTION ALLOCATION - 21 $434,000) 22 (LAND ALLOCATION - $20,000) 23 (DESIGN AND CONTINGENCIES - $130,000) 24 (24) LANDINGVILLE BOROUGH, CANAL STREET 25 BRIDGE OVER SCHUYLKILL RIVER, BRIDGE 26 REPLACEMENT 810,000 27 (BASE CONSTRUCTION ALLOCATION - 28 $640,000) 29 (LAND ALLOCATION - $20,000) 30 (DESIGN AND CONTINGENCIES - $150,000) 19970S0186B0698 - 287 -
1 (25) NORTH MANHEIM TOWNSHIP, MEMORIAL 2 DRIVE OVERPASS, BRIDGE REMOVAL 295,000 3 (BASE CONSTRUCTION ALLOCATION - 4 $250,000) 5 (LAND ALLOCATION - $20,000) 6 (DESIGN AND CONTINGENCIES - $25,000) 7 (26) BRANCH TOWNSHIP, T-564, BRIDGE OVER 8 MUDDY CREEK, BRIDGE REPLACEMENT 360,000 9 (BASE CONSTRUCTION ALLOCATION - 10 $250,000) 11 (LAND ALLOCATION - $10,000) 12 (DESIGN AND CONTINGENCIES - $100,000) 13 (27) ELDRED TOWNSHIP, T-395, BRIDGE OVER 14 LITTLE MAHANTANGO CREEK, BRIDGE 15 REPLACEMENT 362,000 16 (BASE CONSTRUCTION ALLOCATION - 17 $250,000) 18 (LAND ALLOCATION - $12,000) 19 (DESIGN AND CONTINGENCIES - $100,000) 20 (b) State Bridges 21 (1) SR 0054, SR 0054 over Mahanoy Creek, 22 Mahanoy Township, Bridge Replacement 1,005,000 23 (Base Construction Allocation - 24 $770,000) 25 (Design and Contingencies - $235,000) 26 (2) SR 0054, SR 0054 over Reading Blue 27 Mountain and Northern Railroad, Mahanoy 28 Township, Bridge Rehabilitation 650,000 29 (Base Construction Allocation - 30 $500,000) 19970S0186B0698 - 288 -
1 (Design and Contingencies - $150,000) 2 (3) SR 0081, SR 0081 Southbound over 3 Swatara Creek, Pine Grove Township, 4 Bridge Rehabilitation 970,000 5 (Base Construction Allocation - 6 $745,000) 7 (Design and Contingencies - $225,000) 8 (4) SR 0081, SR 0081 Northbound over 9 Swatara Creek, Pine Grove Township, 10 Bridge Rehabilitation 970,000 11 (Base Construction Allocation - 12 $745,000) 13 (Design and Contingencies - $225,000) 14 (5) SR 0081, SR 0081 Southbound over SR 15 0443 and Exit Ramp 3, Pine Grove 16 Township, Bridge Rehabilitation 715,000 17 (Base Construction Allocation - 18 $550,000) 19 (Design and Contingencies - $165,000) 20 (6) SR 0081, SR 0081 Northbound over SR 21 0443 and Exit Ramp 31, Pine Grove 22 Township, Bridge Rehabilitation 515,000 23 (Base Construction Allocation - 24 $390,000) 25 (Design and Contingencies - $125,000) 26 (7) SR 0081, I-81 Southbound over T-886, 27 Oak Grove Road, Pine Grove Township, 28 Bridge Rehabilitation 300,000 29 (Base Construction Allocation - 30 $200,000) 19970S0186B0698 - 289 -
1 (Design and Contingencies - $100,000) 2 (8) SR 0081, I-81 Northbound over T-886, 3 Oak Grove Road, Pine Grove Township, 4 Bridge Rehabilitation 300,000 5 (Base Construction Allocation - 6 $200,000) 7 (Design and Contingencies - $100,000) 8 (9) SR 0061, Bridge over Mahannon Creek at 9 South Liberty Street, North Manheim 10 Township, Bridge Rehabilitation 265,000 11 (Base Construction Allocation - 12 $175,000) 13 (Design and Contingencies - $90,000) 14 (10) SR 0895, SR 0895 over Lizard Creek, 15 Village of Snyders, West Penn Township, 16 Bridge Rehabilitation 290,000 17 (Base Construction Allocation - 18 $190,000) 19 (Design and Contingencies - $100,000) 20 (11) SR 0901, SR 0901 over Mahanoy Creek, 21 Bridge Rehabilitation 680,000 22 (Base Construction Allocation - 23 $520,000) 24 (Design and Contingencies - $160,000) 25 (12) SR 1011, SR 1011 over Big Creek, 26 Village of Brockton, Schuylkill 27 Township, Bridge Replacement 340,000 28 (Base Construction Allocation - 29 $160,000) 30 (Land Allocation - $55,000) 19970S0186B0698 - 290 -
1 (Design and Contingencies - $125,000) 2 (13) SR 1011, SR 1011 over Locust Creek, 3 Ryan Township, Bridge Rehabilitation 365,000 4 (Base Construction Allocation - 5 $180,000) 6 (Land Allocation - $60,000) 7 (Design and Contingencies - $125,000) 8 (14) SR 2018, SR 2018 over Little 9 Schuylkill River, Drehersville, East 10 Brunswick Township, Bridge 11 Rehabilitation 385,000 12 (Base Construction Allocation - 13 $285,000) 14 (Design and Contingencies - $100,000) 15 (15) SR 4013, SR 4013 over Rausch Creek, 16 Hegins Township, Bridge Rehabilitation 280,000 17 (Base Construction Allocation - 18 $180,000) 19 (Design and Contingencies - $100,000) 20 (16) SR 4022, SR 4022 over Tributary of 21 Mahantango Creek, Eldred Township, 22 Bridge Replacement 310,000 23 (Base Construction Allocation - 24 $150,000) 25 (Land Allocation - $50,000) 26 (Design and Contingencies - $110,000) 27 (17) SR 0209, Broad Street over Little 28 Schuylkill River, Tamaqua Borough, 29 Bridge Replacement 600,000 30 (Base Construction Allocation - 19970S0186B0698 - 291 -
1 $360,000) 2 (Land Allocation - $100,000) 3 (Design and Contingencies - $140,000) 4 (18) SR 4022, Broad Street Bridge over 5 Panther Creek, Tamaqua Borough, Bridge 6 Replacement 1,780,000 7 (Base Construction Allocation - 8 $1,220,000) 9 (Land Allocation - $195,000) 10 (Design and Contingencies - $365,000) 11 (19) SR 4022, SR 4022 over Mahanoy Creek, 12 Village of Helfenstein, Eldred 13 Township, Bridge Replacement 1,170,000 14 (Base Construction Allocation - 15 $750,000) 16 (Land Allocation - $195,000) 17 (Design and Contingencies - $225,000) 18 (20) SR 0339, SR 0339 over Catawissa 19 Creek, North Union Township, Bridge 20 Replacement 984,000 21 (Base Construction Allocation - 22 $630,000) 23 (Land Allocation - $165,000) 24 (Design and Contingencies - $189,000) 25 (21) SR 0443, Dock Street Bridge over 26 Tributary of Schuylkill River, Borough 27 of Schuylkill Haven, Bridge 28 Replacement 325,000 29 (Base Construction Allocation - 30 $150,000) 19970S0186B0698 - 292 -
1 (Land Allocation - $50,000) 2 (Design and Contingencies - $125,000) 3 (22) SR 0895, SR 0895 over Schuylkill 4 River, Bridge Replacement 2,370,000 5 (Base Construction Allocation - 6 $1,480,000) 7 (Land Allocation - $390,000) 8 (Design and Contingencies - $500,000) 9 (23) SR 4011, SR 4011 over Pine Creek, 10 Hegins Township, Bridge Replacement 720,000 11 (Base Construction Allocation - 12 $450,000) 13 (Land Allocation - $120,000) 14 (Design and Contingencies - $150,000) 15 (24) SR 0895, Auburn Arch over Schuylkill 16 River, South Manheim Township, Bridge 17 Replacement 550,000 18 (Base Construction Allocation - 19 $350,000) 20 (Land Allocation - $50,000) 21 (Design and Contingencies - $150,000) 22 (25) SR 0061, MADY'S BIG BRIDGE OVER <-- 23 CONRAIL, CITY OF POTTSVILLE, BRIDGE 24 REHABILITATION 1,323,000 25 (BASE CONSTRUCTION ALLOCATION - 26 $1,202,000) 27 (DESIGN AND CONTINGENCIES - $121,000) 28 (26) SR 0061, MADY'S SMALL BRIDGE OVER 29 SCHUYLKILL RIVER, CITY OF POTTSVILLE, 30 BRIDGE REHABILITATION 329,000 19970S0186B0698 - 293 -
1 (BASE CONSTRUCTION ALLOCATION - 2 $299,000) 3 (DESIGN AND CONTINGENCIES - $30,000) 4 (27) SR 0125, PITMAN BRIDGE OVER LITTLE 5 MAHANTANGO CREEK, ELDRED TOWNSHIP, 6 BRIDGE REPLACEMENT 480,000 7 (BASE CONSTRUCTION ALLOCATION - 8 $390,000) 9 (LAND ALLOCATION - $10,000) 10 (DESIGN AND CONTINGENCIES - $80,000) 11 (28) SR 0325, BRIDGE OVER WICONISCO CREEK, 12 PORTER TOWNSHIP, BRIDGE REPLACEMENT 1,175,000 13 (BASE CONSTRUCTION ALLOCATION - 14 $800,000) 15 (LAND ALLOCATION - $40,000) 16 (DESIGN AND CONTINGENCIES - $335,000) 17 (29) SR 0501, BRIDGE OVER LITTLE SWATARA 18 CREEK, PINE GROVE TOWNSHIP, BRIDGE 19 REPLACEMENT 1,400,000 20 (BASE CONSTRUCTION ALLOCATION - 21 $1,000,000) 22 (LAND ALLOCATION - $50,000) 23 (DESIGN AND CONTINGENCIES - $350,000) 24 (30) SR 0501, SMALL BRIDGE OVER LITTLE 25 SWATARA CREEK, PINE GROVE TOWNSHIP, 26 BRIDGE REPLACEMENT 250,000 27 (BASE CONSTRUCTION ALLOCATION - 28 $150,000) 29 (LAND ALLOCATION - $10,000) 30 (DESIGN AND CONTINGENCIES - $90,000) 19970S0186B0698 - 294 -
1 (31) SR 1013, TUSCARORA PARK BRIDGE OVER 2 TRIBUTARY OF LOCUST CREEK, RYAN 3 TOWNSHIP, BRIDGE DECK REPLACEMENT 485,000 4 (BASE CONSTRUCTION ALLOCATION - 5 $375,000) 6 (LAND ALLOCATION - $10,000) 7 (DESIGN AND CONTINGENCIES - $100,000) 8 (32) SR 1016, LOFTY BRIDGE OVER POCONO 9 N.E. RAILROAD, DELANO TOWNSHIP, BRIDGE 10 REPLACEMENT 715,000 11 (BASE CONSTRUCTION ALLOCATION - 12 $500,000) 13 (LAND ALLOCATION - $15,000) 14 (DESIGN AND CONTINGENCIES - $200,000) 15 (33) SR 2006, BRIDGE OVER MAHANNON CREEK, 16 WEST BRUNSWICK TOWNSHIP, BRIDGE 17 REPLACEMENT 107,000 18 (BASE CONSTRUCTION ALLOCATION - 19 $92,000) 20 (LAND ALLOCATION - $5,000) 21 (DESIGN AND CONTINGENCIES - $10,000) 22 (34) SR 3003, BRIDGE OVER WEST BRANCH 23 SCHUYLKILL RIVER, NORTH MANHEIM 24 TOWNSHIP, BRIDGE DECK REPLACEMENT 224,000 25 (BASE CONSTRUCTION ALLOCATION - 26 $195,000) 27 (DESIGN AND CONTINGENCIES - $29,000) 28 (35) SR 3015, BRIDGE OVER WICONISCO CREEK, 29 PORTER TOWNSHIP, BRIDGE REPLACEMENT 200,000 30 (BASE CONSTRUCTION ALLOCATION - 19970S0186B0698 - 295 -
1 $175,000) 2 (LAND ALLOCATION - $8,000) 3 (DESIGN AND CONTINGENCIES - $17,000) 4 (36) SR 4016, BRIDGE OVER LITTLE 5 MAHANTANGO CREEK, UPPER MAHANTONGO 6 TOWNSHIP, BRIDGE REPLACEMENT 165,000 7 (BASE CONSTRUCTION ALLOCATION - 8 $150,000) 9 (DESIGN AND CONTINGENCIES - $15,000) 10 (37) SR 4033, BRIDGE OVER TOMHICKEN CREEK, 11 NORTH UNION TOWNSHIP, BRIDGE DECK 12 REPLACEMENT 350,000 13 (BASE CONSTRUCTION ALLOCATION - 14 $250,000) 15 (DESIGN AND CONTINGENCIES - $100,000) 16 (38) SR 4036, RINGTOWN BRIDGE OVER LITTLE 17 CATAWISSA CREEK, UNION TOWNSHIP, BRIDGE 18 REPLACEMENT 240,000 19 (BASE CONSTRUCTION ALLOCATION - 20 $216,000) 21 (LAND ALLOCATION - $3,000) 22 (DESIGN AND CONTINGENCIES - $21,000) 23 (39) SR 4039, HAAS BRIDGE OVER MAHANTANGO 24 CREEK, UPPER MAHANTONGO TOWNSHIP, 25 BRIDGE REPLACEMENT 153,000 26 (BASE CONSTRUCTION ALLOCATION - 27 $130,000) 28 (LAND ALLOCATION - $10,000) 29 (DESIGN AND CONTINGENCIES - $13,000) 30 Section 59. Snyder County. 19970S0186B0698 - 296 -
1 (a) Local Bridges (Reserved) 2 (b) State Bridges 3 (1) SR 1011, Pine Street Bridge over Penns 4 Creek, Selinsgrove, Bridge 5 Rehabilitation 1,150,000 6 (Base Construction Allocation - 7 $940,000) 8 (Land Allocation - $10,000) 9 (Design and Contingencies - $200,000) 10 (2) SR 3002, Bridge over Mahantango Creek, 11 1.5 Miles South of Meiserville, Perry 12 and Chapman Townships Line, Bridge 13 Rehabilitation 1,425,000 14 (Base Construction Allocation - 15 $1,211,000) 16 (Design and Contingencies - $214,000) 17 (3) SR 4007, Middle Creek Bridge over 18 Middle Creek, North of SR 0522 and 19 South of SR 4012, Bridge Replacement 1,158,000 20 (Base Construction Allocation - 21 $926,000) 22 (Land Allocation - $58,000) 23 (Design and Contingencies - $174,000) 24 (4) SR 0522, Bridge over Middle Creek, 25 Bridge Painting 180,000 26 (Base Construction Allocation - 27 $170,000) 28 (Design and Contingencies - $10,000) 29 (5) SR 0035, SR 0035 over Tributary of 30 Mahantango Creek, Perry Township, 19970S0186B0698 - 297 -
1 Bridge Replacement 815,000 2 (Base Construction Allocation - 3 $652,000) 4 (Land Allocation - $41,000) 5 (Design and Contingencies - $122,000) 6 (6) SR 0104, SR 0104 over Branch of 7 Mahantango Creek, Perry Township, 8 Bridge Replacement 430,000 9 (Base Construction Allocation - 10 $345,000) 11 (Land Allocation - $20,000) 12 (Design and Contingencies - $65,000) 13 (7) SR 0104, SR 0104 over Middle Creek, 14 Franklin Township, Bridge Replacement 440,000 15 (Base Construction Allocation - 16 $350,000) 17 (Land Allocation - $20,000) 18 (Design and Contingencies - $70,000) 19 (8) SR 0522, SR 0522 over Tributary of 20 Middle Creek, Spring Township, Bridge 21 Replacement 500,000 22 (Base Construction Allocation - 23 $400,000) 24 (Land Allocation - $25,000) 25 (Design and Contingencies - $75,000) 26 (9) SR 0522, SR 0522 over Tributary of 27 Middle Creek, Spring Township, Bridge 28 Replacement 896,000 29 (Base Construction Allocation - 30 $717,000) 19970S0186B0698 - 298 -
1 (Land Allocation - $45,000) 2 (Design and Contingencies - $134,000) 3 (10) SR 0522, SR 0522 over Tributary of 4 Middle Creek, Beavertown Borough, 5 Bridge Replacement 244,000 6 (Base Construction Allocation - 7 $195,000) 8 (Land Allocation - $12,000) 9 (Design and Contingencies - $37,000) 10 (11) SR 0522, SR 0522 over Tributary of 11 Middle Creek, Beavertown Borough, 12 Bridge Replacement 245,000 13 (Base Construction Allocation - 14 $196,000) 15 (Land Allocation - $12,000) 16 (Design and Contingencies - $37,000) 17 (12) SR 0522, SR 0522 over Kern Run, 18 Beavertown Borough, Bridge Replacement 570,000 19 (Base Construction Allocation - 20 $456,000) 21 (Land Allocation - $29,000) 22 (Design and Contingencies - $85,000) 23 (13) SR 0522, SR 0522 over Penns Creek, 24 Selinsgrove Borough, Bridge 25 Replacement 3,167,000 26 (Base Construction Allocation - 27 $2,534,000) 28 (Land Allocation - $158,000) 29 (Design and Contingencies - $475,000) 30 (14) SR 1011, SR 1011 over Tributary of 19970S0186B0698 - 299 -
1 Penns Creek, Jackson Township, Bridge 2 Replacement 241,000 3 (Base Construction Allocation - 4 $193,000) 5 (Land Allocation - $12,000) 6 (Design and Contingencies - $36,000) 7 (15) SR 2013, SR 2013 over Tributary of 8 Susquehanna River, Chapman Township, 9 Bridge Replacement 202,000 10 (Base Construction Allocation - 11 $162,000) 12 (Land Allocation - $10,000) 13 (Design and Contingencies - $30,000) 14 (16) SR 3009, SR 3009 over Paxtonville 15 Creek, Franklin Township, Bridge 16 Replacement 1,512,000 17 (Base Construction Allocation - 18 $1,209,000) 19 (Land Allocation - $76,000) 20 (Design and Contingencies - $227,000) 21 Section 60. Somerset County. 22 (a) Local Bridges 23 (1) Middlecreek Township, T-338, Blue Hole 24 Creek Bridge over Blue Hole Creek, 25 Bridge Replacement 505,000 26 (Base Construction Allocation - 27 $400,000) 28 (Land Allocation - $10,000) 29 (Design and Contingencies - $95,000) 30 (2) Paint Borough, Pennsylvania Railroad 19970S0186B0698 - 300 -
1 Bridge over Bedford Street, Bridge 2 Replacement 350,000 3 (Base Construction Allocation - 4 $250,000) 5 (Land Allocation - $25,000) 6 (Design and Contingencies - $75,000) 7 (3) Shade Township, T-712, Lipinski Road 8 Bridge over Dark Shade Creek, Bridge 9 Replacement 560,000 10 (Base Construction Allocation - 11 $450,000) 12 (Land Allocation - $10,000) 13 (Design and Contingencies - $100,000) 14 (4) Somerset Borough, Church Street Bridge 15 over Parsons Run, Bridge Replacement 350,000 16 (Base Construction Allocation - 17 $250,000) 18 (Land Allocation - $25,000) 19 (Design and Contingencies - $75,000) 20 (5) Windber Borough, South 22nd Street 21 Bridge over Seese Run, Bridge 22 Replacement 350,000 23 (Base Construction Allocation - 24 $250,000) 25 (Land Allocation - $25,000) 26 (Design and Contingencies - $75,000) 27 (6) Windber Borough, 24th Street Bridge 28 over Seese Run, Bridge Replacement 350,000 29 (Base Construction Allocation - 30 $250,000) 19970S0186B0698 - 301 -
1 (Land Allocation - $25,000) 2 (Design and Contingencies - $75,000) 3 (7) Windber Borough, Village Street Bridge 4 over Seese Run, Bridge Replacement 350,000 5 (Base Construction Allocation - 6 $250,000) 7 (Land Allocation - $25,000) 8 (Design and Contingencies - $75,000) 9 (8) Summit Township, Keystone Viaduct over 10 SR 2006, CSX Mainline and Flaugherty 11 Creek, Bridge Rehabilitation 715,000 12 (Base Construction Allocation - 13 $663,000) 14 (Design and Contingencies - $52,000) 15 (b) State Bridges 16 (1) SR 0160, SR 0160 over Tributary of 17 Boones Run, Stoney Creek Township, 18 Bridge Replacement 580,000 19 (Base Construction Allocation - 20 $430,000) 21 (Land Allocation - $25,000) 22 (Design and Contingencies - $125,000) 23 (2) SR 0523, SR 0523 over Whites Creek, 24 Addison Township, Bridge Replacement 690,000 25 (Base Construction Allocation - 26 $510,000) 27 (Land Allocation - $50,000) 28 (Design and Contingencies - $130,000) 29 (3) SR 1007, SR 1007 over Lambert Run, 30 Stoney Creek Township, Bridge 19970S0186B0698 - 302 -
1 Replacement 490,000 2 (Base Construction Allocation - 3 $355,000) 4 (Land Allocation - $25,000) 5 (Design and Contingencies - $110,000) 6 (4) SR 1017, SR 1017 over Breastwork Run, 7 Allegheny Township, Bridge Replacement 650,000 8 (Base Construction Allocation - 9 $490,000) 10 (Land Allocation - $25,000) 11 (Design and Contingencies - $135,000) 12 (5) SR 1017, SR 1017 over Breastwork Run, 13 Allegheny Township, Bridge Replacement 580,000 14 (Base Construction Allocation - 15 $440,000) 16 (Land Allocation - $25,000) 17 (Design and Contingencies - $135,000) 18 (6) SR 1018, SR 1018 over Beaverdam Run, 19 Shade Township, Bridge Replacement 545,000 20 (Base Construction Allocation - 21 $400,000) 22 (Land Allocation - $25,000) 23 (Design and Contingencies - $120,000) 24 (7) SR 1018, SR 1018 over Beaverdam Run, 25 Shade Township, Bridge Replacement 515,000 26 (Base Construction Allocation - 27 $375,000) 28 (Land Allocation - $25,000) 29 (Design and Contingencies - $115,000) 30 (8) SR 2005, SR 2005 over Elk Lick Creek, 19970S0186B0698 - 303 -
1 Elk Lick Township, Bridge Replacement 520,000 2 (Base Construction Allocation - 3 $380,000) 4 (Land Allocation - $25,000) 5 (Design and Contingencies - $115,000) 6 (9) SR 4013, SR 4013 over North Branch of 7 Quemahoning Creek, Lincoln Township, 8 Bridge Replacement 585,000 9 (Base Construction Allocation - 10 $435,000) 11 (Land Allocation - $25,000) 12 (Design and Contingencies - $125,000) 13 (10) SR 4019, SR 4019 over Quemahoning 14 Creek, Quemahoning Township, Bridge 15 Replacement 800,000 16 (Base Construction Allocation - 17 $625,000) 18 (Land Allocation - $25,000) 19 (Design and Contingencies - $150,000) 20 (11) SR 3039, SR 3039 over Allen Creek, 21 Middlecreek Township, Bridge 22 Replacement 200,000 23 (Base Construction Allocation - 24 $150,000) 25 (Land Allocation - $5,000) 26 (Design and Contingencies - $45,000) 27 (12) SR 3039, SR 3039 over Allen Creek, 28 Middlecreek Township, Bridge 29 Replacement 220,000 30 (Base Construction Allocation - 19970S0186B0698 - 304 -
1 $150,000) 2 (Land Allocation - $10,000) 3 (Design and Contingencies - $60,000) 4 (13) SR 4001, SR 4001 over Clear Run, 5 Jefferson Township, Bridge Replacement 295,000 6 (Base Construction Allocation - 7 $200,000) 8 (Land Allocation - $10,000) 9 (Design and Contingencies - $85,000) 10 Section 61. Sullivan County. 11 (a) Local Bridges 12 (1) Forks Township, T-448, Old TR 87 13 Bridge, County Bridge No.55 over Little 14 Loyalsock Creek, Bridge Replacement 860,000 15 (Base Construction Allocation - 16 $700,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $150,000) 19 (2) Forks and Laporte Townships, T-346 20 over Loyalsock Creek, Bridge 21 Replacement 840,000 22 (Base Construction Allocation - 23 $730,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $100,000) 26 (b) State Bridges 27 (1) SR 0087, SR 0087 over Lick Run, Forks 28 Township, Bridge Replacement 635,000 29 (Base Construction Allocation - 30 $508,000) 19970S0186B0698 - 305 -
1 (Land Allocation - $32,000) 2 (Design and Contingencies - $95,000) 3 (2) SR 0087, SR 0087 over Little Loyalsock 4 Creek, Cherry Township, Bridge 5 Replacement 655,000 6 (Base Construction Allocation - 7 $524,000) 8 (Land Allocation - $33,000) 9 (Design and Contingencies - $98,000) 10 (3) SR 0154, SR 0154 over Black Water Run, 11 Elkland Township, Bridge Replacement 194,000 12 (Base Construction Allocation - 13 $166,000) 14 (Design and Contingencies - $28,000) 15 (4) SR 0154, SR 0154 over Kings Creek, 16 Elkland Township, Bridge Replacement 404,000 17 (Base Construction Allocation - 18 $323,000) 19 (Land Allocation - $20,000) 20 (Design and Contingencies - $61,000) 21 (5) SR 1012, SR 1012 over Little Loyalsock 22 Creek, Cherry Township, Bridge 23 Replacement 260,000 24 (Base Construction Allocation - 25 $208,000) 26 (Land Allocation - $13,000) 27 (Design and Contingencies - $39,000) 28 Section 62. Susquehanna County. 29 (a) Local Bridges (Reserved) 30 (b) State Bridges 19970S0186B0698 - 306 -
1 (1) SR 0167, Owego Street Bridge over 2 Branch of Fall Brook, Bridgewater 3 Township, Bridge Replacement 413,000 4 (Base Construction Allocation - 5 $342,000) 6 (Land Allocation - $10,000) 7 (Design and Contingencies - $61,000) 8 (2) SR 1016, Salt Lick Creek Bridge over 9 Branch of Salt Lick Creek, New Milford 10 Township, Bridge Replacement 100,000 11 (Base Construction Allocation - 12 $86,000) 13 (Land Allocation - $3,000) 14 (Design and Contingencies - $11,000) 15 (3) SR 0081, Bridge over Trowbridge Creek, 16 1 Mile South of the Pennsylvania and 17 New York State Line, Great Bend 18 Township, Bridge Replacement 890,000 19 (Base Construction Allocation - 20 $700,000) 21 (Land Allocation - $10,000) 22 (Design and Contingencies - $180,000) 23 (4) SR 1017, Gulf Street Bridge, 0.5 Mile 24 North of SR 1015, Lanesboro Borough, 25 Bridge Replacement 305,000 26 (Base Construction Allocation - 27 $220,000) 28 (Land Allocation - $10,000) 29 (Design and Contingencies - $75,000) 30 (5) SR 3003, Bridge over Transue Creek, 19970S0186B0698 - 307 -
1 1.5 Miles South of SR 3005, Auburn 2 Township, Bridge Painting 60,000 3 (Base Construction Allocation - 4 $50,000) 5 (Design and Contingencies - $10,000) 6 (6) SR 3006, Bridge over White Creek, 1.5 7 Miles West of SR 3004, Springville 8 Township, Bridge Painting 70,000 9 (Base Construction Allocation - 10 $60,000) 11 (Design and Contingencies - $10,000) 12 (7) SR 0011, Bridge over Salt Lick Creek, 13 0.6 Mile North of TR 492, New Milford 14 Borough, Bridge Replacement 660,000 15 (Base Construction Allocation - 16 $510,000) 17 (Land Allocation - $20,000) 18 (Design and Contingencies - $130,000) 19 (8) SR 0367, Bridge over Tuscarora Creek, 20 North of SR 3005, Auburn Township, 21 Bridge Replacement 330,000 22 (Base Construction Allocation - 23 $265,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $65,000) 26 (9) SR 1010, Bridge over Bedbug Creek, 27 West of SR 1021, Oakland Township, 28 Bridge Replacement 325,000 29 (Base Construction Allocation - 30 $250,000) 19970S0186B0698 - 308 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $65,000) 3 (10) SR 1010, Bridge over Tributary of 4 Susquehanna River, 2 Miles West of SR 5 1021, Great Bend Township, Bridge 6 Replacement 288,000 7 (Base Construction Allocation - 8 $220,000) 9 (Land Allocation - $10,000) 10 (Design and Contingencies - $58,000) 11 (11) SR 2046, Bridge over Branch of 12 Tunkhannock Creek, East of TR 92, 13 Gibson Township, Bridge Replacement 513,000 14 (Base Construction Allocation - 15 $400,000) 16 (Land Allocation - $10,000) 17 (Design and Contingencies - $103,000) 18 (12) SR 3017, Bridge over Thomas Creek, 19 Southeast of TR 29, Springville 20 Township, Bridge Replacement 285,000 21 (Base Construction Allocation - 22 $220,000) 23 (Land Allocation - $10,000) 24 (Design and Contingencies - $50,000) 25 (13) State Bridges, Countywide Bridge Zone 26 Painting, Bridge Painting 370,000 27 (Base Construction Allocation - 28 $350,000) 29 (Land Allocation - $10,000) 30 (Design and Contingencies - $10,000) 19970S0186B0698 - 309 -
1 (14) SR 0858, Branch of Apolacon Creek, 2 0.3 Mile North of SR 4013, Apolacon 3 Township, Bridge Replacement 220,000 4 (Base Construction Allocation - 5 $180,000) 6 (Land Allocation - $10,000) 7 (Design and Contingencies - $30,000) 8 (15) SR 1010, SR 1010 over Tributary of 9 Susquehanna River, Great Bend Township, 10 Bridge Replacement 230,000 11 (Base Construction Allocation - 12 $190,000) 13 (Land Allocation - $10,000) 14 (Design and Contingencies - $30,000) 15 (16) SR 1010, SR 1010 over Bedbug Creek, 16 Oakland Township, Bridge Replacement 270,000 17 (Base Construction Allocation - 18 $220,000) 19 (Land Allocation - $10,000) 20 (Design and Contingencies - $40,000) 21 (17) SR 2046, SR 2046 over Tunkhannock 22 Creek, Gibson Township, Bridge 23 Replacement 440,000 24 (Base Construction Allocation - 25 $370,000) 26 (Land Allocation - $10,000) 27 (Design and Contingencies - $60,000) 28 (18) SR 1011, Bridge over Hemlock Creek, 29 0.2 Mile North of SR 1009, Harmony 30 Township, Bridge Replacement 330,000 19970S0186B0698 - 310 -
1 (Base Construction Allocation - 2 $280,000) 3 (Land Allocation - $10,000) 4 (Design and Contingencies - $40,000) 5 (19) SR 4002, Bridge over Choconut Creek, 6 0.1 Mile East of TR 267, Choconut 7 Township, Bridge Replacement 290,000 8 (Base Construction Allocation - 9 $240,000) 10 (Land Allocation - $10,000) 11 (Design and Contingencies - $40,000) 12 (20) SR 3009, Bridge over White Creek, 1.8 13 Miles North of County Line, Auburn 14 Township, Bridge Replacement 240,000 15 (Base Construction Allocation - 16 $200,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $30,000) 19 (21) SR 3023, Bridge over East Branch of 20 Wyalusing Creek, 0.1 Mile South of TR 21 706, Rush Township, Bridge Replacement 22 and Intersection Realignment 1,520,000 23 (Base Construction Allocation - 24 $1,300,000) 25 (Land Allocation - $20,000) 26 (Design and Contingencies - $200,000) 27 (22) SR 4008, Bridge over Laurel Lake 28 Creek, 1.7 Miles East of TR 167, Silver 29 Lake Township, Bridge Replacement 430,000 30 (Base Construction Allocation - 19970S0186B0698 - 311 -
1 $360,000) 2 (Land Allocation - $10,000) 3 (Design and Contingencies - $60,000) 4 Section 63. Tioga County. 5 (a) Local Bridges 6 (1) Elkland Borough, North Buffalo Street 7 over Camp Brook Creek, Bridge 8 Replacement 510,000 9 (Base Construction Allocation) - 10 $360,000) 11 (Land Allocation - $20,000) 12 (Design and Contingencies - $130,000) 13 (2) Middlebury Township, T-658 (Monkey Run 14 Road), Bridge over Tributary of Losey 15 Creek, Bridge Replacement 390,000 16 (Base Construction Allocation - 17 $250,000) 18 (Land Allocation - $10,000) 19 (Design and Contingencies - $130,000) 20 (3) Farmington Township, T-758 (Short Hole 21 Road), Bridge over Thorn Bottom Creek, 22 Bridge Replacement 390,000 23 (Base Construction Allocation - 24 $250,000) 25 (Land Allocation - $10,000) 26 (Design and Contingencies - $130,000) 27 (b) State Bridges 28 (1) SR 0249, Losey Creek Bridge, South of 29 SR 4017 in Village of Keeneyville, 30 Middlebury Township, Bridge 19970S0186B0698 - 312 -
1 Rehabilitation 250,000 2 (Base Construction Allocation - 3 $210,000) 4 (Land Allocation - $5,000) 5 (Design and Contingencies - $35,000) 6 (2) SR 1002, Corey Creek Bridge over Corey 7 Creek, Northeast of Mansfield, Bridge 8 Replacement 346,000 9 (Base Construction Allocation - 10 $277,000) 11 (Land Allocation - $17,000) 12 (Design and Contingencies - $52,000) 13 (3) SR 3001, Kettle Creek Bridge, 11 Miles 14 South of Watrous, Bridge Replacement 366,000 15 (Base Construction Allocation - 16 $293,000) 17 (Land Allocation - $18,000) 18 (Design and Contingencies - $55,000) 19 (4) SR 3023, Heise Run North Bridge, West 20 of Wellsboro, Bridge Replacement 240,000 21 (Base Construction Allocation - 22 $192,000) 23 (Land Allocation - $12,000) 24 (Design and Contingencies - $36,000) 25 (5) SR 4017, Holden Creek Bridge No.1, 26 Bridge Replacement 584,000 27 (Base Construction Allocation - 28 $467,000) 29 (Land Allocation - $29,000) 30 (Design and Contingencies - $88,000) 19970S0186B0698 - 313 -
1 (6) SR 4024, Elkhorn Creek Bridge, West of 2 Tioga Borough, Bridge Replacement 451,000 3 (Base Construction Allocation - 4 $401,000) 5 (Land Allocation - $15,000) 6 (Design and Contingencies - $35,000) 7 (7) SR 3007, Bridge over Stoney Fork 8 Creek, Bridge Painting 160,000 9 (Base Construction Allocation - 10 $150,000) 11 (Design and Contingencies - $10,000) 12 (8) SR 4017, Bridge over Cowanesque River, 13 Bridge Painting 475,000 14 (Base Construction Allocation - 15 $465,000) 16 (Design and Contingencies - $10,000) 17 (9) SR 0049, SR 0049 over Cowanesque 18 River, Westfield Township, Bridge 19 Replacement 1,802,000 20 (Base Construction Allocation - 21 $1,442,000) 22 (Land Allocation - $90,000) 23 (Design and Contingencies - $270,000) 24 (10) SR 0287, SR 0287 over Wellsboro 25 Street - Conrail, Tioga Township, 26 Bridge Replacement 1,709,000 27 (Base Construction Allocation - 28 $1,367,000) 29 (Land Allocation - $86,000) 30 (Design and Contingencies - $256,000) 19970S0186B0698 - 314 -
1 (11) SR 0328, SR 0328 over Hammond Creek, 2 Jackson Township, Bridge Replacement 256,000 3 (Base Construction Allocation - 4 $205,000) 5 (Land Allocation - $13,000) 6 (Design and Contingencies - $38,000) 7 (12) SR 0349, SR 0349 over Mill Creek, 8 Clymer Township, Bridge Replacement 1,000,000 9 (Base Construction Allocation - 10 $800,000) 11 (Land Allocation - $50,000) 12 (Design and Contingencies - $150,000) 13 (13) SR 1030, SR 1030 over Conrail, Tioga 14 Township, Bridge Replacement 561,000 15 (Base Construction Allocation - 16 $449,000) 17 (Land Allocation - $28,000) 18 (Design and Contingencies - $84,000) 19 (14) SR 2017, SR 2017 over Mill Creek, 20 Union Township, Bridge Replacement 584,000 21 (Base Construction Allocation - 22 $467,000) 23 (Land Allocation - $27,000) 24 (Design and Contingencies - $88,000) 25 (15) SR 4017, SR 4017 Bridge No.2 over 26 Holden Creek, Osceola Township, Bridge 27 Replacement 542,000 28 (Base Construction Allocation - 29 $434,000) 30 (Land Allocation - $27,000) 19970S0186B0698 - 315 -
1 (Design and Contingencies - $81,000) 2 (16) SR 0015, Mill Creek Bridge spanning 3 Tioga Dam Impoundment at Confluence, 4 Two-Lane Bridge Construction 6,875,000 5 (Base Construction Allocation - 6 $6,250,000) 7 (Design and Contingencies - $625,000) 8 (17) PA 249, Bridge over Crooked Creek, 9 Village of Little Marsh, Chatham 10 Township, Bridge Replacement 1,250,000 11 (Base Construction Allocation - 12 $1,000,000) 13 (Land Allocation - $50,000) 14 (Design and Contingencies - $200,000) 15 Section 64. Union County. 16 (a) Local Bridges (Reserved) 17 (b) State Bridges 18 (1) SR 0192, Rapid Run Bridge II over 19 Rapid Run, Lewis Township, Bridge 20 Rehabilitation 250,000 21 (Base Construction Allocation - 22 $200,000) 23 (Land Allocation - $13,000) 24 (Design and Contingencies - $37,000) 25 (2) SR 0192, Rapid Run Bridge I over Rapid 26 Run, Lewis Township, Bridge 27 Rehabilitation 205,000 28 (Base Construction Allocation - 29 $164,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 316 -
1 (Design and Contingencies - $31,000) 2 (3) SR 0044, Bridge over Spring Creek, 3 Bridge Painting 110,000 4 (Base Construction Allocation - 5 $100,000) 6 (Design and Contingencies - $10,000) 7 (4) SR 1004, Bridge over Little Buffalo 8 Creek, Bridge Painting 75,000 9 (Base Construction Allocation - 10 $65,000) 11 (Design and Contingencies - $10,000) 12 (5) SR 1012, Bridge over White Deer Hole 13 Creek, Bridge Painting 160,000 14 (Base Construction Allocation - 15 $150,000) 16 (Design and Contingencies - $10,000) 17 (6) SR 0235, SR 0235 over Laurel Run, 18 Hartley Township, Bridge Replacement 1,118,000 19 (Base Construction Allocation - 20 $894,000) 21 (Land Allocation - $56,000) 22 (Design and Contingencies - $168,000) 23 (7) SR 0235, SR 0235 over Buffalo Creek, 24 Lewis Township, Bridge Replacement 395,000 25 (Base Construction Allocation - 26 $316,000) 27 (Land Allocation - $20,000) 28 (Design and Contingencies - $59,000) 29 (8) US 15, Bridge over White Deer Hole 30 Creek, Village of Allenwood, Gregg 19970S0186B0698 - 317 -
1 Township, Deck Replacement 1,850,000 2 (Base Construction Allocation - 3 $1,500,000) 4 (Land Allocation - $50,000) 5 (Design and Contingencies - $300,000) 6 (9) US 15, Bridge over SR 1004, Village of 7 West Milton, Kelly Township, 8 Superstructure Replacement 2,450,000 9 (Base Construction Allocation - 10 $2,000,000) 11 (Land Allocation - $50,000) 12 (Design and Contingencies - $400,000) 13 (10) US 15, Bridge over White Deer Creek, 14 White Deer Township, Deck Replacement 2,430,000 15 (Base Construction Allocation - 16 $2,000,000) 17 (Land Allocation - $30,000) 18 (Design and Contingencies - $400,000) 19 (11) US 15, Bridge over SR 1010, White 20 Deer Township, Deck Replacement 1,230,000 21 (Base Construction Allocation - 22 $1,000,000) 23 (Land Allocation - $30,000) 24 (Design and Contingencies - $200,000) 25 Section 65. Venango County. 26 (a) Local Bridges 27 (1) Richland Township, T-552 over Mill 28 Creek, Bridge Replacement 475,000 29 (Base Construction Allocation - 30 $355,000) 19970S0186B0698 - 318 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $110,000) 3 (2) Richland Township, T-361 over unnamed 4 tributary of Mill Creek, Bridge 5 Replacement 337,000 6 (Base Construction Allocation - 7 $242,000) 8 (Land Allocation - $10,000) 9 (Design and Contingencies - $85,000) 10 (3) Richland Township, T-377 over Sage 11 Run, Bridge Replacement 385,000 12 (Base Construction Allocation - 13 $290,000) 14 (Land Allocation - $10,000) 15 (Design and Contingencies - $85,000) 16 (4) Pinegrove Township, T-628 over East 17 Sandy Creek, Bridge Replacement 363,000 18 (Base Construction Allocation - 19 $307,000) 20 (Land Allocation - $6,000) 21 (Design and Contingencies - $50,000) 22 (5) Cranberry Township, T-679 over Branch 23 of Sage Run, Bridge Replacement 106,000 24 (Base Construction Allocation - 25 $100,000) 26 (Land Allocation - $1,000) 27 (Design and Contingencies - $5,000) 28 (6) Oakland Township, T-567 over Branch of 29 Two Mile Run, Bridge Replacement 106,000 30 (Base Construction Allocation - 19970S0186B0698 - 319 -
1 $100,000) 2 (Land Allocation - $1,000) 3 (Design and Contingencies - $5,000) 4 (7) Rockland Township, T-512 over East 5 Sandy Creek, Bridge Replacement 360,000 6 (Base Construction Allocation - 7 $300,000) 8 (Land Allocation - $10,000) 9 (Design and Contingencies - $50,000) 10 (8) Pinegrove Township, T-628 over East 11 Sandy Creek, Bridge Replacement 510,000 12 (Base Construction Allocation - 13 $400,000) 14 (Land Allocation - $10,000) 15 (Design and Contingencies - $100,000) 16 (b) State Bridges 17 (1) SR 4001, SR 4001 over Two Mile Run 18 West Branch, Sugarcreek Borough, Bridge 19 Replacement 205,000 20 (Base Construction Allocation - 21 $150,000) 22 (Land Allocation - $5,000) 23 (Design and Contingencies - $50,000) 24 (2) SR 0227, SR 0227 over Cherry Run, 25 Cornplanter Township, Bridge 26 Replacement 280,000 27 (Base Construction Allocation - 28 $200,000) 29 (Land Allocation - $20,000) 30 (Design and Contingencies - $60,000) 19970S0186B0698 - 320 -
1 (3) SR 0322, SR 0322 over Halls Run, 2 Cranberry Township, Bridge Replacement 2,600,000 3 (Base Construction Allocation - 4 $2,000,000) 5 (Land Allocation - $100,000) 6 (Design and Contingencies - $500,000) 7 (4) SR 3009, SR 3009 over I-80, Scrubgrass 8 Township, Bridge Replacement 810,000 9 (Base Construction Allocation - 10 $700,000) 11 (Land Allocation - $10,000) 12 (Design and Contingencies - $100,000) 13 (5) SR 3017, SR 3017 over Warden Run, 14 Canal Township, Bridge Replacement 920,000 15 (Base Construction Allocation - 16 $800,000) 17 (Land Allocation - $20,000) 18 (Design and Contingencies - $100,000) 19 (6) SR 0038, SR 0038 over Pine Run, 20 Richland Township, Bridge 21 Rehabilitation 110,000 22 (Base Construction Allocation - 23 $100,000) 24 (Design and Contingencies - $10,000) 25 (7) SR 3025, SR 3025 over Hays Run, City 26 of Oil City, Bridge Replacement 340,000 27 (Base Construction Allocation - 28 $300,000) 29 (Land Allocation - $5,000) 30 (Design and Contingencies - $35,000) 19970S0186B0698 - 321 -
1 Section 66. Warren County. 2 (a) Local Bridges (Reserved) 3 (b) State Bridges 4 (1) SR 0006, SR 0006 over Wintroth Run, 5 Brokenstraw Township, Bridge 6 Replacement 260,000 7 (Base Construction Allocation - 8 $180,000) 9 (Land Allocation - $20,000) 10 (Design and Contingencies - $60,000) 11 (2) SR 0006, SR 0006 over Six Mile Run, 12 Mead Township, Bridge Replacement 320,000 13 (Base Construction Allocation - 14 $250,000) 15 (Land Allocation - $10,000) 16 (Design and Contingencies - $60,000) 17 (3) SR 0027, SR 0027 over Pine Creek, 18 Southwest Township, Bridge Replacement 800,000 19 (Base Construction Allocation - 20 $580,000) 21 (Land Allocation - $20,000) 22 (Design and Contingencies - $200,000) 23 (4) SR 0027, SR 0027 over Hazeltine Hollow 24 Run, Brokenstraw Township, Bridge 25 Replacement 310,000 26 (Base Construction Allocation - 27 $210,000) 28 (Land Allocation - $20,000) 29 (Design and Contingencies - $80,000) 30 (5) SR 0062, SR 0062 over Bully Run, 19970S0186B0698 - 322 -
1 Watson Township, Bridge Replacement 300,000 2 (Base Construction Allocation - 3 $230,000) 4 (Land Allocation - $20,000) 5 (Design and Contingencies - $50,000) 6 (6) SR 0957, SR 0957 over Little 7 Brokenstraw Creek, Freehold Township, 8 Bridge Replacement 800,000 9 (Base Construction Allocation - 10 $620,000) 11 (Land Allocation - $20,000) 12 (Design and Contingencies - $160,000) 13 (7) SR 3009, SR 3009 over Tidioute Creek, 14 Deerfield Township, Bridge Replacement 470,000 15 (Base Construction Allocation - 16 $400,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $60,000) 19 (8) SR 4013, SR 4013 over Mathews Run, 20 Youngsville Borough, Bridge 21 Replacement 430,000 22 (Base Construction Allocation - 23 $360,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $60,000) 26 (9) SR 4021, SR 4021 over Brands Run, 27 Sugar Grove Borough, Bridge 28 Replacement 240,000 29 (Base Construction Allocation - 30 $180,000) 19970S0186B0698 - 323 -
1 (Land Allocation - $20,000) 2 (Design and Contingencies - $40,000) 3 (10) SR 0027, Bridge over Hazeltine Hollow 4 Run, Brokenstraw Township, Bridge 5 Replacement 500,000 6 (Base Construction Allocation - 7 $450,000) 8 (Design and Contingencies - $50,000) 9 (11) SR 0062, US 62, Bridge over Bully 10 Run, Watson Township, Bridge 11 Replacement 410,000 12 (Base Construction Allocation - 13 $370,000) 14 (Design and Contingencies - $40,000) 15 (12) SR 3009, Tidioute Creek Road Bridge 16 No.5 over Tidioute Creek, Triumph 17 Township, Bridge Replacement 290,000 18 (Base Construction Allocation - 19 $270,000) 20 (Design and Contingencies - $20,000) 21 Section 67. Washington County. 22 (a) Local Bridges 23 (1) Burgettstown Borough, Raccoon Bridge 24 No.23 over Raccoon Creek, Bridge 25 Rehabilitation 433,000 26 (Base Construction Allocation - 27 $313,000) 28 (Land Allocation - $20,000) 29 (Design and Contingencies - $100,000) 30 (2) Chartiers Township, Allison Hollow 19970S0186B0698 - 324 -
1 Road, One-Lane Bridge, Bridge 2 Replacement 195,000 3 (Base Construction Allocation - 4 $150,000) 5 (Land Allocation - $5,000) 6 (Design and Contingencies - $40,000) 7 (3) Chartiers Township, Allison Hollow 8 Road, One-Lane Bridge, Bridge 9 Replacement 195,000 10 (Base Construction Allocation - 11 $150,000) 12 (Land Allocation - $5,000) 13 (Design and Contingencies - $40,000) 14 (4) Chartiers Township, McGovern Road 15 Bridge, Bridge Replacement 145,000 16 (Base Construction Allocation - 17 $100,000) 18 (Land Allocation - $5,000) 19 (Design and Contingencies - $40,000) 20 (5) North Strabane Township, T-643, Galley 21 Road Bridge over Little Chartiers 22 Creek, Bridge Replacement 570,000 23 (Base Construction Allocation - 24 $450,000) 25 (Land Allocation - $20,000) 26 (Design and Contingencies - $100,000) 27 (6) Donegal Township, T-541, Lindsay 28 Bridge over Buck Run, Bridge 29 Replacement 285,000 30 (Base Construction Allocation - 19970S0186B0698 - 325 -
1 $255,000) 2 (Design and Contingencies - $30,000) 3 (7) Donegal Township, T-423, Mays Bridge 4 over Middle Wheeling Creek, Bridge 5 Replacement 245,000 6 (Base Construction Allocation - 7 $215,000) 8 (Design and Contingencies - $30,000) 9 (8) Independence Township, T-649, Cummins 10 Bridge over Sugar Camp Run, Bridge 11 Replacement 330,000 12 (Base Construction Allocation - 13 $300,000) 14 (Design and Contingencies - $30,000) 15 (9) Mount Pleasant Township, T-749, Sabo 16 Road over Westland Run, Bridge 17 Replacement 25,000 18 (Base Construction Allocation - 19 $20,000) 20 (Design and Contingencies - $5,000) 21 (10) Mount Pleasant Township, T-606, 22 Primrose Road over Millers Run, Bridge 23 Replacement 25,000 24 (Base Construction Allocation - 25 $20,000) 26 (Design and Contingencies - $5,000) 27 (11) Mount Pleasant Township, T-493, 28 Meriage Street over Robinson Run 29 Tributary, Bridge Replacement 25,000 30 (Base Construction Allocation - 19970S0186B0698 - 326 -
1 $20,000) 2 (Design and Contingencies - $5,000) 3 (12) North Bethlehem Township, T-445, 4 Dague Bridge over Pigeon Creek, Bridge 5 Replacement 250,000 6 (Base Construction Allocation - 7 $220,000) 8 (Design and Contingencies - $30,000) 9 (13) North Franklin Township, T-526, Cario 10 Drive over Unnamed Tributary of Catfish 11 Creek, Bridge Replacement 46,000 12 (Base Construction Allocation - 13 $42,000) 14 (Design and Contingencies - $4,000) 15 (14) Nottingham Township, T-782, Sundust 16 Road Culvert, 35 Feet North of 17 Intersection with SR 1059, Bridge 18 Replacement 101,000 19 (Base Construction Allocation - 20 $91,000) 21 (Design and Contingencies - $10,000) 22 (15) Nottingham Township, T-828, Barr 23 Bridge over Mingo Creek, Bridge 24 Replacement 350,000 25 (Base Construction Allocation - 26 $310,000) 27 (Design and Contingencies - $40,000) 28 (16) Robinson Township, T-500, Chamberlain 29 Bridge over Chamberlain Run, Bridge 30 Replacement 285,000 19970S0186B0698 - 327 -
1 (Base Construction Allocation - 2 $255,000) 3 (Design and Contingencies - $30,000) 4 (17) Smith Township, T-843, Dunbar Bridge 5 over Raccoon Creek, Bridge Replacement 285,000 6 (Base Construction Allocation - 7 $255,000) 8 (Design and Contingencies - $30,000) 9 (18) City of Washington, Hanna Street 10 Bridge over Catfish Creek, Bridge 11 Replacement 40,000 12 (Base Construction Allocation - 13 $30,000) 14 (Design and Contingencies - $10,000) 15 (19) City of Washington, Rosewood Avenue 16 Bridge over Catfish Creek, Bridge 17 Replacement 40,000 18 (Base Construction Allocation - 19 $30,000) 20 (Design and Contingencies - $10,000) 21 (20) West Pike Run Township, T-840, Suzy 22 Lane over Pike Run Creek, Bridge 23 Replacement 230,000 24 (Base Construction Allocation - 25 $210,000) 26 (Design and Contingencies - $20,000) 27 (21) California Borough, Daisytown Bridge 28 over Pike Run, Bridge Replacement 925,000 29 (Base Construction Allocation - 30 $700,000) 19970S0186B0698 - 328 -
1 (Land Allocation - $50,000) 2 (Design and Contingencies - $175,000) 3 (22) Coal Center Borough, Water Street 4 Bridge over Pike Run, Bridge 5 Replacement 1,588,000 6 (Base Construction Allocation - 7 $1,288,000) 8 (Land Allocation - $50,000) 9 (Design and Contingencies - $250,000) 10 (23) West Pike Run Township, T-948 over 11 Pike Run, Bridge Replacement 1,075,000 12 (Base Construction Allocation - 13 $850,000) 14 (Land Allocation - $50,0000) 15 (Design and Contingencies - $175,000) 16 (24) Midway Borough, North Avenue over 17 Robinson Run Creek, Bridge Replacement 95,000 18 (Base Construction Allocation - 19 $55,000) 20 (Land Allocation - $20,000) 21 (Design and Contingencies - $20,000) 22 (25) Canonsburg Borough, Adams Street over 23 Brush Run, Bridge Replacement 176,000 24 (Base Construction Allocation - 25 $150,000) 26 (Land Allocation - $1,000) 27 (Design and Contingencies - $25,000) 28 (26) East Finley Township, T-375, County 29 Bridge No. 32 over Templeton Fork, 30 Bridge Replacement 355,000 19970S0186B0698 - 329 -
1 (Base Construction Allocation - 2 $300,000) 3 (Land Allocation - $5,000) 4 (Design and Contingencies - $50,000) 5 (b) State Bridges 6 (1) SR 0018, Bridge over Abandoned 7 Railroad, City of Washington, Bridge 8 Replacement 650,000 9 (Base Construction Allocation - 10 $500,000) 11 (Land Allocation - $25,000) 12 (Design and Contingencies - $125,000) 13 (2) SR 0019, Bridge over Chartiers Creek, 14 North Strabane and Peters Townships, 15 Bridge Painting 161,000 16 (Base Construction Allocation - 17 $156,000) 18 (Design and Contingencies - $5,000) 19 (3) SR 0070, I-70 Westbound Bridge over SR 20 3009, Buffalo Township, Bridge 21 Painting 148,000 22 (Base Construction Allocation - 23 $143,000) 24 (Design and Contingencies - $5,000) 25 (4) SR 0070, I-70 Eastbound Bridge over SR 26 3009, Buffalo Township, Bridge 27 Painting 163,000 28 (Base Construction Allocation - 29 $158,000) 30 (Design and Contingencies - $5,000) 19970S0186B0698 - 330 -
1 (5) SR 0070, I-70 Bridge over 8th Street, 2 Donegal Township, Bridge Replacement 2,486,000 3 (Base Construction Allocation - 4 $2,211,000) 5 (Land Allocation - $25,000) 6 (Design and Contingencies - $250,000) 7 (6) SR 0070, I-70 Bridge over Turnback 8 Road, South Strabane Township, Bridge 9 Rehabilitation 990,000 10 (Base Construction Allocation - 11 $750,000) 12 (Land Allocation - $40,000) 13 (Design and Contingencies - $200,000) 14 (7) SR 0070, I-70 Bridge over SR 0519, 15 Somerset Township, Bridge 16 Rehabilitation 2,000,000 17 (Base Construction Allocation - 18 $1,720,000) 19 (Land Allocation - $40,000) 20 (Design and Contingencies - $240,000) 21 (8) SR 0070, I-70 Bridge over SR 2017, 22 Somerset Township, Bridge 23 Rehabilitation 1,105,000 24 (Base Construction Allocation - 25 $865,000) 26 (Land Allocation - $40,000) 27 (Design and Contingencies - $200,000) 28 (9) SR 0088, Charleroi Bridge over Maple 29 Creek, Charleroi and Speers Boroughs, 30 Bridge Replacement 725,000 19970S0186B0698 - 331 -
1 (Base Construction Allocation - 2 $500,000) 3 (Land Allocation - $25,000) 4 (Design and Contingencies - $200,000) 5 (10) SR 0088, Bridge over Peters Creek, 6 Finleyville Borough, Bridge Painting 65,000 7 (Base Construction Allocation - 8 $65,000) 9 (11) SR 0917, Pigeon Creek Bridge over 10 Branch of Pigeon Creek, Bentleyville 11 Borough, Bridge Replacement 570,000 12 (Base Construction Allocation - 13 $370,000) 14 (Land Allocation - $25,000) 15 (Design and Contingencies - $175,000) 16 (12) SR 1005, Bridge over Millers Run, 17 Cecil Township, Bridge Painting 75,000 18 (Base Construction Allocation - 19 $75,000) 20 (13) SR 1022, Donora Webster Bridge over 21 Monongahela River and Conrail, Donora 22 Borough, Bridge Replacement 20,000,000 23 (Base Construction Allocation - 24 $15,000,000) 25 (Land Allocation - $3,000,000) 26 (Design and Contingencies - $2,000,000) 27 (14) SR 1077, Donora-Monessen Bridge over 28 Monongahela River, PA 837 and 906 and 29 Railroad, Donora Borough, Bridge 30 Painting 1,000,000 19970S0186B0698 - 332 -
1 (Base Construction Allocation - 2 $1,000,000) 3 (15) SR 2005, Sowers Run Bridge over 4 Sowers Run, Amwell Township, Bridge 5 Replacement 435,000 6 (Base Construction Allocation - 7 $235,000) 8 (Land Allocation - $25,000) 9 (Design and Contingencies - $175,000) 10 (16) SR 2011, Bridge over Branch of Little 11 Tenmile Creek, West Bethlehem Township, 12 Bridge Replacement 460,000 13 (Base Construction Allocation - 14 $260,000) 15 (Land Allocation - $25,000) 16 (Design and Contingencies - $175,000) 17 (17) SR 2030, Gorby's Bridge II over Gorby 18 Run, California Borough, Bridge 19 Rehabilitation 300,000 20 (Base Construction Allocation - 21 $300,000) 22 (18) SR 2037, Maple Creek Bridge over 23 Branch of Maple Creek, Fallowfield 24 Township, Bridge Replacement 486,000 25 (Base Construction Allocation - 26 $286,000) 27 (Land Allocation - $25,000) 28 (Design and Contingencies - $175,000) 29 (19) SR 3009, Buffalo Arch Bridge over 30 Branch of Buffalo Creek and Railroad, 19970S0186B0698 - 333 -
1 Buffalo Township, Bridge Replacement 535,000 2 (Base Construction Allocation - 3 $300,000) 4 (Land Allocation - $10,000) 5 (Design and Contingencies - $225,000) 6 (20) SR 4015, Bridge over Cherry Run, 7 Mount Pleasant Township, Bridge 8 Painting 53,000 9 (Base Construction Allocation - 10 $51,000) 11 (Design and Contingencies - $2,000) 12 (21) SR 4022, Chartiers Creek Bridge No.2 13 over Branch of Chartiers Creek, Canton 14 Township, Bridge Replacement 415,000 15 (Base Construction Allocation - 16 $215,000) 17 (Land Allocation - $25,000) 18 (Design and Contingencies - $175,000) 19 (22) SR 4022, Chartiers Creek Bridge No.1 20 over Branch of Chartiers Creek, Canton 21 Township, Bridge Replacement 405,000 22 (Base Construction Allocation - 23 $205,000) 24 (Land Allocation - $25,000) 25 (Design and Contingencies - $175,000) 26 (23) SR 2034, SR 2034 over Branch of Pike 27 Run, West Pike Run Township, Bridge 28 Replacement 438,000 29 (Base Construction Allocation - 30 $313,000) 19970S0186B0698 - 334 -
1 (Land Allocation - $25,000) 2 (Design and Contingencies - $100,000) 3 (24) SR 2079, SR 2079 over Pike Run, West 4 Pike Run Township, Bridge Replacement 988,000 5 (Base Construction Allocation - 6 $788,000) 7 (Land Allocation - $50,000) 8 (Design and Contingencies - $150,000) 9 (25) SR 2030, Bridge No.1 over Gorby Run, 10 California Borough, Bridge Replacement 430,000 11 (Base Construction Allocation - 12 $330,000) 13 (Design and Contingencies - $100,000) 14 Section 68. Wayne County. 15 (a) Local Bridges 16 (1) Honesdale Borough, Old Willow Avenue, 17 Bridge over Corley Brook at 18 Intersection of TR 6, Bridge 19 Replacement 410,000 20 (Base Construction Allocation - 21 $350,000) 22 (Land Allocation - $10,000) 23 (Design and Contingencies - $50,000) 24 (b) State Bridges 25 (1) SR 0371, Cochecton Bridge No.6 over 26 Delaware River, Damascus Township, 27 Bridge Rehabilitation 1,050,000 28 (Base Construction Allocation - 29 $950,000) 30 (Design and Contingencies - $100,000) 19970S0186B0698 - 335 -
1 (2) SR 0380, I-380 Bridge over Lehigh 2 River, Lehigh Township, Bridge 3 Rehabilitation 284,000 4 (Base Construction Allocation - 5 $244,000) 6 (Design and Contingencies - $40,000) 7 (3) SR 4009, Quarry Bridge over Dyberry 8 Creek, Dyberry Township, Bridge 9 Replacement 660,000 10 (Base Construction Allocation - 11 $500,000) 12 (Land Allocation - $10,000) 13 (Design and Contingencies - $150,000) 14 (4) SR 0371, Bridge No.6, Damascus 15 Township, Bridge Painting 2,200,000 16 (Base Construction Allocation - 17 $2,000,000) 18 (Design and Contingencies - $200,000) 19 (5) SR 1020, Bridge No.7 over Delaware 20 River, Damascus Township, Bridge 21 Painting 3,300,000 22 (Base Construction Allocation - 23 $3,000,000) 24 (Design and Contingencies - $300,000) 25 (6) SR 1004, Bridge over Outlet of Beach 26 Lake, Intersection of SR 1011, Berlin 27 Township, Bridge Replacement 345,000 28 (Base Construction Allocation - 29 $265,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 336 -
1 (Design and Contingencies - $70,000) 2 (7) SR 3028, Bridge over TR 191, East of 3 SR 3031, Cherry Ridge Township, Bridge 4 Replacement 450,000 5 (Base Construction Allocation - 6 $350,000) 7 (Land Allocation - $10,000) 8 (Design and Contingencies - $90,000) 9 (8) State Bridges, Countywide Bridge Zone 10 Painting, Bridge Painting 370,000 11 (Base Construction Allocation - 12 $350,000) 13 (Land Allocation - $10,000) 14 (Design and Contingencies - $10,000) 15 (9) SR 1004, SR 1004 over Outlet of Beach 16 Lake, Berlin Township, Bridge 17 Replacement 260,000 18 (Base Construction Allocation - 19 $220,000) 20 (Land Allocation - $10,000) 21 (Design and Contingencies - $30,000) 22 (10) SR 3028, SR 3028 over TR 191, Cherry 23 Ridge Township, Bridge Replacement 400,000 24 (Base Construction Allocation - 25 $340,000) 26 (Land Allocation - $10,000) 27 (Design and Contingencies - $50,000) 28 (11) SR 0371, Bridge No.1 over Dyberry 29 Creek at Junction of SR 1023, Lebanon 30 Township, Bridge Replacement 400,000 19970S0186B0698 - 337 -
1 (Base Construction Allocation - 2 $340,000) 3 (Land Allocation - $10,000) 4 (Design and Contingencies - $50,000) 5 (12) SR 0371, Bridge No.5 over Beaver Dam 6 Creek, 0.1 Mile West of SR 1031, 7 Damascus Township, Bridge Replacement 470,000 8 (Base Construction Allocation - 9 $400,000) 10 (Land Allocation - $10,000) 11 (Design and Contingencies - $60,000) 12 (13) SR 3006, Bridge No.3 over Ariel 13 Creek, 0.6 Mile North of SR 3008, Salem 14 Township, Bridge Replacement 470,000 15 (Base Construction Allocation - 16 $400,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $60,000) 19 (14) SR 4014, Bridge No.4 over Balls 20 Creek, 0.5 Mile East of SR 4037, Scott 21 Township, Bridge Replacement 380,000 22 (Base Construction Allocation - 23 $320,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $50,000) 26 (15) SR 0348, Bridge over Jones Creek, 0.1 27 Mile West of SR 3019, Salem Township, 28 Bridge Replacement 470,000 29 (Base Construction Allocation - 30 $400,000) 19970S0186B0698 - 338 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $60,000) 3 (16) SR 4043, Bridge over Branch of Oquaga 4 Creek, 1.5 Miles West of SR 4037, Scott 5 Township, Bridge Replacement 240,000 6 (Base Construction Allocation - 7 $200,000) 8 (Land Allocation - $10,000) 9 (Design and Contingencies - $30,000) 10 (17) SR 1007, Bridge over Branch of Boyd's 11 Creek, 0.5 Mile East of SR 1019, 12 Damascus Township, Bridge Replacement 310,000 13 (Base Construction Allocation - 14 $260,000) 15 (Land Allocation - $10,000) 16 (Design and Contingencies - $40,000) 17 Section 69. Westmoreland County. 18 (a) Local Bridges 19 (1) Hempfield Township, Airport Hill Road 20 Bridge over Slate Creek, Bridge 21 Replacement 350,000 22 (Base Construction Allocation - 23 $280,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $60,000) 26 (2) Hempfield Township, Sweitzer Road 27 Bridge over Sewickley Creek, Bridge 28 Replacement 975,000 29 (Base Construction Allocation - 30 $800,000) 19970S0186B0698 - 339 -
1 (Land Allocation - $15,000) 2 (Design and Contingencies - $160,000) 3 (3) Hempfield Township, Ladysmith Road 4 Bridge over Little Sewickley Creek, 5 Bridge Replacement 610,000 <-- 6 (Base Construction Allocation - 7 $500,000) 8 (Land Allocation - $10,000) 9 (Design and Contingencies - $100,000) 10 BRIDGE REPLACEMENT 813,000 <-- 11 (BASE CONSTRUCTION ALLOCATION - 12 $613,000) 13 (LAND ALLOCATION - $50,000) 14 (DESIGN AND CONTINGENCIES - $150,000) 15 (4) Hempfield Township, Old Route 30 16 Bridge over Slate Creek, Bridge 17 Replacement 370,000 18 (Base Construction Allocation - 19 $300,000) 20 (Land Allocation - $10,000) 21 (Design and Contingencies - $60,000) 22 (5) Hempfield Township, Old Route 119 23 Bridge over Tributary of Jacks Run, 24 Bridge Replacement 400,000 <-- 25 (Base Construction Allocation - 26 $280,000) 27 (Land Allocation - $20,000) 28 (Design and Contingencies - $100,000) 29 BRIDGE REPLACEMENT 428,000 <-- 30 (BASE CONSTRUCTION ALLOCATION - 19970S0186B0698 - 340 -
1 $288,000) 2 (LAND ALLOCATION - $15,000) 3 (DESIGN AND CONTINGENCIES - $125,000) 4 (6) Jeanette City, 6th Street Bridge over 5 Brush Creek, Bridge Replacement 460,000 6 (Base Construction Allocation - 7 $340,000) 8 (Land Allocation - $20,000) 9 (Design and Contingencies - $100,000) 10 (7) Ligonier Township, T-605 Bridge over 11 Two Mile Run, Bridge Replacement 320,000 12 (Base Construction Allocation - 13 $200,000) 14 (Land Allocation - $20,000) 15 (Design and Contingencies - $100,000) 16 (8) Ligonier Township, T-617, Bridge over 17 Mill Run, Bridge Replacement 310,000 18 (Base Construction Allocation - 19 $190,000) 20 (Land Allocation - $20,000) 21 (Design and Contingencies - $100,000) 22 (9) Hempfield Township, Possum Hollow Road 23 Bridge over Tributary of Little 24 Sewickley Creek, Bridge Replacement 300,000 <-- 25 (Base Construction Allocation - 26 $180,000) 27 (Land Allocation - $20,000) 28 (Design and Contingencies - $100,000) 29 SEWICKLEY CREEK, BRIDGE REPLACEMENT 428,000 <-- 30 (BASE CONSTRUCTION ALLOCATION - 19970S0186B0698 - 341 -
1 $288,000) 2 (LAND ALLOCATION - $15,000) 3 (DESIGN AND CONTINGENCIES - $125,000) 4 (10) South Huntington Township, T-390, 5 Williams Road Bridge, Bridge 6 Replacement 125,000 7 (Base Construction Allocation - 8 $100,000) 9 (Land Allocation - $5,000) 10 (Design and Contingencies - $20,000) 11 (11) South Huntington Township, T-562, 12 J.D. Smith Road Bridge, Bridge 13 Replacement 155,000 14 (Base Construction Allocation - 15 $125,000) 16 (Land Allocation - $5,000) 17 (Design and Contingencies - $25,000) 18 (12) South Huntington Township, T-386, 19 Bridge No. 1, Mount Etna Road Bridge, 20 Bridge Replacement 145,000 21 (Base Construction Allocation - 22 $115,000) 23 (Land Allocation - $5,000) 24 (Design and Contingencies - $25,000) 25 (13) South Huntington Township, T-386, 26 Bridge No.2, Mount Etna Road at Remo 27 Road, Bridge Replacement 135,000 28 (Base Construction Allocation - 29 $110,000) 30 (Land Allocation - $5,000) 19970S0186B0698 - 342 -
1 (Design and Contingencies - $20,000) 2 (14) South Huntington Township, T-385, 3 Commer Road Bridge, Bridge Replacement 150,000 4 (Base Construction Allocation - 5 $120,000) 6 (Land Allocation - $5,000) 7 (Design and Contingencies - $25,000) 8 (15) Washington Township, T-979, Pleasant 9 View Road Bridge over Beaver Run, 10 Bridge Replacement 385,000 11 (Base Construction Allocation - 12 $265,000) 13 (Land Allocation - $20,000) 14 (Design and Contingencies - $100,000) 15 (16) Derry Township, T-924, Bridge over 16 Union Run, Bridge Replacement 578,000 17 (Base Construction Allocation - 18 $463,000) 19 (Land Allocation - $15,000) 20 (Design and Contingencies - $100,000) 21 (17) Derry Township, T-937, Bridge over 22 Stony Run, Bridge Replacement 553,000 23 (Base Construction Allocation - 24 $438,000) 25 (Land Allocation - $15,000) 26 (Design and Contingencies - $100,000) 27 (18) Derry Township, T-941, Bridge over 28 Stony Run, Bridge Replacement 590,000 29 (Base Construction Allocation - 30 $475,000) 19970S0186B0698 - 343 -
1 (Land Allocation - $15,000) 2 (Design and Contingencies - $100,000) 3 (19) Donegal Township, T-916, Bridge over 4 Indian Creek, Bridge Replacement 465,000 5 (Base Construction Allocation - 6 $350,000) 7 (Land Allocation - $15,000) 8 (Design and Contingencies - $100,000) 9 (20) Donegal Township, T-880, Bridge over 10 Four Mile Run, Bridge No.3, Bridge 11 Replacement 415,000 12 (Base Construction Allocation - 13 $300,000) 14 (Land Allocation - $15,000) 15 (Design and Contingencies - $100,000) 16 (21) Donegal Township, T-880, Bridge over 17 Four Mile Run, Bridge No.5, Bridge 18 Replacement 415,000 19 (Base Construction Allocation - 20 $300,000) 21 (Land Allocation - $15,000) 22 (Design and Contingencies - $100,000) 23 (22) Fairfield Township, T-739, Berkey's 24 Bridge over Unnamed Tributary, Bridge 25 Replacement 200,000 26 (Base Construction Allocation - 27 $170,000) 28 (Land Allocation - $10,000) 29 (Design and Contingencies - $20,000) 30 (23) Fairfield Township, T-847, Bailey's 19970S0186B0698 - 344 -
1 Bridge over Hendricks Run, Bridge 2 Replacement 200,000 3 (Base Construction Allocation - 4 $170,000) 5 (Land Allocation - $10,000) 6 (Design and Contingencies - $20,000) 7 (24) Fairfield Township, T-847, Toby 8 Bridge over Unnamed Tributary, Bridge 9 Replacement 200,000 10 (Base Construction Allocation - 11 $170,000) 12 (Land Allocation - $10,000) 13 (Design and Contingencies - $20,000) 14 (25) Fairfield Township, T-931, Patterson 15 Bridge No.1 over Bear Pond Run, Bridge 16 Replacement 200,000 17 (Base Construction Allocation - 18 $170,000) 19 (Land Allocation - $10,000) 20 (Design and Contingencies - $20,000) 21 (26) Fairfield Township, T-984, Love 22 Hollow Bridge No.1 over Hendricks Run, 23 Bridge Replacement 200,000 24 (Base Construction Allocation - 25 $170,000) 26 (Land Allocation - $10,000) 27 (Design and Contingencies - $20,000) 28 (27) Fairfield Township, T-984, Love 29 Hollow Bridge No.2 over Hendricks Run, 30 Bridge Replacement 200,000 19970S0186B0698 - 345 -
1 (Base Construction Allocation - 2 $170,000) 3 (Land Allocation - $10,000) 4 (Design and Contingencies - $20,000) 5 (28) Fairfield Township, T-988, Yeager 6 Hollow Bridge No.1 over Unnamed 7 Tributary, Bridge Replacement 200,000 8 (Base Construction Allocation - 9 $170,000) 10 (Land Allocation - $10,000) 11 (Design and Contingencies - $20,000) 12 (29) Fairfield Township, T-988, Yeager 13 Hollow Bridge No.2 over Unnamed 14 Tributary, Bridge Replacement 200,000 15 (Base Construction Allocation - 16 $170,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $20,000) 19 (30) Fairfield Township, T-990, Patterson 20 Bridge No.2 over Unnamed Tributary, 21 Bridge Replacement 200,000 22 (Base Construction Allocation - 23 $170,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $20,000) 26 (31) Ligonier Township, T-505, Horner Hill 27 Road over Laughlintown Run, Bridge 28 Replacement 175,000 29 (Base Construction Allocation - 30 $125,000) 19970S0186B0698 - 346 -
1 (Land Allocation - $15,000) 2 (Design and Contingencies - $35,000) 3 (32) Ligonier Township, T-607, Weller Road 4 over Unnamed Stream, Bridge 5 Replacement 10,000 6 (Base Construction Allocation - $8,000) 7 (Design and Contingencies - $2,000) 8 (33) Ligonier Township, T-617, Robb Road 9 over Hannas Run, Bridge Replacement 310,000 10 (Base Construction Allocation - 11 $250,000) 12 (Land Allocation - $10,000) 13 (Design and Contingencies - $50,000) 14 (34) Ligonier Township, T-719, Peoples 15 Road over Unnamed Stream, Bridge 16 Replacement 100,000 17 (Base Construction Allocation - 18 $75,000) 19 (Land Allocation - $5,000) 20 (Design and Contingencies - $20,000) 21 (35) Ligonier Township, T-721, Bridge over 22 North Fork of Trout Run, Bridge 23 Replacement 200,000 24 (Base Construction Allocation - 25 $125,000) 26 (Land Allocation - $10,000) 27 (Design and Contingencies - $65,000) 28 (36) Ligonier Township, T-942, Zion Church 29 Road over Unnamed Stream, Bridge 30 Replacement 50,000 19970S0186B0698 - 347 -
1 (Base Construction Allocation - 2 $35,000) 3 (Land Allocation - $5,000) 4 (Design and Contingencies - $10,000) 5 (37) Ligonier Township, T-984, Mill Road 6 over Mill Race, Bridge Replacement 50,000 7 (Base Construction Allocation - 8 $35,000) 9 (Land Allocation - $5,000) 10 (Design and Contingencies - $10,000) 11 (38) Ligonier Township, T-950, Old Lincoln 12 Highway East over Unnamed Stream, 13 Bridge Rehabilitation 25,000 14 (Base Construction Allocation - 15 $20,000) 16 (Design and Contingencies - $5,000) 17 (39) Ligonier Township, T-984, Harvey Road 18 over Macks Run, Bridge Rehabilitation 5,000 19 (Base Construction Allocation - $4,000) 20 (Design and Contingencies - $1,000) 21 (40) Saint Clair Township, T-994, Bridge 22 over Tubmill Creek, Bridge Replacement 440,000 23 (Base Construction Allocation - 24 $325,000) 25 (Land Allocation - $15,000) 26 (Design and Contingencies - $100,000) 27 (41) Sewickley Township, T-318, Bridge 28 No.3 over Tributary of Youghiogheny 29 River, Bridge Replacement 100,000 30 (Base Construction Allocation - 19970S0186B0698 - 348 -
1 $70,000) 2 (Land Allocation - $5,000) 3 (Design and Contingencies - $25,000) 4 (42) Derry Township, Conrail Overpass over 5 SR 0981, Bridge Replacement 1,600,000 6 (Base Construction Allocation - 7 $1,200,000) 8 (Land Allocation - $200,000) 9 (Design and Contingencies - $200,000) 10 (43) Hempfield Township, T-399 over Jacks 11 Run, Bridge Replacement 428,000 12 (Base Construction Allocation - 13 $288,000) 14 (Land Allocation - $15,000) 15 (Design and Contingencies - $125,000) 16 (44) Hempfield Township, T-550 over 17 Tributary to Little Sewickley Creek, 18 Bridge Replacement 428,000 19 (Base Construction Allocation - 20 $288,000) 21 (Land Allocation - $15,000) 22 (Design and Contingencies - $125,000) 23 (45) Ligonier Township, T-984 over Mill 24 Creek, Bridge Replacement 650,000 25 (Base Construction Allocation - 26 $450,000) 27 (Land Allocation - $50,000) 28 (Design and Contingencies - $150,000) 29 (46) Salem Township, T-881, Bridge over 30 Loyalhanna Creek, Bridge Replacement 81,000 19970S0186B0698 - 349 -
1 (Base Construction Allocation - 2 $67,000) 3 (Design and Contingencies - $14,000) 4 (47) SEWICKLEY TOWNSHIP, T-633, GREEN <-- 5 HILLS ROAD BRIDGE OVER LITTLE SEWICKLEY 6 CREEK, BRIDGE REPLACEMENT 465,000 7 (BASE CONSTRUCTION ALLOCATION - 8 $325,000) 9 (LAND ALLOCATION - $15,000) 10 (DESIGN AND CONTINGENCIES - $125,000) 11 (b) State Bridges 12 (1) SR 0030, Mill Creek Bridge over Mill 13 Creek, Ligonier Township, Bridge 14 Replacement 910,000 15 (Base Construction Allocation - 16 $710,000) 17 (Land Allocation - $25,000) 18 (Design and Contingencies - $175,000) 19 (2) SR 0031, Jacobs Creek Bridge over 20 Jacobs Creek, Mount Pleasant and 21 Bullskin Townships, Bridge Replacement 715,000 22 (Base Construction Allocation - 23 $500,000) 24 (Land Allocation - $40,000) 25 (Design and Contingencies - $175,000) 26 (3) SR0056, Seward Bridge over Conrail and 27 Local Road, St. Clair Township, Bridge 28 Painting 600,000 29 (Base Construction Allocation - 30 $600,000) 19970S0186B0698 - 350 -
1 (4) SR 0070, I-70 Bridge over N&W 2 Railroad, Rostraver Township, Bridge 3 Rehabilitation 1,565,000 4 (Base Construction Allocation - 5 $1,305,000) 6 (Land Allocation - $60,000) 7 (Design and Contingencies - $200,000) 8 (5) SR 0070, I-70 Bridge over Conrail, 9 South Huntington Township, Bridge 10 Rehabilitation 3,125,000 11 (Base Construction Allocation - 12 $2,780,000) 13 (Land Allocation - $45,000) 14 (Design and Contingencies - $300,000) 15 (6) SR 0119, Crabtree Creek Bridge No.2 16 over Crabtree Creek, Hempfield 17 Township, Bridge Replacement 577,000 18 (Base Construction Allocation - 19 $377,000) 20 (Land Allocation - $25,000) 21 (Design and Contingencies - $175,000) 22 (7) SR 0136, West Newton Bridge over 23 Youghiogheny River, West Newton 24 Borough, Bridge Painting 250,000 25 (Base Construction Allocation - 26 $250,000) 27 (8) SR 0259, Boliver Underpass Conrail 28 Railroad over SR 0259, Fairfield 29 Township, Bridge Replacement 310,000 30 (Base Construction Allocation - 19970S0186B0698 - 351 -
1 $200,000) 2 (Land Allocation - $10,000) 3 (Design and Contingencies - $100,000) 4 (9) SR 0271, Bridge over Mill Creek, 5 Ligonier Township, Bridge Painting 87,000 6 (Base Construction Allocation - 7 $87,000) 8 (10) SR 0711, Bridge over Mill Creek, 9 Ligonier Township, Bridge Painting 125,000 10 (Base Construction Allocation - 11 $125,000) 12 (11) SR 0819, Bridge over Stauffer Bridge, 13 Scottdale Borough, Bridge Painting 92,000 14 (Base Construction Allocation - 15 $92,000) 16 (12) SR 0981, Bridge over Branch of Barron 17 Run, South Huntington Township, Bridge 18 Replacement 250,000 19 (Base Construction Allocation - 20 $250,000) 21 (13) SR 0982, Bradenville Bridge over 22 Saxman Run, Derry Township, Bridge 23 Replacement 330,000 24 (Base Construction Allocation - 25 $330,000) 26 (14) SR 1027, Stoney Run Bridge over 27 Stoney Run, Derry Township, Bridge 28 Replacement 340,000 29 (Base Construction Allocation - 30 $255,000) 19970S0186B0698 - 352 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $75,000) 3 (15) SR 2008, Fourmile Run Bridge over 4 Fourmile Run, Cook Township, Bridge 5 Painting 83,000 6 (Base Construction Allocation - 7 $83,000) 8 (16) SR 2010, Bridge over Branch of Boyer 9 Run, Mount Pleasant Township, Bridge 10 Replacement 450,000 11 (Base Construction Allocation - 12 $250,000) 13 (Land Allocation - $25,000) 14 (Design and Contingencies - $175,000) 15 (17) SR 8036, New Stanton Ramp Bridge over 16 SR 3091, New Stanton Borough, Bridge 17 Rehabilitation 475,000 18 (Base Construction Allocation - 19 $395,000) 20 (Design and Contingencies - $80,000) 21 (18) SR 0030, SR 0030 over Mill Creek, 22 Ligonier Township, Bridge 23 Rehabilitation 200,000 24 (Base Construction Allocation - 25 $150,000) 26 (Design and Contingencies - $50,000) 27 (19) SR 0030, SR 0030 over Branch of 28 Loyalhanna Creek, Unity Township, 29 Bridge Replacement 245,000 30 (Base Construction Allocation - 19970S0186B0698 - 353 -
1 $125,000) 2 (Land Allocation - $20,000) 3 (Design and Contingencies - $100,000) 4 (20) SR 0217, SR 0217 over Miller Run, 5 Derry Township, Bridge Replacement 293,000 6 (Base Construction Allocation - 7 $188,000) 8 (Land Allocation - $5,000) 9 (Design and Contingencies - $100,000) 10 (21) SR 0259, SR 0259 over Branch of 11 Freeman Run, Fairfield Township, Bridge 12 Replacement 218,000 13 (Base Construction Allocation - 14 $113,000) 15 (Land Allocation - $5,000) 16 (Design and Contingencies - $100,000) 17 (22) SR 0381, SR 0381 over Branch of 18 Loyalhanna Creek, Cook Township, Bridge 19 Replacement 670,000 20 (Base Construction Allocation - 21 $450,000) 22 (Land Allocation - $20,000) 23 (Design and Contingencies - $200,000) 24 (23) SR 0381, SR 0381 over Camp Run, 25 Donegal Township, Bridge Replacement 608,000 26 (Base Construction Allocation - 27 $388,000) 28 (Land Allocation - $20,000) 29 (Design and Contingencies - $200,000) 30 (24) SR 0711, SR 0711 over Mill Creek, 19970S0186B0698 - 354 -
1 Ligonier Township, Bridge Replacement 600,000 2 (Base Construction Allocation - 3 $450,000) 4 (Land Allocation - $50,000) 5 (Design and Contingencies - $100,000) 6 (25) SR 0982, SR 0982 over Jacobs Creek, 7 Mount Pleasant Township, Bridge 8 Replacement 938,000 9 (Base Construction Allocation - 10 $688,000) 11 (Land Allocation - $50,000) 12 (Design and Contingencies - $200,000) 13 (26) SR 0982, SR 0982 over Nine Mile Run, 14 Unity Township, Bridge Replacement 348,000 15 (Base Construction Allocation - 16 $238,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $100,000) 19 (27) SR 0982, SR 0982 over Indian Camp 20 Run, Unity Township, Bridge 21 Replacement 335,000 22 (Base Construction Allocation - 23 $225,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $100,000) 26 (28) SR 1004, SR 1004 over Hendricks 27 Creek, Fairfield Township, Bridge 28 Replacement 200,000 29 (Base Construction Allocation - 30 $170,000) 19970S0186B0698 - 355 -
1 (Land Allocation - $10,000) 2 (Design and Contingencies - $20,000) 3 (29) SR 1006, SR 1006 over Freeman Run, 4 Fairfield Township, Bridge Replacement 833,000 5 (Base Construction Allocation - 6 $613,000) 7 (Land Allocation - $20,000) 8 (Design and Contingencies - $200,000) 9 (30) SR 1006, West Bolivar Bridge near 10 Treasure Island, Fairfield Township, 11 Bridge Replacement 200,000 12 (Base Construction Allocation - 13 $170,000) 14 (Land Allocation - $10,000) 15 (Design and Contingencies - $20,000) 16 (31) SR 1007, SR 1007 over Tubmill Run, 17 Fairfield Township, Bridge Replacement 465,000 18 (Base Construction Allocation - 19 $350,000) 20 (Land Allocation - $15,000) 21 (Design and Contingencies - $100,000) 22 (32) SR 1012, SR 1012 over Branch of Megee 23 Run, Derry Township, Bridge 24 Replacement 318,000 25 (Base Construction Allocation - 26 $213,000) 27 (Land Allocation - $5,000) 28 (Design and Contingencies - $100,000) 29 (33) SR 1014, SR 1014 over Abandoned 30 Railroad, Derry Township, Bridge 19970S0186B0698 - 356 -
1 Replacement 268,000 2 (Base Construction Allocation - 3 $163,000) 4 (Land Allocation - $5,000) 5 (Design and Contingencies - $100,000) 6 (34) SR 1015, SR 1015 over Hypocrite 7 Creek, Fairfield Township, Bridge 8 Replacement 200,000 9 (Base Construction Allocation - 10 $170,000) 11 (Land Allocation - $10,000) 12 (Design and Contingencies - $20,000) 13 (35) SR 1027, SR 1027 over Branch of Stony 14 Run, Derry Township, Bridge 15 Replacement 305,000 16 (Base Construction Allocation - 17 $200,000) 18 (Land Allocation - $5,000) 19 (Design and Contingencies - $100,000) 20 (36) SR 1031, SR 1031 over McCune Run, 21 Derry Township, Bridge Replacement 293,000 22 (Base Construction Allocation - 23 $188,000) 24 (Land Allocation - $5,000) 25 (Design and Contingencies - $100,000) 26 (37) SR 2006, SR 2006 over Branch of 27 Jacobs Creek, Mt. Pleasant Township, 28 Bridge Replacement 403,000 29 (Base Construction Allocation - 30 $288,000) 19970S0186B0698 - 357 -
1 (Land Allocation - $15,000) 2 (Design and Contingencies - $100,000) 3 (38) SR 2007, SR 2007 over Shupe Run, Mt. 4 Pleasant Township, Bridge Replacement 218,000 5 (Base Construction Allocation - 6 $113,000) 7 (Land Allocation - $5,000) 8 (Design and Contingencies - $100,000) 9 (39) SR 2012, SR 2012 over Brinker Run, 10 Mt. Pleasant Township, Bridge 11 Replacement 415,000 12 (Base Construction Allocation - 13 $300,000) 14 (Land Allocation - $15,000) 15 (Design and Contingencies - $100,000) 16 (40) SR 2021, SR 2021 over Sewickley 17 Creek, Mt. Pleasant Township, Bridge 18 Replacement 1,463,000 19 (Base Construction Allocation - 20 $1,213,000) 21 (Land Allocation - $50,000) 22 (Design and Contingencies - $200,000) 23 (41) SR 2025, SR 2025 over Tributary of 24 Jacobs Creek, Mt. Pleasant Township, 25 Bridge Replacement 250,000 26 (Base Construction Allocation - 27 $225,000) 28 (Design and Contingencies - $25,000) 29 (42) SR 4034, SR 4034 over Pine Run, 30 Allegheny Township, Bridge Replacement 818,000 19970S0186B0698 - 358 -
1 (Base Construction Allocation - 2 $588,000) 3 (Land Allocation - $30,000) 4 (Design and Contingencies - $200,000) 5 (43) SR 4071, SR 4071 over Branch of Pine 6 Run, Allegheny Township, Bridge 7 Replacement 305,000 8 (Base Construction Allocation - 9 $200,000) 10 (Land Allocation - $5,000) 11 (Design and Contingencies - $100,000) 12 (44) SR 4089, SR 4089 over Branch of 13 Chartiers Run, Allegheny Township, 14 Bridge Replacement 348,000 15 (Base Construction Allocation - 16 $238,000) 17 (Land Allocation - $10,000) 18 (Design and Contingencies - $100,000) 19 (45) T-987, (formerly SR 1071) over 20 Hypocrite Creek, Fairfield Township, 21 Four State Bridges, Bridge Replacement 800,000 22 (Base Construction Allocation - 23 $680,000) 24 (Land Allocation - $40,000) 25 (Design and Contingencies - $80,000) 26 (46) SR 0381, SR 0381 over Laughlintown 27 Run, Ligonier Township, Bridge 28 Replacement 465,000 29 (Base Construction Allocation - 30 $350,000) 19970S0186B0698 - 359 -
1 (Land Allocation - $15,000) 2 (Design and Contingencies - $100,000) 3 (47) SR 2043, SR 2043 over Two Mile Run, 4 Ligonier Township, Bridge Replacement 465,000 5 (Base Construction Allocation - 6 $350,000) 7 (Land Allocation - $15,000) 8 (Design and Contingencies - $100,000) 9 (48) SR 2045, SR 2045 over Two Mile Run, 10 Ligonier Township, Bridge Replacement 465,000 11 (Base Construction Allocation - 12 $350,000) 13 (Land Allocation - $15,000) 14 (Design and Contingencies - $100,000) 15 (49) SR 2045, SR 2045 over Loyalhanna 16 Creek, Ligonier Township, Bridge 17 Replacement 1,588,000 18 (Base Construction Allocation - 19 $1,313,000) 20 (Land Allocation - $75,000) 21 (Design and Contingencies - $200,000) 22 (50) SR 0119, Bridge No.2 over Crabtree 23 Creek, Hempfield Township, Bridge 24 Replacement 577,000 25 (Base Construction Allocation - 26 $377,000) 27 (Land Allocation - $25,000) 28 (Design and Contingencies - $175,000) 29 (51) SR 8036, New Stanton Ramp Bridge over 30 SR 3091, Turnback Project, New Stanton 19970S0186B0698 - 360 -
1 Borough, Bridge Rehabilitation 475,000 2 (Base Construction Allocation - 3 $395,000) 4 (Design and Contingencies - $80,000) 5 (52) SR 2045, BRIDGE OVER LOYALHANNA <-- 6 CREEK, LIGONIER TOWNSHIP, BRIDGE 7 REPLACEMENT 800,000 8 (BASE CONSTRUCTION ALLOCATION - 9 $600,000) 10 (LAND ALLOCATION - $25,000) 11 (DESIGN AND CONTINGENCIES - $175,000) 12 Section 70. Wyoming County. 13 (a) Local Bridges 14 (1) Exeter Township, T-336, Bridge No.1, 2 15 Miles Southwest of Falls, Bridge 16 Replacement 280,000 17 (Base Construction Allocation - 18 $240,000) 19 (Land Allocation - $10,000) 20 (Design and Contingencies - $30,000) 21 (2) Falls Township, T-336 over White Lock 22 Stream, Bridge Replacement 280,000 23 (Base Construction Allocation - 24 $240,000) 25 (Land Allocation - $10,000) 26 (Design and Contingencies - $30,000) 27 (3) Exeter Township, T-336 over Mill 28 Creek, Bridge Replacement 214,000 29 (Base Construction Allocation - 30 $166,000) 19970S0186B0698 - 361 -
1 (Land Allocation - $20,000) 2 (Design and Contingencies - $28,000) 3 (4) Eaton Township, T-413, Pedestrian 4 Bridge over Bowman's Creek at 5 Eatonville, Bridge Rehabilitation 125,000 6 (Base Construction Allocation - 7 $113,000) 8 (Design and Contingencies - $12,000) 9 (b) State Bridges 10 (1) SR 3001, Bridge at Junction with SR 11 4004 over Branch of Susquehanna River, 12 Windham Township, Bridge Painting 60,000 13 (Base Construction Allocation - 14 $50,000) 15 (Design and Contingencies - $10,000) 16 (2) State Bridges, Countywide Bridge Zone 17 Painting, Bridge Painting 370,000 18 (Base Construction Allocation - 19 $350,000) 20 (Land Allocation - $10,000) 21 (Design and Contingencies - $10,000) 22 Section 71. York County. 23 (a) Local Bridges 24 (1) Carroll Township, Gettysburg Road 25 Bridge over Yellow Breeches Creek, 26 Bridge Replacement 860,000 27 (Base Construction Allocation - 28 $700,000) 29 (Land Allocation - $10,000) 30 (Design and Contingencies - $150,000) 19970S0186B0698 - 362 -
1 (2) Codorus Township, Seitzville Road over 2 South Branch of Codorus Creek, Bridge 3 Replacement 300,000 4 (Base Construction Allocation - 5 $200,000) 6 (Land Allocation - $15,000) 7 (Design and Contingencies - $85,000) 8 (3) Dover Township, Cardinal Lane over Fox 9 Run, Bridge Replacement 115,000 10 (Base Construction Allocation - 11 $70,000) 12 (Land Allocation - $15,000) 13 (Design and Contingencies - $30,000) 14 (4) Dover Township, Conewago Road over 15 Salem Run, Bridge Replacement 300,000 16 (Base Construction Allocation - 17 $200,000) 18 (Land Allocation - $15,000) 19 (Design and Contingencies - $85,000) 20 (5) East Hopewell Township, South Church 21 Street Extended, Bridge No.1, Bridge 22 Rehabilitation 9,000 23 (Base Construction Allocation - $8,000) 24 (Design and Contingencies - $1,000) 25 (6) East Hopewell Township, South Church 26 Street Extended, Bridge No.2, over 27 Rambo Run, Bridge Rehabilitation 60,000 28 (Base Construction Allocation - 29 $50,000) 30 (Design and Contingencies - $10,000) 19970S0186B0698 - 363 -
1 (7) East Hopewell Township, Manifold 2 School Road Bridge, Bridge 3 Rehabilitation 7,000 4 (Base Construction Allocation - $6,000) 5 (Design and Contingencies - $1,000) 6 (8) East Hopewell Township, Trout School 7 Road Bridge, Bridge Replacement 45,000 8 (Base Construction Allocation - 9 $30,000) 10 (Land Allocation - $5,000) 11 (Design and Contingencies - $10,000) 12 (9) Hellam Township, Valley Acres Road 13 over Tributary of Kreutz Creek, Bridge 14 Rehabilitation 40,000 15 (Base Construction Allocation - 16 $35,000) 17 (Design and Contingencies - $5,000) 18 (10) Hellam Township, Libhart Mill Road 19 over Tributary of Kreutz Creek, Bridge 20 Rehabilitation 40,000 21 (Base Construction Allocation - 22 $35,000) 23 (Design and Contingencies - $5,000) 24 (11) Manchester Township, T-900, Woodland 25 View Drive over Conrail, Bridge 26 Replacement 395,000 27 (Base Construction Allocation - 28 $275,000) 29 (Land Allocation - $30,000) 30 (Design and Contingencies - $90,000) 19970S0186B0698 - 364 -
1 (12) Manchester Township, T-940, Bear Road 2 2,000 Feet North of Susquehanna Trail, 3 Bridge Replacement 40,000 4 (Base Construction Allocation - 5 $25,000) 6 (Land Allocation - $5,000) 7 (Design and Contingencies - $10,000) 8 (13) Manheim Township, T-320 over Unnamed 9 Tributary of Gunpowder Falls Creek, 10 Bridge Replacement 150,000 11 (Base Construction Allocation - 12 $100,000) 13 (Land Allocation - $10,000) 14 (Design and Contingencies - $40,000) 15 (14) Manheim Township, T-346 over West 16 Branch of Codorus Creek, Bridge 17 Replacement 250,000 18 (Base Construction Allocation - 19 $190,000) 20 (Land Allocation - $10,000) 21 (Design and Contingencies - $50,000) 22 (15) Manheim Township, T-357 over Unnamed 23 Tributary of West Branch of Codorus 24 Creek, Bridge Replacement 160,000 25 (Base Construction Allocation - 26 $110,000) 27 (Land Allocation - $10,000) 28 (Design and Contingencies - $40,000) 29 (16) Manheim Township, T-370 over West 30 Branch of Codorus Creek, Bridge 19970S0186B0698 - 365 -
1 Replacement 200,000 2 (Base Construction Allocation - 3 $140,000) 4 (Land Allocation - $10,000) 5 (Design and Contingencies - $50,000) 6 (17) Manheim Township, T-413 over West 7 Branch of Codorus Creek, Bridge 8 Replacement 150,000 9 (Base Construction Allocation - 10 $100,000) 11 (Land Allocation - $10,000) 12 (Design and Contingencies - $40,000) 13 (18) Manheim Township, Tannery Road over 14 West Branch of Codorus Creek, Bridge 15 Replacement 250,000 16 (Base Construction Allocation - 17 $180,000) 18 (Land Allocation - $10,000) 19 (Design and Contingencies - $60,000) 20 (19) Paradise Township, Shady Dell Road, 21 Bridge Replacement 190,000 22 (Base Construction Allocation - 23 $110,000) 24 (Land Allocation - $10,000) 25 (Design and Contingencies - $70,000) 26 (20) Paradise Township, Beaver Creek Road 27 over Beaver Creek, Bridge Replacement 275,000 28 (Base Construction Allocation - 29 $195,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 366 -
1 (Design and Contingencies - $70,000) 2 (21) Penn Township, Center Street over 3 Tributary of Oil Creek, Bridge 4 Replacement 183,000 5 (Base Construction Allocation - 6 $163,000) 7 (Land Allocation - $10,000) 8 (Design and Contingencies - $10,000) 9 (22) Penn Township, Westminster Avenue 10 over Plum Creek, Bridge Replacement 230,000 11 (Base Construction Allocation - 12 $207,000) 13 (Land Allocation - $8,000) 14 (Design and Contingencies - $15,000) 15 (23) Penn Township, Park Heights over 16 Tributary of Plum Creek, Bridge 17 Replacement 244,000 18 (Base Construction Allocation - 19 $234,000) 20 (Design and Contingencies - $10,000) 21 (24) Red Lion Borough, North Charles 22 Street over Former Maryland and 23 Pennsylvania Railroad, Bridge 24 Replacement 395,000 25 (Base Construction Allocation - 26 $275,000) 27 (Land Allocation - $30,000) 28 (Design and Contingencies - $90,000) 29 (25) Spring Garden Township, Tri Hill Road 30 over Tyler Run, Bridge Replacement 200,000 19970S0186B0698 - 367 -
1 (Base Construction Allocation - 2 $120,000) 3 (Land Allocation - $20,000) 4 (Design and Contingencies - $60,000) 5 (26) Windsor Borough, West Gay Street over 6 Fishing Creek, Bridge Replacement 200,000 7 (Base Construction Allocation - 8 $120,000) 9 (Land Allocation - $20,000) 10 (Design and Contingencies - $60,000) 11 (27) York Township, School Street over 12 Branch of Mill Creek, Bridge 13 Replacement 250,000 14 (Base Construction Allocation - 15 $200,000) 16 (Design and Contingencies - $50,000) 17 (b) State Bridges 18 (1) SR 0194, Broadway Street Bridge over 19 Red Run, Washington Township, Bridge 20 Replacement 245,000 21 (Base Construction Allocation - 22 $150,000) 23 (Land Allocation - $10,000) 24 (Design and Contingencies - $85,000) 25 (2) SR 0234, East Berlin Road Bridge over 26 Paradise Creek, Jackson Township, 27 Bridge Replacement 325,000 28 (Base Construction Allocation - 29 $250,000) 30 (Land Allocation - $10,000) 19970S0186B0698 - 368 -
1 (Design and Contingencies - $65,000) 2 (3) SR 3074, Smoketown Road Bridge over 3 Cod Creek, Manheim Township, Bridge 4 Replacement 325,000 5 (Base Construction Allocation - 6 $215,000) 7 (Land Allocation - $10,000) 8 (Design and Contingencies - $100,000) 9 (4) SR 0116, York Street over Tributary of 10 Oil Creek, Penn Township, Bridge 11 Replacement 275,000 12 (Base Construction Allocation - 13 $240,000) 14 (Land Allocation - $15,000) 15 (Design and Contingencies - $20,000) 16 (5) SR 0116, SR 0116 over Codorus Creek, 17 Spring Grove Borough, Bridge 18 Replacement 300,000 19 (Base Construction Allocation - 20 $240,000) 21 (Land Allocation - $15,000) 22 (Design and Contingencies - $45,000) 23 (6) SR 0194, Frederick Street over Plum 24 Creek, Penn Township, Bridge 25 Replacement 262,000 26 (Base Construction Allocation - 27 $234,000) 28 (Land Allocation - $8,000) 29 (Design and Contingencies - $20,000) 30 (7) SR 1012, Emig Road over Conrail, 19970S0186B0698 - 369 -
1 Manchester Township, Bridge 2 Replacement 395,000 3 (Base Construction Allocation - 4 $275,000) 5 (Land Allocation - $30,000) 6 (Design and Contingencies - $90,000) 7 (8) SR 2031, Penn Street over Fishing 8 Creek, Windsor Borough, Bridge 9 Replacement 200,000 10 (Base Construction Allocation - 11 $120,000) 12 (Land Allocation - $20,000) 13 (Design and Contingencies - $60,000) 14 (9) SR 3001, South George Street over 15 Tyler Run, Spring Garden Township, 16 Bridge Replacement 200,000 17 (Base Construction Allocation - 18 $120,000) 19 (Land Allocation - $20,000) 20 (Design and Contingencies - $60,000) 21 (10) SR 3074, Smoketown Road Bridge over 22 Codorus Creek, Manheim Township, Bridge 23 Replacement 240,000 24 (Base Construction Allocation - 25 $150,000) 26 (Land Allocation - $10,000) 27 (Design and Contingencies - $80,000) 28 Section 72. Statewide. 29 Construction of advanced wetland mitigation 30 projects necessary to replace wetlands displaced 19970S0186B0698 - 370 -
1 by bridge projects authorized under the act of 2 December 8, 1982 (P.L.848, No.235), known as the 3 Highway-Railroad and Highway Bridge Capital Budget 4 Act for 1982-1983 3,100,000 5 (Base Construction Allocation - 6 $2,500,000) 7 (Land Allocation - $350,000) 8 (Design and Contingencies - $250,000) 9 Section 72.1. State forestry bridge projects itemized. 10 Projects in the category of State forestry bridge projects to 11 be constructed by the Department of Conservation and Natural 12 Resources, its successors or assigns, and to be financed by oil 13 company franchise tax revenues pursuant to 75 Pa.C.S. § 14 9502(a)(2)(iv) (relating to imposition of tax), are hereby 15 itemized, together with their respective estimated costs, as 16 follows: 17 (a) State Bridges 18 (1) Adams County 19 (A) Replacement of Bridge No.01-0005, 20 District Road Bridge over Carbaugh Run 120,000 21 (B) Replacement of Bridge No.01-0004, Dead 22 Womans Hollow Road Bridge over Mountain 23 Creek 150,000 24 (2) Bedford County 25 (A) Replacement of Bridge No.02-0002, 26 Wertz Road Bridge over Cove Creek 100,000 27 (B) Replacement of Bridge No.02-0001, 28 Wertz Road Bridge over Cove Creek 150,000 29 (3) Cameron County 30 (A) Replacement of Bridge No.13-0012, 19970S0186B0698 - 371 -
1 Brooks Run Road Bridge over Brooks 2 Road 220,000 3 (B) Replacement of Bridge No.13-0060, 4 Brooks State House Bridge over Brooks 5 Road 250,000 6 (C) Replacement of Bridge No.13-0037, Mix 7 Run Road Bridge over Mix Run 200,000 8 (D) Replacement of Bridge No.13-0038, Mix 9 Run Road over Mix Run 166,000 10 (4) Centre County 11 (A) Replacement of Bridge No.07-0010, 12 Siglerville Millheim Pike Bridge 162,000 13 (B) Replacement of Bridge No.07-0015, 14 Green Valley Road Bridge 260,000 15 (C) Replacement of Bridge No.07-0033, Pine 16 Creek Road Bridge 386,000 17 (D) Replacement of Bridge No.07-0045, 18 McCall Dam Road Bridge over White Deer 19 Creek 180,000 20 (E) Replacement of Bridge No.09-0030, Six 21 Mile Run Bridge 192,000 22 (F) Replacement of Bridge No.10-0028, 23 State Line Road Bridge 196,000 24 (G) Replacement of Bridge No.05-0003, 25 Krise Valley Road Bridge over Potter 26 Run 100,000 27 (H) Replacement of Bridge No.05-0004, Bear 28 Meadows Road Bridge over Sinking Creek 100,000 29 (I) Replacement of Bridge No.05-0005, Bear 30 Meadows Road Bridge over Galbraith Run 150,000 19970S0186B0698 - 372 -
1 (J) Replacement of Bridge No.07-0008, Poe 2 Valley Road Bridge over Big Poe Creek 200,000 3 (K) Replacement of Bridge No.07-0028, 4 Cherry Run Road Bridge over Cherry Run 102,000 5 (L) Replacement of Bridge No.07-0029, 6 Cherry Run Road Bridge over Cherry Run 240,000 7 (M) Replacement of Bridge No.07-0035, 8 Stoney Run Road Bridge over Pine Creek 375,000 9 (N) Replacement of Bridge No.09-0026, 10 Huckleberry Road Bridge over Black 11 Moshannon Creek 250,000 12 (O) Replacement of Bridge No.09-0029, 13 Claymine Road Bridge over Six Mile Run 200,000 14 (P) Replacement of Bridge No.10-0026, 15 Panther Road Bridge over Wolf Run 150,000 16 (Q) Replacement of Bridge No.07-0007, Poe 17 Paddy Drive Bridge over Big Poe Creek 170,000 18 (5) Clearfield County 19 (A) Replacement of Bridge No.09-0005, 20 Tyler Road Bridge over Laurel Run 284,000 21 (B) Replacement of Bridge No.09-0019, 22 Dent's Branch Road Bridge 282,000 23 (C) Replacement of Bridge No.09-0022, 24 Merrill Road Bridge 197,000 25 (D) Replacement of Bridge No.09-0012, 26 Little Medix Road Bridge over Little 27 Medix Run 220,000 28 (E) Replacement of Bridge No.09-0013, 29 Little Medix Road Bridge over Little 30 Medix Run 100,000 19970S0186B0698 - 373 -
1 (F) Replacement of Bridge No.09-0014, 2 Little Medix Road Bridge over Little 3 Medix Run 100,000 4 (G) Replacement of Bridge No.09-0015, 5 Little Medix Road Bridge over Little 6 Medix Run 100,000 7 (H) Replacement of Bridge No.09-0018, 8 Dent's Branch Road Bridge over Dent's 9 Branch Street 160,000 10 (I) Replacement of Bridge No.09-0020, 11 Dent's Branch Road Bridge over Dent's 12 Branch Street 165,000 13 (J) Replacement of Bridge No.09-0021, Ames 14 Road Bridge over Deer Creek 145,000 15 (K) Replacement of Bridge No.09-0023, Lost 16 Run Road Bridge over Giffor Run 138,000 17 (L) Replacement of Bridge No.09-0034, 18 Reservoir Road Bridge over Upper Three 19 Run 120,000 20 (6) Clinton County 21 (A) Replacement of Bridge No.10-0033, 22 Cooks Run Road Bridge over Cooks Run 110,000 23 (B) Replacement of Bridge No.10-0042, Two 24 Mile Road Bridge 100,000 25 (C) Replacement of Bridge No.10-0043, Big 26 Basin Road Bridge over Shintown Run 206,000 27 (D) Replacement of Bridge No.10-059, 28 Bridge over Right Branch of Young 29 Womans Creek Road 287,000 30 (E) Replacement of Bridge No.10-0064, 19970S0186B0698 - 374 -
1 Trout Run Bridge 255,000 2 (F) Replacement of Bridge No.15-0021, 3 County Line Road Bridge 167,000 4 (G) Replacement of Bridge No.10-0032, 5 Cooks Run Road Bridge over Crowley Run 145,000 6 (H) Replacement of Bridge No.10-0044, 7 Robbins Road Bridge over Shintown Run 120,000 8 (I) Replacement of Bridge No.10-0051, Fork 9 Hill Road Bridge over Lebo Run 168,000 10 (J) Replacement of Bridge No.10-0052, Left 11 Branch Young Womans Road Bridge over 12 Mud Lick Run 140,000 13 (K) Replacement of Bridge No.10-0053, Left 14 Branch Young Womans Road Bridge over 15 Shingle Branch 145,000 16 (L) Replacement of Bridge No.10-0054, Left 17 Branch Young Womans Road Bridge over 18 Greenlick Run 135,000 19 (M) Replacement of Bridge No.10-0057, 20 Sandy Run Road Bridge over Paddy Run 140,000 21 (N) Replacement of Bridge No.10-0061, 22 Graham Road Bridge over Ferney Run 135,000 23 (O) Replacement of Bridge No.10-0063, 24 Hyner Run Road Bridge over Long Fork 110,000 25 (P) Replacement of Bridge No.10-0035, 26 Bridge over Camp Run 100,000 27 (Q) Replacement of Bridge No.10-0037, 28 Bridge over Cooks Run 160,000 29 (R) Replacement of Bridge No.12-0032, 30 Gotshall Road Bridge over Gotshall Run 120,000 19970S0186B0698 - 375 -
1 (S) REPLACEMENT OF BRIDGE NO.10-0036, OVER <-- 2 ROCK RUN 90,000 3 (T) REPLACEMENT OF BRIDGE NO.07-0054, LONG 4 RUN 91,000 5 (U) REPLACEMENT OF BRIDGE NO.07-0055, OVER 6 COOPER RUN 70,000 7 (7) Cumberland County 8 (A) Replacement of Bridge No.01-0006, 9 Woodrow Road Run Bridge over Mountain 10 Creek 150,000 11 (B) Replacement of Bridge No.01-0010, 12 Milesburn Road Bridge 102,000 13 (C) Replacement of Bridge No.01-0008, 14 Strohms Hollow Road Bridge over Strohms 15 Hollow Run 138,000 16 (D) Replacement of Bridge No.01-0023, Togg 17 Run Road Bridge over Togg Run 138,000 18 (8) Dauphin County 19 (A) Replacement of large culvert, White 20 Oak Road Bridge over White Oak Run 100,000 21 (9) Elk County 22 (A) Replacement of Bridge No.13-0040, Red 23 Run Road Bridge 160,000 24 (B) Replacement of Bridge No.13-0049, 25 Shaffer Draft Road Bridge 175,000 26 (C) Replacement of Bridge No.13-0050, West 27 Hicks Run Road Bridge 175,000 28 (D) Replacement of Bridge No.13-0052, 29 Bridge over East Branch of Hicks Run 175,000 30 (E) Replacement of Bridge No.13-0053, 19970S0186B0698 - 376 -
1 Bridge over East Branch of Hicks Run 175,000 2 (F) Replacement of Bridge No.09-0006, 3 Blackwell Road Bridge over Laurel Road 142,000 4 (G) Replacement of Bridge No.13-0028, 5 Porcupine Road Bridge over Dent's Run 183,000 6 (H) Replacement of Bridge No.13-0032, 7 Dent's Run Road Bridge over Little 8 Dent's Run 110,000 9 (I) Replacement of Bridge No.13-0039, Mix 10 Run Road Bridge over Red Run 184,000 11 (10) Franklin County 12 (A) Replacement of Bridge No.01-0016, Wirt 13 Road Bridge 147,000 14 (B) Replacement of Bridge No.01-0022, 15 Rattlesnake Run Road Bridge 149,000 16 (C) Replacement of Bridge No.01-0021, 17 Lindsay Lot Road Bridge over Furnace 18 Run 100,000 19 (D) Replacement of Bridge No.01-0019, 20 Biesecker Gap Road Bridge over 21 Biesecker Run 110,000 22 (11) Huntingdon County 23 (A) Replacement of Bridge No.05-0012, 24 Colerain Road Bridge 235,000 25 (B) Replacement of Bridge No.05-0014, 26 Coopers Gap Road Bridge 160,000 27 (C) Replacement of Bridge No.05-0021, 28 Stone Creek Road Bridge 182,000 29 (D) Replacement of Bridge No.05-0027, 30 Diamond Valley Road Bridge over Globe 19970S0186B0698 - 377 -
1 Run 100,000 2 (E) Replacement of Bridge No.05-0028, 3 Laurel Run Road Bridge 213,000 4 (F) Replacement of Bridge No.05-0051, 5 Coopers Gap Road Bridge 174,000 6 (G) Replacement of Bridge No.05-0010, 7 Martin Road Bridge over Standing Stone 8 Creek 173,000 9 (H) Replacement of Bridge No.05-0011, 10 Pennsylvania Furnace Road Bridge over 11 Globe Run 140,000 12 (I) Replacement of Bridge No.05-0017, Pine 13 Swamp Road Bridge over Shaver Creek 150,000 14 (J) Replacement of Bridge No.05-0018, 15 Beidler Road Bridge over Laurel Run 142,000 16 (K) Replacement of Bridge No.05-0020, Rag 17 Hollow Road Bridge over East Branch 18 Stone Creek 150,000 19 (L) Replacement of Bridge No.05-0026, 20 Pennsylvania Furnace Road Bridge over 21 Pennsylvania Furnace Run 110,000 22 (M) REPLACEMENT OF BRIDGE NO.05-0019, <-- 23 STONE CREEK ROAD OVER DETWEILER RUN 60,000 24 (N) REPLACEMENT OF BRIDGE NO.05-0022, 25 SEEGER ROAD OVER STOIVE CREEK 70,000 26 (12) Jefferson County 27 (A) Replacement of Bridge No.08-0003, 28 Callen Run Road Bridge over Callen Run 200,000 29 (B) Replacement of Bridge No.08-0001, 30 Corbett Road Bridge over Clear Creek 170,000 19970S0186B0698 - 378 -
1 (13) Juniata County 2 (A) Replacement of Bridge No.03-0007, 3 Spectacle Gap Bridge 158,000 4 (B) Replacement of Bridge No.03-0005, East 5 Licking Drive Bridge over East Licking 6 Creek 242,000 7 (C) Replacement of Bridge No.03-0006, East 8 Licking Drive Bridge over East Licking 9 Creek 222,000 10 (13.1) LACKAWANNA COUNTY <-- 11 (A) REPLACEMENT OF BRIDGE NO.11-9000, 12 SASSAFRAS ROAD OVER SPRING RUN 80,000 13 (14) Lycoming County 14 (A) Replacement of Bridge No.12-0015, Rock 15 Run Road Bridge 175,000 16 (B) Replacement of Bridge No.12-0016, Rock 17 Run Road Bridge 164,000 18 (C) Replacement of Bridge No.12-0019, 19 Little Bear Bridge 193,000 20 (D) Replacement of Bridge No.12-0020, 21 Little Bear Bridge 193,000 22 (E) Replacement of Bridge No.12-0021, 23 Little Bear Bridge 193,000 24 (F) Replacement of Bridge No.12-0022, 25 Little Bear Creek Road Bridge 237,000 26 (G) Replacement of Bridge No.12-0028, 27 Fourth Gap Road Bridge 100,000 28 (H) Replacement of Large Culvert, Frances 29 Road at Big Hollow 100,000 30 (I) Replacement of Bridge No.12-0017, 19970S0186B0698 - 379 -
1 Yellow Dog Road Bridge over Rock Run 245,000 2 (J) Replacement of Bridge No.12-0040, 3 English Run Road Bridge over English 4 Run 238,000 5 (K) Replacement of Bridge No.12-0046, 6 Morris Run Road Bridge over Slate Run 240,000 7 (L) Replacement of Bridge No.12-0013, 8 Hillgrove Road Bridge over Pleasant 9 Stream 150,000 10 (M) Replacement of Bridge No.12-0027, Cove 11 Road Bridge over Fourth Gap 140,000 12 (N) Replacement of Bridge No.12-0023, 13 Little Bear Road Bridge over Little 14 Bear Creek 120,000 15 (15) Mifflin County 16 (A) Replacement of Bridge No.03-0008, 17 Spectacle Gap Road Bridge over East 18 Licking Creek 150,000 19 (B) Replacement of Bridge No.07-0004, 20 Havice Valley Road Bridge over Panther 21 Run 257,000 22 (C) Replacement of Bridge No.05-0051, 23 Cooper Gap Road Bridge over Cooper Gap 24 Run 172,000 25 (D) Replacement of Bridge No.07-0057, 26 Stillhouse Hollow Road Bridge over 27 Greens Valley Street 128,000 28 (E) Replacement of Bridge No.07-0003, 29 Havice Valley Road Bridge over Swift 30 Run 125,000 19970S0186B0698 - 380 -
1 (16) Monroe County 2 (A) Replacement of Bridge No.19-0001, 3 Laurel Run Road Bridge 159,000 4 (17) Perry County 5 (A) Replacement of Bridge No.03-0010, Elk 6 Hill Road Bridge 152,000 7 (B) Replacement of Bridge No.03-0011, Elk 8 Hill Road Bridge 152,000 9 (C) Replacement of Bridge No.03-0014, 10 Laurel Run Road Bridge over Laurel Run, 11 North Branch 100,000 12 (D) Replacement of Bridge No.03-0015, 13 Sheaffer Run Bridge, Undermining at 14 South Abutment 150,000 15 (E) Replacement of Bridge No.03-0016, 16 Laurel Run Road Bridge 185,000 17 (F) Replacement of Bridge No.03-0018, Twin 18 Bridge over Laurel Run 180,000 19 (G) Replacement of Culvert, Shearer Dug 20 Box Culvert 100,000 21 (18) Pike County 22 (A) Replacement of Bridge No.19-0004, Pine 23 Flats Run Road Bridge 160,000 24 (B) Replacement of Bridge No.19-0005, 25 Bruce Lake Road Bridge over Tributary 26 Egypt Meadow Lake 120,000 27 (C) Replacement of Bridge No.19-0803, 28 Bruce Lake Road Bridge over Egypt 29 Meadow Lake 145,000 30 (D) Replacement of Bridge No.19-0002, Hay 19970S0186B0698 - 381 -
1 Road Bridge over Middle Branch 115,000 2 (19) Potter County 3 (A) Replacement of Bridge No.15-0013, 4 Windfall Road Bridge 160,000 5 (B) Replacement of Bridge No.15-0015, 6 Joerg Run Road Bridge 160,000 7 (C) Replacement of Bridge No.15-0018, Lebo 8 Run Road Bridge 160,000 9 (D) Replacement of Bridge No.15-0020, 10 Robinson Road Bridge 230,000 11 (E) Replacement of Bridge No.15-0024, 12 Robinson Road Bridge 140,000 13 (F) Replacement of Bridge No.16-0015, 14 Butternut Hollow Road Bridge over 15 Kettle Creek 110,000 16 (G) Replacement of Bridge No.15-0003, 17 Jones Run Road Bridge over Freeman Run 175,000 18 (H) Replacement of Bridge No.15-0010, 19 Black Diamond Road Bridge over Big 20 Moores Run 163,000 21 (I) Replacement of Bridge No.15-0011, 22 Horton Run Road Bridge over East Fork 23 Sinnemahoning Creek 125,000 24 (J) Replacement of Bridge No.15-0014, 25 Hungry Hollow Road Bridge over Cross 26 Fork Creek 192,000 27 (K) Replacement of Bridge No.15-0025, 28 Nelson Run Road Bridge over Big Nelson 29 Run 138,000 30 (L) Replacement of Bridge No.15-0027, 19970S0186B0698 - 382 -
1 Ellis Hollow Road Bridge over Nine Mile 2 Run 146,000 3 (M) Replacement of Bridge No.15-0012, 4 Bailey Run Bridge over Bailey Run 250,000 5 (N) Replacement of Bridge No.15-0019, 6 Twelve Mile Bridge over Spring Brook 107,000 7 (20) Schuykill County 8 (A) Replacement of Bridge No.18-0003, 9 Panther Road Bridge over Panther Creek 80,000 10 (21) Snyder County 11 (A) Replacement of Bridge No.07-0025, 12 Swift Run Road Bridge over Swift Run 138,000 13 (22) Somerset County 14 (A) Replacement of Bridge No.04-0002, Blue 15 Hole Road Bridge 192,000 16 (B) Replacement of Bridge No.04-0008, Cole 17 Run Road Bridge 138,000 18 (C) Replacement of Bridge No.04-0004, 19 South Wolf Run Road Bridge over Tub 20 Mill Run 184,000 21 (D) Replacement of Bridge No.04-0006, 22 Jones Mill Run Road Bridge over Jones 23 Mill Run 140,000 24 (E) Replacement of Bridge No.06-0002, 25 State Forest Road Bridge over Tributary 26 to Roaring Fork 82,000 27 (F) Replacement of Bridge No.06-0004, 28 Shade Road Bridge over Mile Run 131,000 29 (23) Sullivan County 30 (A) Replacement of Bridge No.20-0002, 19970S0186B0698 - 383 -
1 Brunnerdale Road Bridge 220,000 2 (B) Replacement of Bridge No.20-0008, 3 Shanerburg Road Bridge 212,000 4 (C) Replacement of Bridge No.20-0011, 5 Shanerburg Road Bridge over Shanerburg 6 Run 110,000 7 (D) Replacement of Bridge No.20-0004, Mill 8 Creek Road Bridge over Mill Creek 135,000 9 (E) Replacement of Bridge No.20-0005, Mill 10 Creek Road Bridge over Mill Creek 100,000 11 (24) Tioga County 12 (A) Replacement of Bridge No.16-0004, Left 13 Asaph Road Bridge 248,000 14 (B) Replacement of Bridge No.16-0005, 15 Asaph Run Bridge 414,000 16 (C) Replacement of Bridge No.16-0010, 17 Painter Leetonia Road Bridge 170,000 18 (D) Replacement of Bridge No.16-0011, 19 Cedar Run Bridge 170,000 20 (E) Replacement of Bridge No.16-0020, Mine 21 Hole Road Bridge 107,000 22 (F) Replacement of Bridge No.16-0003, Left 23 Asaph Road Bridge over Left Asaph Run 186,000 24 (G) Replacement of Bridge No.16-0008, 25 Owasse Road Bridge over Chimney Hollow 120,000 26 (H) Replacement of Bridge No.16-0015, 27 Butternut Hollow Road Bridge over 28 Kettle Creek 145,000 29 (I) Replacement of Bridge No.12-0049, 30 Francis Road Bridge over Francis 19970S0186B0698 - 384 -
1 Branch 150,000 2 (J) Replacement of Bridge No.16-0016, Bear 3 Run Road Bridge over Cushman Branch 160,000 4 (K) Replacement of Bridge No.16-0018, Mine 5 Hole Road Bridge over Mine Hole Run 150,000 6 (L) REPLACEMENT OF BRIDGE NO.12-0002, LEFT <-- 7 ASAPH OVER BAKER BRANCH 200,000 8 (25) Union County 9 (A) Replacement of Bridge No.07-0016, 10 Hoofnagle Road Bridge 235,000 11 (B) Replacement of Bridge No.07-0017, 12 Weikert Run Road Bridge 235,000 13 (C) Replacement of Bridge No.07-0047, 14 White Deer Creek Road Bridge 234,000 15 (D) Replacement of Bridge No.07-0046, 16 Cooper Mill Road Bridge over White Deer 17 Creek 212,000 18 (E) Replacement of Bridge No.07-0048, 19 White Deer Creek Road Bridge over White 20 Deer Creek 235,000 21 (F) Replacement of Bridge No.07-0041, 22 Brandon Road Bridge over North Branch 23 of Buffalo Creek 107,000 24 (G) Replacement of Bridge No.07-0040, Pine 25 Creek Road Bridge over Rapid Run 165,000 26 (26) Westmoreland County 27 (A) Replacement of Bridge No.04-0011, Linn 28 Run Road Bridge over Linn Run 125,000 29 (B) Replacement of Bridge No.04-0012, Linn 30 Run Road Bridge over Rock Run 135,000 19970S0186B0698 - 385 -
1 SECTION 72.2. STATEWIDE BICYCLE AND PEDESTRIAN <--
2 STRUCTURES.
3 REHABILITATION, CONSTRUCTION AND DEMOLITION OF
4 BRIDGES AND OTHER CROSSING STRUCTURES ON BICYCLE
5 AND PEDESTRIAN WAYS TO BE IDENTIFIED BY THE
6 DEPARTMENT OF CONSERVATION AND NATURAL RESOURCES 5,000,000
7 Section 73. Limitation on expenditure of funds.
8 Any moneys derived from the incurring of debt shall be used
9 solely for effecting the rehabilitation, replacement or removal
10 of bridges located on State highways or State forestry bridges.
11 All other bridge rehabilitation, replacement or removal shall be
12 financed and State bridge or State forestry bridge
13 rehabilitation, replacement or removal may also be financed from
14 current revenue.
15 Section 74. Debt authorization.
16 The Governor, Auditor General and State Treasurer are hereby
17 authorized and directed to borrow from time to time, in addition
18 to any authorization heretofore or hereafter enacted, on the
19 credit of the Commonwealth, subject to the limitations provided
20 in the current capital budget, money not exceeding in the
21 aggregate the sum of $962,844,000 $989,925,000 as may be found <--
22 necessary to carry out the acquisition and construction of the
23 State projects specifically itemized in this act.
24 Section 75. Issue of bonds.
25 The indebtedness authorized in this act shall be incurred
26 from time to time and shall be evidenced by one or more series
27 of general obligation bonds of the Commonwealth in such
28 aggregate principal amount for each series as the Governor,
29 Auditor General and State Treasurer shall determine, but the
30 latest stated maturity date shall not exceed 30 years from the
19970S0186B0698 - 386 -
1 date of the bond first issued for each series.
2 Section 76. Estimated useful life of projects.
3 The General Assembly states the estimated useful life of the
4 projects itemized in this act as 30 years.
5 Section 77. Appropriation.
6 The net proceeds of the sale of the obligations authorized in
7 this act are hereby appropriated from the Capital Facilities
8 Fund to the department in the maximum amount of $962,844,000 <--
9 $989,925,000 to be used by it exclusively to defray the
10 financial costs of the State projects specifically itemized in
11 this capital budget. After reserving or paying the expenses of
12 the sale of the obligation, the State Treasurer shall pay out to
13 the department the moneys as required and certified by it to be
14 legally due and payable.
15 Section 78. Federal funds.
16 In addition to those funds appropriated in section 77, all
17 moneys received from the Federal Government for the public
18 improvement projects specifically itemized in this act are also
19 hereby appropriated for those projects.
20 Section 79. Allocation of funds.
21 (a) General rule.--Whenever the department or the Department
22 of Conservation and Natural Resources determines that the full
23 estimated financial costs of the projects itemized in this act
24 are not necessary for the proper design, acquisition or
25 construction of such projects, the excess funds no longer
26 required may be allocated by the department or the Department of
27 Conservation and Natural Resources to increase the estimated
28 costs of any one or more of the projects specifically itemized
29 in a capital budget.
30 (b) Reimbursement of municipal expenditures.--Moneys raised
19970S0186B0698 - 387 -
1 or expended by municipalities after the effective date of this 2 act, in anticipation of receipt of funds authorized for projects 3 itemized by this act, may be reimbursable to those 4 municipalities. 5 Section 80. Policy on jobs and materials. 6 (a) Jobs.--It is the declared policy of the Commonwealth 7 that the construction projects authorized in this act be used, 8 to the greatest extent possible, to provide for the creation of 9 jobs and the rehiring of the unemployed in this Commonwealth. In 10 order to reach this goal, firms with Commonwealth-based 11 facilities shall be actively solicited to make bids on contracts 12 to furnish products and materials, including, but not limited 13 to, steel and steel products, to be used in these projects. 14 (b) Materials.--Every contract document entered into to 15 undertake a project contained in this act shall provide that any 16 steel or other products to be used or supplied in the 17 performance of this contract shall be required to be 18 manufactured by plants in the United States unless the secretary 19 determines, on a contract by contract basis, that certain 20 required products are not produced in the United States in 21 sufficient quantities to meet the requirements of the contract. 22 Such a determination and the reasons therefor shall be published 23 in the Pennsylvania Bulletin. Decisions made under this 24 subsection shall not be inconsistent with the general provisions 25 of the act of March 3, 1978 (P.L.6, No.3), known as the Steel 26 Products Procurement Act. 27 (c) Minorities and women.--It is also the declared policy of 28 the Commonwealth to require and encourage substantial 29 participation by minorities and women in the construction 30 projects authorized by this act. 19970S0186B0698 - 388 -
1 Section 81. Payment of capital debt service. 2 The repayment of any debt incurred pursuant to this act shall 3 be made from the account and such repayment shall have first 4 claim on the revenues of the account. 5 Section 82. Authorization and debt cumulation. 6 The additional authorization and debt allowance provided for 7 in this act shall be added to the total authorizations and debt 8 incurred pursuant to the act of December 8, 1982 (P.L.848, 9 No.235), known as the Highway-Railroad and Highway Bridge 10 Capital Budget Act for 1982-1983, as amended and supplemented. 11 Section 83. Editorial changes. 12 In editing and preparing this act for printing following the 13 final enactment, the Legislative Reference Bureau shall insert 14 or revise letters or numbers for projects where the letters or 15 numbers are missing or require revision. The bureau shall also 16 revise the total monetary amounts for the total authorization, 17 debt authorization, appropriations and departmental totals as 18 necessary to agree with the total monetary amounts of the 19 projects. 20 Section 84. Effective date. 21 This act shall take effect immediately. A3L86BIL/19970S0186B0698 - 389 -