        PRIOR PRINTER'S NOS. 179, 445                  PRINTER'S NO. 698

THE GENERAL ASSEMBLY OF PENNSYLVANIA


SENATE BILL

No. 186 Session of 1997


        INTRODUCED BY CORMAN AND STOUT, JANUARY 23, 1997

        SENATOR TILGHMAN, APPROPRIATIONS, RE-REPORTED AS AMENDED,
           MARCH 11, 1997

                                  A SUPPLEMENT

     1  To the act of December 8, 1982 (P.L.848, No.235), entitled "An
     2     act providing for the adoption of capital projects related to
     3     the repair, rehabilitation or replacement of highway bridges
     4     to be financed from current revenue or by the incurring of
     5     debt and capital projects related to highway and safety
     6     improvement projects to be financed from current revenue of
     7     the Motor License Fund," itemizing additional local and State
     8     bridge projects.

     9     The General Assembly of the Commonwealth of Pennsylvania
    10  hereby enacts as follows:
    11  Section 1.  Short title.
    12     This act shall be known and may be cited as the Highway-
    13  Railroad and Highway Bridge Capital Budget Supplemental Act for
    14  1996-1997.
    15  Section 2.  Definitions.
    16     The following words and phrases when used in this act shall
    17  have the meanings given to them in this section unless the
    18  context clearly indicates otherwise:
    19     "Account."  The Highway Bridge Improvement Restricted Account
    20  within the Motor License Fund.

     1     "Capital project."  A capital project as defined in section
     2  1602-B of the act of April 9, 1929 (P.L.343, No.176), known as
     3  The Fiscal Code, and shall include a county or municipal bridge
     4  rehabilitation, replacement or improvement project as set forth
     5  in this act.
     6     "Department."  The Department of Transportation of the
     7  Commonwealth.
     8     "Secretary."  The Secretary of Transportation of the
     9  Commonwealth.
    10  Section 3.  Total authorization for bridge projects.
    11     (a)  Total projects.--The total authorization for the costs
    12  of the projects itemized pursuant to this act and to be financed
    13  from current revenue or by the incurring of debt shall be
    14  $1,246,492,000 $1,309,837,000.                                    <--
    15     (b)  State projects.--The authorization for capital projects
    16  in the category of highway bridge projects and forestry bridge
    17  projects to be constructed by the Department of Transportation
    18  or the Department of Conservation and Natural Resources, or
    19  their successors or assigns, and to be financed by the incurring
    20  of debt or from the highway account, itemized in this act under
    21  the category of State bridges, shall be $962,844,000              <--
    22  $989,925,000.
    23     (c)  Non-State projects.--The authorization for non-State
    24  highway bridge projects to be constructed by municipalities and
    25  to be financed in part with grants not exceeding 80% of the non-
    26  Federal share of the costs made to the local government
    27  municipalities by the department from revenues deposited in the
    28  account itemized in this act under the category of local
    29  bridges, shall be $283,648,000 $319,912,000.                      <--
    30  Section 4.  Itemization of bridge projects.
    19970S0186B0698                  - 2 -

     1     The individual capital projects in the category of highway
     2  projects to be constructed by the Department of Transportation,
     3  its successors or assigns, and to be financed from current
     4  revenue or by the incurring of debt are hereby itemized,
     5  together with their estimated financial costs, in the following
     6  sections.
     7  Section 5.  Adams County.
     8     (a)  Local Bridges
     9         (1)  Cumberland Township, T-338, Herr's
    10             Ridge Road Bridge over Willoughby Run,
    11             Bridge Rehabilitation                         170,000
    12             (Base Construction Allocation -
    13             $100,000)
    14             (Land Allocation - $10,000)
    15             (Design and Contingencies - $60,000)
    16         (2)  Cumberland Township, T-402, Horner
    17             Road Bridge over Marsh Creek, County
    18             Bridge No.111, Bridge Replacement           1,075,000
    19             (Base Construction Allocation -
    20             $725,000)
    21             (Land Allocation - $25,000)
    22             (Design and Contingencies - $325,000)
    23         (3)  Cumberland Township, T-417, Goulden
    24             Road Bridge over Rock Creek, County
    25             Bridge No.123, Bridge Rehabilitation          330,000
    26             (Base Construction Allocation -
    27             $250,000)
    28             (Land Allocation - $5,000)
    29             (Design and Contingencies - $75,000)
    30         (4)  Cumberland and Freedom Townships,
    19970S0186B0698                  - 3 -

     1             Sach's Mill Covered Bridge over Marsh
     2             Creek, Pedestrian Bridge, Bridge
     3             Rehabilitation                                600,000
     4             (Base Construction Allocation -
     5             $500,000)
     6             Design and Contingencies - $100,000
     7     (b)  State Bridges (Reserved)
     8  Section 6.  Allegheny County.
     9     (a)  Local Bridges
    10         (1)  Plum Borough, Mary Street Bridge over
    11             Plum Creek, Bridge Replacement                630,000
    12             (Base Construction Allocation -
    13             $400,000)
    14             (Land Allocation - $50,000)
    15             (Design and Contingencies - $180,000)
    16         (2)  City of Pittsburgh, Glenwood Bridge,
    17             Phase II over Monongahela River, Three
    18             Railroads and Carson Street, Bridge
    19             Rehabilitation                              4,180,000
    20             (Base Construction Allocation -
    21             $3,905,000)
    22             (Design and Contingencies - $275,000)
    23         (3)  Elizabeth Township, Patterson Road,
    24             Boyd Hollow Bridge, Bridge Replacement        225,000
    25             (Base Construction Allocation -
    26             $180,000)
    27             (Land Allocation - $11,000)
    28             (Design and Contingencies - $34,000)
    29         (4)  Elizabeth Township, Yates Street
    30             Bridge, Bridge Replacement                    198,000
    19970S0186B0698                  - 4 -

     1             (Base Construction Allocation -
     2             $158,000)
     3             (Land Allocation - $10,000)
     4             (Design and Contingencies - $30,000)
     5         (5)  Shaler Township, South of Martha
     6             Avenue, Anderson Road over Wible Run,
     7             Bridge Replacement                            500,000
     8             (Base Construction Allocation -
     9             $400,000)
    10             (Design and Contingencies - $100,000)
    11         (6)  Baldwin Borough, Old Clairton Road
    12             over CSX Railroad, Bridge
    13             Rehabilitation                                 80,000
    14             (Base Construction Allocation -
    15             $65,000)
    16             (Design and Contingencies - $15,000)
    17         (7)  Ben Avon Borough, Spruce Run Road over
    18             Spruce Run, Bridge Rehabilitation             265,000
    19             (Base Construction Allocation -
    20             $200,000)
    21             (Land Allocation - $5,000)
    22             (Design and Contingencies - $60,000)
    23         (8)  City of Pittsburgh, Swinburne Street,
    24             Bridge Painting                             1,530,000
    25             (Base Construction Allocation -
    26             $1,500,000)
    27             (Design and Contingencies - $30,000)
    28         (9)  City of Pittsburgh, Railroad Bridge
    29             (Hot Metal Bridge) at Former LTV Steel
    30             Company over Monongahela River, Bridge
    19970S0186B0698                  - 5 -

     1             Rehabilitation                             25,000,000
     2             (Base Construction Allocation -
     3             $22,500,000)
     4             (Design and Contingencies - $2,500,000)
     5         (10)  Edgeworth Borough, Beaver Street over
     6             Little Sewickley Creek, Bridge
     7             Replacement                                   358,000
     8             (Base Construction Allocation -
     9             $250,000)
    10             (Land Allocation - $8,000)
    11             (Design and Contingencies - $100,000)
    12         (11)  Forward Township, Pangburn Hollow
    13             Road over Pangburn Run, Bridge
    14             Replacement                                   200,000
    15             (Base Construction Allocation -
    16             $150,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $40,000)
    19         (12)  Hampton Township, Duncan Avenue over
    20             Pine Creek, Bridge Replacement                200,000
    21             (Base Construction Allocation -
    22             $150,000)
    23             (Land Allocation - $10,000)
    24             (Design and Contingencies - $40,000)
    25         (13)  Harrison Township, Natrona Road over
    26             Small Branch of Allegheny River, Bridge
    27             Rehabilitation                                210,000
    28             (Base Construction Allocation -
    29             $160,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                  - 6 -

     1             (Design and Contingencies - $40,000)
     2         (14)  Jefferson Borough, Coal Valley Road
     3             Bridge No.2 over McRoberts Run, Bridge
     4             Rehabilitation                                200,000
     5             (Base Construction Allocation -
     6             $150,000)
     7             (Land Allocation - $10,000)
     8             (Design and Contingencies - $40,000)
     9         (15)  Jefferson Borough, Coal Valley Road
    10             Bridge No.4 over McRoberts Run, Bridge
    11             Rehabilitation                                200,000
    12             (Base Construction Allocation -
    13             $150,000)
    14             (Land Allocation - $10,000)
    15             (Design and Contingencies - $40,000)
    16         (16)  Leetsdale Borough, Beaver Road over
    17             Big Sewickley Creek, Bridge
    18             Replacement                                   420,000
    19             (Base Construction Allocation -
    20             $300,000)
    21             (Land Allocation - $10,000)
    22             (Design and Contingencies - $110,000)
    23         (17)  Municipality of Penn Hills, Mt.
    24             Carmel Road over Sandy Creek, Bridge
    25             Replacement                                   230,000
    26             (Base Construction Allocation -
    27             $170,000)
    28             (Land Allocation - $10,000)
    29             (Design and Contingencies - $50,000)
    30         (18)  Municipality of Penn Hills, Lincoln
    19970S0186B0698                  - 7 -

     1             Road Bridge No.6 over Sandy Creek,
     2             Bridge Replacement                            215,000
     3             (Base Construction Allocation -
     4             $150,000)
     5             (Land Allocation - $5,000)
     6             (Design and Contingencies - $60,000)
     7         (19)  Municipality of Penn Hills, Lincoln
     8             Road Bridge No.12 over Sandy Creek,
     9             Bridge Replacement                            215,000
    10             (Base Construction Allocation -
    11             $150,000)
    12             (Land Allocation - $5,000)
    13             (Design and Contingencies - $60,000)
    14         (20)  Sewickley Heights Borough, Blackburn
    15             Road over Kilbuck Run, Bridge
    16             Rehabilitation                                145,000
    17             (Base Construction Allocation -
    18             $110,000)
    19             (Land Allocation - $5,000)
    20             (Design and Contingencies - $30,000)
    21         (21)  South Park Township, Sleepy Hollow
    22             Road over Sleepy Hollow, Bridge
    23             Replacement                                   295,000
    24             (Base Construction Allocation -
    25             $200,000)
    26             (Land Allocation - $5,000)
    27             (Design and Contingencies - $90,000)
    28         (22)  South Park Township, Cochran's Mill
    29             Road over Licks Run, Bridge
    30             Replacement                                   215,000
    19970S0186B0698                  - 8 -

     1             (Base Construction Allocation -
     2             $150,000)
     3             (Land Allocation - $5,000)
     4             (Design and Contingencies - $60,000)
     5         (23)  Hampton Township, T-357, Bridge over
     6             Gourdhead Run, Bridge Rehabilitation          320,000
     7             (Base Construction Allocation -
     8             $280,000)
     9             (Design and Contingencies - $40,000)
    10         (24)  Hampton Township, T-984, South
    11             Pioneer Road Bridge No.1 over Crouse
    12             Run, Bridge Rehabilitation                    250,000
    13             (Base Construction Allocation -
    14             $210,000)
    15             (Design and Contingencies - $40,000)
    16         (25)  Hampton Township, T-984, South
    17             Pioneer Road Bridge No.2 over Crouse
    18             Run, Bridge Rehabilitation                    250,000
    19             (Base Construction Allocation -
    20             $210,000)
    21             (Design and Contingencies - $40,000)
    22         (26)  Marshall Township, T-482, Northgate
    23             Drive Bridge over Brush Creek, Bridge
    24             Replacement                                   320,000
    25             (Base Construction Allocation -
    26             $280,000)
    27             (Land Allocation - $5,000)
    28             (Design and Contingencies - $35,000)
    29         (27)  Town of McCandless, Blazier Drive
    30             Bridge No.1 over Pine Creek, Bridge
    19970S0186B0698                  - 9 -

     1             Rehabilitation                                 17,000
     2             (Base Construction Allocation -
     3             $15,000)
     4             (Design and Contingencies - $2,000)
     5         (28)  Town of McCandless, Blazier Drive
     6             Bridge No.2 over Pine Creek, Bridge
     7             Rehabilitation                                 28,000
     8             (Base Construction Allocation -
     9             $26,000)
    10             (Design and Contingencies - $2,000)
    11         (29)  Town of McCandless, Blazier Drive
    12             Bridge No.3 over Pine Creek, Bridge
    13             Rehabilitation                                  3,000
    14             (Base Construction Allocation - $2,000)
    15             (Design and Contingencies - $1,000)
    16         (30)  Town of McCandless, Oakridge Drive
    17             over Pine Creek, Bridge Rehabilitation         10,000
    18             (Base Construction Allocation - $8,000)
    19             (Design and Contingencies - $2,000)
    20         (31)  Town of McCandless, Meinert Road over
    21             Pine Creek, Bridge Rehabilitation               3,000
    22             (Base Construction Allocation - $2,000)
    23             (Design and Contingencies - $1,000)
    24         (32)  Collier Township, Thom's Run Road-
    25             Oakdale Road No.4 over Thom's Run,
    26             Bridge Replacement                            210,000
    27             (Base Construction Allocation -
    28             $160,000)
    29             (Land Allocation - $10,000)
    30             (Design and Contingencies - $40,000)
    19970S0186B0698                 - 10 -

     1         (33)  Collier Township, Thom's Run Road-
     2             Oakdale Road No.5 over Thom's Run,
     3             Bridge Replacement                            210,000
     4             (Base Construction Allocation -
     5             $160,000)
     6             (Land Allocation - $10,000)
     7             (Design and Contingencies - $40,000)
     8         (34)  Collier Township, Thom's Run Road-
     9             Oakdale Road No.9 over Thom's Run,
    10             Bridge Replacement                            180,000
    11             (Base Construction Allocation -
    12             $130,000)
    13             (Land Allocation - $10,000)
    14             (Design and Contingencies - $40,000)
    15         (35)  Etna Borough, Dewey Street over
    16             Little Pine Creek, Bridge
    17             Rehabilitation                                 23,000
    18             (Base Construction Allocation -
    19             $20,000)
    20             (Design and Contingencies - $3,000)
    21         (36)  Forward Township, Roberts Hollow Road
    22             over Fallen Timber Run, Bridge
    23             Replacement                                   200,000
    24             (Base Construction Allocation -
    25             $160,000)
    26             (Land Allocation - $10,000)
    27             (Design and Contingencies - $30,000)
    28         (37)  Hampton Township, Duncan Avenue over
    29             Stillhouse Run, Bridge Replacement            230,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 11 -

     1             $170,000)
     2             (Land Allocation - $10,000)
     3             (Design and Contingencies - $50,000)
     4         (38)  Penn Hills Township, Lincoln Road
     5             over Ryans Run, Bridge Replacement            190,000
     6             (Base Construction Allocation -
     7             $140,000)
     8             (Land Allocation - $10,000)
     9             (Design and Contingencies - $40,000)
    10         (39)  Penns Hills Township, Lincoln Road
    11             over Sandy Creek, Bridge Replacement          195,000
    12             (Base Construction Allocation -
    13             $150,000)
    14             (Land Allocation - $5,000)
    15             (Design and Contingencies - $40,000)
    16         (40)  North Versailles Township, Crooked
    17             Run Road over Crooked Run, Bridge
    18             Replacement                                   170,000
    19             (Base Construction Allocation -
    20             $130,000)
    21             (Land Allocation - $10,000)
    22             (Design and Contingencies - $30,000)
    23         (41)  O'Hara Township, Brownhill Road over
    24             Little Pine Creek, Bridge Replacement         275,000
    25             (Base Construction Allocation -
    26             $231,000)
    27             (Design and Contingencies - $44,000)
    28         (42)  Ross Township, Thompson Run Road over
    29             South Branch of Pine Creek, Bridge
    30             Replacement                                   210,000
    19970S0186B0698                 - 12 -

     1             (Base Construction Allocation -
     2             $160,000)
     3             (Land Allocation - $8,000)
     4             (Design and Contingencies - $42,000)
     5         (43)  Moon Township, T-114, Becks Run Road
     6             over Flaugherty Run, Bridge
     7             Replacement                                   420,000
     8             (Base Construction Allocation -
     9             $350,000)
    10             (Land Allocation - $20,000)
    11             (Design and Contingencies - $50,000)
    12         (44)  Homestead Borough, High Level Bridge,
    13             Bridge Rehabilitation and Upgrade             250,000
    14         (45)  North Braddock Borough, Hawkins
    15             Avenue Bridge, Bridge Rehabilitation          300,000
    16         (46)  Penn Hills Borough, Beechtree Road
    17             Box Culvert Bridge, Bridge
    18             Rehabilitation                                100,000
    19         (47)  Whitaker Borough, Rankin Bridge,
    20             Bridge Rehabilitation                         100,000
    21         (48)  SWISSVALE BOROUGH, KENMAUR BRIDGE                    <--
    22             CONNECTING SWISSVALE AND RANKIN, BRIDGE
    23             REPLACEMENT                                   320,000
    24             (BASE CONSTRUCTION ALLOCATION -
    25             $270,000)
    26             (DESIGN AND CONTINGENCIES - $50,000)
    27         (49)  WILKINS TOWNSHIP, BROWN AVENUE BRIDGE
    28             OVER BROWN RUN, BRIDGE REPLACEMENT            475,000
    29             (BASE CONSTRUCTION ALLOCATION -
    30             $380,000)
    19970S0186B0698                 - 13 -

     1             (DESIGN AND CONTINGENCIES - $95,000)
     2         (50)  WILKINS TOWNSHIP, IVY STREET BRIDGE
     3             OVER BROWN RUN, BRIDGE REPLACEMENT            268,000
     4             (BASE CONSTRUCTION ALLOCATION -
     5             $214,000)
     6             (DESIGN AND CONTINGENCIES - $54,000)
     7         (51)  WILKINS TOWNSHIP, BAKER STREET BRIDGE
     8             OVER CHALFANT RUN, BRIDGE REPLACEMENT         205,000
     9             (BASE CONSTRUCTION ALLOCATION -
    10             $164,000)
    11             (DESIGN AND CONTINGENCIES - $41,000)
    12         (52)  UPPER ST. CLAIR TOWNSHIP, WALTHER
    13             LANE BRIDGE, BRIDGE REPLACEMENT               700,000
    14             (BASE CONSTRUCTION ALLOCATION -
    15             $650,000)
    16             (DESIGN AND CONTINGENCIES - $50,000)
    17         (53)  GREEN TREE BOROUGH, TRUMBALL DRIVE
    18             BRIDGE OVER WHEELING AND LAKE ERIE
    19             RAILROAD, BRIDGE REHABILITATION               575,000
    20             (BASE CONSTRUCTION ALLOCATION -
    21             $500,000)
    22             (DESIGN AND CONTINGENCIES - $75,000)
    23     (b)  State Bridges
    24         (1)  SR 0028, Etna Bridge, Northbound
    25             Bridge No.4 to Existing SR 0028, Etna
    26             Borough, Shaler Township, Sharpsburg
    27             Borough and O'Hara Township, Bridge
    28             Rehabilitation                              7,415,000
    29             (Base Construction Allocation -
    30             $7,115,000)
    19970S0186B0698                 - 14 -

     1             (Land Allocation - $300,000)
     2         (2)  SR 0028, Etna Bridge to 62nd Street
     3             Bridge, Etna Borough, Shaler Township,
     4             Sharpsburg Borough and O'Hara Township,
     5             Bridge Rehabilitation                      17,222,000
     6             (Base Construction Allocation -
     7             $17,022,000)
     8             (Land Allocation - $200,000)
     9         (3)  SR 0030, Ardmore Westbound Electric
    10             over SR 2112, Chalfant Borough, Bridge
    11             Replacement                                 3,100,000
    12             (Base Construction Allocation -
    13             $3,000,000)
    14             (Design and Contingencies - $100,000)
    15         (4)  SR 0030, Ardmore Eastbound Electric
    16             over SR 2112, Chalfant Borough, Bridge
    17             Replacement                                 2,500,000
    18             (Base Construction Allocation -
    19             $2,400,000)
    20             (Design and Contingencies - $100,000)
    21         (5)  SR 0030, Ardmore Boulevard Bridge No.1
    22             over Falls Run, North of SR 8012
    23             Interchange, Forest Hills Borough,
    24             Bridge Replacement                            550,000
    25             (Base Construction Allocation -
    26             $400,000)
    27             (Land Allocation - $50,000)
    28             (Design and Contingencies - $100,000)
    29         (6)  SR 0048, Boston Hollow Road Bridge
    30             over Unnamed Stream, North of Lincoln
    19970S0186B0698                 - 15 -

     1             Borough, Elizabeth Borough, Bridge
     2             Replacement                                   340,000
     3             (Base Construction Allocation -
     4             $200,000)
     5             (Land Allocation - $40,000)
     6             (Design and Contingencies - $100,000)
     7         (7)  SR 0050, Bridge over Chartiers Creek,
     8             Northbound Lane, Heidelberg Borough,
     9             Scott Township, Bridge Rehabilitation       3,750,000
    10             (Base Construction Allocation -
    11             $3,300,000)
    12             (Land Allocation - $50,000)
    13             (Design and Contingencies - $400,000)
    14         (8)  SR 0060, South Main Street Bridge over
    15             Saw Mill Run, South of West End Circle,
    16             City of Pittsburgh, Bridge Painting           178,000
    17             (Base Construction Allocation -
    18             $173,000)
    19             (Design and Contingencies - $5,000)
    20         (9)  SR 0130, Tri-Borough Extended Bridge
    21             over Patton Street at SR 8076
    22             Interchange, Wilmerding Borough, Bridge
    23             Rehabilitation                                505,000
    24             (Base Construction Allocation -
    25             $400,000)
    26             (Land Allocation - $30,000)
    27             (Design and Contingencies - $75,000)
    28         (10)  SR 0148, Bridge over Crooked Run
    29             Creek near SR 2037, White Oak Borough,
    30             Bridge Replacement                            350,000
    19970S0186B0698                 - 16 -

     1             (Base Construction Allocation -
     2             $200,000)
     3             (Land Allocation - $50,000)
     4             (Design and Contingencies - $100,000)
     5         (11)  SR 0791, Bridge over Chalfont Run at
     6             SR 2048, Wilkins Township, Bridge
     7             Replacement                                   450,000
     8             (Base Construction Allocation -
     9             $300,000)
    10             (Land Allocation - $50,000)
    11             (Design and Contingencies - $100,000)
    12         (12)  SR 0837, Northbound Ramp A to SR 0885
    13             Southbound, City of Pittsburgh, Bridge
    14             Rehabilitation                              1,350,000
    15             (Base Construction Allocation -
    16             $1,250,000)
    17             (Design and Contingencies - $100,000)
    18         (13)  SR 0978, Miller's Run Road Bridge
    19             over Dolphin Run, South Fayette
    20             Township, Bridge Replacement                  300,000
    21             (Base Construction Allocation -
    22             $200,000)
    23             (Design and Contingencies - $100,000)
    24         (14)  SR 1001, West 7th Avenue Bridge over
    25             Bull Creek, Tarentum Borough, Bridge
    26             Replacement                                   400,000
    27             (Base Construction Allocation -
    28             $300,000)
    29             (Design and Contingencies - $100,000)
    30         (15)  SR 1011, Guys Run Road Bridge over
    19970S0186B0698                 - 17 -

     1             Guys Run, North of SR 0028, Harmar
     2             Township, Bridge Replacement                  350,000
     3             (Base Construction Allocation -
     4             $200,000)
     5             (Land Allocation - $50,000)
     6             (Design and Contingencies - $100,000)
     7         (16)  SR 2001, Glassport-Elizabeth Road
     8             Bridge over Burns Run, North of
     9             Elizabeth Township, Lincoln Borough,
    10             Bridge Replacement                            350,000
    11             (Base Construction Allocation -
    12             $200,000)
    13             (Land Allocation - $50,000)
    14             (Design and Contingencies - $100,000)
    15         (17)  SR 2081, Turtle Creek-Monroeville
    16             Road over US 22 Business, Monroeville
    17             Borough, Bridge Replacement                 1,060,000
    18             (Base Construction Allocation -
    19             $960,000)
    20             (Design and Contingencies - $100,000)
    21         (18)  SR 2094, Jerome Street Bridge over SR
    22             2027, Youghiogheny River, McKeesport
    23             Borough, Bridge Rehabilitation              4,600,000
    24             (Base Construction Allocation -
    25             $4,500,000)
    26             (Design and Contingencies - $100,000)
    27         (19)  SR 3066, Steubenville Pike Bridge
    28             over US 22, North Fayette Township,
    29             Bridge Rehabilitation                         500,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 18 -

     1             $400,000)
     2             (Land Allocation - $25,000)
     3             (Design and Contingencies - $75,000)
     4         (20)  SR 3069, Liberty Tunnel Airshaft
     5             between SR 0051 and Liberty Bridge,
     6             City of Pittsburgh, Airshaft
     7             Restoration                                 1,570,000
     8             (Base Construction Allocation -
     9             $1,370,000)
    10             (Design and Contingencies - $200,000)
    11         (21)  SR 3104, McKees Rocks Sidewalk over
    12             Harriet Street, McKees Rocks Borough,
    13             Bridge Rehabilitation                       6,800,000
    14             (Base Construction Allocation -
    15             $6,700,000)
    16             (Design and Contingencies - $100,000)
    17         (22)  SR 4036, Big Sewickley Creek Road
    18             over Big Sewickley Creek at SR 2003,
    19             Bell Acres Borough, Bridge
    20             Rehabilitation                                500,000
    21             (Base Construction Allocation -
    22             $400,000)
    23             (Land Allocation - $25,000)
    24             (Design and Contingencies - $75,000)
    25         (23)  SR 8043, Southbound Ramp Bridge over
    26             SR 0019 and SR 0065, City of
    27             Pittsburgh, Bridge Rehabilitation           2,400,000
    28             (Base Construction Allocation -
    29             $2,100,000)
    30             (Land Allocation - $50,000)
    19970S0186B0698                 - 19 -

     1             (Design and Contingencies - $250,000)
     2         (24)  SR 8045, Ramp at Stadium over SR 0065
     3             and Stadium Drive, City of Pittsburgh,
     4             Bridge Rehabilitation                         600,000
     5             (Base Construction Allocation -
     6             $600,000)
     7         (25)  SR 8049, SR 0019 Bridge Ramp, Chateau
     8             Street to SR 0019, City of Pittsburgh,
     9             Bridge Rehabilitation                       2,350,000
    10             (Base Construction Allocation -
    11             $2,000,000)
    12             (Land Allocation - $50,000)
    13             (Design and Contingencies - $300,000)
    14         (26)  SR 8049, Bridge Ramp from SR 0065
    15             Northbound to SR 0019, City of
    16             Pittsburgh, Bridge Rehabilitation           2,850,000
    17             (Base Construction Allocation -
    18             $2,500,000)
    19             (Land Allocation - $50,000)
    20             (Design and Contingencies - $300,000)
    21         (27)  SR 8049, I-279 Bridge Ramp to SR 0065
    22             Northbound, City of Pittsburgh, Bridge
    23             Rehabilitation                              1,730,000
    24             (Base Construction Allocation -
    25             $1,500,000)
    26             (Land Allocation - $30,000)
    27             (Design and Contingencies - $200,000)
    28         (28)  SR 0030, Ardmore Boulevard Bridge
    29             No.2 over Falls Run, North of SR 8012
    30             Interchange, Forest Hills Borough,
    19970S0186B0698                 - 20 -

     1             Bridge Replacement                            550,000
     2             (Base Construction Allocation -
     3             $400,000)
     4             (Land Allocation - $50,000)
     5             (Design and Contingencies - $100,000)
     6         (29)  SR 3004, McLaughlin Road Bridge over
     7             McLaughlin Run, Bridgeville Borough,
     8             Bridge Replacement                            227,000
     9             (Base Construction Allocation -
    10             $177,000)
    11             (Land Allocation - $10,000)
    12             (Design and Contingencies - $40,000)
    13         (30)  SR 0028, Northbound Bridge over
    14             Pennsylvania Turnpike, Harmar Township,
    15             Bridge Rehabilitation                         344,000
    16             (Base Construction Allocation -
    17             $314,000)
    18             (Design and Contingencies - $30,000)
    19         (31)  SR 0028, Southbound Bridge over
    20             Pennsylvania Turnpike, Harmar Township,
    21             Bridge Rehabilitation                         356,000
    22             (Base Construction Allocation -
    23             $325,000)
    24             (Design and Contingencies - $31,000)
    25         (32)  SR 0028, Northbound Bridge over SR
    26             1028, Harrison Township, Bridge
    27             Rehabilitation                                106,000
    28             (Base Construction Allocation -
    29             $97,000)
    30             (Design and Contingencies - $9,000)
    19970S0186B0698                 - 21 -

     1         (33)  SR 0028, Southbound Bridge over SR
     2             1028, Harrison Township, Bridge
     3             Rehabilitation                                105,000
     4             (Base Construction Allocation -
     5             $96,000)
     6             (Design and Contingencies - $9,000)
     7         (34)  SR 0050, Washington Avenue Bridge
     8             over Chartiers Creek, Bridgeville
     9             Borough, Bridge Rehabilitation                119,000
    10             (Base Construction Allocation -
    11             $109,000)
    12             (Design and Contingencies - $10,000)
    13         (35)  SR 0051, Clairton Boulevard Bridge
    14             over Lewis Run, Pleasant Hills Borough,
    15             Bridge Replacement                            600,000
    16             (Base Construction Allocation -
    17             $500,000)
    18             (Design and Contingencies - $100,000)
    19         (36)  SR 0065, Ohio River Boulevard Bridge
    20             over Forest Avenue, Ben Avon Borough,
    21             Bridge Replacement                            396,000
    22             (Base Construction Allocation -
    23             $360,000)
    24             (Design and Contingencies - $36,000)
    25         (37)  SR 0065, Bridge over Ramps, Railroad
    26             and Chateau Street, City of Pittsburgh,
    27             Bridge Rehabilitation                      13,284,000
    28             (Base Construction Allocation -
    29             $12,784,000)
    30             (Design and Contingencies - $500,000)
    19970S0186B0698                 - 22 -

     1         (38)  SR 0079, Neville Island Bridge over
     2             Ohio River, Neville Township, Bridge
     3             Rehabilitation                             12,700,000
     4             (Base Construction Allocation -
     5             $11,200,000)
     6             (Design and Contingencies - $1,500,000)
     7         (39)  SR 0088, Library Road Bridge No.1
     8             over Piney Fork Creek, Bethel Park
     9             Borough, Bridge Replacement                   161,000
    10             (Base Construction Allocation -
    11             $128,000)
    12             (Land Allocation - $20,000)
    13             (Design and Contingencies - $13,000)
    14         (40)  SR 0088, Library Road Bridge No.2
    15             over Branch of Piney Fork Creek, Bethel
    16             Park Borough, Bridge Replacement              161,000
    17             (Base Construction Allocation -
    18             $128,000)
    19             (Land Allocation - $20,000)
    20             (Design and Contingencies - $13,000)
    21         (41)  SR 0885, Mifflin Road Bridge over
    22             Branch of Streets Run, City of
    23             Pittsburgh, Bridge Replacement                600,000
    24             (Base Construction Allocation -
    25             $500,000)
    26             (Design and Contingencies - $100,000)
    27         (42)  SR 0910, Gibsonia Road Bridge over
    28             Rawlins Run, Indiana Township, Bridge
    29             Deck Replacement                              132,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 23 -

     1             $120,000)
     2             (Design and Contingencies - $12,000)
     3         (43)  SR 1027, Pleasantville Road Bridge
     4             over Little Bull Creek, Harrison
     5             Township, Bridge Replacement                  400,000
     6             (Base Construction Allocation -
     7             $300,000)
     8             (Design and Contingencies - $100,000)
     9         (44)  SR 1032, Burtner Road Bridge over
    10             Little Bull Creek, Harrison Township,
    11             Bridge Deck Replacement                       198,000
    12             (Base Construction Allocation -
    13             $180,000)
    14             (Design and Contingencies - $18,000)
    15         (45)  SR 2008, Lovedale Road Bridge over
    16             Wylie Run Creek, Elizabeth Township,
    17             Bridge Replacement                            430,000
    18             (Base Construction Allocation -
    19             $300,000)
    20             (Land Allocation - $30,000)
    21             (Design and Contingencies - $100,000)
    22         (46)  SR 2017, Pineview Drive Bridge No.1
    23             over Gillespie Run, Elizabeth Township,
    24             Bridge Deck Replacement                       255,000
    25             (Base Construction Allocation -
    26             $135,000)
    27             (Land Allocation - $20,000)
    28             (Design and Contingencies - $100,000)
    29         (47)  SR 2017, Pineview Drive Bridge No.2
    30             over Gillespie Run, Elizabeth Township,
    19970S0186B0698                 - 24 -

     1             Bridge Deck Replacement                       243,000
     2             (Base Construction Allocation -
     3             $123,000)
     4             (Land Allocation - $20,000)
     5             (Design and Contingencies - $100,000)
     6         (48)  SR 2018, West Smithfield Road Bridge
     7             over Unnamed Creek, Elizabeth Township,
     8             Bridge Deck Replacement                       218,000
     9             (Base Construction Allocation -
    10             $118,000)
    11             (Design and Contingencies - $100,000)
    12         (49)  SR 2031, Lincoln Way Bridge over Long
    13             Run, White Oak Borough, Bridge
    14             Replacement                                   600,000
    15             (Base Construction Allocation -
    16             $500,000)
    17             (Design and Contingencies - $100,000)
    18         (50)  SR 2051, Brinton Road Bridge over I-
    19             376, Edgewood Borough, Bridge
    20             Rehabilitation                                996,000
    21             (Base Construction Allocation -
    22             $846,000)
    23             (Design and Contingencies - $150,000)
    24         (51)  SR 4019, Mount Royal Boulevard Bridge
    25             over Pine Creek, Hampton Township,
    26             Bridge Rehabilitation                          94,000
    27             (Base Construction Allocation -
    28             $89,000)
    29             (Design and Contingencies - $5,000)
    30         (52)  SR 4043, Big Sewickley Road Bridge
    19970S0186B0698                 - 25 -

     1             over Branch of Big Sewickley Creek,
     2             Franklin Park Borough, Bridge
     3             Replacement                                    84,000
     4             (Base Construction Allocation -
     5             $76,000)
     6             (Design and Contingencies - $8,000)
     7         (53)  SR 8002, Crosstown Boulevard Bridge
     8             over Forbes and Diamond Street and
     9             Ramps, City of Pittsburgh, Bridge
    10             Painting                                      310,000
    11             (Base Construction Allocation -
    12             $300,000)
    13             (Design and Contingencies - $10,000)
    14         (54)  SR 8002, Ramp L Road Bridge over
    15             Forbes and Diamond Streets, City of
    16             Pittsburgh, Bridge Painting                   110,000
    17             (Base Construction Allocation -
    18             $100,000)
    19             (Design and Contingencies - $10,000)
    20         (55)  SR 8015, Ramp D Road Bridge over Ohio
    21             River Back Channel, Neville Township,
    22             Bridge Rehabilitation                         800,000
    23             (Base Construction Allocation -
    24             $700,000)
    25             (Design and Contingencies - $100,000)
    26         (56)  SR 8015, Ramp E Road Bridge over PC&Y
    27             Railroad, Neville Township, Bridge
    28             Rehabilitation                                670,000
    29             (Base Construction Allocation -
    30             $500,000)
    19970S0186B0698                 - 26 -

     1             (Design and Contingencies - $170,000)
     2         (57)  SR 8015, I-79 Ramp H Bridge over PC&Y
     3             Railroad, Neville Township, Bridge
     4             Rehabilitation                                700,000
     5             (Base Construction Allocation -
     6             $600,000)
     7             (Design and Contingencies - $100,000)
     8         (58)  SR 8015, Ramp J Road Bridge over
     9             Neville Road, Neville Township, Bridge
    10             Rehabilitation                                220,000
    11             (Base Construction Allocation -
    12             $200,000)
    13             (Design and Contingencies - $20,000)
    14         (59)  SR 8017, Ramp B2 Road Bridge over SR
    15             4025 and SR 4033, Glenfield Borough,
    16             Bridge Rehabilitation                         110,000
    17             (Base Construction Allocation -
    18             $100,000)
    19             (Design and Contingencies - $10,000)
    20         (60)  SR 8017, Ramp B Road Bridge over Ramp
    21             A and SR 4033, Glenfield Borough,
    22             Bridge Rehabilitation                         120,000
    23             (Base Construction Allocation -
    24             $110,000)
    25             (Design and Contingencies - $10,000)
    26         (61)  SR 8017, Ramp B1 Road Bridge over SR
    27             0065 Ramps A1 and R, Glenfield Borough,
    28             Bridge Rehabilitation                         165,000
    29             (Base Construction Allocation -
    30             $150,000)
    19970S0186B0698                 - 27 -

     1             (Design and Contingencies - $15,000)
     2         (62)  SR 8017, Ramp A Road Bridge over Ramp
     3             B3, Glenfield Borough, Bridge
     4             Rehabilitation                                110,000
     5             (Base Construction Allocation -
     6             $100,000)
     7             (Design and Contingencies - $10,000)
     8         (63)  SR 0028, Etna Bridges, Phase III,
     9             Northbound Bridge No.4 to Existing SR
    10             0028, Two Structures, Etna and
    11             Sharpsburg Boroughs, Bridge
    12             Rehabilitation                              6,300,000
    13             (Base Construction Allocation -
    14             $6,000,000)
    15             (Land Allocation - $300,000)
    16         (64)  SR 0028, Etna Bridge, Phase II,
    17             Southbound Bridge No.3 and Northbound
    18             Bridge for SR 0008 Connection, Etna and
    19             Sharpsburg Boroughs and Shaler
    20             Township, Bridge Rehabilitation            13,200,000
    21             (Base Construction Allocation -
    22             $12,200,000)
    23             (Land Allocation - $1,000,000)
    24         (65)  SR 2013, Monessen-Elizabeth Road
    25             Bridge over Becketts Run, Forward
    26             Township, Bridge Replacement                  450,000
    27             (Base Construction Allocation -
    28             $300,000)
    29             (Land Allocation - $50,000)
    30             (Design and Contingencies - $100,000)
    19970S0186B0698                 - 28 -

     1         (66)  SR 2016, JEFFERSON HEIGHTS ROAD                      <--
     2             BRIDGE OVER I-376, WILKINS TOWNSHIP,
     3             BRIDGE RECONSTRUCTION                       1,600,000
     4             (BASE CONSTRUCTION ALLOCATION -
     5             $1,200,000)
     6             (DESIGN AND CONTINGENCIES - $400,000)
     7  Section 7.  Armstrong County.
     8     (a)  Local Bridges
     9         (1)  Boggs Township, T-850, Scrubgrass
    10             Bridge over Scrubgrass Creek, Bridge
    11             Rehabilitation                                230,000
    12             (Base Construction Allocation -
    13             $170,000)
    14             (Land Allocation - $10,000)
    15             (Design and Contingencies - $50,000)
    16         (2)  Boggs Township, T-632, Scrubgrass
    17             Bridge No.2 over Scrubgrass Creek,
    18             Bridge Rehabilitation                         185,000
    19             (Base Construction Allocation -
    20             $150,000)
    21             (Land Allocation - $10,000)
    22             (Design and Contingencies - $25,000)
    23         (3)  Boggs Township, T-821, Pine Creek
    24             Bridge over North Fork of Pine Creek,
    25             Bridge Rehabilitation                         140,000
    26             (Base Construction Allocation -
    27             $100,000)
    28             (Land Allocation - $10,000)
    29             (Design and Contingencies - $30,000)
    30         (4)  North Buffalo Township, T-300, Blaine
    19970S0186B0698                 - 29 -

     1             Bridge over Buffalo Creek, Bridge
     2             Replacement                                   500,000
     3             (Base Construction Allocation -
     4             $400,000)
     5             (Land Allocation - $20,000)
     6             (Design and Contingencies - $80,000)
     7         (5)  North Buffalo Township, T-414, Church
     8             Road Bridge over Stream, Bridge
     9             Replacement                                   150,000
    10             (Base Construction Allocation -
    11             $100,000)
    12             (Land Allocation - $10,000)
    13             (Design and Contingencies - $40,000)
    14         (6)  West Kittanning Borough, T-759, Bridge
    15             over Stream, Bridge Replacement               325,000
    16             (Base Construction Allocation -
    17             $265,000)
    18             (Land Allocation - $10,000)
    19             (Design and Contingencies - $50,000)
    20     (b)  State Bridges
    21         (1)  SR 0028, Buffalo Creek Bridge over
    22             Buffalo Creek and Conrail, South
    23             Buffalo Township, Bridge Painting           3,010,000
    24             (Base Construction Allocation -
    25             $3,000,000)
    26             (Design and Contingencies - $10,000)
    27         (2)  SR 3023, Iron Bridge Road, Pine Run
    28             Bridge Replacement, South Buffalo
    29             Township, Bridge Replacement                  550,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 30 -

     1             $510,000)
     2             (Land Allocation - $20,000)
     3             (Design and Contingencies - $20,000)
     4         (3)  SR 0156, Long Run Bridge over Long
     5             Run, Kiskiminetas Township, Bridge
     6             Painting                                       75,000
     7             (Base Construction Allocation -
     8             $60,000)
     9             (Design and Contingencies - $15,000)
    10         (4)  SR 0422, US 422 Eastbound Overpass
    11             Bridge over SR 0028, East Franklin
    12             Township, Bridge Painting                     190,000
    13             (Base Construction Allocation -
    14             $175,000)
    15             (Design and Contingencies - $15,000)
    16         (5)  SR 0422, US 422 Westbound Overpass
    17             Bridge over SR 0028, East Franklin
    18             Township, Bridge Painting                     190,000
    19             (Base Construction Allocation -
    20             $175,000)
    21             (Design and Contingencies - $15,000)
    22         (6)  SR 1028, Oscar Bridge over Pine Creek,
    23             Boggs Township, Bridge Painting                95,000
    24             (Base Construction Allocation -
    25             $80,000)
    26             (Design and Contingencies - $15,000)
    27         (7)  SR 0028, Buffalo Creek Bridge over
    28             Buffalo Creek, South Buffalo Township,
    29             Bridge Painting                             1,730,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 31 -

     1             $1,700,000)
     2             (Design and Contingencies - $30,000)
     3         (8)  SR 0066, Guffy Run Bridge over Guffy
     4             Run, Parks Township, Bridge Painting           85,000
     5             (Base Construction Allocation -
     6             $70,000)
     7             (Design and Contingencies - $15,000)
     8         (9)  SR 0066, Garrett's Run Bridge over
     9             Garrett's Run and Old 66, Manor
    10             Township, Bridge Painting                   1,230,000
    11             (Base Construction Allocation -
    12             $1,200,000)
    13             (Design and Contingencies - $30,000)
    14         (10)  SR 0128, Cadogan Bridge over
    15             Tributary of Allegheny River, Cadogan
    16             Township, Bridge Painting                     380,000
    17             (Base Construction Allocation -
    18             $360,000)
    19             (Design and Contingencies - $20,000)
    20         (11)  SR 0422, Judge Graff Bridge over
    21             Allegheny River, North Buffalo
    22             Township, Bridge Painting                   2,930,000
    23             (Base Construction Allocation -
    24             $2,900,000)
    25             (Design and Contingencies - $30,000)
    26         (12)  SR 0422, Ramp C and F Bridge over End
    27             of Bypass, Manor Township, Bridge
    28             Painting                                      180,000
    29             (Base Construction Allocation -
    30             $165,000)
    19970S0186B0698                 - 32 -

     1             (Design and Contingencies - $15,000)
     2         (13)  SR 0422, Ramp F Bridge over SR 0066,
     3             Manor Township, Bridge Painting               190,000
     4             (Base Construction Allocation -
     5             $175,000)
     6             (Design and Contingencies - $15,000)
     7         (14)  SR 1021, Eddyville Bridge over Pine
     8             Run, Redbank Township, Bridge Painting        100,000
     9             (Base Construction Allocation -
    10             $85,000)
    11             (Design and Contingencies - $15,000)
    12         (15)  SR 1028, Bryan Bridge over Branch of
    13             Pine Creek, Cowanshannock Township,
    14             Bridge Painting                                50,000
    15             (Base Construction Allocation -
    16             $35,000)
    17             (Design and Contingencies - $15,000)
    18         (16)  SR 1034, Mosgrove Bridge over North
    19             Fork of Pine Creek, Boggs Township,
    20             Bridge Painting                                65,000
    21             (Base Construction Allocation -
    22             $50,000)
    23             (Design and Contingencies - $15,000)
    24         (17)  SR 1037, Echo Bridge over Pine Creek,
    25             Wayne Township, Bridge Painting                85,000
    26             (Base Construction Allocation -
    27             $70,000)
    28             (Design and Contingencies - $15,000)
    29         (18)  SR 2001, Rural Valley Bridge over
    30             Cowanshannock Creek, Rural Valley
    19970S0186B0698                 - 33 -

     1             Borough, Bridge Painting                      130,000
     2             (Base Construction Allocation -
     3             $115,000)
     4             (Design and Contingencies - $15,000)
     5         (19)  SR 2005, Brick Church Bridge over
     6             Branch of Cherry Run, Burrell Township,
     7             Bridge Painting                                75,000
     8             (Base Construction Allocation -
     9             $60,000)
    10             (Design and Contingencies - $15,000)
    11         (20)  SR 2005, Cherry Run Bridge over
    12             Cherry Run, Plumcreek Township, Bridge
    13             Painting                                       85,000
    14             (Base Construction Allocation -
    15             $70,000)
    16             (Design and Contingencies - $15,000)
    17         (21)  SR 2005, Elgin Cemetery Bridge over
    18             Cowanshannock Creek, Cowanshannock
    19             Township, Bridge Painting                      85,000
    20             (Base Construction Allocation -
    21             $70,000)
    22             (Design and Contingencies - $15,000)
    23         (22)  SR 2010, Garrett's Run Bridge over
    24             Garrett's Run, Manor Township, Bridge
    25             Painting                                       75,000
    26             (Base Construction Allocation -
    27             $60,000)
    28             (Design and Contingencies - $15,000)
    29         (23)  SR 2023, Wheel-in-Campground Bridge
    30             over Plum Creek, Plumcreek Township,
    19970S0186B0698                 - 34 -

     1             Bridge Painting                               125,000
     2             (Base Construction Allocation -
     3             $110,000)
     4             (Design and Contingencies - $15,000)
     5         (24)  SR 2025, Garrett's Run Bridge No.1
     6             over Garrett's Run, Manor Township,
     7             Bridge Painting                                80,000
     8             (Base Construction Allocation -
     9             $65,000)
    10             (Design and Contingencies - $15,000)
    11         (25)  SR 2025, Garrett's Run Bridge No.2
    12             over Garrett's Run, Manor Township,
    13             Bridge Painting                                80,000
    14             (Base Construction Allocation -
    15             $65,000)
    16             (Design and Contingencies - $15,000)
    17         (26)  SR 2025, Garrett's Run Bridge No.3
    18             over Garrett's Run, Manor Township,
    19             Bridge Painting                                90,000
    20             (Base Construction Allocation -
    21             $75,000)
    22             (Design and Contingencies - $15,000)
    23         (27)  SR 2027, Girty Bridge over Crooked
    24             Creek, South Bend Township, Bridge
    25             Painting                                      155,000
    26             (Base Construction Allocation -
    27             $140,000)
    28             (Design and Contingencies - $15,000)
    29         (28)  SR 2029, Kelly's Station Road Bridge
    30             over Taylor Run, Bethel Township,
    19970S0186B0698                 - 35 -

     1             Bridge Painting                                60,000
     2             (Base Construction Allocation -
     3             $45,000)
     4             (Design and Contingencies - $15,000)
     5         (29)  SR 2036, Stilt's Run Bridge over
     6             Stilt's Run, Parks Township, Bridge
     7             Painting                                       50,000
     8             (Base Construction Allocation -
     9             $35,000)
    10             (Design and Contingencies - $15,000)
    11         (30)  SR 2036, Carnahan Run Bridge over
    12             Carnahan Run, Parks Township, Bridge
    13             Painting                                       75,000
    14             (Base Construction Allocation -
    15             $60,000)
    16             (Design and Contingencies - $15,000)
    17         (31)  SR 2050, Rattling Run Bridge over
    18             Rattling Run, Kiskiminetas Township,
    19             Bridge Painting                                65,000
    20             (Base Construction Allocation -
    21             $50,000)
    22             (Design and Contingencies - $15,000)
    23         (32)  SR 2051, Flat Run Bridge over Flat
    24             Run, Kiskiminetas Township, Bridge
    25             Painting                                       55,000
    26             (Base Construction Allocation -
    27             $40,000)
    28             (Design and Contingencies - $15,000)
    29         (33)  SR 2051, Equitable Bridge over
    30             Rattling Run, Kiskiminetas Township,
    19970S0186B0698                 - 36 -

     1             Bridge Painting                                55,000
     2             (Base Construction Allocation -
     3             $40,000)
     4             (Design and Contingencies - $15,000)
     5         (34)  SR 2057, Parks Pump Station Bridge
     6             No.1 over Carnahan Run, Parks Township,
     7             Bridge Painting                                80,000
     8             (Base Construction Allocation -
     9             $65,000)
    10             (Design and Contingencies - $15,000)
    11         (35)  SR 2058, Parks Pump Station Bridge
    12             No.2 over Carnahan Run, Parks Township,
    13             Bridge Painting                                75,000
    14             (Base Construction Allocation -
    15             $60,000)
    16             (Design and Contingencies - $15,000)
    17         (36)  SR 3005, Glade Run Bridge over Glade
    18             Run, North Buffalo Township, Bridge
    19             Painting                                       75,000
    20             (Base Construction Allocation -
    21             $60,000)
    22             (Design and Contingencies - $15,000)
    23         (37)  SR 3013, Little Buffalo Bridge over
    24             Little Buffalo Creek, West Franklin
    25             Township, Bridge Painting                     100,000
    26             (Base Construction Allocation -
    27             $85,000)
    28             (Design and Contingencies - $15,000)
    29         (38)  SR 3013, Harrigan Run Bridge over
    30             Harrigan Run, West Franklin Township,
    19970S0186B0698                 - 37 -

     1             Bridge Painting                                60,000
     2             (Base Construction Allocation -
     3             $45,000)
     4             (Design and Contingencies - $15,000)
     5         (39)  SR 3017, West Penn Power Bridge over
     6             SR 0422 and SR 0028, East Franklin
     7             Township, Bridge Painting                     375,000
     8             (Base Construction Allocation -
     9             $360,000)
    10             (Design and Contingencies - $15,000)
    11         (40)  SR 4007, Kaylor Bridge over Sugar
    12             Creek, Bradys Bend Township, Bridge
    13             Painting                                       60,000
    14             (Base Construction Allocation -
    15             $45,000)
    16             (Design and Contingencies - $15,000)
    17         (41)  SR 4013, Foster Mills Bridge over
    18             Branch of Patterson Run, Sugarcreek
    19             Township, Bridge Painting                      70,000
    20             (Base Construction Allocation -
    21             $55,000)
    22             (Design and Contingencies - $15,000)
    23         (42)  SR 8008, Ford City Ramp from Judge
    24             Graff Bridge over a ravine, Manor
    25             Township, Bridge Painting                     555,000
    26             (Base Construction Allocation -
    27             $540,000)
    28             (Design and Contingencies - $15,000)
    29         (43)  SR 4035, Craigsville Bridge over
    30             Buffalo Creek, West Franklin Township,
    19970S0186B0698                 - 38 -

     1             Bridge Painting                               140,000
     2             (Base Construction Allocation -
     3             $125,000)
     4             (Design and Contingencies - $15,000)
     5         (44)  SR 0068, Kaylor Overpass, Railroad
     6             over PA 68, Bradys Bend Township,
     7             Bridge Removal                                560,000
     8             (Base Construction Allocation -
     9             $500,000)
    10             (Land Allocation - $10,000)
    11             (Design and Contingencies - $50,000)
    12         (45)  SR 0068, B&LE Railroad Overpass,
    13             Bradys Bend Township, Bridge Removal           55,000
    14             (Base Construction Allocation -
    15             $50,000)
    16             (Design and Contingencies - $5,000)
    17  Section 8.  Beaver County.
    18     (a)  Local Bridges
    19         (1)  Ambridge and Aliquippa Boroughs,
    20             Ambridge - Aliquippa Bridge over Ohio
    21             River, Bridge Construction                 38,000,000
    22             (Base Construction Allocation -
    23             $30,000,000)
    24             (Land Allocation - $4,000,000)
    25             (Design and Contingencies - $4,000,000)
    26         (2)  Vanport Township, Vanport Bridge No.6
    27             over Two Mile Run, Bridge Replacement         465,000
    28             (Base Construction Allocation -
    29             $375,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 39 -

     1             (Design and Contingencies - $80,000)
     2         (3)  Vanport Township, Vanport Bridge No.7
     3             over Two Mile Run, Bridge Replacement         470,000
     4             (Base Construction Allocation -
     5             $380,000)
     6             (Land Allocation - $10,000)
     7             (Design and Contingencies - $80,000)
     8         (4)  Vanport Township, Vanport Bridge No.8
     9             over Two Mile Run, Bridge Replacement         510,000
    10             (Base Construction Allocation -
    11             $420,000)
    12             (Land Allocation - $10,000)
    13             (Design and Contingencies - $80,000)
    14         (5)  Vanport Township, Vanport Bridge No.9
    15             over Two Mile Run, Bridge Replacement         440,000
    16             (Base Construction Allocation -
    17             $350,000)
    18             (Land Allocation - $10,000)
    19             (Design and Contingencies - $80,000)
    20         (6)  BOROUGH OF NEW GALILEE, WASHINGTON                    <--
    21             STREET BRIDGE OVER JORDAN RUN, BRIDGE
    22             REPLACEMENT                                 1,000,000
    23     (b)  State Bridges
    24         (1)  SR 0051, Bridge over New York Avenue,
    25             Ramp A, Rochester Borough, Bridge Deck
    26             Replacement                                 5,600,000
    27             (Base Construction Allocation -
    28             $5,500,000)
    29             (Design and Contingencies - $100,000)
    30         (2)  SR 0351, 5th Street, Koppel-Ellwood
    19970S0186B0698                 - 40 -

     1             Bridge over Beaver River, Koppel
     2             Borough and North Sewickley Township,
     3             Bridge Replacement, Phase I                33,500,000
     4             (Base Construction Allocation -
     5             $30,000,000)
     6             (Land Allocation - $1,000,000)
     7             (Design and Contingencies - $2,500,000)
     8         (3)  SR 1014, Wise's Grove Road Bridge over
     9             Brush Creek, Marion Township, Bridge
    10             Rehabilitation                                750,000
    11             (Base Construction Allocation -
    12             $600,000)
    13             (Land Allocation - $50,000)
    14             (Design and Contingencies - $100,000)
    15         (4)  SR 1022, 13th Street Bridge over
    16             Blockhouse Run at Pulaski County Line,
    17             New Brighton Borough, Bridge
    18             Replacement                                   780,000
    19             (Base Construction Allocation -
    20             $480,000)
    21             (Land Allocation - $50,000)
    22             (Design and Contingencies - $250,000)
    23         (5)  SR 4032, Engle Road Bridge over Six
    24             Mile Run Creek, Industry Borough,
    25             Bridge Replacement                            350,000
    26             (Base Construction Allocation -
    27             $200,000)
    28             (Land Allocation - $50,000)
    29             (Design and Contingencies - $100,000)
    30         (6)  SR 4033, Wildwood Road Bridge over
    19970S0186B0698                 - 41 -

     1             Brady's Run, Patterson Township, Bridge
     2             Replacement                                   400,000
     3             (Base Construction Allocation -
     4             $250,000)
     5             (Land Allocation - $50,000)
     6             (Design and Contingencies - $100,000)
     7         (7)  SR 8035, Ramp A at LR 641 over Slope,
     8             Rochester Borough, Bridge
     9             Rehabilitation                              1,200,000
    10             (Base Construction Allocation -
    11             $1,000,000)
    12             (Land Allocation - $50,000)
    13             (Design and Contingencies - $150,000)
    14         (8)  SR 8037, Ramp F over TR 51 and TR 65
    15             Northbound, Rochester Borough, Bridge
    16             Replacement                                   550,000
    17             (Base Construction Allocation -
    18             $400,000)
    19             (Land Allocation - $50,000)
    20             (Design and Contingencies - $100,000)
    21         (9)  SR 8039, Ramp AD, SR 0168 over TR 51,
    22             Bridgewater Borough, Bridge
    23             Rehabilitation                                700,000
    24             (Base Construction Allocation -
    25             $550,000)
    26             (Land Allocation - $50,000)
    27             (Design and Contingencies - $100,000)
    28         (10)  SR 3018, Culvert-pipe Style Bridge
    29             over Moody's Run, Greene Township,
    30             Bridge Construction                           385,000
    19970S0186B0698                 - 42 -

     1             (Base Construction Allocation -
     2             $350,000)
     3             (Design and Contingencies - $35,000)
     4         (11)  SR 0051, Pennsylvania Avenue Bridge
     5             over Brady's Run Creek, Fallston
     6             Borough, Bridge Replacement                   757,000
     7             (Base Construction Allocation -
     8             $637,000)
     9             (Land Allocation - $20,000)
    10             (Design and Contingencies - $100,000)
    11         (12)  SR 0060, Beaver Valley Extension
    12             Southbound Bridge over T-535, Brighton
    13             Township, Bridge Rehabilitation               167,000
    14             (Base Construction Allocation -
    15             $153,000)
    16             (Design and Contingencies - $14,000)
    17         (13)  SR 0060, Beaver Valley Extension
    18             Northbound Bridge over T-535, Brighton
    19             Township, Bridge Rehabilitation               178,000
    20             (Base Construction Allocation -
    21             $163,000)
    22             (Design and Contingencies - $15,000)
    23         (14)  SR 0060, Beaver Valley Expansion
    24             Bridge over SR 0151, Hopewell Township,
    25             Bridge Deck Replacement                     1,125,000
    26             (Base Construction Allocation -
    27             $1,000,000)
    28             (Design and Contingencies - $125,000)
    29         (15)  SR 0588, Riverview Road Bridge over
    30             Pine Run, Marion Township, Bridge
    19970S0186B0698                 - 43 -

     1             Replacement                                   250,000
     2             (Base Construction Allocation -
     3             $150,000)
     4             (Design and Contingencies - $100,000)
     5         (16)  SR 1009, Hartzel Road Bridge over
     6             Connoquenessing Creek, Marion Township,
     7             Bridge Replacement                          1,150,000
     8             (Base Construction Allocation -
     9             $1,000,000)
    10             (Land Allocation - $50,000)
    11             (Design and Contingencies - $100,000)
    12         (17)  SR 1016, Tatko Road Bridge over Brush
    13             Creek, New Sewickley Township, Bridge
    14             Replacement                                   420,000
    15             (Base Construction Allocation -
    16             $300,000)
    17             (Land Allocation - $20,000)
    18             (Design and Contingencies - $100,000)
    19         (18)  SR 1032, New York Avenue Bridge over
    20             Conrail, SR 1032 and Local Street,
    21             Rochester Borough, Bridge
    22             Rehabilitation                              3,100,000
    23             (Base Construction Allocation -
    24             $3,000,000)
    25             (Design and Contingencies - $100,000)
    26         (19)  SR 4035, Sebring Road Bridge over SR
    27             0060, Brighton Township, Bridge
    28             Rehabilitation                                394,000
    29             (Base Construction Allocation -
    30             $361,000)
    19970S0186B0698                 - 44 -

     1             (Design and Contingencies - $33,000)
     2         (20)  SR 3032, Kendal Harshavile Road
     3             Bridge over Branch of Traverse Creek,
     4             Hanover Township, Bridge Replacement          250,000
     5             (Base Construction Allocation -
     6             $100,000)
     7             (Land Allocation - $50,000)
     8             (Design and Contingencies - $100,000)
     9  Section 9.  Bedford County.
    10     (a)  Local Bridges
    11         (1)  Broad Top Township, T-550, Mosquito
    12             Bridge over Six Mile Run, Bridge
    13             Replacement                                   505,000
    14             (Base Construction Allocation -
    15             $400,000)
    16             (Land Allocation - $10,000)
    17             (Design and Contingencies - $95,000)
    18         (2)  Broad Top Township, T-553, Langdondale
    19             Bridge over Sandy Run, Bridge
    20             Replacement                                   395,000
    21             (Base Construction Allocation -
    22             $300,000)
    23             (Land Allocation - $10,000)
    24             (Design and Contingencies - $85,000)
    25         (3)  Broad Top Township, T-583, Longs Run
    26             Bridge over Longs Run, Bridge
    27             Replacement                                   395,000
    28             (Base Construction Allocation -
    29             $300,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 45 -

     1             (Design and Contingencies - $85,000)
     2         (4)  Harrison Township, T-418, Turner
     3             Covered Bridge over Juniata River,
     4             Bridge Rehabilitation                         825,000
     5             (Base Construction Allocation -
     6             $700,000)
     7             (Land Allocation - $25,000)
     8             (Design and Contingencies - $100,000)
     9         (5)  Monroe Township, T-354, Sideling Hill
    10             over East Branch Sideling Hill Creek,
    11             Bridge Replacement                            335,000
    12             (Base Construction Allocation -
    13             $250,000)
    14             (Land Allocation - $10,000)
    15             (Design and Contingencies - $75,000)
    16         (6)  South Woodbury Township, T-705 over
    17             Three Springs Run, Bridge Replacement         450,000
    18             (Base Construction Allocation -
    19             $325,000)
    20             (Land Allocation - $50,000)
    21             (Design and Contingencies - $75,000)
    22         (7)  West St. Clair Township, T-565 over
    23             Dunning Creek, Bridge Replacement             550,000
    24             (Base Construction Allocation -
    25             $450,000)
    26             (Land Allocation - $25,000)
    27             (Design and Contingencies - $75,000)
    28         (8)  Londonderry Township, T-653 over Wills
    29             Creek, Bridge Replacement                     945,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 46 -

     1             $850,000)
     2             (Land Allocation - $20,000)
     3             (Design and Contingencies - $75,000)
     4         (9)  East Providence Township, T-419 over
     5             Brush Creek, Bridge Replacement             1,170,000
     6             (Base Construction Allocation -
     7             $1,000,000)
     8             (Land Allocation - $20,000)
     9             (Design and Contingencies - $150,000)
    10         (10)  Broadtop Township, T-677, Riddlesburg
    11             Bridge, County Bridge No.35 over Six
    12             Mile Run, Bridge Replacement                  190,000
    13             (Base Construction Allocation -
    14             $150,000)
    15             (Land Allocation - $5,000)
    16             Design and Contingencies - $35,000)
    17     (b)  State Bridges
    18         (1)  SR 0220, US 220, Northbound Bridge
    19             over Pennsylvania Turnpike, Bedford
    20             Township, Bridge Painting                     180,000
    21             (Base Construction Allocation -
    22             $150,000)
    23             (Design and Contingencies - $30,000)
    24         (2)  SR 0220, US 220, Southbound Bridge
    25             over Pennsylvania Turnpike, Bedford
    26             Township, Bridge Painting                     170,000
    27             (Base Construction Allocation -
    28             $140,000)
    29             (Design and Contingencies - $30,000)
    30  Section 10.  Berks County.
    19970S0186B0698                 - 47 -

     1     (a)  Local Bridges
     2         (1)  City of Reading, Fritz Island Bridge
     3             over Angelica Creek, Bridge
     4             Rehabilitation                                 23,000
     5             (Base Construction Allocation -
     6             $20,000)
     7             (Design and Contingencies - $3,000)
     8         (2)  City of Reading, Bernadine Street over
     9             Angelica Creek, Bridge Rehabilitation         175,000
    10             (Base Construction Allocation -
    11             $145,000)
    12             (Design and Contingencies - $30,000)
    13         (3)  City of Reading, Tulpehocken Street
    14             Footbridge, Bridge Rehabilitation               6,000
    15             (Base Construction Allocation - $5,000)
    16             (Design and Contingencies - $1,000)
    17         (4)  West Reading Borough, Museum Road over
    18             Wyomissing Creek, Bridge
    19             Rehabilitation                                 15,000
    20             (Base Construction Allocation -
    21             $12,000)
    22             (Design and Contingencies - $3,000)
    23         (5)  Amity Township, Lake Drive over
    24             Tributary of Schuylkill River, Bridge
    25             Rehabilitation                                 86,000
    26             (Base Construction Allocation -
    27             $75,000)
    28             (Design and Contingencies - $11,000)
    29         (6)  Amity Township, Browns Mill Road over
    30             Spring Creek, Bridge Rehabilitation             6,000
    19970S0186B0698                 - 48 -

     1             (Base Construction Allocation - $5,000)
     2             (Design and Contingencies - $1,000)
     3         (7)  Amity Township, Valley Road over
     4             Spring Creek, Bridge Rehabilitation            10,000
     5             (Base Construction Allocation - $8,000)
     6             (Design and Contingencies - $2,000)
     7         (8)  Amity Township, Monocacy Road over
     8             Monocacy Creek, Bridge Rehabilitation          11,000
     9             (Base Construction Allocation - $9,000)
    10             (Design and Contingencies - $2,000)
    11         (9)  Bethel Township, T-492 over Little
    12             Swatara Creek, Bridge Replacement             700,000
    13             (Base Construction Allocation -
    14             $500,000)
    15             (Land Allocation - $50,000)
    16             (Design and Contingencies - $150,000)
    17         (10)  Bethel Township, T-682 over Crosskill
    18             Creek, Bridge Replacement                     750,000
    19             (Base Construction Allocation -
    20             $550,000)
    21             (Land Allocation - $50,000)
    22             (Design and Contingencies - $150,000)
    23         (11)  Lenhartsville Borough, Penn Avenue
    24             over Maiden Creek, Bridge Replacement         960,000
    25             (Base Construction Allocation -
    26             $750,000)
    27             (Land Allocation - $10,000)
    28             (Design and Contingencies - $200,000)
    29         (12)  Mohnton Borough, Main Street over
    30             Wyomissing Creek, Bridge Replacement          750,000
    19970S0186B0698                 - 49 -

     1             (Base Construction Allocation -
     2             $550,000)
     3             (Land Allocation - $50,000)
     4             (Design and Contingencies - $150,000)
     5         (13)  Muhlenberg Township, Hain Avenue over
     6             Laurel Run, Bridge Rehabilitation             100,000
     7             (Base Construction Allocation -
     8             $80,000)
     9             (Design and Contingencies - $20,000)
    10         (14)  Oley Township, T-500 over Furnace
    11             Creek, Bridge Replacement                     700,000
    12             (Base Construction Allocation -
    13             $500,000)
    14             (Land Allocation - $50,000)
    15             (Design and Contingencies - $150,000)
    16         (15)  Robesonia Borough, Freeman Street
    17             over Furnace Creek, Bridge Replacement        700,000
    18             (Base Construction Allocation -
    19             $500,000)
    20             (Land Allocation - $50,000)
    21             (Design and Contingencies - $150,000)
    22         (16)  Washington Township, T-884 over Swamp
    23             Creek, Bridge Replacement                     700,000
    24             (Base Construction Allocation -
    25             $500,000)
    26             (Land Allocation - $50,000)
    27             (Design and Contingencies - $150,000)
    28         (17)  Upper Bern Township, Mill Hill Road,
    29             T-712 over Mill Creek, Bridge
    30             Replacement                                    70,000
    19970S0186B0698                 - 50 -

     1             (Base Construction Allocation -
     2             $40,000)
     3             (Land Allocation - $10,000)
     4             (Design and Contingencies - $20,000)
     5         (18)  North Heidelberg Township, T-501,
     6             Milestone Road Bridge over Tributary of
     7             Spring Creek, Bridge Replacement               94,000
     8             (Base Construction Allocation -
     9             $82,000)
    10             (Land Allocation - $4,000)
    11             (Design and Contingencies - $8,000)
    12         (19)  Robeson Township, T-366, Bridge over
    13             Allegheny Creek, Bridge Replacement           133,000
    14             (Base Construction Allocation -
    15             $117,000)
    16             (Land Allocation - $5,000)
    17             (Design and Contingencies - $11,000)
    18     (b)  State Bridges
    19         (1)  SR 0010, Reading Road over Tributary
    20             of Conestoga Creek, Caernarvon
    21             Township, Bridge Rehabilitation               775,000
    22             (Base Construction Allocation -
    23             $490,000)
    24             (Land Allocation - $100,000)
    25             (Design and Contingencies - $185,000)
    26         (2)  SR 0222, SR 0222 Northbound over SR
    27             0737 Exit, Maxatawny Township, Bridge
    28             Painting                                       45,000
    29             (Base Construction Allocation -
    30             $45,000)
    19970S0186B0698                 - 51 -

     1         (3)  SR 0222, North Elm Street over SR
     2             0222, Kutztown Borough, Bridge
     3             Painting                                       45,000
     4             (Base Construction Allocation -
     5             $45,000)
     6         (4)  SR 0222, SR 0222 Northbound over SR
     7             8015, Ramp G, Maxatawny Township,
     8             Bridge Painting                                45,000
     9             (Base Construction Allocation -
    10             $45,000)
    11         (5)  SR 0222, SR 0222 Southbound over SR
    12             8015, Ramp G, Maxatawny Township,
    13             Bridge Painting                                45,000
    14             (Base Construction Allocation -
    15             $45,000)
    16         (6)  SR 2038, Grist Mill Road over
    17             Ironstone Creek, Douglass Township,
    18             Bridge Replacement                            405,000
    19             (Base Construction Allocation -
    20             $235,000)
    21             (Land Allocation - $70,000)
    22             (Design and Contingencies - $100,000)
    23         (7)  SR 0073, Bridge over Railroad, Maiden
    24             Creek Township, Bridge Rehabilitation          14,000
    25             (Base Construction Allocation -
    26             $12,000)
    27             (Design and Contingencies - $2,000)
    28         (8)  SR 2014, Spring Street Subway, City of
    29             Reading, Bridge Rehabilitation                 18,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 52 -

     1             $15,000)
     2             (Design and Contingencies - $3,000)
     3         (9)  SR 0073, SR 0073 over Manatawny Creek,
     4             Oley Township, Bridge Rehabilitation          500,000
     5             (Base Construction Allocation -
     6             $450,000)
     7             (Design and Contingencies - $50,000)
     8         (10)  SR 0061, SR 0061 over Blue Mountain
     9             Railroad, Borough of Hamburg, Bridge
    10             Rehabilitation                                200,000
    11             (Base Construction Allocation -
    12             $175,000)
    13             (Design and Contingencies - $25,000)
    14         (11)  SR 0078, SR 0078 over SR 1024,
    15             Greenwich Township, Bridge
    16             Rehabilitation                                500,000
    17             (Base Construction Allocation -
    18             $450,000)
    19             (Design and Contingencies - $50,000)
    20         (12)  SR 0078, SR 0078 over T-808, Windsor
    21             Township, Bridge Rehabilitation               500,000
    22             (Base Construction Allocation -
    23             $450,000)
    24             (Design and Contingencies - $50,000)
    25         (13)  SR 0078, SR 0078 over Fifth Street,
    26             Borough of Hamburg, Bridge
    27             Rehabilitation                                200,000
    28             (Base Construction Allocation -
    29             $175,000)
    30             (Design and Contingencies - $25,000)
    19970S0186B0698                 - 53 -

     1         (14)  SR 0078, SR 0078 over T-688, Bethel
     2             Township, Bridge Rehabilitation               250,000
     3             (Base Construction Allocation -
     4             $225,000)
     5             (Design and Contingencies - $25,000)
     6         (15)  SR 0176, SR 0176 over T-568, Robeson
     7             Township, Bridge Rehabilitation               250,000
     8             (Base Construction Allocation -
     9             $200,000)
    10             (Design and Contingencies - $50,000)
    11         (16)  SR 0176, SR 0176 2/10 mile south of
    12             SR 0422, Cumru Township, Bridge
    13             Rehabilitation                                350,000
    14             (Base Construction Allocation -
    15             $300,000)
    16             (Design and Contingencies - $50,000)
    17         (17)  SR 1083, SR 0183 over Little
    18             Northkill Creek, Jefferson Township,
    19             Bridge Replacement                          1,000,000
    20             (Base Construction Allocation -
    21             $750,000)
    22             (Land Allocation - $100,000)
    23             (Design and Contingencies - $150,000)
    24         (18)  SR 0222, SR 0222 over Abandoned
    25             Railroad, City of Reading, Bridge
    26             Rehabilitation                                200,000
    27             (Base Construction Allocation -
    28             $150,000)
    29             (Design and Contingencies - $50,000)
    30         (19)  SR 0422, SR 0422 over Tulpehocken
    19970S0186B0698                 - 54 -

     1             Creek, Borough of Womelsdorf, Bridge
     2             Rehabilitation                                200,000
     3             (Base Construction Allocation -
     4             $150,000)
     5             (Design and Contingencies - $50,000)
     6         (20)  SR 0568, SR 0568 over Allegheny
     7             Creek, Robeson Township, Bridge
     8             Rehabilitation                                100,000
     9             (Base Construction Allocation -
    10             $80,000)
    11             (Design and Contingencies - $20,000)
    12         (21)  SR 0737, SR 0737 2.63 miles north of
    13             Kutztown, Greenwich Township, Bridge
    14             Rehabilitation                                500,000
    15             (Base Construction Allocation -
    16             $450,000)
    17             (Design and Contingencies - $50,000)
    18         (22)  SR 0737, SR 0737 2.82 miles north of
    19             Kutztown, Greenwich Township, Bridge
    20             Rehabilitation                                500,000
    21             (Base Construction Allocation -
    22             $450,000)
    23             (Design and Contingencies - $50,000)
    24         (23)  SR 2025, SR 2025 1/2 mile east of SR
    25             0422, Amity Township, Bridge
    26             Replacement                                   300,000
    27             (Base Construction Allocation -
    28             $200,000)
    29             (Land Allocation - $15,000)
    30             (Design and Contingencies - $85,000)
    19970S0186B0698                 - 55 -

     1         (24)  SR 2031, SR 2031 over Hay Creek,
     2             Robeson Township, Bridge
     3             Rehabilitation                                500,000
     4             (Base Construction Allocation -
     5             $450,000)
     6             (Design and Contingencies - $50,000)
     7         (25)  SR 2032, SR 2032 over Tributary of
     8             Swamp Creek, Washington Township,
     9             Bridge Replacement                            500,000
    10             (Base Construction Allocation -
    11             $375,000)
    12             (Land Allocation - $25,000)
    13             (Design and Contingencies - $100,000)
    14         (26)  SR 2039, SR 2039 over SR 0422, Exeter
    15             Township, Bridge Replacement                2,750,000
    16             (Base Construction Allocation -
    17             $2,000,000)
    18             (Land Allocation - $250,000)
    19             (Design and Contingencies - $500,000)
    20         (27)  SR 2041, SR 2041 2 miles west of
    21             Weavertown, Amity Township, Bridge
    22             Replacement                                   200,000
    23             (Base Construction Allocation -
    24             $125,000)
    25             (Land Allocation - $15,000)
    26             (Design and Contingencies - $60,000)
    27         (28)  SR 2057, SR 2057 over Leaf Creek,
    28             Amity Township, Bridge Replacement            600,000
    29             (Base Construction Allocation -
    30             $425,000)
    19970S0186B0698                 - 56 -

     1             (Land Allocation - $25,000)
     2             (Design and Contingencies - $150,000)
     3         (29)  SR 3003, SR 3003 over Angelica Creek,
     4             Cumru Township, Bridge Replacement            200,000
     5             (Base Construction Allocation -
     6             $125,000)
     7             (Land Allocation - $15,000)
     8             (Design and Contingencies - $60,000)
     9         (30)  SR 4026, SR 4026 over Irish Creek,
    10             Borough of Centerport, Bridge
    11             Rehabilitation                                250,000
    12             (Base Construction Allocation -
    13             $225,000)
    14             (Design and Contingencies - $25,000)
    15         (31)  SR 0073, Bridge over Maiden Creek,
    16             Ontelaunee Township, Bridge
    17             Replacement                                 2,120,000
    18             (Base Construction Allocation -
    19             $2,000,000)
    20             (Land Allocation - $20,000)
    21             (Design and Contingencies - $100,000)
    22         (32)  SR 2021, Mineral Spring Road,
    23             Lindbergh Viaduct, City of Reading,
    24             Bridge Rehabilitation                       4,000,000
    25  Section 11.  Blair County.
    26     (a)  Local Bridges
    27         (1)  Antis Township, T-490, Becker Road
    28             Bridge over Tributary of Little Juniata
    29             River, Bridge Replacement                     310,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 57 -

     1             $250,000)
     2             (Land Allocation - $10,000)
     3             (Design and Contingencies - $50,000)
     4         (2)  Taylor Township, T-332, Halter Creek
     5             Bridge over Halter Creek, Bridge
     6             Replacement                                   395,000
     7             (Base Construction Allocation -
     8             $300,000)
     9             (Land Allocation - $10,000)
    10             (Design and Contingencies - $85,000)
    11         (3)  Greenfield Township, T-531 over South
    12             Poplar Run, Construct new bridge              280,000
    13             (Base Construction Allocation -
    14             $200,000)
    15             (Land Allocation - $20,000)
    16             (Design and Contingencies - $60,000)
    17         (4)  Greenfield Township, T-531 over Big
    18             Lick Branch of South Poplar Run, Bridge
    19             Replacement                                   565,000
    20             (Base Construction Allocation -
    21             $465,000)
    22             (Land Allocation - $30,000)
    23             (Design and Contingencies - $70,000)
    24         (5)  Greenfield Township, County Road 101
    25             over Polecat Run, Bridge Replacement          520,000
    26             (Base Construction Allocation -
    27             $400,000)
    28             (Land Allocation - $20,000)
    29             (Design and Contingencies - $100,000)
    30         (6)  Newry Borough, Allegheny Street over
    19970S0186B0698                 - 58 -

     1             Tributary of Poplar Run, Bridge
     2             Rehabilitation                                425,000
     3             (Base Construction Allocation -
     4             $350,000)
     5             (Land Allocation - $25,000)
     6             (Design and Contingencies - $50,000)
     7         (7)  Allegheny Township, Ellenberger Road,
     8             Quarry Bridge over Mill Run Creek,
     9             Bridge Replacement                            319,000
    10             (Base Construction Allocation -
    11             $277,000)
    12             (Design and Contingencies - $42,000)
    13     (b)  State bridges
    14         (1)  SR 0022, Canal Park Bridges over the
    15             Juniata River, Hollidaysburg Borough,
    16             Bridge Replacement                          3,000,000
    17             (Base Construction Allocation -
    18             $2,000,000)
    19             (Land Allocation - $650,000)
    20             (Design and Contingencies - $350,000)
    21         (2)  SR 4008, SR 4008 over Tributary of
    22             Glenwhite Run, Logan Township, Bridge
    23             Replacement                                   240,000
    24             (Base Construction Allocation -
    25             $200,000)
    26             (Land Allocation - $5,000)
    27             (Design and Contingencies - $35,000)
    28  Section 12.  Bradford County.
    29     (a)  Local Bridges
    30         (1)  Burlington Township, T-547 over Wallis
    19970S0186B0698                 - 59 -

     1             Run, Bridge Replacement                       395,000
     2             (Base Construction Allocation -
     3             $310,000)
     4             (Land Allocation - $10,000)
     5             (Design and Contingencies - $75,000)
     6         (2)  Pike Township, T-790 over Gaylord
     7             Creek and South Creek, Bridge
     8             Replacement                                   495,000
     9             (Base Construction Allocation -
    10             $410,000)
    11             (Land Allocation - $10,000)
    12             (Design and Contingencies - $75,000)
    13         (3)  Canton Township, T-889, County Bridge
    14             No.45 over Towanda Creek, Bridge
    15             Replacement                                   480,000
    16             (Base Construction Allocation -
    17             $400,000)
    18             (Land Allocation - $25,000)
    19             (Design and Contingencies - $55,000)
    20         (4)  Tuscarora Township, T-874, County
    21             Bridge No.36 over Fargo Creek, Bridge
    22             Replacement                                   265,000
    23             (Base Construction Allocation -
    24             $215,000)
    25             (Land Allocation - $15,000)
    26             (Design and Contingencies - $35,000)
    27         (5)  Franklin Township, T-358, County
    28             Bridge No.12 over Towanda Creek, Bridge
    29             Replacement                                 1,020,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 60 -

     1             $850,000)
     2             (Land Allocation - $50,000)
     3             (Design and Contingencies - $120,000)
     4         (6)  Litchfield Township, T-900, Parks
     5             Creek Structure Bridge over Parks
     6             Creek, Bridge Replacement                     390,000
     7             (Base Construction Allocation -
     8             $220,000)
     9             (Land Allocation - $20,000)
    10             (Design and Contingencies - $150,000)
    11         (7)  Albany Township, T-377, Bridge over
    12             Bowman Creek                                  390,000
    13             (Base Construction Allocation -
    14             $250,000)
    15             (Land Allocation - $10,000)
    16             (Design and Contingencies - $130,000)
    17         (8)  TOWANDA TOWNSHIP, T-545, BRIDGE OVER                  <--
    18             SUGAR CREEK, BRIDGE REPLACEMENT             1,247,000
    19             (BASE CONSTRUCTION ALLOCATION -
    20             $1,033,000)
    21             (LAND ALLOCATION - $65,000)
    22             (DESIGN AND CONTINGENCIES - $149,000)
    23         (9)  WELLS TOWNSHIP, T-763, BRIDGE OVER
    24             SEELY CREEK, BRIDGE REPLACEMENT               428,000
    25             (BASE CONSTRUCTION ALLOCATION -
    26             $355,000)
    27             (LAND ALLOCATION - $22,000)
    28             (DESIGN AND CONTINGENCIES - $51,000)
    29         (10)  TERRY TOWNSHIP, T-420, BRIDGE OVER
    30             FOSTER BRANCH OF SUGAR CREEK, BRIDGE
    19970S0186B0698                 - 61 -

     1             REPLACEMENT                                   663,000
     2             (BASE CONSTRUCTION ALLOCATION -
     3             $550,000)
     4             (LAND ALLOCATION - $33,000)
     5             (DESIGN AND CONTINGENCIES - $80,000)
     6     (b)  State Bridges
     7         (1)  SR 0006, North Bridge over Sugar
     8             Creek, South of Longs Pond Road, Bridge
     9             Replacement                                 1,139,000
    10             (Base Construction Allocation -
    11             $911,000)
    12             (Land Allocation - $57,000)
    13             (Design and Contingencies - $171,000)
    14         (2)  SR 0409, Billing Creek Bridge, Village
    15             of Camptown, Bridge Replacement               318,000
    16             (Base Construction Allocation -
    17             $254,000)
    18             (Land Allocation - $16,000)
    19             (Design and Contingencies - $48,000)
    20         (3)  SR 3029, Towanda Creek Bridges between
    21             T-327 and T-326 on Gulf Road, Village
    22             of Granville Center, Bridge
    23             Replacement                                   593,000
    24             (Base Construction Allocation -
    25             $474,000)
    26             (Land Allocation - $30,000)
    27             (Design and Contingencies - $89,000)
    28         (4)  SR 4008, Bridge over Tributary of
    29             Sugar Creek, Columbia Township, Bridge
    30             Replacement                                   298,000
    19970S0186B0698                 - 62 -

     1             (Base Construction Allocation -
     2             $238,000)
     3             (Land Allocation - $15,000)
     4             (Design and Contingencies - $45,000)
     5         (5)  SR 0414, Bridge over Towanda Creek,
     6             Bradford Borough, Bridge Painting             195,000
     7             (Base Construction Allocation -
     8             $185,000)
     9             (Design and Contingencies - $10,000)
    10         (6)  US 6, US 6 over Sugar Creek, Sylvania
    11             Borough, Bridge Replacement                   633,000
    12             (Base Construction Allocation -
    13             $506,000)
    14             (Land Allocation - $32,000)
    15             (Design and Contingencies - $95,000)
    16         (7)  SR 0014, SR 0014 over Tributary of
    17             Sugar Creek, Troy Township, Bridge
    18             Replacement                                   410,000
    19             (Base Construction Allocation -
    20             $280,000)
    21             (Land Allocation - $30,000)
    22             (Design and Contingencies - $100,000)
    23         (8)  SR 0187, SR 0187 over Wappensing                      <--
    24             WAPPASENING Creek, Windham Township,                   <--
    25             Bridge Replacement                          2,000,000
    26             (Base Construction Allocation -
    27             $1,600,000)
    28             (Land Allocation - $100,000)
    29             (Design and Contingencies - $300,000)
    30         (9)  SR 0414, SR 0414 over Tributary of
    19970S0186B0698                 - 63 -

     1             Towanda Creek, Canton Township, Bridge
     2             Replacement                                   320,000
     3             (Base Construction Allocation -
     4             $256,000)
     5             (Land Allocation - $16,000)
     6             (Design and Contingencies - $48,000)
     7         (10)  SR 0467, SR 0467 over Johnsons Creek,
     8             Orwell Township, Bridge Replacement           751,000
     9             (Base Construction Allocation -
    10             $601,000)
    11             (Land Allocation - $37,000)
    12             (Design and Contingencies - $113,000)
    13         (11)  SR 0514, SR 0514 over North Branch of
    14             Towanda Creek, Granville Township,
    15             Bridge Replacement                            638,000
    16             (Base Construction Allocation -
    17             $510,000)
    18             (Land Allocation - $32,000)
    19             (Design and Contingencies - $96,000)
    20         (12)  SR 1022, Ulster Bridge, Ulster
    21             Township, Bridge Painting                   6,299,000
    22             (Base Construction Allocation -
    23             $5,039,000)
    24             (Land Allocation - $315,000)
    25             (Design and Contingencies - $945,000)
    26         (13)  SR 1026, SR 1026 over Wyalusing
    27             Creek, Pike Township, Bridge
    28             Replacement                                   650,000
    29             (Base Construction Allocation -
    30             $520,000)
    19970S0186B0698                 - 64 -

     1             (Land Allocation - $30,000)
     2             (Design and Contingencies - $100,000)
     3         (14)  SR 1049, SR 1049 over Tributary of
     4             Pendleton Creek, Warren Township,
     5             Bridge Replacement                            340,000
     6             (Base Construction Allocation -
     7             $270,000)
     8             (Land Allocation - $15,000)
     9             (Design and Contingencies - $55,000)
    10         (15)  SR 1055, SR 1055 over Parks Creek,
    11             Rome Township, Bridge Replacement             315,000
    12             (Base Construction Allocation -
    13             $250,000)
    14             (Land Allocation - $15,000)
    15             (Design and Contingencies - $50,000)
    16         (16)  SR 2018, SR 2018 over Tributary of
    17             Susquehanna River, Asylum Township,
    18             Bridge Replacement                            260,000
    19             (Base Construction Allocation -
    20             $208,000)
    21             (Land Allocation - $39,000)
    22             (Design and Contingencies - $13,000)
    23         (17)  SR 3005, SR 3005 over Towanda Creek,
    24             Canton Township, Bridge Replacement           666,000
    25             (Base Construction Allocation -
    26             $533,000)
    27             (Land Allocation - $33,000)
    28             (Design and Contingencies - $100,000)
    29         (18)  SR 3029, SR 3029 over Mud Creek, Troy
    30             Township, Bridge Replacement                  457,000
    19970S0186B0698                 - 65 -

     1             (Base Construction Allocation -
     2             $366,000)
     3             (Land Allocation - $23,000)
     4             (Design and Contingencies - $68,000)
     5         (19)  SR 4002, SR 4002 over Browns Creek,
     6             Burlington Township, Bridge
     7             Replacement                                   561,000
     8             (Base Construction Allocation -
     9             $449,000)
    10             (Land Allocation - $28,000)
    11             (Design and Contingencies - $84,000)
    12         (20)  SR 4013, SR 4013 over Justice Run,
    13             Ridgebury Township, Bridge Replacement        351,000
    14             (Base Construction Allocation -
    15             $281,000)
    16             (Land Allocation - $18,000)
    17             (Design and Contingencies - $52,000)
    18         (21)  SR 4014, SR 4014 over Branch of
    19             Tomjack Creek, Smithfield Township,
    20             Bridge Replacement                            360,000
    21             (Base Construction Allocation -
    22             $288,000)
    23             (Land Allocation - $18,000)
    24             (Design and Contingencies - $54,000)
    25         (22)  SR 4015, SR 4015 over Mill Creek,
    26             Springfield Township, Bridge
    27             Replacement                                   390,000
    28             (Base Construction Allocation -
    29             $312,000)
    30             (Land Allocation - $20,000)
    19970S0186B0698                 - 66 -

     1             (Design and Contingencies - $58,000)
     2         (23)  SR 4031, SR 4031 over Tributary of
     3             Beckwith Creek, Wells Township, Bridge
     4             Replacement                                   243,000
     5             (Base Construction Allocation -
     6             $196,000)
     7             (Land Allocation - $10,000)
     8             (Design and Contingencies - $37,000)
     9         (24)  SR 2024, Bridge over Towanda Creek,
    10             Towanda Township, Bridge Replacement        1,740,000
    11             (Base Construction Allocation -
    12             $1,400,000)
    13             (Land Allocation - $40,000)
    14             (Design and Contingencies - $300,000)
    15         (25)  SR 4015, Bridge over Mill Creek,
    16             Springfield Township, Bridge
    17             Replacement                                   740,000
    18             (Base Construction Allocation -
    19             $600,000)
    20             (Land Allocation - $20,000)
    21             (Design and Contingencies - $120,000)
    22         (26)  PA 514, Bridge over North Branch of
    23             Towanda Creek, Granville Township,
    24             Bridge Replacement                            630,000
    25             (Base Construction Allocation -
    26             $500,000)
    27             (Land Allocation - $30,000)
    28             (Design and Contingencies - $100,000)
    29         (27)  US 6, Bridge over Sugar Creek,
    30             Sylvania Borough, Bridge Replacement          680,000
    19970S0186B0698                 - 67 -

     1             (Base Construction Allocation -
     2             $550,000)
     3             (Land Allocation - $30,000)
     4             (Design and Contingencies - $100,000)
     5         (28)  PA 549, Bridge over Daggett Creek,
     6             Wells Township, Bridge Replacement          1,180,000
     7             (Base Construction Allocation -
     8             $950,000)
     9             (Land Allocation - $30,000)
    10             (Design and Contingencies - $200,000)
    11         (29)  SR 4002, Bridge over Browns Creek,
    12             Burlington Township, Bridge
    13             Replacement                                   560,000
    14             (Base Construction Allocation -
    15             $450,000)
    16             (Land Allocation - $30,000)
    17             (Design and Contingencies - $80,000)
    18         (30)  SR 1026, Bridge over Wyalusing Creek,
    19             Pike Township, Bridge Replacement             650,000
    20             (Base Construction Allocation -
    21             $520,000)
    22             (Land Allocation - $30,000)
    23             (Design and Contingencies - $100,000)
    24         (31)  PA 187, Bridge over Wappasening
    25             Creek, Windham Township, Bridge
    26             Replacement                                 2,000,000
    27             (Base Construction Allocation -
    28             $1,600,000)
    29             (Land Allocation - $100,000)
    30             (Design and Contingencies - $300,000)
    19970S0186B0698                 - 68 -

     1         (32)  PA 199, Bridge over Chemung River
     2             Overflow Channel, Athens Township,
     3             Bridge Replacement                          2,000,000
     4             (Base Construction Allocation -
     5             $1,600,000)
     6             (Land Allocation - $100,000)
     7             (Design and Contingencies - $300,000)
     8         (33)  US 220, Bridge over Bridge Street,
     9             Towanda Borough, Bridge Rehabilitation        385,000
    10             (Base Construction Allocation -
    11             $350,000)
    12             (Design and Contingencies - $35,000)
    13         (34)  US 220, Bridge over SR 3020, Towanda
    14             Township, Bridge Rehabilitation               495,000
    15             (Base Construction Allocation -
    16             $450,000)
    17             (Design and Contingencies - $45,000)
    18         (35)  US 220, Bridge over SR 2036, North
    19             Towanda Township, Bridge
    20             Rehabilitation                                715,000
    21             (Base Construction Allocation -
    22             $650,000)
    23             (Design and Contingencies - $65,000)
    24         (36)  US 220, Bridge over SR 3022, North
    25             Towanda Township, Bridge
    26             Rehabilitation                                770,000
    27             (Base Construction Allocation -
    28             $700,000)
    29             (Design and Contingencies - $70,000)
    30         (37)  US 220, Bridge over US 6, North
    19970S0186B0698                 - 69 -

     1             Towanda Township, Bridge
     2             Reconstruction                              1,700,000
     3             (Base Construction Allocation -
     4             $1,500,000)
     5             (Design and Contingencies - $200,000)
     6  Section 13.  Bucks County.
     7     (a)  Local Bridges
     8         (1)  Springfield Township, I-479, Bridge
     9             Street Bridge over Cooks Creek, Bridge
    10             Replacement                                   500,000
    11             (Base Construction Allocation -
    12             $365,000)
    13             (Land Allocation - $35,000)
    14             (Design and Contingencies - $100,000)
    15         (2)  Springfield Township, T-404, Hawks
    16             Mill County Bridge No.196, Shale Road
    17             over Cooks Creek, Bridge
    18             Rehabilitation                                100,000
    19             (Base Construction Allocation -
    20             $90,000)
    21             (Design and Contingencies - $10,000)
    22     (b)  State Bridges
    23         (1)  SR 0032, River Road at Fleecydale over
    24             Paunacussing Creek, Solebury Township,
    25             Bridge Replacement                          1,400,000
    26             (Base Construction Allocation -
    27             $1,200,000)
    28             (Design and Contingencies - $200,000)
    29         (2)  SR 2002, Otter Street Bridge over
    30             Otter Creek, Bristol Borough, Bridge
    19970S0186B0698                 - 70 -

     1             Replacement                                 1,150,000
     2             (Base Construction Allocation -
     3             $900,000)
     4             (Land Allocation - $50,000)
     5             (Design and Contingencies - $200,000)
     6         (3)  SR 2025, Bristol Road Bridge over
     7             Little Neshaminy Creek, Warwick
     8             Township, Bridge Replacement                1,120,000
     9             (Base Construction Allocation -
    10             $900,000)
    11             (Land Allocation - $80,000)
    12             (Design and Contingencies - $140,000)
    13         (4)  SR 2047, Hulmeville Avenue Bridge over
    14             Conrail, Middletown, Bridge
    15             Replacement                                 5,600,000
    16             (Base Construction Allocation -
    17             $4,000,000)
    18             (Land Allocation - $800,000)
    19             (Design and Contingencies - $800,000)
    20         (5)  SR 4033, Upper Ridge Road Bridge over
    21             Unami Creek, Milford Township, Bridge
    22             Replacement                                 2,000,000
    23             (Base Construction Allocation -
    24             $1,600,000)
    25             (Land Allocation - $100,000)
    26             (Design and Contingencies - $300,000)
    27         (6)  SR 4091, Kellers Church Road Bridge
    28             over Deep Run, Bedminster, Bridge
    29             Replacement                                 2,000,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 71 -

     1             $1,500,000)
     2             (Land Allocation - $150,000)
     3             (Design and Contingencies - $350,000)
     4         (7)  SR 0202, Doylestown Bypass (Five
     5             Bridges) over SR 0611, Doylestown
     6             Township, Bridge Rehabilitations            2,200,000
     7             (Base Construction Allocation -
     8             $2,000,000)
     9             (Land Allocation - $50,000)
    10             (Design and Contingencies - $150,000)
    11         (8)  SR 0611, Easton Road (Two Bridges)
    12             over Tohickon and Deep Run Creeks,
    13             Bedminister Township, Bridge
    14             Replacements                                1,650,000
    15             (Base Construction Allocation -
    16             $1,500,000)
    17             (Land Allocation - $50,000)
    18             (Design and Contingencies - $100,000)
    19         (9)  SR 2089, Almshouse Road Bridge over
    20             Neshaminy Creek, Doylestown Township,
    21             Bridge Replacement                          1,800,000
    22             (Base Construction Allocation -
    23             $1,500,000)
    24             (Land Allocation - $150,000)
    25             (Design and Contingencies - $150,000)
    26         (10)  SR 0013, Bristol Pike over Otter
    27             Creek, Bristol Township, Bridge
    28             Replacement                                 1,600,000
    29             (Base Construction Allocation -
    30             $1,200,000)
    19970S0186B0698                 - 72 -

     1             (Land Allocation - $100,000)
     2             (Design and Contingencies - $300,000)
     3         (11)  SR 0413, Bridge over Mill Creek,
     4             Bristol Township, Bridge Replacement          600,000
     5             (Base Construction Allocation -
     6             $350,000)
     7             (Land Allocation - $50,000)
     8             (Design and Contingencies - $200,000)
     9         (12)  SR 2002, State Road over Neshaminy
    10             Creek, Bristol Township, Bridge
    11             Replacement                                 3,700,000
    12             (Base Construction Allocation -
    13             $3,000,000)
    14             (Land Allocation - $250,000)
    15             (Design and Contingencies - $450,000)
    16         (13)  SR 0013, Bristol Pike over St.
    17             Francis Creek, Bensalem Township,
    18             Bridge Replacement                            550,000
    19             (Base Construction Allocation -
    20             $400,000)
    21             (Land Allocation - $50,000)
    22             (Design and Contingencies - $100,000)
    23         (14)  SR 0013, SR 0013 over Conrail and
    24             Newbold Road, Falls Township, Bridge
    25             Replacement                                 5,000,000
    26             (Base Construction Allocation -
    27             $4,500,000)
    28             (Land Allocation - $150,000)
    29             (Design and Contingencies - $350,000)
    30         (15)  SR 0032, West Bridge Street over
    19970S0186B0698                 - 73 -

     1             Tributary of Delaware River,
     2             Morrisville Borough, Bridge
     3             Replacement                                   550,000
     4             (Base Construction Allocation -
     5             $400,000)
     6             (Land Allocation - $50,000)
     7             (Design and Contingencies - $100,000)
     8         (16)  SR 0213, West Maple Avenue over
     9             Neshaminy Creek, Middletown Township,
    10             Bridge Replacement                          2,000,000
    11             (Base Construction Allocation -
    12             $1,700,000)
    13             (Land Allocation - $100,000)
    14             (Design and Contingencies - $200,000)
    15         (17)  SR 1004, Cold Spring Creamery Road
    16             over Branch of Pine Run Creek,
    17             Buckingham Township, Bridge
    18             Replacement                                   450,000
    19             (Base Construction Allocation -
    20             $380,000)
    21             (Land Allocation - $10,000)
    22             (Design and Contingencies - $60,000)
    23         (18)  SR 2005, Cornwells Avenue over
    24             Poquessing Creek, Bensalem Township,
    25             Bridge Replacement                            350,000
    26             (Base Construction Allocation -
    27             $250,000)
    28             (Land Allocation - $25,000)
    29             (Design and Contingencies - $75,000)
    30         (19)  SR 2026, Trenton Avenue over Rock
    19970S0186B0698                 - 74 -

     1             Run, Falls Township, Bridge
     2             Replacement                                   700,000
     3             (Base Construction Allocation -
     4             $500,000)
     5             (Land Allocation - $50,000)
     6             (Design and Contingencies - $150,000)
     7         (20)  SR 2037, Lincoln Highway Eastbound
     8             over Queen Anne Creek, Falls Township,
     9             Bridge Replacement                            700,000
    10             (Base Construction Allocation -
    11             $500,000)
    12             (Land Allocation - $75,000)
    13             (Design and Contingencies - $125,000)
    14         (21)  SR 2037, Lincoln Highway over Branch
    15             of Queen Anne Creek, Falls Township,
    16             Bridge Replacement                            500,000
    17             (Base Construction Allocation -
    18             $350,000)
    19             (Land Allocation - $50,000)
    20             (Design and Contingencies - $100,000)
    21         (22)  SR 2047, Hulmeville Avenue over
    22             Conrail, Middletown Township, Bridge
    23             Replacement                                 1,200,000
    24             (Base Construction Allocation -
    25             $1,000,000)
    26             (Land Allocation - $75,000)
    27             (Design and Contingencies - $125,000)
    28  Section 14.  Butler County.
    29     (a)  Local Bridges
    30         (1)  Muddy Creek and Worth Townships, T-
    19970S0186B0698                 - 75 -

     1             348, Muddy Creek Bridge over Muddy
     2             Creek, Bridge Replacement                     730,000
     3             (Base Construction Allocation -
     4             $550,000)
     5             (Land Allocation - $15,000)
     6             (Design and Contingencies - $165,000)
     7         (2)  Allegheny Township, T-542, Farrington
     8             Bridge, Bridge Replacement                    700,000
     9             (Base Construction Allocation -
    10             $500,000)
    11             (Land Allocation - $25,000)
    12             (Design and Contingencies - $175,000)
    13         (3)  Concord Township, T-508, Greece City
    14             Bridge, Bridge Replacement                    700,000
    15             (Base Construction Allocation -
    16             $500,000)
    17             (Land Allocation - $25,000)
    18             (Design and Contingencies - $175,000)
    19         (4)  Cranberry Township, T-326 over Brush
    20             Creek, Bridge Replacement                     700,000
    21             (Base Construction Allocation -
    22             $500,000)
    23             (Land Allocation - $25,000)
    24             (Design and Contingencies - $175,000)
    25         (5)  Cranberry Township, T-300, Bridge
    26             Replacement                                   700,000
    27             (Base Construction Allocation -
    28             $500,000)
    29             (Land Allocation - $25,000)
    30             (Design and Contingencies - $175,000)
    19970S0186B0698                 - 76 -

     1         (6)  Jackson Township, T-323, Senn Bridge,
     2             Bridge Replacement                            700,000
     3             (Base Construction Allocation -
     4             $500,000)
     5             (Land Allocation - $25,000)
     6             (Design and Contingencies - $175,000)
     7         (7)  Jackson Township, T-325, Eidewau
     8             Bridge, Bridge Replacement                    700,000
     9             (Base Construction Allocation -
    10             $500,000)
    11             (Land Allocation - $25,000)
    12             (Design and Contingencies - $175,000)
    13         (8)  Jefferson Township, T-844 over Thorn
    14             Creek, Bridge Replacement                     700,000
    15             (Base Construction Allocation -
    16             $500,000)
    17             (Land Allocation - $25,000)
    18             (Design and Contingencies - $175,000)
    19         (9)  Mars Borough, Hook Street, Bridge
    20             Replacement                                   700,000
    21             (Base Construction Allocation -
    22             $500,000)
    23             (Land Allocation - $25,000)
    24             (Design and Contingencies - $175,000)
    25         (10)  Mars Borough, Church Street, Kocher
    26             Bridge, Bridge Replacement                    700,000
    27             (Base Construction Allocation -
    28             $500,000)
    29             (Land Allocation - $25,000)
    30             (Design and Contingencies - $175,000)
    19970S0186B0698                 - 77 -

     1         (11)  Middlesex Township, T-380 over Glade
     2             Run, Bridge Replacement                       700,000
     3             (Base Construction Allocation -
     4             $500,000)
     5             (Land Allocation - $25,000)
     6             (Design and Contingencies - $175,000)
     7         (12)  Worth Township, T-318, Payne Bridge,
     8             Bridge Replacement                            700,000
     9             (Base Construction Allocation -
    10             $500,000)
    11             (Land Allocation - $25,000)
    12             (Design and Contingencies - $175,000)
    13         (13)  Cranberry Township, T-326 over
    14             Tributary of Brush Creek, Bridge
    15             Replacement                                   167,000
    16             (Base Construction Allocation -
    17             $135,000)
    18             (Land Allocation - $19,000)
    19             (Design and Contingencies - $13,000)
    20     (b)  State Bridges
    21         (1)  SR 0228, Houseville Bridge over B&LE
    22             Railroad, Clinton Township, Bridge Deck
    23             Replacement                                   636,000
    24             (Base Construction Allocation -
    25             $600,000)
    26             (Design and Contingencies - $36,000)
    27         (2)  SR 0019, Rose Point Bridge over SR
    28             0422, Muddycreek Township, Bridge
    29             Painting                                      115,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 78 -

     1             $100,000)
     2             (Design and Contingencies - $15,000)
     3         (3)  SR 0058, Blocks Run Bridge No.1 over
     4             Blocks Run, Marion Township, Bridge
     5             Painting                                       65,000
     6             (Base Construction Allocation -
     7             $50,000)
     8             (Design and Contingencies - $15,000)
     9         (4)  SR 0058, Blocks Run Bridge No.2 over
    10             Blocks Run, Venango Township, Bridge
    11             Painting                                       60,000
    12             (Base Construction Allocation -
    13             $45,000)
    14             (Design and Contingencies - $15,000)
    15         (5)  SR 0058, Murrin Run Bridge over Murrin
    16             Run, Venango Township, Bridge Painting         60,000
    17             (Base Construction Allocation -
    18             $45,000)
    19             (Design and Contingencies - $15,000)
    20         (6)  SR 0068, Glade Run Bridge over Glade
    21             Run, Zelienople Borough, Bridge
    22             Painting                                       70,000
    23             (Base Construction Allocation -
    24             $55,000)
    25             (Design and Contingencies - $15,000)
    26         (7)  SR 0079, Muddy Creek Bridge Northbound
    27             over SR 0422 and Muddy Creek, Muddy
    28             Creek Township, Bridge Painting               255,000
    29             (Base Construction Allocation -
    30             $240,000)
    19970S0186B0698                 - 79 -

     1             (Design and Contingencies - $15,000)
     2         (8)  SR 0079, Muddy Creek Bridge Southbound
     3             over SR 0422 and Muddy Creek, Muddy
     4             Creek Township, Bridge Painting               255,000
     5             (Base Construction Allocation -
     6             $240,000)
     7             (Design and Contingencies - $15,000)
     8         (9)  SR 0108, Slippery Rock Exit Bridge
     9             over I-79, Worth Township, Bridge
    10             Painting                                      225,000
    11             (Base Construction Allocation -
    12             $210,000)
    13             (Design and Contingencies - $15,000)
    14         (10)  SR 0138, Glades Wildlife Lake Bridge
    15             over South Branch of Slippery Rock
    16             Creek, Concord Township, Bridge
    17             Painting                                       85,000
    18             (Base Construction Allocation -
    19             $70,000)
    20             (Design and Contingencies - $15,000)
    21         (11)  SR 0258, Wolf Creek Bridge over Wolf
    22             Creek, Slippery Rock Township, Bridge
    23             Painting                                      125,000
    24             (Base Construction Allocation -
    25             $110,000)
    26             (Design and Contingencies - $15,000)
    27         (12)  SR 0308, Renick Bridge over Stoney
    28             Run and Railroad, Center Township,
    29             Bridge Painting                               405,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 80 -

     1             $390,000)
     2             (Design and Contingencies - $15,000)
     3         (13)  SR 0422, Mount Chestnut Bridge
     4             Eastbound over Little Connoquenessing
     5             Creek and SR 3007, Butler Township,
     6             Bridge Painting                               355,000
     7             (Base Construction Allocation -
     8             $340,000)
     9             (Design and Contingencies - $15,000)
    10         (14)  SR 0422, Bonnie Brook Bridge over
    11             Bonnie Brook, Summit Township, Bridge
    12             Painting                                       90,000
    13             (Base Construction Allocation -
    14             $75,000)
    15             (Design and Contingencies - $15,000)
    16         (15)  SR 1004, Bruin Bridge over Bear
    17             Creek, Bruin Borough, Bridge Painting          85,000
    18             (Base Construction Allocation -
    19             $70,000)
    20             (Design and Contingencies - $15,000)
    21         (16)  SR 1011, Rattigan Bridge No.1 over
    22             Buffalo Creek, Donegal Township, Bridge
    23             Painting                                       55,000
    24             (Base Construction Allocation -
    25             $40,000)
    26             (Design and Contingencies - $15,000)
    27         (17)  SR 1016, Eastland Drive Bridge over
    28             Connoquenessing Creek, Butler Township,
    29             Bridge Painting                                80,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 81 -

     1             $65,000)
     2             (Design and Contingencies - $15,000)
     3         (18)  SR 1019, Rough Run Bridge over Rough
     4             Run, Windfield Township, Bridge
     5             Painting                                       95,000
     6             (Base Construction Allocation -
     7             $80,000)
     8             (Design and Contingencies - $15,000)
     9         (19)  SR 1019, Chicora Bridge over Buffalo
    10             Creek, Chicora Borough, Bridge
    11             Painting                                       70,000
    12             (Base Construction Allocation -
    13             $55,000)
    14             (Design and Contingencies - $15,000)
    15         (20)  SR 1021, Rattigan Bridge No.2 over
    16             Buffalo Creek, Donegal Township, Bridge
    17             Painting                                       70,000
    18             (Base Construction Allocation -
    19             $55,000)
    20             (Design and Contingencies - $15,000)
    21         (21)  SR 1025, Bonnie Brook Bridge No.1
    22             over Bonnie Brook, Summit Township,
    23             Bridge Painting                                90,000
    24             (Base Construction Allocation -
    25             $75,000)
    26             (Design and Contingencies - $15,000)
    27         (22)  SR 2004, Connoquenessing Creek Bridge
    28             over Connoquenessing Creek, Butler
    29             City, Bridge Painting                         135,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 82 -

     1             $120,000)
     2             (Design and Contingencies - $15,000)
     3         (23)  SR 2004, Bonnie Brook Bridge No.2
     4             over Bonnie Brook, East Butler Borough,
     5             Bridge Painting                                90,000
     6             (Base Construction Allocation -
     7             $75,000)
     8             (Design and Contingencies - $15,000)
     9         (24)  SR 2011, Lardintown Run Bridge No.1
    10             over Lardintown Run, Clinton Township,
    11             Bridge Painting                                75,000
    12             (Base Construction Allocation -
    13             $60,000)
    14             (Design and Contingencies - $15,000)
    15         (25)  SR 2011, Lardintown Run Bridge No.2
    16             over Lardintown Run, Clinton Township,
    17             Bridge Painting                                65,000
    18             (Base Construction Allocation -
    19             $50,000)
    20             (Design and Contingencies - $15,000)
    21         (26)  SR 2011, Lardintown Run Bridge No.3
    22             over Lardintown Run, Clinton Township,
    23             Bridge Painting                                65,000
    24             (Base Construction Allocation -
    25             $50,000)
    26             (Design and Contingencies - $15,000)
    27         (27)  SR 3004, McCalmont Bridge over
    28             Connoquenessing Creek, Butler Township,
    29             Bridge Painting                               105,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 83 -

     1             $90,000)
     2             (Design and Contingencies - $15,000)
     3         (28)  SR 3007, Reinfrew Bridge over
     4             Connoquenessing Creek, Penn Township,
     5             Bridge Painting                               115,000
     6             (Base Construction Allocation -
     7             $100,000)
     8             (Design and Contingencies - $15,000)
     9         (29)  SR 3010, Zeno Bridge over Glade Run,
    10             Forward Township, Bridge Painting             105,000
    11             (Base Construction Allocation -
    12             $90,000)
    13             (Design and Contingencies - $15,000)
    14         (30)  SR 3017, Kaufman Run Bridge over
    15             Kaufman Run, Adams Township, Bridge
    16             Painting                                       70,000
    17             (Base Construction Allocation -
    18             $55,000)
    19             (Design and Contingencies - $15,000)
    20         (31)  SR 3017, Breakneck Creek Bridge over
    21             Breakneck Creek, Adams Township, Bridge
    22             Painting                                      105,000
    23             (Base Construction Allocation -
    24             $90,000)
    25             (Design and Contingencies - $15,000)
    26         (32)  SR 3025, Little Connoquenessing Creek
    27             Bridge over Little Connoquenessing
    28             Creek, Lancaster Township, Bridge
    29             Painting                                      125,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 84 -

     1             $110,000)
     2             (Design and Contingencies - $15,000)
     3         (33)  SR 4006, Keister's Bridge over
     4             Slippery Rock Creek, Slippery Rock
     5             Township, Bridge Painting                     105,000
     6             (Base Construction Allocation -
     7             $90,000)
     8             (Design and Contingencies - $15,000)
     9         (34)  SR 4007, Lake Arthur Tributary Bridge
    10             over a tributary of Lake Arthur, Worth
    11             Township, Bridge Painting                      50,000
    12             (Base Construction Allocation -
    13             $35,000)
    14             (Design and Contingencies - $15,000)
    15         (35)  SR 4007, I-79 North Bridge No.1 over
    16             I-79, Worth Township, Bridge Painting         245,000
    17             (Base Construction Allocation -
    18             $230,000)
    19             (Design and Contingencies - $15,000)
    20         (36)  SR 4007, I-79 North Bridge No.2 over
    21             I-79, Worth Township, Bridge Painting         215,000
    22             (Base Construction Allocation -
    23             $200,000)
    24             (Design and Contingencies - $15,000)
    25         (37)  SR 4010, Bull Valley Bridge over Bull
    26             Valley Creek, Washington Township,
    27             Bridge Painting                                65,000
    28             (Base Construction Allocation -
    29             $50,000)
    30             (Design and Contingencies - $15,000)
    19970S0186B0698                 - 85 -

     1         (38)  SR 4012, Seaton Creek Bridge over
     2             Seaton Creek, Marion Township, Bridge
     3             Painting                                       65,000
     4             (Base Construction Allocation -
     5             $50,000)
     6             (Design and Contingencies - $15,000)
     7         (39)  SR 8002, North Shore Exit Bridge over
     8             Muddy Creek, Worth Township, Bridge
     9             Painting                                       85,000
    10             (Base Construction Allocation -
    11             $70,000)
    12             (Design and Contingencies - $15,000)
    13         (40)  SR 0422, Route 422 Overpass,
    14             Muddycreek Township, Bridge
    15             Replacement                                 1,450,000
    16             (Base Construction Allocation -
    17             $1,000,000)
    18             (Land Allocation - $100,000)
    19             (Design and Contingencies - $350,000)
    20         (41)  SR 0008, B&LE Railroad Overpass,
    21             Mercer Township, Bridge Replacement         1,450,000
    22             (Base Construction Allocation -
    23             $1,000,000)
    24             (Land Allocation - $100,000)
    25             (Design and Contingencies - $350,000)
    26         (42)  SR 0038, B&LE Railroad Overpass,
    27             Concord Township, Bridge Replacement        1,050,000
    28             (Base Construction Allocation -
    29             $750,000)
    30             (Land Allocation - $50,000)
    19970S0186B0698                 - 86 -

     1             (Design and Contingencies - $250,000)
     2         (43)  SR 2002, Conrail Railroad Overpass,
     3             Summit Township, Bridge Replacement         1,050,000
     4             (Base Construction Allocation -
     5             $750,000)
     6             (Land Allocation - $50,000)
     7             (Design and Contingencies - $250,000)
     8         (44)  SR 2012, B&LE Railroad Overpass,
     9             Jefferson Township, Bridge Replacement      1,050,000
    10             (Base Construction Allocation -
    11             $750,000)
    12             (Land Allocation - $50,000)
    13             (Design and Contingencies - $250,000)
    14         (45)  SR 3004, B&LE Railroad Overpass,
    15             Butler Township, Bridge Replacement           595,000
    16             (Base Construction Allocation -
    17             $400,000)
    18             (Land Allocation - $20,000)
    19             (Design and Contingencies - $175,000)
    20         (46)  SR 0008, Bridge over Armco Private
    21             Drive, Butler Township, Bridge
    22             Replacement                                 1,450,000
    23             (Base Construction Allocation -
    24             $1,000,000)
    25             (Land Allocation - $100,000)
    26             (Design and Contingencies - $350,000)
    27         (47)  SR 0019, Scholars Run Bridge, Jackson
    28             Township, Bridge Replacement                1,050,000
    29             (Base Construction Allocation -
    30             $750,000)
    19970S0186B0698                 - 87 -

     1             (Land Allocation - $50,000)
     2             (Design and Contingencies - $250,000)
     3         (48)  SR 0019, SR 0019 over SR 0422,
     4             Muddycreek Township, Bridge
     5             Replacement                                 1,050,000
     6             (Base Construction Allocation -
     7             $750,000)
     8             (Land Allocation - $50,000)
     9             (Design and Contingencies - $250,000)
    10         (49)  SR 0058, McMurray Run Bridge, Marion
    11             Township, Bridge Replacement                1,050,000
    12             (Base Construction Allocation -
    13             $750,000)
    14             (Land Allocation - $50,000)
    15             (Design and Contingencies - $250,000)
    16         (50)  SR 0068, Sullivan Run Bridge, Butler
    17             Township, Bridge Replacement                1,450,000
    18             (Base Construction Allocation -
    19             $1,000,000)
    20             (Land Allocation - $100,000)
    21             (Design and Contingencies - $350,000)
    22         (51)  SR 0080, I-80 over TR 540, Allegheny
    23             Township, Bridge Replacement                1,450,000
    24             (Base Construction Allocation -
    25             $1,000,000)
    26             (Land Allocation - $100,000)
    27             (Design and Contingencies - $350,000)
    28         (52)  SR 0138, Muddy Creek Bridge, Clay
    29             Township, Bridge Replacement                  595,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 88 -

     1             $400,000)
     2             (Land Allocation - $20,000)
     3             (Design and Contingencies - $175,000)
     4         (53)  SR 0173, Slippery Rock Creek Bridge,
     5             Slippery Rock Township, Bridge
     6             Replacement                                 1,050,000
     7             (Base Construction Allocation -
     8             $750,000)
     9             (Land Allocation - $50,000)
    10             (Design and Contingencies - $250,000)
    11         (54)  SR 0079, I-79 North Bridge over Ramp,
    12             Jackson Township, Bridge Replacement        1,450,000
    13             (Base Construction Allocation -
    14             $1,000,000)
    15             (Land Allocation - $100,000)
    16             (Design and Contingencies - $350,000)
    17         (55)  SR 0079, I-79 South Bridge over Ramp,
    18             Jackson Township, Bridge Replacement        1,450,000
    19             (Base Construction Allocation -
    20             $1,000,000)
    21             (Land Allocation - $100,000)
    22             (Design and Contingencies - $350,000)
    23         (56)  SR 0079, I-79 over SR 0068, Jackson
    24             Township, Bridge Replacement                1,450,000
    25             (Base Construction Allocation -
    26             $1,000,000)
    27             (Land Allocation - $100,000)
    28             (Design and Contingencies - $350,000)
    29         (57)  SR 0079, I-79 over TR 347, Lancaster
    30             Township, Bridge Replacement                1,450,000
    19970S0186B0698                 - 89 -

     1             (Base Construction Allocation -
     2             $1,000,000)
     3             (Land Allocation - $100,000)
     4             (Design and Contingencies - $350,000)
     5         (58)  SR 0079, I-79 North Bridge over SR
     6             0422, Worth Township, Bridge
     7             Replacement                                 1,450,000
     8             (Base Construction Allocation -
     9             $1,000,000)
    10             (Land Allocation - $100,000)
    11             (Design and Contingencies - $350,000)
    12         (59)  SR 0079, I-79 South Bridge over SR
    13             0422, Worth Township, Bridge
    14             Replacement                                 1,450,000
    15             (Base Construction Allocation -
    16             $1,000,000)
    17             (Land Allocation - $100,000)
    18             (Design and Contingencies - $350,000)
    19         (60)  SR 0422, SR 0422 over SR 4005,
    20             Muddycreek Township, Bridge
    21             Replacement                                 1,450,000
    22             (Base Construction Allocation -
    23             $1,000,000)
    24             (Land Allocation - $100,000)
    25             (Design and Contingencies - $350,000)
    26         (61)  SR 0528, SR 0528 over SR 0422,
    27             Franklin Township, Bridge Replacement       1,050,000
    28             (Base Construction Allocation -
    29             $750,000)
    30             (Land Allocation - $50,000)
    19970S0186B0698                 - 90 -

     1             (Design and Contingencies - $250,000)
     2         (62)  SR 1010, Bear Creek Bridge, Fairview
     3             Township, Bridge Replacement                1,050,000
     4             (Base Construction Allocation -
     5             $750,000)
     6             (Land Allocation - $50,000)
     7             (Design and Contingencies - $250,000)
     8         (63)  SR 1014, Bonnie Brook Bridge over
     9             Bonnie Brook, Summit Township, Bridge
    10             Replacement                                   595,000
    11             (Base Construction Allocation -
    12             $400,000)
    13             (Land Allocation - $20,000)
    14             (Design and Contingencies - $175,000)
    15         (64)  SR 1016, Connoquenessing Creek
    16             Bridge, Summit Township, Bridge
    17             Replacement                                   595,000
    18             (Base Construction Allocation -
    19             $400,000)
    20             (Land Allocation - $20,000)
    21             (Design and Contingencies - $175,000)
    22         (65)  SR 2006, SR 2006 over SR 0422, Summit
    23             Township, Bridge Replacement                1,050,000
    24             (Base Construction Allocation -
    25             $750,000)
    26             (Land Allocation - $50,000)
    27             (Design and Contingencies - $250,000)
    28         (66)  SR 2010, Bridge over Branch of Thorn
    29             Creek, Jefferson Township, Bridge
    30             Replacement                                 1,050,000
    19970S0186B0698                 - 91 -

     1             (Base Construction Allocation -
     2             $750,000)
     3             (Land Allocation - $50,000)
     4             (Design and Contingencies - $250,000)
     5         (67)  SR 2010, Little Buffalo Creek Bridge,
     6             Winfield Township, Bridge Replacement       1,050,000
     7             (Base Construction Allocation -
     8             $750,000)
     9             (Land Allocation - $50,000)
    10             (Design and Contingencies - $250,000)
    11         (68)  SR 2011, Bridge over Branch of Bull
    12             Creek, Clinton Township, Bridge
    13             Replacement                                   595,000
    14             (Base Construction Allocation -
    15             $400,000)
    16             (Land Allocation - $20,000)
    17             (Design and Contingencies - $175,000)
    18         (69)  SR 2011, Little Bull Run Bridge No.4
    19             over Bull Run, Clinton Township, Bridge
    20             Replacement                                   595,000
    21             (Base Construction Allocation -
    22             $400,000)
    23             (Land Allocation - $20,000)
    24             (Design and Contingencies - $175,000)
    25         (70)  SR 2018, Bridge No.1 over Branch of
    26             Buffalo Creek, Winfield Township,
    27             Bridge Replacement                          1,050,000
    28             (Base Construction Allocation -
    29             $750,000)
    30             (Land Allocation - $50,000)
    19970S0186B0698                 - 92 -

     1             (Design and Contingencies - $250,000)
     2         (71)  SR 2018, Bridge No.2 over Branch of
     3             Buffalo Creek, Winfield Township,
     4             Bridge Replacement                          1,050,000
     5             (Base Construction Allocation -
     6             $750,000)
     7             (Land Allocation - $50,000)
     8             (Design and Contingencies - $250,000)
     9         (72)  SR 3025, Little Connoquenessing Creek
    10             Bridge, Lancaster Township, Bridge
    11             Replacement                                   595,000
    12             (Base Construction Allocation -
    13             $400,000)
    14             (Land Allocation - $20,000)
    15             (Design and Contingencies - $175,000)
    16         (73)  SR 4007, SR 4007 over SR 0422, Worth
    17             Township, Bridge Replacement                1,050,000
    18             (Base Construction Allocation -
    19             $750,000)
    20             (Land Allocation - $50,000)
    21             (Design and Contingencies - $250,000)
    22         (74)  SR 4007, Park Road Bridge, Worth
    23             Township, Bridge Replacement                1,050,000
    24             (Base Construction Allocation -
    25             $750,000)
    26             (Land Allocation - $50,000)
    27             (Design and Contingencies - $250,000)
    28         (75)  SR 4010, Long Run Bridge, Slippery
    29             Rock Township, Bridge Replacement             595,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 93 -

     1             $400,000)
     2             (Land Allocation - $20,000)
     3             (Design and Contingencies - $175,000)
     4         (76)  SR 8005, SR 8005 over SR 0019,
     5             Jackson Township, Bridge Replacement          595,000
     6             (Base Construction Allocation -
     7             $400,000)
     8             (Land Allocation - $20,000)
     9             (Design and Contingencies - $175,000)
    10         (77)  SR 0008, William Flynn Bridge,
    11             Middlesex Township, Bridge Replacement      1,450,000
    12             (Base Construction Allocation -
    13             $1,000,000)
    14             (Land Allocation - $100,000)
    15             (Design and Contingencies - $350,000)
    16         (78)  SR 0008, Glade Run Bridge, Middlesex
    17             Township, Bridge Rehabilitation             1,450,000
    18             (Base Construction Allocation -
    19             $1,000,000)
    20             (Land Allocation - $100,000)
    21             (Design and Contingencies - $350,000)
    22         (79)  SR 0008, Little Glade Run Bridge
    23             No.1, Middlesex Township, Bridge
    24             Rehabilitation                              1,450,000
    25             (Base Construction Allocation -
    26             $1,000,000)
    27             (Land Allocation - $100,000)
    28             (Design and Contingencies - $350,000)
    29         (80)  SR 0008, Little Glade Run Bridge
    30             No.2, Middlesex Township, Bridge
    19970S0186B0698                 - 94 -

     1             Rehabilitation                              1,450,000
     2             (Base Construction Allocation -
     3             $1,000,000)
     4             (Land Allocation - $100,000)
     5             (Design and Contingencies - $350,000)
     6         (81)  SR 0008, Glade Run Bridge No.2,
     7             Middlesex Township, Bridge
     8             Rehabilitation                              1,450,000
     9             (Base Construction Allocation -
    10             $1,000,000)
    11             (Land Allocation - $100,000)
    12             (Design and Contingencies - $350,000)
    13         (82)  SR 0008, Bulcher Run Bridge, Butler
    14             Township, Bridge Rehabilitation             1,450,000
    15             (Base Construction Allocation -
    16             $1,000,000)
    17             (Land Allocation - $100,000)
    18             (Design and Contingencies - $350,000)
    19         (83)  SR 0008, Bridge No.2 over Branch of
    20             Muddy Creek, Clay Township, Bridge
    21             Rehabilitation                              1,450,000
    22             (Base Construction Allocation -
    23             $1,000,000)
    24             (Land Allocation - $100,000)
    25             (Design and Contingencies - $350,000)
    26         (84)  SR 0008, Muddy Creek Bridge, Clay
    27             Township, Bridge Rehabilitation             1,450,000
    28             (Base Construction Allocation -
    29             $1,000,000)
    30             (Land Allocation - $100,000)
    19970S0186B0698                 - 95 -

     1             (Design and Contingencies - $350,000)
     2         (85)  SR 0008, Glade Run Bridge No.3, Brady
     3             Township, Bridge Rehabilitation             1,450,000
     4             (Base Construction Allocation -
     5             $1,000,000)
     6             (Land Allocation - $100,000)
     7             (Design and Contingencies - $350,000)
     8         (86)  SR 0008, McDonalds Run Bridge, Mercer
     9             Township, Bridge Replacement                1,450,000
    10             (Base Construction Allocation -
    11             $1,000,000)
    12             (Land Allocation - $100,000)
    13             (Design and Contingencies - $350,000)
    14         (87)  SR 0008, McMurry MCMURRAY Run Bridge,                <--
    15             Mercer Township, Bridge Rehabilitation      1,450,000
    16             (Base Construction Allocation -
    17             $1,000,000)
    18             (Land Allocation - $100,000)
    19             (Design and Contingencies - $350,000)
    20         (88)  SR 0019, Glade Run Bridge No.2,
    21             Jackson Township, Bridge
    22             Rehabilitation                              1,050,000
    23             (Base Construction Allocation -
    24             $750,000)
    25             (Land Allocation - $50,000)
    26             (Design and Contingencies - $250,000)
    27         (89)  SR 0019, Glade Run Bridge No.2,
    28             Jackson Township, Bridge
    29             Rehabilitation                              1,050,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 96 -

     1             $750,000)
     2             (Land Allocation - $50,000)
     3             (Design and Contingencies - $250,000)
     4         (90)  SR 0038, Connoquenessing Creek
     5             Bridge, Center Township, Bridge
     6             Rehabilitation                              1,050,000
     7             (Base Construction Allocation -
     8             $750,000)
     9             (Land Allocation - $50,000)
    10             (Design and Contingencies - $250,000)
    11         (91)  SR 0038, Pine Run Bridge, Oakland
    12             Township, Bridge Rehabilitation             1,050,000
    13             (Base Construction Allocation -
    14             $750,000)
    15             (Land Allocation - $50,000)
    16             (Design and Contingencies - $250,000)
    17         (92)  SR 0038, Concord Bridge, Concord
    18             Township, Bridge Rehabilitation             1,050,000
    19             (Base Construction Allocation -
    20             $750,000)
    21             (Land Allocation - $50,000)
    22             (Design and Contingencies - $250,000)
    23         (93)  SR 0038, Little Connoquenessing Creek
    24             Bridge No.1, Concord Township, Bridge
    25             Rehabilitation                              1,050,000
    26             (Base Construction Allocation -
    27             $750,000)
    28             (Land Allocation - $50,000)
    29             (Design and Contingencies - $250,000)
    30         (94)  SR 0038, Little Connoquenessing Creek
    19970S0186B0698                 - 97 -

     1             Bridge, Concord Township, Bridge
     2             Rehabilitation                              1,050,000
     3             (Base Construction Allocation -
     4             $750,000)
     5             (Land Allocation - $50,000)
     6             (Design and Contingencies - $250,000)
     7         (95)  SR 0038, Little Scrubgrass Creek
     8             Bridge, Allegheny Township, Bridge
     9             Rehabilitation                              1,050,000
    10             (Base Construction Allocation -
    11             $750,000)
    12             (Land Allocation - $50,000)
    13             (Design and Contingencies - $250,000)
    14         (96)  SR 0038, Bridge over Tributary of
    15             Scrubgrass Creek, Allegheny Township,
    16             Bridge Rehabilitation                       1,050,000
    17             (Base Construction Allocation -
    18             $750,000)
    19             (Land Allocation - $50,000)
    20             (Design and Contingencies - $250,000)
    21         (97)  SR 0058, Murrin Run Bridge, Venango
    22             Township, Bridge Rehabilitation             1,050,000
    23             (Base Construction Allocation -
    24             $750,000)
    25             (Land Allocation - $50,000)
    26             (Design and Contingencies - $250,000)
    27         (98)  SR 0068, B&LE Railroad Bridge, Summit
    28             and Butler Townships, Bridge
    29             Rehabilitation                              1,450,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 98 -

     1             $1,000,000)
     2             (Land Allocation - $100,000)
     3             (Design and Contingencies - $350,000)
     4         (99)  SR 0068, Connoquenessing Creek
     5             Bridge, Summit Township, Bridge
     6             Rehabilitation                              1,050,000
     7             (Base Construction Allocation -
     8             $750,000)
     9             (Land Allocation - $50,000)
    10             (Design and Contingencies - $250,000)
    11         (100)  SR 0068, Buffalo Creek Bridge,
    12             Chicora Township, Bridge
    13             Rehabilitation                              1,050,000
    14             (Base Construction Allocation -
    15             $750,000)
    16             (Land Allocation - $50,000)
    17             (Design and Contingencies - $250,000)
    18         (101)  SR 0068, Buffalo Run Bridge,
    19             Fairview Township, Bridge
    20             Rehabilitation                              1,050,000
    21             (Base Construction Allocation -
    22             $750,000)
    23             (Land Allocation - $50,000)
    24             (Design and Contingencies - $250,000)
    25         (102)  SR 0079, Bridge over Tributary of
    26             Glade Run, Jackson Township, Bridge
    27             Rehabilitation                              1,450,000
    28             (Base Construction Allocation -
    29             $1,000,000)
    30             (Land Allocation - $100,000)
    19970S0186B0698                 - 99 -

     1             (Design and Contingencies - $350,000)
     2         (103)  SR 0079, Bridge No.1 over Branch of
     3             Yellow Creek, Lancaster Township,
     4             Bridge Rehabilitation                       1,450,000
     5             (Base Construction Allocation -
     6             $1,000,000)
     7             (Land Allocation - $100,000)
     8             (Design and Contingencies - $350,000)
     9         (104)  SR 0079, Bridge No.2 over Branch of
    10             Yellow Creek, Lancaster Township,
    11             Bridge Rehabilitation                       1,450,000
    12             (Base Construction Allocation -
    13             $1,000,000)
    14             (Land Allocation - $100,000)
    15             (Design and Contingencies - $350,000)
    16         (105)  SR 0079, Bridge No.3 over Branch of
    17             Yellow Creek, Lancaster Township,
    18             Bridge Rehabilitation                       1,450,000
    19             (Base Construction Allocation -
    20             $1,000,000)
    21             (Land Allocation - $100,000)
    22             (Design and Contingencies - $350,000)
    23         (106)  SR 0079, Little Yellow Creek Bridge,
    24             Lancaster Township, Bridge
    25             Rehabilitation                              1,450,000
    26             (Base Construction Allocation -
    27             $1,000,000)
    28             (Land Allocation - $100,000)
    29             (Design and Contingencies - $350,000)
    30         (107)  SR 0079, Bridge No.4 over Branch of
    19970S0186B0698                 - 100 -

     1             Yellow Creek, Muddycreek Township,
     2             Bridge Rehabilitation                       1,450,000
     3             (Base Construction Allocation -
     4             $1,000,000)
     5             (Land Allocation - $100,000)
     6             (Design and Contingencies - $350,000)
     7         (108)  SR 0079, Bridge at Milepost 100,
     8             Worth Township, Bridge Rehabilitation       1,450,000
     9             (Base Construction Allocation -
    10             $1,000,000)
    11             (Land Allocation - $100,000)
    12             (Design and Contingencies - $350,000)
    13         (109)  SR 0079, Black Run Bridge, Worth
    14             Township, Bridge Rehabilitation             1,450,000
    15             (Base Construction Allocation -
    16             $1,000,000)
    17             (Land Allocation - $100,000)
    18             (Design and Contingencies - $350,000)
    19         (110)  SR 0268, Bridge over Branch of Bear
    20             Creek, Petrolia Borough, Bridge
    21             Rehabilitation                              1,050,000
    22             (Base Construction Allocation -
    23             $750,000)
    24             (Land Allocation - $50,000)
    25             (Design and Contingencies - $250,000)
    26         (111)  SR 0268, Lowrey Run Bridge,
    27             Allegheny Township, Bridge
    28             Rehabilitation                              1,050,000
    29             (Base Construction Allocation -
    30             $750,000)
    19970S0186B0698                 - 101 -

     1             (Land Allocation - $50,000)
     2             (Design and Contingencies - $250,000)
     3         (112)  SR 0308, B&LE Railroad Bridge,
     4             Center Township, Bridge Rehabilitation      1,050,000
     5             (Base Construction Allocation -
     6             $750,000)
     7             (Land Allocation - $50,000)
     8             (Design and Contingencies - $250,000)
     9         (113)  SR 0308, Stony Run Bridge, Center
    10             Township, Bridge Rehabilitation             1,050,000
    11             (Base Construction Allocation -
    12             $750,000)
    13             (Land Allocation - $50,000)
    14             (Design and Contingencies - $250,000)
    15         (114)  SR 0356, Little Buffalo Creek
    16             Bridge, Buffalo Township, Bridge
    17             Rehabilitation                              1,050,000
    18             (Base Construction Allocation -
    19             $750,000)
    20             (Land Allocation - $50,000)
    21             (Design and Contingencies - $250,000)
    22         (115)  SR 0356, Big Coal Run Bridge, Summit
    23             Township, Bridge Rehabilitation             1,050,000
    24             (Base Construction Allocation -
    25             $750,000)
    26             (Land Allocation - $50,000)
    27             (Design and Contingencies - $250,000)
    28         (116)  SR 0422, Lake Arthur Bridge,
    29             Franklin Township, Bridge
    30             Rehabilitation                              1,450,000
    19970S0186B0698                 - 102 -

     1             (Base Construction Allocation -
     2             $1,000,000)
     3             (Land Allocation - $100,000)
     4             (Design and Contingencies - $350,000)
     5         (117)  SR 0422, Big Run Bridge, Franklin
     6             Township, Bridge Rehabilitation             1,450,000
     7             (Base Construction Allocation -
     8             $1,000,000)
     9             (Land Allocation - $100,000)
    10             (Design and Contingencies - $350,000)
    11         (118)  SR 0422, Mulligan Run Bridge,
    12             Franklin Township, Bridge
    13             Rehabilitation                              1,450,000
    14             (Base Construction Allocation -
    15             $1,000,000)
    16             (Land Allocation - $100,000)
    17             (Design and Contingencies - $350,000)
    18         (119)  SR 0422, Big Mulligan Run Bridge,
    19             Franklin Township, Bridge
    20             Rehabilitation                              1,450,000
    21             (Base Construction Allocation -
    22             $1,000,000)
    23             (Land Allocation - $100,000)
    24             (Design and Contingencies - $350,000)
    25         (120)  SR 0422, Big Sullivan Run Bridge,
    26             Butler Township, Bridge Rehabilitation      1,450,000
    27             (Base Construction Allocation -
    28             $1,000,000)
    29             (Land Allocation - $100,000)
    30             (Design and Contingencies - $350,000)
    19970S0186B0698                 - 103 -

     1         (121)  SR 0422, Connoquenessing Creek
     2             Bridge, Butler Township, Bridge
     3             Rehabilitation                              1,450,000
     4             (Base Construction Allocation -
     5             $1,000,000)
     6             (Land Allocation - $100,000)
     7             (Design and Contingencies - $350,000)
     8         (122)  SR 0422, Bridge No.1 over Tributary
     9             of Connoquenessing Creek, Summit
    10             Township, Bridge Rehabilitation             1,450,000
    11             (Base Construction Allocation -
    12             $1,000,000)
    13             (Land Allocation - $100,000)
    14             (Design and Contingencies - $350,000)
    15         (123)  SR 0422, Bridge No.2 over Tributary
    16             of Bonnie Brook, Butler Township,
    17             Bridge Rehabilitation                       1,450,000
    18             (Base Construction Allocation -
    19             $1,000,000)
    20             (Land Allocation - $100,000)
    21             (Design and Contingencies - $350,000)
    22         (124)  SR 0422, Bonnie Brook Bridge No.1,
    23             Summit Township, Bridge Rehabilitation      1,450,000
    24             (Base Construction Allocation -
    25             $1,000,000)
    26             (Land Allocation - $100,000)
    27             (Design and Contingencies - $350,000)
    28         (125)  SR 0422, Bridge No.3 over Tributary
    29             of Bonnie Brook, Summit Township,
    30             Bridge Rehabilitation                       1,450,000
    19970S0186B0698                 - 104 -

     1             (Base Construction Allocation -
     2             $1,000,000)
     3             (Land Allocation - $100,000)
     4             (Design and Contingencies - $350,000)
     5         (126)  SR 0422, Bonnie Brook Bridge No.2,
     6             Summit Township, Bridge Rehabilitation      1,450,000
     7             (Base Construction Allocation -
     8             $1,000,000)
     9             (Land Allocation - $100,000)
    10             (Design and Contingencies - $350,000)
    11         (127)  SR 0422, Bridge No.4 over Tributary
    12             of Bonnie Brook, Summit Township,
    13             Bridge Rehabilitation                       1,450,000
    14             (Base Construction Allocation -
    15             $1,000,000)
    16             (Land Allocation - $100,000)
    17             (Design and Contingencies - $350,000)
    18         (128)  SR 0422, Little Buffalo Creek
    19             Bridge, Clearfield Township, Bridge
    20             Rehabilitation                              1,450,000
    21             (Base Construction Allocation -
    22             $1,000,000)
    23             (Land Allocation - $100,000)
    24             (Design and Contingencies - $350,000)
    25         (129)  SR 0422, Buffalo Creek Bridge,
    26             Clearfield Township, Bridge
    27             Rehabilitation                              1,450,000
    28             (Base Construction Allocation -
    29             $1,000,000)
    30             (Land Allocation - $100,000)
    19970S0186B0698                 - 105 -

     1             (Design and Contingencies - $350,000)
     2         (130)  SR 0528, Likens Run Bridge, Evans
     3             City Borough, Bridge Rehabilitation         1,050,000
     4             (Base Construction Allocation -
     5             $750,000)
     6             (Land Allocation - $50,000)
     7             (Design and Contingencies - $250,000)
     8         (131)  SR 1010, Glade Run Bridge, Brady
     9             Township, Bridge Rehabilitation               595,000
    10             (Base Construction Allocation -
    11             $400,000)
    12             (Land Allocation - $20,000)
    13             (Design and Contingencies - $175,000)
    14         (132)  SR 1010, Big Bear Creek Bridge,
    15             Fairview Township, Bridge
    16             Rehabilitation                                595,000
    17             (Base Construction Allocation -
    18             $400,000)
    19             (Land Allocation - $20,000)
    20             (Design and Contingencies - $175,000)
    21         (133)  SR 1011, Buffalo Creek Bridge,
    22             Fairview Township, Bridge
    23             Rehabilitation                                595,000
    24             (Base Construction Allocation -
    25             $400,000)
    26             (Land Allocation - $20,000)
    27             (Design and Contingencies - $175,000)
    28         (134)  SR 1019, Big Buffalo Run Bridge,
    29             Donegal Township, Bridge
    30             Rehabilitation                              1,050,000
    19970S0186B0698                 - 106 -

     1             (Base Construction Allocation -
     2             $750,000)
     3             (Land Allocation - $50,000)
     4             (Design and Contingencies - $250,000)
     5         (135)  SR 1025, Bonnie Brook Bridge, Summit
     6             Township, Bridge Rehabilitation             1,050,000
     7             (Base Construction Allocation -
     8             $750,000)
     9             (Land Allocation - $50,000)
    10             (Design and Contingencies - $250,000)
    11         (136)  SR 2002, Coal Run Bridge, City of
    12             Butler and Butler Township, Bridge
    13             Rehabilitation                              1,050,000
    14             (Base Construction Allocation -
    15             $750,000)
    16             (Land Allocation - $50,000)
    17             (Design and Contingencies - $250,000)
    18         (137)  SR 2004, Bonnie Brook Bridge, Summit
    19             Township, Bridge Rehabilitation             1,050,000
    20             (Base Construction Allocation -
    21             $750,000)
    22             (Land Allocation - $50,000)
    23             (Design and Contingencies - $250,000)
    24         (138)  SR 2012, Thorn Creek Bridge No.1,
    25             Jefferson Township, Bridge
    26             Rehabilitation                              1,050,000
    27             (Base Construction Allocation -
    28             $750,000)
    29             (Land Allocation - $50,000)
    30             (Design and Contingencies - $250,000)
    19970S0186B0698                 - 107 -

     1         (139)  SR 2012, Thorn Creek Bridge No.2,
     2             Jefferson Township, Bridge
     3             Rehabilitation                              1,050,000
     4             (Base Construction Allocation -
     5             $750,000)
     6             (Land Allocation - $50,000)
     7             (Design and Contingencies - $250,000)
     8         (140)  SR 3001, West Butler Creek Bridge,
     9             Butler Township, Bridge Rehabilitation      1,450,000
    10             (Base Construction Allocation -
    11             $1,000,000)
    12             (Land Allocation - $100,000)
    13             (Design and Contingencies - $350,000)
    14         (141)  SR 3007, Thorn Creek Bridge, Butler
    15             Township, Bridge Rehabilitation             1,050,000
    16             (Base Construction Allocation -
    17             $750,000)
    18             (Land Allocation - $50,000)
    19             (Design and Contingencies - $250,000)
    20         (142)  SR 3009, Cranberry Run Bridge, Penn
    21             Township, Bridge Rehabilitation               595,000
    22             (Base Construction Allocation -
    23             $400,000)
    24             (Land Allocation - $20,000)
    25             (Design and Contingencies - $175,000)
    26         (143)  SR 3010, Saw Mill Run Bridge, Penn
    27             Township, Bridge Rehabilitation               595,000
    28             (Base Construction Allocation -
    29             $400,000)
    30             (Land Allocation - $20,000)
    19970S0186B0698                 - 108 -

     1             (Design and Contingencies - $175,000)
     2         (144)  SR 3015, Bridge No.2 over Tributary
     3             of Wolf Run, Forward Township, Bridge
     4             Rehabilitation                              1,050,000
     5             (Base Construction Allocation -
     6             $750,000)
     7             (Land Allocation - $50,000)
     8             (Design and Contingencies - $250,000)
     9         (145)  SR 3015, Bridge No.3 over Tributary
    10             of Wolf Run, Forward Township, Bridge
    11             Rehabilitation                              1,050,000
    12             (Base Construction Allocation -
    13             $750,000)
    14             (Land Allocation - $50,000)
    15             (Design and Contingencies - $250,000)
    16         (146)  SR 3025, Bridge over Branch of
    17             Yellow Creek, Lancaster Township,
    18             Bridge Rehabilitation                         595,000
    19             (Base Construction Allocation -
    20             $400,000)
    21             (Land Allocation - $20,000)
    22             (Design and Contingencies - $175,000)
    23         (147)  SR 3031, SR 3031 over US 422, Butler
    24             Township, Bridge Rehabilitation               595,000
    25             (Base Construction Allocation -
    26             $400,000)
    27             (Land Allocation - $20,000)
    28             (Design and Contingencies - $175,000)
    29         (148)  SR 3034, Bridge over Branch of
    30             Semiconon, Prospect Borough, Bridge
    19970S0186B0698                 - 109 -

     1             Rehabilitation                                595,000
     2             (Base Construction Allocation -
     3             $400,000)
     4             (Land Allocation - $20,000)
     5             (Design and Contingencies - $175,000)
     6         (149)  SR 4001, SR 4001 over US 422, Butler
     7             Township, Bridge Rehabilitation             1,050,000
     8             (Base Construction Allocation -
     9             $750,000)
    10             (Land Allocation - $50,000)
    11             (Design and Contingencies - $250,000)
    12         (150)  SR 4002, Bridge over Branch of Muddy
    13             Creek, Clay Township, Bridge
    14             Rehabilitation                              1,050,000
    15             (Base Construction Allocation -
    16             $750,000)
    17             (Land Allocation - $50,000)
    18             (Design and Contingencies - $250,000)
    19         (151)  T-716, Old Plank Road Bridge, Penn
    20             Township, Bridge Replacement                  390,000
    21             (Base Construction Allocation -
    22             $300,000)
    23             (Land Allocation - $10,000)
    24             (Design and Contingencies - $80,000)
    25         (152)  SR 3007, Crooked Run Bridge, Center
    26             Township, Bridge Replacement                1,050,000
    27             (Base Construction Allocation -
    28             $750,000)
    29             (Land Allocation - $50,000)
    30             (Design and Contingencies - $250,000)
    19970S0186B0698                 - 110 -

     1         (153)  SR 3010, Glade Run Bridge, Forward
     2             Township, Bridge Replacement                  595,000
     3             (Base Construction Allocation -
     4             $400,000)
     5             (Land Allocation - $20,000)
     6             (Design and Contingencies - $175,000)
     7         (154)  SR 3013, Big Connoquessing                          <--
     8             CONNOQUENESSING Bridge, Forward                        <--
     9             Township, Bridge Replacement                  595,000
    10             (Base Construction Allocation -
    11             $400,000)
    12             (Land Allocation - $20,000)
    13             (Design and Contingencies - $175,000)
    14         (155)  SR 0019, SR 0019 over Brush Creek,
    15             Cranberry Township, Bridge Replacement      1,050,000
    16             (Base Construction Allocation -
    17             $800,000)
    18             (Land Allocation - $75,000)
    19             (Design and Contingencies - $175,000)
    20         (156)  SR 0079, SR 0079 over Big Brush
    21             Creek, Cranberry Township, Bridge
    22             Replacement                                 1,450,000
    23             (Base Construction Allocation -
    24             $1,100,000)
    25             (Land Allocation - $75,000)
    26             (Design and Contingencies - $275,000)
    27         (157)  SR 0079, SR 0079 over Coal Run,
    28             Cranberry Township, Bridge Replacement      1,450,000
    29             (Base Construction Allocation -
    30             $1,100,000)
    19970S0186B0698                 - 111 -

     1             (Land Allocation - $75,000)
     2             (Design and Contingencies - $275,000)
     3         (158)  SR 0228, SR 0228 over CSX Railroad,
     4             Adams Township, Bridge Replacement          1,450,000
     5             (Base Construction Allocation -
     6             $1,100,000)
     7             (Land Allocation - $75,000)
     8             (Design and Contingencies - $275,000)
     9         (159)  SR 3015, Breakneck Bridge, Adams
    10             Township, Bridge Replacement                  595,000
    11             (Base Construction Allocation -
    12             $400,000)
    13             (Land Allocation - $20,000)
    14             (Design and Contingencies - $175,000)
    15         (160)  SR 3022, SR 3022 over Brush Creek,
    16             Cranberry Township, Bridge Replacement      1,050,000
    17             (Base Construction Allocation -
    18             $800,000)
    19             (Land Allocation - $75,000)
    20             (Design and Contingencies - $175,000)
    21         (161)  SR 3024, SR 3024 over Big Brush
    22             Creek, Cranberry Township, Bridge
    23             Replacement                                   595,000
    24             (Base Construction Allocation -
    25             $400,000)
    26             (Land Allocation - $20,000)
    27             (Design and Contingencies - $175,000)
    28  Section 15.  Cambria County
    29     (a)  Local Bridges
    30         (1)  Summerhill Township, T-346, Bridge
    19970S0186B0698                 - 112 -

     1             No.1, Howard Avenue over Beaverdam Run,
     2             Bridge Replacement                            450,000
     3             (Base Construction Allocation -
     4             $350,000)
     5             (Design and Contingencies - $100,000)
     6         (2)  West Carroll Township, T-505 over
     7             Blacklick Creek, Bridge Replacement           235,000
     8             (Base Construction Allocation -
     9             $200,000)
    10             (Land Allocation - $10,000)
    11             (Design and Contingencies - $25,000)
    12         (3)  West Carroll Township, T-626 over Fox
    13             Run, Bridge Replacement                       235,000
    14             (Base Construction Allocation -
    15             $200,000)
    16             (Land Allocation - $10,000)
    17             (Design and Contingencies - $25,000)
    18     (b)  State Bridges
    19         (1)  SR 1030, Carl Road over Slate Lick
    20             Creek, Clearfield Township, Bridge
    21             Replacement                                   240,000
    22             (Base Construction Allocation -
    23             $200,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $30,000)
    26         (2)  SR 0271, Maple Avenue Bridge over
    27             Little Conemaugh River and Conrail,
    28             Phase II, City of Johnstown, Bridge
    29             Painting                                      500,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 113 -

     1             $500,000)
     2         (3)  SR 3033, PA 56 Detour Bridge over
     3             Solomon Run, Richland Township, Bridge
     4             Replacement                                   350,000
     5             (Base Construction Allocation -
     6             $250,000)
     7             (Land Allocation - $15,000)
     8             (Design and Contingencies - $85,000)
     9  Section 16.  (Reserved).
    10  Section 17.  Carbon County.
    11     (a)  Local Bridges
    12         (1)  Penn Forest Township, T-481, County
    13             Bridge No.21 over Panther Creek, Bridge
    14             Replacement                                   290,000
    15             (Base Construction Allocation -
    16             $180,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $100,000)
    19         (2)  MAHONING TOWNSHIP, T-390, BRIDGE OVER                 <--
    20             MAHONING CREEK, BRIDGE REPLACEMENT             92,000
    21             (BASE CONSTRUCTION ALLOCATION -
    22             $80,000)
    23             (LAND ALLOCATION - $4,000)
    24             (DESIGN AND CONTINGENCIES - $8,000)
    25         (3)  LAUSANNE TOWNSHIP, T-502, BRIDGE OVER
    26             SCHAFFERS RUN, BRIDGE REPLACEMENT             320,000
    27             (BASE CONSTRUCTION ALLOCATION -
    28             $212,000)
    29             (LAND ALLOCATION - $8,000)
    30             (DESIGN AND CONTINGENCIES - $100,00)
    19970S0186B0698                 - 114 -

     1         (4)  TOWAMENSING TOWNSHIP, T-435, BRIDGE
     2             OVER WILD CREEK, BRIDGE REPLACEMENT           357,000
     3             (BASE CONSTRUCTION ALLOCATION -
     4             $220,000)
     5             (LAND ALLOCATION - $9,000)
     6             (DESIGN AND CONTINGENCIES - $128,000)
     7         (5)  BOWMANSTOWN BOROUGH, ORE STREET BRIDGE
     8             OVER FIRELINE CREEK, BRIDGE
     9             REPLACEMENT                                   360,000
    10             (BASE CONSTRUCTION ALLOCATION -
    11             $250,000)
    12             (LAND ALLOCATION - $10,000)
    13             (DESIGN AND CONTINGENCIES - $100,000)
    14         (6)  PACKER TOWNSHIP, T-463, BRIDGE OVER
    15             WETZEL CREEK, BRIDGE REPLACEMENT              360,000
    16             (BASE CONSTRUCTION ALLOCATION -
    17             $250,000)
    18             (LAND ALLOCATION - $10,000)
    19             (DESIGN AND CONTINGENCIES - $100,000)
    20         (7)  EAST PENN TOWNSHIP, T-354, COUNTY
    21             BRIDGE NO.6 OVER LIZARD CREEK, BRIDGE
    22             REPLACEMENT                                   974,000
    23             (BASE CONSTRUCTION ALLOCATION -
    24             $600,000)
    25             (LAND ALLOCATION - $300,000)
    26             (DESIGN AND CONTINGENCIES - $74,000)
    27     (b)  State Bridges
    28         (1)  SR 2002, Delaware Avenue over Palmer
    29             Creek, Palmerton Borough, Bridge
    30             Replacement                                   568,000
    19970S0186B0698                 - 115 -

     1             (Base Construction Allocation -
     2             $318,000)
     3             (Land Allocation - $150,000)
     4             (Design and Contingencies - $100,000)
     5         (2)  SR 4010, SR 4010 over Quakake Creek,
     6             Packer Township, Bridge Replacement           412,000
     7             (Base Construction Allocation -
     8             $202,000)
     9             (Land Allocation - $150,000)
    10             (Design and Contingencies - $60,000)
    11         (3)  SR 0209, SR 0209 Turnpike Ramp,
    12             Mahoning Interchange, Franklin
    13             Township, Bridge Replacement                1,260,000
    14             (Base Construction Allocation -
    15             $750,000)
    16             (Land Allocation - $300,000)
    17             (Design and Contingencies - $210,000)
    18         (4)  SR 0248, SR 0248 over Pohopoco Creek,
    19             Parryville Borough Line, Lower
    20             Towamensing Township, Bridge
    21             Rehabilitation                                415,000
    22             (Base Construction Allocation -
    23             $315,000)
    24             (Design and Contingencies - $100,000)
    25         (5)  SR 4010, SR 4010 over Hartz Creek,
    26             Packer Township, Bridge Replacement           615,000
    27             (Base Construction Allocation -
    28             $370,000)
    29             (Land Allocation - $150,000)
    30             (Design and Contingencies - $95,000)
    19970S0186B0698                 - 116 -

     1         (6)  SR 0534, SR 0534 over Sand Spring Run,
     2             2 Miles South of Lehigh Tannery, Kidder
     3             Township, Bridge Replacement                  340,000
     4             (Base Construction Allocation -
     5             $160,000)
     6             (Land Allocation - $125,000)
     7             (Design and Contingencies - $55,000)
     8         (7)  SR 0209, SR 0209 over Pohopoco Creek,
     9             Village of Harrity, Franklin Township,
    10             Bridge Rehabilitation                         885,000
    11             (Base Construction Allocation -
    12             $680,000)
    13             (Design and Contingencies - $205,000)
    14         (8)  SR 0534, Pa 534 over I-80, Kidder
    15             Township, Bridge Rehabilitation               540,000
    16             (Base Construction Allocation -
    17             $440,000)
    18             (Design and Contingencies - $100,000)
    19         (9)  SR 0248, BRIDGE OVER AQUASHICOLA                      <--
    20             CREEK, LOWER TOWAMENSING TOWNSHIP,
    21             BRIDGE REHABILITATION                         310,000
    22             (BASE CONSTRUCTION ALLOCATION -
    23             $300,000)
    24             (DESIGN AND CONTINGENCIES - $10,000)
    25         (10)  SR 0534, BRIDGE OVER HICKORY RUN,
    26             KIDDER TOWNSHIP, BRIDGE REHABILITATION        830,000
    27             (BASE CONSTRUCTION ALLOCATION -
    28             $700,000)
    29             (LAND ALLOCATION - $30,000)
    30             (DESIGN AND CONTINGENCIES - $100,000)
    19970S0186B0698                 - 117 -

     1         (11)  SR 0903, BRIDGE OVER LEHIGH RIVER,
     2             JIM THORPE BOROUGH, BRIDGE
     3             REHABILITATION                              1,250,000
     4             (BASE CONSTRUCTION ALLOCATION -
     5             $1,000,000)
     6             (LAND ALLOCATION - $50,000)
     7             (DESIGN AND CONTINGENCIES - $200,000)
     8         (12)  SR 0940, BRIDGE OVER BLACK CREEK,
     9             KIDDER TOWNSHIP, BRIDGE REPLACEMENT           185,000
    10             (BASE CONSTRUCTION ALLOCATION -
    11             $150,000)
    12             (DESIGN AND CONTINGENCIES - $35,000)
    13         (13)  SR 2006, BRIDGE OVER BUCKWHA CREEK,
    14             LOWER TOWAMENSING TOWNSHIP, BRIDGE
    15             REPLACEMENT                                 1,240,000
    16             (BASE CONSTRUCTION ALLOCATION -
    17             $700,000)
    18             (LAND ALLOCATION - $90,000)
    19             (DESIGN AND CONTINGENCIES - $450,000)
    20         (14)  SR 2008, BRIDGE OVER POHOPOCO CREEK,
    21             PARRYVILLE BOROUGH, BRIDGE REPLACEMENT        920,000
    22             (BASE CONSTRUCTION ALLOCATION -
    23             $600,000)
    24             (LAND ALLOCATION - $90,000)
    25             (DESIGN AND CONTINGENCIES - $230,000)
    26         (15)  SR 3005, BRIDGE OVER MAHONING CREEK,
    27             MAHONING TOWNSHIP, BRIDGE REPLACEMENT         308,000
    28             (BASE CONSTRUCTION ALLOCATION -
    29             $280,000)
    30             (DESIGN AND CONTINGENCIES - $28,000)
    19970S0186B0698                 - 118 -

     1         (16)  SR 4014, BRIDGE OVER TRIBUTARY OF
     2             INDIAN RUN, LEHIGH TOWNSHIP, BRIDGE
     3             REPLACEMENT                                   153,000
     4             (BASE CONSTRUCTION ALLOCATION -
     5             $130,000)
     6             (LAND ALLOCATION - $10,000)
     7             (DESIGN AND CONTINGENCIES - $13,000)
     8         (17)  SR 4014, BRIDGE OVER TRIBUTARY OF
     9             INDIAN RUN, LEHIGH TOWNSHIP, BRIDGE
    10             REPLACEMENT                                    88,000
    11             (BASE CONSTRUCTION ALLOCATION -
    12             $80,000)
    13             (DESIGN AND CONTINGENCIES - $8,000)
    14  Section 18.  Centre County.
    15     (a)  Local Bridges
    16         (1)  Greene Township, T-350, Stover Road
    17             Bridge, Bridge Replacement                    230,000
    18             (Base Construction Allocation -
    19             $180,000)
    20             (Land Allocation - $10,000)
    21             (Design and Contingencies - $40,000)
    22         (2)  Howard Township, T-398 over Bullit
    23             Run, Bridge Rehabilitation                     11,000
    24             (Base Construction Allocation - $9,000)
    25             (Design and Contingencies - $2,000)
    26         (3)  Halfmoon Township, T-307 over
    27             Loveville Creek, Bridge Replacement            21,000
    28             (Base Construction Allocation -
    29             $19,000)
    30             (Design and Contingencies - $2,000)
    19970S0186B0698                 - 119 -

     1         (4)  Penn Township, T-839 over Pine Creek,
     2             Bridge Rehabilitation                          80,000
     3             (Base Construction Allocation -
     4             $60,000)
     5             (Design and Contingencies - $20,000)
     6         (5)  Port Matilda Borough, Pedestrian
     7             Bridge over Bald Eagle Creek, Bridge
     8             Rehabilitation                                200,000
     9             (Base Construction Allocation -
    10             $175,000)
    11             (Design and Contingencies - $25,000)
    12         (6)  Spring Township, T-367, Hill Road
    13             Bridge, Bridge Replacement                    200,000
    14             (Base Construction Allocation -
    15             $150,000)
    16             (Land Allocation - $10,000)
    17             (Design and Contingencies - $40,000)
    18     (b)  State Bridges
    19         (1)  SR 0080, I-80 Viaduct over Moshannon
    20             Creek and Conrail, Rush Township,
    21             Bridge Rehabilitation                      14,510,000
    22             (Base Construction Allocation -
    23             $13,210,000)
    24             (Design and Contingencies - $1,300,000)
    25         (2)  SR 1002, Marsh Creek Bridge over Marsh
    26             Creek, Boggs Township, Bridge
    27             Replacement                                   760,000
    28             (Base Construction Allocation -
    29             $630,000)
    30             (Land Allocation - $20,000)
    19970S0186B0698                 - 120 -

     1             (Design and Contingencies - $110,000)
     2         (3)  SR 1002, Little Marsh Creek Bridge
     3             over Little Marsh Creek, Curtin
     4             Township, Bridge Replacement                  700,000
     5             (Base Construction Allocation -
     6             $600,000)
     7             (Land Allocation - $20,000)
     8             (Design and Contingencies - $80,000)
     9         (4)  SR 2012, Penns Creek Bridge Northwest
    10             of the Village of Spring Mills, Gregg
    11             Township, Bridge Replacement                  470,000
    12             (Base Construction Allocation -
    13             $360,000)
    14             (Land Allocation - $20,000)
    15             (Design and Contingencies - $90,000)
    16         (5)  SR 0220, SR 0220 over Laurel Run, Port
    17             Matilda Borough, Bridge Rehabilitation        450,000
    18             (Base Construction Allocation -
    19             $400,000)
    20             (Design and Contingencies - $50,000)
    21  Section 19.  Chester County.
    22     (a)  Local Bridges
    23         (1)  Parkesburg Borough, State Street
    24             Pedestrian Bridge over Amtrak, Bridge
    25             Replacement                                 1,700,000
    26             (Base Construction Allocation -
    27             $1,000,000)
    28             (Land Allocation - $500,000)
    29             (Design and Contingencies - $200,000)
    30         (2)  East Fallowfield Township, T-362,
    19970S0186B0698                 - 121 -

     1             Timacuia Road under Penn Central
     2             Railroad, Bridge Removal                      445,000
     3             (Base Construction Allocation -
     4             $400,000)
     5             (Land Allocation - $30,000)
     6             (Design and Contingencies - $15,000)
     7         (3)  East Marlborough Township, T-402,
     8             County Bridge No.65, Mill Road Bridge
     9             over West Branch of Red Clay Creek,
    10             Bridge Replacement                            345,000
    11             (Base Construction Allocation -
    12             $291,000)
    13             (Land Allocation - $25,000)
    14             (Design and Contingencies - $29,000)
    15         (4)  Oxford Borough, Broad Street Bridge
    16             over SEPTA, Bridge Replacement              1,304,000
    17             (Base Construction Allocation -
    18             $1,125,000)
    19             (Land Allocation - $20,000)
    20             (Design and Contingencies - $159,000)
    21         (5)  Penn Township, County Bridge No.260,
    22             Posey Mill Road Bridge over Big Elk
    23             Creek, Bridge Replacement                     425,000
    24             (Base Construction Allocation -
    25             $300,000)
    26             (Land Allocation - $25,000)
    27             (Design and Contingencies - $100,000)
    28         (6)  Tredyffrin Township, Old Lancaster
    29             Pike Bridge over Amtrak, Bridge
    30             Rehabilitation                                465,000
    19970S0186B0698                 - 122 -

     1             (Base Construction Allocation -
     2             $400,000)
     3             (Land Allocation - $30,000)
     4             (Design and Contingencies - $35,000)
     5         (7)  Tredyffrin Township, T-807, Evans Road
     6             Bridge over Conrail, Bridge
     7             Replacement                                   195,000
     8             (Base Construction Allocation -
     9             $150,000)
    10             (Land Allocation - $30,000)
    11             (Design and Contingencies - $15,000)
    12         (8)  West Caln and West Brandywine
    13             Townships, County Bridge No.283, Reid
    14             Road Bridge over West Branch of
    15             Brandywine Creek, Bridge Replacement          740,000
    16             (Base Construction Allocation -
    17             $600,000)
    18             (Land Allocation - $40,000)
    19             (Design and Contingencies - $100,000)
    20         (9)  West Goshen Township, T-210, Old
    21             Eachus Mill Road Bridge over SEPTA,
    22             Bridge Replacement                            615,000
    23             (Base Construction Allocation -
    24             $500,000)
    25             (Land Allocation - $15,000)
    26             (Design and Contingencies - $100,000)
    27         (10)  West Goshen Township, T-328, Bridge
    28             over Penn Central Railroad, Bridge
    29             Removal                                       132,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 123 -

     1             $110,000)
     2             (Land Allocation - $5,000)
     3             (Design and Contingencies - $17,000)
     4         (11)  West Marlborough Township, T-368,
     5             Creek Road Bridge under Penn Central
     6             Railroad, Bridge Removal                      580,000
     7             (Base Construction Allocation -
     8             $500,000)
     9             (Land Allocation - $5,000)
    10             (Design and Contingencies - $75,000)
    11         (12)  West Marlborough Township, Bridge
    12             over Doe Run, Bridge Replacement              915,000
    13             (Base Construction Allocation -
    14             $750,000)
    15             (Land Allocation - $25,000)
    16             (Design and Contingencies - $140,000)
    17         (13)  East Coventry Township, Zeiber Road
    18             over Pigeon Creek, Bridge Replacement         375,000
    19             (Base Construction Allocation -
    20             $300,000)
    21             (Land Allocation - $15,000)
    22             (Design and Contingencies - $60,000)
    23         (14)  South Coventry Township, Young Road
    24             over Pigeon Creek, Bridge
    25             Rehabilitation                                  6,000
    26             (Base Construction Allocation - $6,000)
    27         (15)  Franklin Township, T-356, Mount
    28             Olivet Road Bridge over Unnamed
    29             Tributary of Big Elk Creek, Bridge
    30             Rehabilitation                              8,100,000  <--
    19970S0186B0698                 - 124 -

     1             (Base Construction Allocation -
     2             $6,600,000)
     3             (Design and Contingencies - $1,500,000)
     4             REHABILITATION                                  9,000  <--
     5             (BASE CONSTRUCTION ALLOCATION - $7,000)
     6             (DESIGN AND CONTINGENCIES - $2,000)
     7         (16)  NORTH COVENTRY TOWNSHIP, SOUTH KEIM
     8             STREET, BRIDGE NO.270 OVER SMALL RUN,
     9             BRIDGE REPLACEMENT                            510,000
    10             (BASE CONSTRUCTION ALLOCATION -
    11             $150,000)
    12             (LAND ALLOCATION - $10,000)
    13             (DESIGN AND CONTINGENCIES - $350,000)
    14     (b)  State Bridges
    15         (1)  SR 1010, Swedesford Road Bridge over
    16             US 422, Drummers Lane and Warner Road,
    17             Tredyffrin, Chester County, Upper
    18             Merion, Montgomery County, Bridge
    19             Replacement                                 6,795,000
    20             (Base Construction Allocation -
    21             $6,210,000)
    22             (Land Allocation - $180,000)
    23             (Design and Contingencies - $405,000)
    24         (2)  SR 1045, Hares Hill Road Bridge over
    25             French Creek, East Pikeland Township,
    26             Bridge Rehabilitation                       1,000,000
    27             (Base Construction Allocation -
    28             $740,000)
    29             (Land Allocation - $60,000)
    30             (Design and Contingencies - $200,000)
    19970S0186B0698                 - 125 -

     1         (3)  SR 3014, Lees Road Bridge over Black
     2             Run, West Nottingham Township, Bridge
     3             Replacement                                 1,125,000
     4             (Base Construction Allocation -
     5             $850,000)
     6             (Land Allocation - $75,000)
     7             (Design and Contingencies - $200,000)
     8         (4)  SR 3030, Street Road Bridge over
     9             Octoraro Creek, Upper Oxford Township,
    10             Bridge Replacement                          1,875,000
    11             (Base Construction Allocation -
    12             $1,600,000)
    13             (Land Allocation - $75,000)
    14             (Design and Contingencies - $200,000)
    15         (5)  SR 0003, Gay Street Bridge over
    16             Abandoned Conrail, West Chester
    17             Borough, Bridge Removal                       180,000
    18             (Base Construction Allocation -
    19             $150,000)
    20             (Land Allocation - $10,000)
    21             (Design and Contingencies - $20,000)
    22         (6)  SR 0842, Shaws Bridges (Two Bridges)
    23             over Branch of Brandywine Creek, East
    24             Bradford and Pocopson Townships, Bridge
    25             Replacement                                 1,500,000
    26             (Base Construction Allocation -
    27             $1,288,000)
    28             (Land Allocation - $100,000)
    29             (Design and Contingencies - $112,000)
    30         (7)  SR 0842, Bridge Road Bridge over East
    19970S0186B0698                 - 126 -

     1             Branch of Brandywine Creek, East
     2             Bradford Township, Bridge Painting            214,000
     3             (Base Construction Allocation -
     4             $186,000)
     5             (Design and Contingencies - $28,000)
     6         (8)  SR 1049, Rapp's Dam Covered Bridge,
     7             East Pikeland Township, Bridge
     8             Painting                                       47,000
     9             (Base Construction Allocation -
    10             $41,000)
    11             (Design and Contingencies - $6,000)
    12         (9)  SR 2011, Phoenixville Pike Bridge
    13             under Abandoned Penn Central Railroad,
    14             West Goshen Township, Bridge Removal          125,000
    15             (Base Construction Allocation -
    16             $100,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $15,000)
    19         (10)  SR 2018, Green Hill Road Bridge under
    20             Abandoned Penn Central Railroad, West
    21             Goshen Township, Bridge Removal               125,000
    22             (Base Construction Allocation -
    23             $100,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $15,000)
    26         (11)  SR 3045, Springdell Road Bridge under
    27             Abandoned Penn Central Railroad, West
    28             Marborough Township, Bridge Removal           125,000
    29             (Base Construction Allocation -
    30             $100,000)
    19970S0186B0698                 - 127 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $15,000)
     3         (12)  SR 3049, Hilltop View Road Bridge
     4             over Buck and Doe Run Creek, Newlin
     5             Township, Bridge Replacement                1,450,000
     6             (Base Construction Allocation -
     7             $1,300,000)
     8             (Land Allocation - $50,000)
     9             (Design and Contingencies - $100,000)
    10         (13)  SR 1012, Bridge over Trout Creek,
    11             Tredyffrin Township, Bridge
    12             Replacement                                   850,000
    13             (Base Construction Allocation -
    14             $550,000)
    15             (Land Allocation - $50,000)
    16             (Design and Contingencies - $250,000)
    17  Section 20.  Clarion County.
    18     (a)  Local Bridges
    19         (1)  Beaver Township, T-400, Canoe Creek
    20             Bridge over Canoe Creek, Bridge
    21             Replacement                                   380,000
    22             (Base Construction Allocation -
    23             $300,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $70,000)
    26         (2)  Beaver Township, T-422, Deer Creek
    27             Bridge over Deer Creek, Bridge
    28             Replacement                                   540,000
    29             (Base Construction Allocation -
    30             $450,000)
    19970S0186B0698                 - 128 -

     1             (Land Allocation - $30,000)
     2             (Design and Contingencies - $60,000)
     3         (3)  Clarion and Millcreek Townships, T-
     4             490, Mill Creek Bridge over Mill Creek,
     5             Bridge Replacement                            540,000
     6             (Base Construction Allocation -
     7             $450,000)
     8             (Land Allocation - $10,000)
     9             (Design and Contingencies - $80,000)
    10         (4)  Elk Township, T-424, Deer Creek Bridge
    11             over Deer Creek, Bridge Replacement           620,000
    12             (Base Construction Allocation -
    13             $500,000)
    14             (Land Allocation - $20,000)
    15             (Design and Contingencies - $100,000)
    16         (5)  Farmington Township, T-562, Walley Run
    17             Bridge over Walley Run, Bridge
    18             Replacement                                   375,000
    19             (Base Construction Allocation -
    20             $300,000)
    21             (Land Allocation - $5,000)
    22             (Design and Contingencies - $70,000)
    23         (6)  Knox Township, T-850, Toby Creek
    24             Bridge over Toby Creek, Bridge
    25             Replacement                                   480,000
    26             (Base Construction Allocation -
    27             $400,000)
    28             (Land Allocation - $20,000)
    29             (Design and Contingencies - $60,000)
    30         (7)  Knox Township, T-600, Licking Creek
    19970S0186B0698                 - 129 -

     1             Bridge over Licking Creek, Bridge
     2             Replacement                                   445,000
     3             (Base Construction Allocation -
     4             $350,000)
     5             (Land Allocation - $15,000)
     6             (Design and Contingencies - $80,000)
     7         (8)  Madison Township, T-460, Red Bank
     8             Creek Bridge over Tributary of Red Bank
     9             Creek, Bridge Replacement                     390,000
    10             (Base Construction Allocation -
    11             $300,000)
    12             (Land Allocation - $20,000)
    13             (Design and Contingencies - $70,000)
    14         (9)  Porter Township, T-462, Fiddlers Run
    15             Bridge over Fiddlers Run, Bridge
    16             Replacement                                   390,000
    17             (Base Construction Allocation -
    18             $300,000)
    19             (Land Allocation - $10,000)
    20             (Design and Contingencies - $80,000)
    21         (10)  Porter Township, T-472, Leatherwood
    22             Creek Bridge over Leatherwood Creek,
    23             Bridge Replacement                            455,000
    24             (Base Construction Allocation -
    25             $375,000)
    26             (Land Allocation - $20,000)
    27             (Design and Contingencies - $60,000)
    28         (11)  Porter Township, T-750, Leisure Run
    29             Bridge over Leisure Run, Bridge
    30             Replacement                                   390,000
    19970S0186B0698                 - 130 -

     1             (Base Construction Allocation -
     2             $300,000)
     3             (Land Allocation - $10,000)
     4             (Design and Contingencies - $80,000)
     5         (12)  Red Bank Township, T-840, Beaver
     6             Creek Bridge over Beaver Creek, Bridge
     7             Replacement                                   420,000
     8             (Base Construction Allocation -
     9             $350,000)
    10             (Land Allocation - $15,000)
    11             (Design and Contingencies - $55,000)
    12         (13)  Red Bank Township, T-508, County
    13             Bridge No.46, Pine Creek Bridge over
    14             Pine Creek, Bridge Replacement                378,000
    15             (Base Construction Allocation -
    16             $300,000)
    17             (Land Allocation - $8,000)
    18             (Design and Contingencies - $70,000)
    19         (14)  Richland Township, T-382, Turkey Run
    20             Bridge over Turkey Run, Bridge
    21             Replacement                                   360,000
    22             (Base Construction Allocation -
    23             $300,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $50,000)
    26         (15)  Richland Township, T-382, Turkey Run
    27             Bridge over Turkey Run, Bridge
    28             Replacement                                   360,000
    29             (Base Construction Allocation -
    30             $300,000)
    19970S0186B0698                 - 131 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $50,000)
     3         (16)  Sligo Borough, Madison Street Bridge
     4             over Little Licking Creek, Bridge
     5             Replacement                                   445,000
     6             (Base Construction Allocation -
     7             $350,000)
     8             (Land Allocation - $15,000)
     9             (Design and Contingencies - $80,000)
    10         (17)  Beaver Township, T-332 over Beaver                   <--
    11             Creek, Bridge Replacement                     400,000
    12             (Base Construction Allocation -
    13             $275,000)
    14             (Land Allocation - $50,000)
    15             (Design and Contingencies - $75,000)
    16         (17)  BEAVER TOWNSHIP, T-332, BRIDGE NO.17                 <--
    17             OVER BEAVER CREEK, BRIDGE REPLACEMENT         560,000
    18             (BASE CONSTRUCTION ALLOCATION -
    19             $400,000)
    20             (LAND ALLOCATION - $10,000)
    21             (DESIGN AND CONTINGENCIES - $150,000)
    22         (18)  Beaver Township, T-385 over Canoe
    23             Creek, Bridge Replacement                     490,000
    24             (Base Construction Allocation -
    25             $320,000)
    26             (Land Allocation - $80,000)
    27             (Design and Contingencies - $90,000)
    28         (19)  Highland Township, T-573 over Toby
    29             Creek, Bridge Replacement                     500,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 132 -

     1             $360,000)
     2             (Land Allocation - $40,000)
     3             (Design and Contingencies - $100,000)
     4         (20)  Knox Township, T-850 over Step Creek,
     5             Bridge Replacement                            240,000
     6             (Base Construction Allocation -
     7             $180,000)
     8             (Land Allocation - $20,000)
     9             (Design and Contingencies - $40,000)
    10         (21)  Perry Township, T-301, Bridge
    11             Replacement                                   200,000
    12             (Base Construction Allocation -
    13             $130,000)
    14             (Land Allocation - $30,000)
    15             (Design and Contingencies - $40,000)
    16         (22)  Millcreek Township, T-564 over Little
    17             Mill Creek, Bridge Replacement                480,000
    18             (Base Construction Allocation -
    19             $400,000)
    20             (Land Allocation - $20,000)
    21             (Design and Contingencies - $60,000)
    22         (23)  Paint Township, T-578 over Step
    23             Creek, Bridge Replacement                     500,000
    24             (Base Construction Allocation -
    25             $400,000)
    26             (Land Allocation - $20,000)
    27             (Design and Contingencies - $80,000)
    28         (24)  Monroe Township, T-486, County Bridge
    29             No.22 over Piney Creek, Bridge
    30             Replacement                                   480,000
    19970S0186B0698                 - 133 -

     1             (Base Construction Allocation -
     2             $400,000)
     3             (Land Allocation - $10,000)
     4             (Design and Contingencies - $70,000)
     5         (25)  Clarion Township, T-532 over Brush
     6             Run, Bridge Replacement                       245,000
     7             (Base Construction Allocation -
     8             $200,000)
     9             (Land Allocation - $10,000)
    10             (Design and Contingencies - $35,000)
    11         (26)  Clarion Township, T-561 over Jones
    12             Run, Bridge Replacement                       245,000
    13             (Base Construction Allocation -
    14             $200,000)
    15             (Land Allocation - $10,000)
    16             (Design and Contingencies - $35,000)
    17         (27)  Elk Township, T-582 over Mahles Run,
    18             Bridge Replacement                            245,000
    19             (Base Construction Allocation -
    20             $200,000)
    21             (Land Allocation - $10,000)
    22             (Design and Contingencies - $35,000)
    23         (28)  Farmington Township, T-609 over Engle
    24             Run, Bridge Replacement                       245,000
    25             (Base Construction Allocation -
    26             $200,000)
    27             (Land Allocation - $10,000)
    28             (Design and Contingencies - $35,000)
    29         (29)  Paint Township, T-577 over Toby
    30             Creek, Bridge Replacement                     106,000
    19970S0186B0698                 - 134 -

     1             (Base Construction Allocation -
     2             $100,000)
     3             (Land Allocation - $1,000)
     4             (Design and Contingencies - $5,000)
     5         (30)  Paint Township, T-576 over Toby
     6             Creek, Bridge Replacement                     106,000
     7             (Base Construction Allocation -
     8             $100,000)
     9             (Land Allocation - $1,000)
    10             (Design and Contingencies - $5,000)
    11         (31)  Beaver Township, T-405 over Canoe
    12             Creek, Bridge Replacement                     106,000
    13             (Base Construction Allocation -
    14             $100,000)
    15             (Land Allocation - $1,000)
    16             (Design and Contingencies - $5,000)
    17         (32)  Beaver Township, T-411 over Boyd Run,
    18             Bridge Replacement                            106,000
    19             (Base Construction Allocation -
    20             $100,000)
    21             (Land Allocation - $1,000)
    22             (Design and Contingencies - $5,000)
    23         (33)  Elk Township, T-424 over Deer Creek,
    24             Bridge Replacement                            250,000
    25             (Base Construction Allocation -
    26             $200,000)
    27             (Land Allocation - $10,000)
    28             (Design and Contingencies - $40,000)
    29         (34)  Highland Township, T-577, Bridge over
    30             Toby Creek, Bridge Replacement                518,000
    19970S0186B0698                 - 135 -

     1             (Base Construction Allocation -
     2             $380,000)
     3             (Land Allocation - $8,000)
     4             (Design and Contingencies - $130,000)
     5         (35)  Beaver Township, T-423, Bridge over
     6             Canoe Creek, Bridge Replacement               510,000
     7             (Base Construction Allocation -
     8             $400,000)
     9             (Land Allocation - $10,000)
    10             (Design and Contingencies - $100,000)
    11         (36)  Elk Township, T-418, Bridge over Deer
    12             Creek, Bridge Replacement                     380,000
    13             (Base Construction Allocation -
    14             $300,000)
    15             (Land Allocation - $10,000)
    16             (Design and Contingencies - $70,000)
    17         (37)  Paint Township, T-582, Bridge over
    18             Little Paint Creek, Bridge Replacement        424,000
    19             (Base Construction Allocation -
    20             $350,000)
    21             (Land Allocation - $9,000)
    22             (Design and Contingencies - $65,000)
    23         (38)  ASHLAND TOWNSHIP, T-863, BRIDGE OVER                 <--
    24             LITTLE CANOE CREEK, BRIDGE REPLACEMENT        330,000
    25             (BASE CONSTRUCTION ALLOCATION -
    26             $200,000)
    27             (LAND ALLOCATION - $10,000)
    28             (DESIGN AND CONTINGENCIES - $120,000)
    29         (39)  BEAVER TOWNSHIP, T-325, SCHETTLER
    30             ROAD BRIDGE OVER CANOE CREEK, BRIDGE
    19970S0186B0698                 - 136 -

     1             REPLACEMENT                                   395,000
     2             (BASE CONSTRUCTION ALLOCATION -
     3             $250,000)
     4             (LAND ALLOCATION - $15,000)
     5             (DESIGN AND CONTINGENCIES - $130,000)
     6         (40)  MADISON TOWNSHIP, T-442, BRIDGE NO.34
     7             OVER WILDCAT RUN, BRIDGE REPLACEMENT          425,000
     8             (BASE CONSTRUCTION ALLOCATION -
     9             $275,000)
    10             (LAND ALLOCATION - $10,000)
    11             (DESIGN AND CONTINGENCIES - $140,000)
    12         (41)  MADISON TOWNSHIP, T-689, BRIDGE NO.33
    13             OVER WILDCAT RUN, BRIDGE REPLACEMENT          460,000
    14             (BASE CONSTRUCTION ALLOCATION -
    15             $300,000)
    16             (LAND ALLOCATION - $10,000)
    17             (DESIGN AND CONTINGENCIES - $150,000)
    18         (42)  MADISON TOWNSHIP, T-880, BRIDGE
    19             NO.2050 OVER TURKEY RUN, BRIDGE
    20             REPLACEMENT                                   330,000
    21             (BASE CONSTRUCTION ALLOCATION -
    22             $200,000)
    23             (LAND ALLOCATION - $10,000)
    24             (DESIGN AND CONTINGENCIES - $120,000)
    25     (b)  State Bridges
    26         (1)  SR 0058, Callensburg Bridge over
    27             Clarion River, Licking Township, Bridge
    28             Painting                                      365,000
    29             (Base Construction Allocation -
    30             $350,000)
    19970S0186B0698                 - 137 -

     1             (Design and Contingencies - $15,000)
     2         (2)  SR 0080, Beaver Creek Eastbound Bridge
     3             over Beaver Creek, Beaver Township,
     4             Bridge Painting                               390,000
     5             (Base Construction Allocation -
     6             $375,000)
     7             (Design and Contingencies - $15,000)
     8         (3)  SR 0080, Beaver Creek Westbound Bridge
     9             over Beaver Creek, Beaver Township,
    10             Bridge Painting                               390,000
    11             (Base Construction Allocation -
    12             $375,000)
    13             (Design and Contingencies - $15,000)
    14         (4)  SR 0080, Canoe Creek Eastbound Bridge
    15             over Canoe Creek, Beaver Township,
    16             Bridge Painting                             1,230,000
    17             (Base Construction Allocation -
    18             $1,200,000)
    19             (Design and Contingencies - $30,000)
    20         (5)  SR 0080, Canoe Creek Westbound Bridge
    21             over Canoe Creek, Beaver Township,
    22             Bridge Painting                             1,290,000
    23             (Base Construction Allocation -
    24             $1,260,000)
    25             (Design and Contingencies - $30,000)
    26         (6)  SR 0080, TR 558 Bridge over I-80,
    27             Clarion Township, Bridge Painting             195,000
    28             (Base Construction Allocation -
    29             $180,000)
    30             (Design and Contingencies - $15,000)
    19970S0186B0698                 - 138 -

     1         (7)  SR 0322, Exit 11 Bridge over I-80,
     2             Clarion Township, Clarion Bridge
     3             Painting                                      205,000
     4             (Base Construction Allocation -
     5             $190,000)
     6             (Design and Contingencies - $15,000)
     7         (8)  SR 0536, Mayport Bridge over Redbank
     8             Creek, Red Bank Township, Bridge
     9             Painting                                      215,000
    10             (Base Construction Allocation -
    11             $200,000)
    12             (Design and Contingencies - $15,000)
    13         (9)  SR 1009, Brush Creek Bridge over Brush
    14             Creek, Clarion Township, Bridge
    15             Painting                                       70,000
    16             (Base Construction Allocation -
    17             $55,000)
    18             (Design and Contingencies - $15,000)
    19         (10)  SR 2001, Piney Creek Bridge over
    20             Piney Creek, Limestone Township, Bridge
    21             Painting                                       85,000
    22             (Base Construction Allocation -
    23             $70,000)
    24             (Design and Contingencies - $15,000)
    25         (11)  SR 2001, Little Piney Creek Bridge
    26             over Little Piney Creek, Limestone
    27             Township, Bridge Painting                      70,000
    28             (Base Construction Allocation -
    29             $55,000)
    30             (Design and Contingencies - $15,000)
    19970S0186B0698                 - 139 -

     1         (12)  SR 2005, Glade Run Bridge over Glade
     2             Run, Limestone Township, Bridge
     3             Painting                                       60,000
     4             (Base Construction Allocation -
     5             $45,000)
     6             (Design and Contingencies - $15,000)
     7         (13)  SR 2007, Licking Creek Bridge over
     8             Licking Creek, Monroe Township, Bridge
     9             Painting                                       75,000
    10             (Base Construction Allocation -
    11             $60,000)
    12             (Design and Contingencies - $15,000)
    13         (14)  SR 2009, Lawsonham Bridge over
    14             Redbank Creek, Madison Township, Bridge
    15             Painting                                      195,000
    16             (Base Construction Allocation -
    17             $180,000)
    18             (Design and Contingencies - $15,000)
    19         (15)  SR 2009, Wildcat Run Bridge over
    20             Wildcat Run, Madison Township, Bridge
    21             Painting                                       85,000
    22             (Base Construction Allocation -
    23             $70,000)
    24             (Design and Contingencies - $15,000)
    25         (16)  SR 2015, Little Piney Creek Bridge
    26             over Little Piney Creek, Limestone
    27             Township, Bridge Painting                      60,000
    28             (Base Construction Allocation -
    29             $45,000)
    30             (Design and Contingencies - $15,000)
    19970S0186B0698                 - 140 -

     1         (17)  SR 3020, Alum Rock Bridge over Turkey
     2             Run, Richland Township, Bridge
     3             Painting                                       75,000
     4             (Base Construction Allocation -
     5             $60,000)
     6             (Design and Contingencies - $15,000)
     7         (18)  SR 4003, Turkey Run Bridge over
     8             Turkey Run, Richland Township, Bridge
     9             Painting                                       65,000
    10             (Base Construction Allocation -
    11             $50,000)
    12             (Design and Contingencies - $15,000)
    13         (19)  SR 4005, Canoe Creek Bridge over
    14             Canoe Creek, Beaver Township, Bridge
    15             Painting                                       70,000
    16             (Base Construction Allocation -
    17             $55,000)
    18             (Design and Contingencies - $15,000)
    19         (20)  SR 0208, Conrail Overpass, Elk
    20             Township, Bridge Removal                      120,000
    21             (Base Construction Allocation -
    22             $80,000)
    23             (Land Allocation - $10,000)
    24             (Design and Contingencies - $30,000)
    25         (21)  SR 0322, Conrail Overpass, Elk
    26             Township, Bridge Removal                      250,000
    27             (Base Construction Allocation -
    28             $200,000)
    29             (Land Allocation - $10,000)
    30             (Design and Contingencies - $40,000)
    19970S0186B0698                 - 141 -

     1         (22)  SR 1011, Lake Erie, Franklin and
     2             Clarion Railroad Overpass, Clarion
     3             Township, Bridge Removal                       12,000
     4             (Base Construction Allocation -
     5             $10,000)
     6             (Design and Contingencies - $2,000)
     7         (23)  SR 0066, Bridge over Piney Creek,
     8             Limestone Township, Bridge Replacement        650,000
     9             (Base Construction Allocation -
    10             $500,000)
    11             (Land Allocation - $20,000)
    12             (Design and Contingencies - $130,000)
    13         (24)  SR 0066, Bridge over Little Piney
    14             Creek, Limestone Township, Bridge
    15             Replacement                                   600,000
    16             (Base Construction Allocation -
    17             $450,000)
    18             (Land Allocation - $20,000)
    19             (Design and Contingencies - $130,000)
    20         (25)  SR 0068, Bridge over Brush Run,
    21             Monroe Township, Bridge Replacement           650,000
    22             (Base Construction Allocation -
    23             $500,000)
    24             (Land Allocation - $20,000)
    25             (Design and Contingencies - $130,000)
    26         (26)  SR 0208, Bridge over Canoe Creek,
    27             Beaver Township, Bridge Replacement           550,000
    28             (Base Construction Allocation -
    29             $400,000)
    30             (Land Allocation - $20,000)
    19970S0186B0698                 - 142 -

     1             (Design and Contingencies - $130,000)
     2         (27)  SR 2001, Bridge over Little Piney
     3             Creek, Limestone Township, Bridge
     4             Replacement                                   490,000
     5             (Base Construction Allocation -
     6             $350,000)
     7             (Land Allocation - $20,000)
     8             (Design and Contingencies - $120,000)
     9         (28)  SR 0208, SR 0208 over Deer Creek, Elk
    10             Township, Bridge Replacement                  505,000
    11             (Base Construction Allocation -
    12             $450,000)
    13             (Land Allocation - $5,000)
    14             (Design and Contingencies - $50,000)
    15         (29)  SR 2007, SR 2007 over Deer Creek,
    16             Beaver Township, Bridge Replacement           455,000
    17             (Base Construction Allocation -
    18             $400,000)
    19             (Land Allocation - $5,000)
    20             (Design and Contingencies - $50,000)
    21         (30)  SR 4005, SR 4005 over Canoe Creek,
    22             Beaver Township, Bridge Replacement           405,000
    23             (Base Construction Allocation -
    24             $350,000)
    25             (Land Allocation - $5,000)
    26             (Design and Contingencies - $50,000)
    27         (31)  SR 4008, SR 4008 over Paint Creek,
    28             Knox Township, Bridge Replacement             505,000
    29             (Base Construction Allocation -
    30             $450,000)
    19970S0186B0698                 - 143 -

     1             (Land Allocation - $5,000)
     2             (Design and Contingencies - $50,000)
     3  Section 21.  Clearfield County.
     4     (a)  Local Bridges
     5         (1)  Knox Township, T-565 Bridge over Potts
     6             Run, Bridge Replacement                       510,000
     7             (Base Construction Allocation -
     8             $350,000)
     9             (Land Allocation - $10,000)
    10             (Design and Contingencies - $150,000)
    11         (2)  Houtzdale Borough, McAteer Street
    12             Bridge, Bridge Replacement                    430,000
    13             (Base Construction Allocation -
    14             $270,000)
    15             (Land Allocation - $20,000)
    16             (Design and Contingencies - $140,000)
    17         (3)  Penn Township, T-461 over Bell Run,
    18             Bridge Replacement                            106,000
    19             (Base Construction Allocation -
    20             $100,000)
    21             (Land Allocation - $1,000)
    22             (Design and Contingencies - $5,000)
    23     (b)  State Bridges
    24         (1)  SR 0879, Bridge over US 322 near
    25             Clearfield Mall, Lawrence Township,
    26             Bridge Painting                               644,000
    27             (Base Construction Allocation -
    28             $614,000)
    29             (Design and Contingencies - $30,000)
    30         (2)  SR 0729, Bridge over Muddy Run,
    19970S0186B0698                 - 144 -

     1             Beccaria Township, Bridge Painting             35,000
     2             (Base Construction Allocation -
     3             $30,000)
     4             (Design and Contingencies - $5,000)
     5         (3)  SR 0879, Bridge over Susquehanna
     6             River, Lawrence Township, Bridge
     7             Painting                                      183,000
     8             (Base Construction Allocation -
     9             $163,000)
    10             (Design and Contingencies - $20,000)
    11         (4)  SR 0970, Bridge over Moshannon Creek,
    12             Osceola Mills, Bridge Painting                145,000
    13             (Base Construction Allocation -
    14             $120,000)
    15             (Design and Contingencies - $25,000)
    16         (5)  SR 0970, Bridge over Susquehanna
    17             River, Village of Shawville, Bridge
    18             Painting                                      163,000
    19             (Base Construction Allocation -
    20             $143,000)
    21             (Design and Contingencies - $20,000)
    22         (6)  SR 1009, Bridge over Alder Run, Morris
    23             Township, Bridge Painting                      18,000
    24             (Base Construction Allocation -
    25             $15,000)
    26             (Design and Contingencies - $3,000)
    27         (7)  SR 1014, Bridge over Alder Run, Graham
    28             Township, Bridge Painting                      18,000
    29             (Base Construction Allocation -
    30             $15,000)
    19970S0186B0698                 - 145 -

     1             (Design and Contingencies - $3,000)
     2         (8)  SR 2010, Bridge over Beaver Run,
     3             Woodward Township, Bridge Painting             18,000
     4             (Base Construction Allocation -
     5             $15,000)
     6             (Design and Contingencies - $3,000)
     7         (9)  SR 2024, Bridge over Conrail, Pike
     8             Township, Bridge Painting                      28,000
     9             (Base Construction Allocation -
    10             $24,000)
    11             (Design and Contingencies - $4,000)
    12         (10)  SR 3001, Bridge over Chest Creek,
    13             Mahaffey Borough, Bridge Replacement        1,750,000
    14             (Base Construction Allocation -
    15             $1,300,000)
    16             (Land Allocation - $150,000)
    17             (Design and Contingencies - $300,000)
    18         (11)  SR 3012, Bridge over Matthews Run,
    19             Beccaria Township, Bridge Painting             18,000
    20             (Base Construction Allocation -
    21             $15,000)
    22             (Design and Contingencies - $3,000)
    23         (12)  SR 3012, Bridge over Clearfield
    24             Creek, Beccaria Township, Bridge
    25             Painting                                      100,000
    26             (Base Construction Allocation -
    27             $90,000)
    28             (Design and Contingencies - $10,000)
    29         (13)  SR 0219, SR 0219 over Bear Run, Bell
    30             Township, Bridge Replacement                  505,000
    19970S0186B0698                 - 146 -

     1             (Base Construction Allocation -
     2             $450,000)
     3             (Land Allocation - $5,000)
     4             (Design and Contingencies - $50,000)
     5         (14)  SR 2014, BRIDGE OVER COAL RUN,                       <--
     6             DECATUR TOWNSHIP, BRIDGE REPLACEMENT          692,000
     7             (BASE CONSTRUCTION ALLOCATION -
     8             $512,000)
     9             (LAND ALLOCATION - $30,000)
    10             (DESIGN AND CONTINGENCIES - $150,000)
    11         (15)  SR 3012, BRIDGE OVER CLEARFIELD
    12             CREEK, BECCARIA TOWNSHIP, BRIDGE
    13             PAINTING                                       18,000
    14             (BASE CONSTRUCTION ALLOCATION -
    15             $15,000)
    16             (DESIGN AND CONTINGENCIES - $3,000)
    17  Section 22.  Clinton County.
    18     (a)  Local Bridges
    19         (1)  Mill Hall Borough, Church Street over
    20             Fishing Creek, Bridge Rehabilitation            5,000
    21             (Base Construction Allocation - $4,000)
    22             (Design and Contingencies - $1,000)
    23     (b)  State Bridges
    24         (1)  SR 0044, Bridge over SR 0220, 1 Mile
    25             Northeast of Avis, Pine Creek Township,
    26             Bridge Painting                               580,000
    27             (Base Construction Allocation -
    28             $525,000)
    29             (Design and Contingencies - $55,000)
    30         (2)  SR 0080, Lamar Interchange (Two
    19970S0186B0698                 - 147 -

     1             Bridges) over PA 64 at Exit 25, Porter
     2             Township, Bridge Rehabilitation             4,100,000
     3             (Base Construction Allocation -
     4             $3,400,000)
     5             (Design and Contingencies - $700,000)
     6         (3)  SR 0144, Bridge over Kettle Creek, 1
     7             Mile East of Hammersley Fork, Leidy
     8             Township, Bridge Painting                     660,000
     9             (Base Construction Allocation -
    10             $600,000)
    11             (Design and Contingencies - $60,000)
    12  Section 23.  Columbia County.
    13     (a)  Local Bridges (Reserved)
    14     (b)  State Bridges
    15         (1)  SR 0044, Chillisquaque Creek Bridge
    16             over Chillisquaque Creek, 3 Miles
    17             Northwest of Jerseytown, Bridge
    18             Replacement                                   477,000
    19             (Base Construction Allocation -
    20             $382,000)
    21             (Land Allocation - $24,000)
    22             (Design and Contingencies - $71,000)
    23         (2)  SR 0093, Bridge over North Branch of
    24             Briar Creek, Bridge Replacement               350,000
    25             (Base Construction Allocation -
    26             $275,000)
    27             (Land Allocation - $15,000)
    28             (Design and Contingencies - $60,000)
    29         (3)  SR 0093, Briar Creek Bridge over Briar
    30             Creek, 3 Miles West of Berwick, Bridge
    19970S0186B0698                 - 148 -

     1             Replacement                                   392,000
     2             (Base Construction Allocation -
     3             $315,000)
     4             (Land Allocation - $18,000)
     5             (Design and Contingencies - $59,000)
     6         (4)  SR 0239, West Creek Bridge over West
     7             Creek, Southeast of Benton and
     8             Sugarloaf Townships, Bridge
     9             Replacement                                   670,000
    10             (Base Construction Allocation -
    11             $536,000)
    12             (Land Allocation - $34,000)
    13             (Design and Contingencies - $100,000)
    14         (5)  SR 0442, West Branch Run Bridge over
    15             West Branch Run, 1.5 Miles North of
    16             Iola, Bridge Replacement                      206,000
    17             (Base Construction Allocation -
    18             $165,000)
    19             (Land Allocation - $10,000)
    20             (Design and Contingencies - $31,000)
    21         (6)  SR 1004, Erie-Lackawanna Railroad
    22             Bridge, Viaduct over Conrail, South
    23             Centre Township, Bridge Replacement         1,900,000
    24             (Base Construction Allocation -
    25             $1,600,000)
    26             (Land Allocation - $110,000)
    27             (Design and Contingencies - $190,000)
    28         (7)  SR 1019, Briar Creek Bridge over Briar
    29             Creek, Briar Creek Township, Bridge
    30             Replacement                                   404,000
    19970S0186B0698                 - 149 -

     1             (Base Construction Allocation -
     2             $323,000)
     3             (Land Allocation - $20,000)
     4             (Design and Contingencies - $61,000)
     5         (8)  SR 4012, Little Hemlock Creek Bridge
     6             over Little Hemlock Creek, 10 Miles
     7             Southeast of Jerseytown, Bridge
     8             Replacement                                   284,000
     9             (Base Construction Allocation -
    10             $227,000)
    11             (Land Allocation - $14,000)
    12             (Design and Contingencies - $43,000)
    13         (9)  SR 4037, Mud Run Bridge over Mud Run,
    14             5 Miles Northwest of Millville Borough,
    15             Bridge Replacement                            307,000
    16             (Base Construction Allocation -
    17             $246,000)
    18             (Land Allocation - $15,000)
    19             (Design and Contingencies - $46,000)
    20         (10)  SR 0011, Bridge over Fishing Creek,
    21             Bridge Painting                               530,000
    22             (Base Construction Allocation -
    23             $520,000)
    24             (Design and Contingencies - $10,000)
    25         (11)  SR 1022, Bridge over Fishing Creek,
    26             Bridge Painting                               380,000
    27             (Base Construction Allocation -
    28             $370,000)
    29             (Design and Contingencies - $10,000)
    30         (12)  SR 1022, Bridge over Old Channel,
    19970S0186B0698                 - 150 -

     1             Bridge Painting                               125,000
     2             (Base Construction Allocation -
     3             $115,000)
     4             (Design and Contingencies - $10,000)
     5         (13)  SR 4009, Bridge over Fishing Creek,
     6             Bridge Painting                               315,000
     7             (Base Construction Allocation -
     8             $305,000)
     9             (Design and Contingencies - $10,000)
    10         (14)  SR 0042, SR 0042 over Roaring Creek,
    11             Conyngham Township, Bridge Replacement        457,000
    12             (Base Construction Allocation -
    13             $366,000)
    14             (Land Allocation - $23,000)
    15             (Design and Contingencies - $68,000)
    16         (15)  SR 0239, SR 0239 over West Creek,
    17             Benton Township, Bridge Replacement           760,000
    18             (Base Construction Allocation -
    19             $560,000)
    20             (Land Allocation - $35,000)
    21             (Design and Contingencies - $165,000)
    22         (16)  SR 0254, SR 0254 over Little Fishing
    23             Creek, Millville Borough, Bridge
    24             Replacement                                 1,020,000
    25             (Base Construction Allocation -
    26             $816,000)
    27             (Land Allocation - $51,000)
    28             (Design and Contingencies - $153,000)
    29         (17)  SR 0339, SR 0339 over Beaver Run,
    30             Beaver Township, Bridge Replacement           320,000
    19970S0186B0698                 - 151 -

     1             (Base Construction Allocation -
     2             $256,000)
     3             (Land Allocation - $16,000)
     4             (Design and Contingencies - $48,000)
     5         (18)  SR 0487, SR 0487 over Stony Brook,
     6             Orange Township, Bridge Replacement           380,000
     7             (Base Construction Allocation -
     8             $304,000)
     9             (Land Allocation - $19,000)
    10             (Design and Contingencies - $57,000)
    11         (19)  SR 1014, SR 1014 over Little Briar
    12             Creek, Briar Creek Township, Bridge
    13             Replacement                                   415,000
    14             (Base Construction Allocation -
    15             $332,000)
    16             (Land Allocation - $21,000)
    17             (Design and Contingencies - $62,000)
    18         (20)  SR 1023, SR 1023 over East Briar
    19             Creek, Briar Creek Township, Bridge
    20             Replacement                                   520,000
    21             (Base Construction Allocation -
    22             $466,000)
    23             (Land Allocation - $29,000)
    24             (Design and Contingencies - $25,000)
    25         (21)  SR 2003, SR 2003 over Tributary of
    26             Roaring Creek, Roaring Creek Township,
    27             Bridge Replacement                            171,000
    28             (Base Construction Allocation -
    29             $136,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 152 -

     1             (Design and Contingencies - $25,000)
     2         (22)  SR 2003, SR 2003 over Tributary of
     3             Roaring Creek, Locust Township, Bridge
     4             Replacement                                   245,000
     5             (Base Construction Allocation -
     6             $196,000)
     7             (Land Allocation - $12,000)
     8             (Design and Contingencies - $37,000)
     9         (23)  SR 2009, SR 2009 over Catawissa
    10             Creek, Main Township, Bridge
    11             Replacement                                   436,000
    12             (Base Construction Allocation -
    13             $349,000)
    14             (Land Allocation - $22,000)
    15             (Design and Contingencies - $65,000)
    16         (24)  SR 4009, SR 4009 over Little Fishing
    17             Creek, Mt. Pleasant Township, Bridge
    18             Replacement                                 1,232,000
    19             (Base Construction Allocation -
    20             $986,000)
    21             (Land Allocation - $61,000)
    22             (Design and Contingencies - $185,000)
    23         (25)  SR 4033, SR 4033 over Wolfhouse Run,
    24             Pine Township, Bridge Replacement             252,000
    25             (Base Construction Allocation -
    26             $202,000)
    27             (Land Allocation - $12,000)
    28             (Design and Contingencies - $38,000)
    29         (26)  SR 4045, SR 4045 over Green Creek,
    30             Greenwood Township, Bridge Replacement        435,000
    19970S0186B0698                 - 153 -

     1             (Base Construction Allocation -
     2             $348,000)
     3             (Land Allocation - $22,000)
     4             (Design and Contingencies - $65,000)
     5         (27)  SR 4049, SR 4049 over Coles Creek,
     6             Sugarloaf Township, Bridge Replacement      1,095,000
     7             (Base Construction Allocation -
     8             $876,000)
     9             (Land Allocation - $55,000)
    10             (Design and Contingencies - $164,000)
    11  Section 24.  Crawford County.
    12     (a) Local Bridges
    13         (1)  Fairfield Township, T-636 over Branch
    14             of French Creek, Bridge Replacement           108,000
    15             (Base Construction Allocation -
    16             $100,000)
    17             (Land Allocation - $1,000)
    18             (Design and Contingencies - $7,000)
    19         (2)  Fairfield Township, T-321 Bridge No.1
    20             over Branch of French Creek, Bridge
    21             Replacement                                   106,000
    22             (Base Construction Allocation -
    23             $100,000)
    24             (Land Allocation - $1,000)
    25             (Design and Contingencies - $5,000)
    26         (3)  Fairfield Township, T-321 Bridge No.2
    27             over Branch of French Creek, Bridge
    28             Replacement                                   106,000
    29             (Base Construction Allocation -
    30             $100,000)
    19970S0186B0698                 - 154 -

     1             (Land Allocation - $1,000)
     2             (Design and Contingencies - $5,000)
     3         (4)  Spring Township, T-747 over Branch of
     4             Conneaut Creek, Bridge Replacement            126,000
     5             (Base Construction Allocation -
     6             $120,000)
     7             (Land Allocation - $1,000)
     8             (Design and Contingencies - $5,000)
     9         (5)  Wayne Township, T-347 over Branch of
    10             Powdermill Run, Bridge Replacement            106,000
    11             (Base Construction Allocation -
    12             $100,000)
    13             (Land Allocation - $1,000)
    14             (Design and Contingencies - $5,000)
    15         (6)  Wayne Township, T-457 over Tributary
    16             of Lake Creek, Bridge Replacement             106,000
    17             (Base Construction Allocation -
    18             $100,000)
    19             (Land Allocation - $1,000)
    20             (Design and Contingencies - $5,000)
    21     (b)  State Bridges
    22         (1)  SR 0006, SR 0006 over Padan Creek,
    23             Conneaut Township, Bridge Replacement       1,004,000
    24             (Base Construction Allocation -
    25             $784,000)
    26             (Land Allocation - $20,000)
    27             (Design and Contingencies - $200,000)
    28         (2)  SR 0006, SR 0006 over French Creek,
    29             Woodcock Township, Bridge Replacement       2,325,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 155 -

     1             $1,840,000)
     2             (Land Allocation - $20,000)
     3             (Design and Contingencies - $465,000)
     4         (3)  SR 0079, SR 0079 under Maple Drive,
     5             Hayfield Township, Bridge Replacement       2,401,000
     6             (Base Construction Allocation -
     7             $1,901,000)
     8             (Land Allocation - $20,000)
     9             (Design and Contingencies - $480,000)
    10         (4)  SR 0089, SR 0089 over Shirley Run,
    11             Rome Township, Bridge Replacement             510,000
    12             (Base Construction Allocation -
    13             $420,000)
    14             (Land Allocation - $20,000)
    15             (Design and Contingencies - $70,000)
    16         (5)  SR 0098, SR 0098 over Van Horne Run,
    17             Vernon Township, Bridge Replacement           320,000
    18             (Base Construction Allocation -
    19             $260,000)
    20             (Land Allocation - $10,000)
    21             (Design and Contingencies - $50,000)
    22         (6)  SR 0099, SR 0099 over Little
    23             Conneauttee Creek, Cambridge Township,
    24             Bridge Replacement                            950,000
    25             (Base Construction Allocation -
    26             $700,000)
    27             (Land Allocation - $50,000)
    28             (Design and Contingencies - $200,000)
    29         (7)  SR 0099, SR 0099 over Conneaut Creek,
    30             Cambridge Township, Bridge Replacement        600,000
    19970S0186B0698                 - 156 -

     1             (Base Construction Allocation -
     2             $500,000)
     3             (Land Allocation - $30,000)
     4             (Design and Contingencies - $70,000)
     5         (8)  SR 0198, SR 0198 over Carr Run,
     6             Woodcock Township, Bridge Replacement         260,000
     7             (Base Construction Allocation -
     8             $200,000)
     9             (Land Allocation - $20,000)
    10             (Design and Contingencies - $40,000)
    11         (9)  SR 0285, SR 0285 over Bennett Run,
    12             North Shenango Township, Bridge
    13             Replacement                                   750,000
    14             (Base Construction Allocation -
    15             $650,000)
    16             (Land Allocation - $20,000)
    17             (Design and Contingencies - $80,000)
    18         (10)  SR 1002, SR 1002 over Acker Run,
    19             Venango Township, Bridge Replacement          370,000
    20             (Base Construction Allocation -
    21             $300,000)
    22             (Land Allocation - $20,000)
    23             (Design and Contingencies - $50,000)
    24         (11)  SR 1024, SR 1024 over Britton Run,
    25             Sparta Township, Bridge Replacement           340,000
    26             (Base Construction Allocation -
    27             $250,000)
    28             (Land Allocation - $20,000)
    29             (Design and Contingencies - $70,000)
    30         (12)  SR 2005, SR 2005 over French Creek,
    19970S0186B0698                 - 157 -

     1             East Fairfield Township, Bridge
     2             Replacement                                 1,300,000
     3             (Base Construction Allocation -
     4             $1,130,000)
     5             (Land Allocation - $20,000)
     6             (Design and Contingencies - $150,000)
     7         (13)  SR 2010, SR 2010 over Little Sugar
     8             Creek, Wayne Township, Bridge
     9             Replacement                                   260,000
    10             (Base Construction Allocation -
    11             $200,000)
    12             (Land Allocation - $20,000)
    13             (Design and Contingencies - $40,000)
    14         (14)  SR 3016, SR 3016 over B&LE Railroad,
    15             Summit Township, Bridge Replacement         1,150,000
    16             (Base Construction Allocation -
    17             $1,000,000)
    18             (Land Allocation - $30,000)
    19             (Design and Contingencies - $120,000)
    20         (15)  SR 0018, SR 0018 Bridge over
    21             Tributary of Conneaut Creek, Summit
    22             Township, Bridge Rehabilitation               115,000
    23             (Base Construction Allocation -
    24             $100,000)
    25             (Design and Contingencies - $15,000)
    26         (16)  SR 0098, SR 0098 Bridge over
    27             Tributary of Cussewago Creek, Hayfield
    28             Township, Bridge Rehabilitation               110,000
    29             (Base Construction Allocation -
    30             $100,000)
    19970S0186B0698                 - 158 -

     1             (Design and Contingencies - $10,000)
     2         (17)  SR 2003, Mercer Pike Bridge over
     3             Conneaut Creek Outlet, Union Township,
     4             Bridge Replacement                            600,000
     5             (Base Construction Allocation -
     6             $520,000)
     7             (Land Allocation - $30,000)
     8             (Design and Contingencies - $50,000)
     9  Section 25.  (Reserved).
    10  Section 26.  Dauphin County.
    11     (a)  Local Bridges
    12         (1)  City of Harrisburg, Mulberry Street
    13             Ramp to Cameron Street, Bridge
    14             Rehabilitation                                108,000
    15             (Base Construction Allocation -
    16             $73,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $ 25,000)
    19         (2)  City of Harrisburg, Maclay Street
    20             Bridge over Railroad, Bridge
    21             Rehabilitation                                218,000
    22             (Base Construction Allocation -
    23             $183,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $25,000)
    26         (3)  Mifflin Township, T-631, Reitz Road
    27             Bridge over Little Wiconisco Creek,
    28             County Bridge No.24, Bridge
    29             Replacement                                   290,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 159 -

     1             $200,000)
     2             (Land Allocation - $10,000)
     3             (Design and Contingencies - $80,000)
     4         (4)  Mifflin Township, T-556, Kessler Road
     5             Bridge over Little Wiconisco Creek,
     6             Bridge Replacement                            235,000
     7             (Base Construction Allocation -
     8             $150,000)
     9             (Land Allocation - $10,000)
    10             (Design and Contingencies - $75,000)
    11         (5)  Washington Township, Bolts Road Bridge
    12             over Wiconisco Creek, Bridge
    13             Rehabilitation                                469,000
    14             (Base Construction Allocation -
    15             $374,000)
    16             (Land Allocation - $10,000)
    17             (Design and Contingencies - $85,000)
    18         (6)  Wayne Township, T-496, Lebo Road
    19             Bridge over Powell Creek, Bridge
    20             Rehabilitation                                263,000
    21             (Base Construction Allocation -
    22             $168,000)
    23             (Land Allocation - $10,000)
    24             (Design and Contingencies - $85,000)
    25         (7)  Conewago Township, T-602 and T-749
    26             over Conewago Creek, Bridge
    27             Replacement                                   722,000
    28             (Base Construction Allocation -
    29             $556,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 160 -

     1             (Design and Contingencies - $156,000)
     2         (8)  Halifax Township, T-454 over Armstrong
     3             Creek, Bridge Replacement                     480,000
     4             (Base Construction Allocation -
     5             $367,000)
     6             (Land Allocation - $10,000)
     7             (Design and Contingencies - $103,000)
     8         (9)  Jackson Township, T-544 over Armstrong
     9             Creek, Bridge Replacement                     379,000
    10             (Base Construction Allocation -
    11             $288,000)
    12             (Land Allocation - $10,000)
    13             (Design and Contingencies - $81,000)
    14         (10)  Jefferson Township, T-534 over Powell
    15             Creek, Bridge Replacement                     397,000
    16             (Base Construction Allocation -
    17             $302,000)
    18             (Land Allocation - $10,000)
    19             (Design and Contingencies - $85,000)
    20         (11)  Upper Paxton Township, T-460 over
    21             Wiconisco Creek, Bridge Replacement           427,000
    22             (Base Construction Allocation -
    23             $326,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $91,000)
    26         (12)  Washington Township, T-595 over
    27             Wiconisco Creek, Bridge Replacement           669,000
    28             (Base Construction Allocation -
    29             $515,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 161 -

     1             (Design and Contingencies - $144,000)
     2         (13)  Washington Township, T-462 over
     3             Wiconisco Creek, Bridge Replacement           668,000
     4             (Base Construction Allocation -
     5             $514,000)
     6             (Land Allocation - $10,000)
     7             (Design and Contingencies - $144,000)
     8         (14)  Wayne Township, T-448 over Powell
     9             Creek, Bridge Replacement                     438,000
    10             (Base Construction Allocation -
    11             $334,000)
    12             (Land Allocation (Design and                           <--
    13             Contingencies
    14             - $94,000)
    15             (LAND ALLOCATION - $10,000)                            <--
    16             (DESIGN AND CONTINGENCIES - $94,000)
    17     (b)  State Bridges (Reserved)
    18  Section 27.  Delaware County.
    19     (a)  Local Bridges
    20         (1)  City of Chester, West 7th Street,
    21             County Bridge No.186 over Chester
    22             Creek, Bridge Replacement                   1,630,000
    23             (Base Construction Allocation -
    24             $1,470,000)
    25             (Land Allocation - $10,000)
    26             (Design and Contingencies - $150,000)
    27     (b)  State Bridges
    28         (1)  SR 0030, Pedestrian Tunnel under SR
    29             0030 and Ithan Avenue at Villanova
    30             University, Radnor Township, Pedestrian
    19970S0186B0698                 - 162 -

     1             Facilities                                  7,360,000
     2             (Base Construction Allocation -
     3             $6,500,000)
     4             (Land Allocation - $650,000)
     5             (Design and Contingencies - $210,000)
     6         (2)  SR 1015, Darby-Paoli Road Bridge over
     7             Branch of Little Darby Creek, Radnor
     8             Township, Bridge Replacement                1,000,000
     9             (Base Construction Allocation -
    10             $760,000)
    11             (Land Allocation - $40,000)
    12             (Design and Contingencies - $200,000)
    13         (3)  SR 0291, 4th Street Bridge over Ridley
    14             Creek, Chester Township, Bridge
    15             Painting                                      291,000
    16             (Base Construction Allocation -
    17             $253,000)
    18             (Design and Contingencies - $38,000)
    19         (4)  SR 0291, Essington Avenue Bridge over
    20             Darby Creek, Ridley Township, Bridge
    21             Painting                                      546,000
    22             (Base Construction Allocation -
    23             $487,000)
    24             (Design and Contingencies - $59,000)
    25         (5)  SR 1019, Conestoga Road Bridge over
    26             PennDOT Railroad Right-of-Way, Radnor
    27             Township, Bridge Removal                      125,000
    28             (Base Construction Allocation -
    29             $100,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 163 -

     1             (Design and Contingencies - $15,000)
     2         (6)  SR 3019, Rosevally Road Bridge over
     3             SEPTA, Upper Providence Township,
     4             Bridge Replacement                            875,000
     5             (Base Construction Allocation -
     6             $700,000)
     7             (Land Allocation - $100,000)
     8             (Design and Contingencies - $75,000)
     9  Section 28.  Elk County.
    10     (a)  Local Bridges
    11         (1)  Village of Wilcox, T-631, Bridge over
    12             Clarion River, Bridge Replacement           1,100,000
    13             (Base Construction Allocation -
    14             $850,000)
    15             (Land Allocation - $50,000)
    16             (Design and Contingencies - $200,000)
    17     (b)  State Bridges (Reserved)
    18  Section 29.  Erie County.
    19     (a)  Local Bridges
    20         (1)  Girard Township, Beckman Bridge over
    21             I-90, Bridge Painting                         200,000
    22             (Base Construction Allocation -
    23             $200,000)
    24         (2)  Millcreek Township, T-707, Zimmerly
    25             Road Bridge over I-79, New 2-Lane
    26             Bridge Construction, New Bridge             2,150,000
    27             (Base Construction Allocation -
    28             $1,900,000)
    29             (Land Allocation - $50,000)
    30             (Design and Contingencies - $200,000)
    19970S0186B0698                 - 164 -

     1         (3)  City of Erie, Norman Way, Bridge over
     2             Millcreek, Bridge Rehabilitation              225,000
     3             (Base Construction Allocation -
     4             $200,000)
     5             (Design and Contingencies - $25,000)
     6         (4)  City of Erie, McBride Viaduct-East
     7             Avenue, Bridge over Railroad Lines,
     8             Bridge Rehabilitation                       1,340,000
     9             (Base Construction Allocation -
    10             $1,300,000)
    11             (Design and Contingencies - $40,000)
    12         (5)  City of Erie, Kahkwa Bridge over
    13             Ravine Drive, Bridge Rehabilitation            60,000
    14             (Base Construction Allocation -
    15             $50,000)
    16             (Design and Contingencies - $10,000)
    17         (6)  Greenfield Township, T-974, Old Route
    18             89 Bridge over West Branch of French
    19             Creek Tributary, Bridge Replacement           350,000
    20             (Base Construction Allocation -
    21             $300,000)
    22             (Land Allocation - $10,000)
    23             (Design and Contingencies - $40,000)
    24         (7)  Franklin Township, T-479 T-424, Bridge                <--
    25             No.1 over Falk Run, Bridge Replacement        350,000
    26             (Base Construction Allocation -
    27             $300,000)
    28             (Land Allocation - $10,000)
    29             (Design and Contingencies - $40,000)
    30         (8)  Franklin Township, T-479 T-424, Bridge                <--
    19970S0186B0698                 - 165 -

     1             No.2 over Falk Run, Bridge Replacement        350,000
     2             (Base Construction Allocation -
     3             $300,000)
     4             (Land Allocation - $10,000)
     5             (Design and Contingencies - $40,000)
     6         (9)  Franklin Township, T-424, Falls Road                  <--
     7             Bridge over Falk Run, Bridge
     8             Replacement                                   300,000
     9             (Base Construction Allocation -
    10             $250,000)
    11             (Land Allocation - $10,000)
    12             (Design and Contingencies - $40,000)
    13         (10) (9)  Millcreek Township, T-707,
    14             Zimmerly Road Bridge over I-79, Two-
    15             Lane Bridge Construction                    2,150,000
    16             (Base Construction Allocation -
    17             $1,900,000)
    18             (Land Allocation - $50,000)
    19             (Design and Contingencies - $200,000)
    20     (b)  State Bridges
    21         (1)  SR 0005, SR 0005 over Scott Run,
    22             Harborcreek Township, Bridge
    23             Replacement                                   140,000
    24             (Base Construction Allocation -
    25             $100,000)
    26             (Land Allocation - $10,000)
    27             (Design and Contingencies - $30,000)
    28         (2)  SR 0006, SR 0006 over French Creek, Le
    29             Boeuf Township, Bridge Replacement            700,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 166 -

     1             $600,000)
     2             (Land Allocation - $20,000)
     3             (Design and Contingencies - $80,000)
     4         (3)  SR 0019, SR 0019 over LeBoeuf Creek,
     5             Waterford Township, Bridge Replacement        950,000
     6             (Base Construction Allocation -
     7             $840,000)
     8             (Land Allocation - $30,000)
     9             (Design and Contingencies - $80,000)
    10         (4)  SR 0020, SR 0020 over I-79, City of
    11             Erie, Bridge Replacement                    2,000,000
    12             (Base Construction Allocation -
    13             $1,770,000)
    14             (Land Allocation - $30,000)
    15             (Design and Contingencies - $200,000)
    16         (5)  SR 0089, SR 0089 over Sixteen Mile
    17             Creek, North East Township, Bridge
    18             Replacement                                   490,000
    19             (Base Construction Allocation -
    20             $400,000)
    21             (Land Allocation - $20,000)
    22             (Design and Contingencies - $70,000)
    23         (6)  SR 0090, SR 0090 over Crooked Creek,
    24             Girard Township, Bridge Replacement         1,420,000
    25             (Base Construction Allocation -
    26             $1,330,000)
    27             (Land Allocation - $30,000)
    28             (Design and Contingencies - $60,000)
    29         (7)  SR 0090, SR 0090 under Cherry Street,
    30             Summit Township, Bridge Replacement         1,600,000
    19970S0186B0698                 - 167 -

     1             (Base Construction Allocation -
     2             $1,410,000)
     3             (Land Allocation - $40,000)
     4             (Design and Contingencies - $150,000)
     5         (8)  SR 0090, SR 0090 under Clark Road,
     6             Harborcreek Township, Bridge
     7             Replacement                                 2,100,000
     8             (Base Construction Allocation -
     9             $1,880,000)
    10             (Land Allocation - $40,000)
    11             (Design and Contingencies - $180,000)
    12         (9)  SR 0098, SR 0098 over Cussewago Creek,
    13             Elk Creek Township, Bridge Replacement        400,000
    14             (Base Construction Allocation -
    15             $300,000)
    16             (Land Allocation - $20,000)
    17             (Design and Contingencies - $80,000)
    18         (10)  SR 0474, SR 0474 over Dean Run,
    19             Venango Township, Bridge Replacement          200,000
    20             (Base Construction Allocation -
    21             $160,000)
    22             (Land Allocation - $10,000)
    23             (Design and Contingencies - $30,000)
    24         (11)  SR 1001, SR 1001 over Conrail,
    25             Millcreek Township, Bridge Replacement        720,000
    26             (Base Construction Allocation -
    27             $600,000)
    28             (Land Allocation - $20,000)
    29             (Design and Contingencies - $100,000)
    30         (12)  SR 1011, SR 1011 over Alder Brook,
    19970S0186B0698                 - 168 -

     1             Venango Township, Bridge Replacement          470,000
     2             (Base Construction Allocation -
     3             $400,000)
     4             (Land Allocation - $10,000)
     5             (Design and Contingencies - $60,000)
     6         (13)  SR 1013, SR 1013 over I-90, North
     7             East Township, Bridge Replacement           1,220,000
     8             (Base Construction Allocation -
     9             $1,100,000)
    10             (Land Allocation - $20,000)
    11             (Design and Contingencies - $100,000)
    12         (14)  SR 3001, SR 3001 over Conneaut Creek,
    13             Conneaut Township, Bridge Replacement       1,020,000
    14             (Base Construction Allocation -
    15             $900,000)
    16             (Land Allocation - $20,000)
    17             (Design and Contingencies - $100,000)
    18         (15)  SR 3003, SR 3003 over West Branch
    19             Conneaut Creek, Conneaut Township,
    20             Bridge Replacement                            630,000
    21             (Base Construction Allocation -
    22             $550,000)
    23             (Land Allocation - $20,000)
    24             (Design and Contingencies - $60,000)
    25         (16)  SR 3014, SR 3014 over Trout Run,
    26             Waterford Borough, Bridge Replacement         370,000
    27             (Base Construction Allocation -
    28             $300,000)
    29             (Land Allocation - $20,000)
    30             (Design and Contingencies - $50,000)
    19970S0186B0698                 - 169 -

     1         (17)  SR 4007, SR 4007 over I-90, Fairview
     2             Township, Bridge Replacement                1,920,000
     3             (Base Construction Allocation -
     4             $1,800,000)
     5             (Land Allocation - $20,000)
     6             (Design and Contingencies - $100,000)
     7  Section 30.  Fayette County.
     8     (a)  Local Bridges
     9         (1)  Brownsville Township, Lynn Run Road
    10             Bridge over Redstone Creek, Bridge
    11             Replacement                                   200,000
    12             (Base Construction Allocation -
    13             $130,000)
    14             (Land Allocation - $10,000)
    15             (Design and Contingencies - $60,000)
    16         (2)  Dunbar Township, Falls Avenue Bridge
    17             over Possum Run, Bridge Replacement           450,000
    18             (Base Construction Allocation -
    19             $350,000)
    20             (Land Allocation - $15,000)
    21             (Design and Contingencies - $85,000)
    22         (3)  Georges Township, County Bridge No.162
    23             over Mountain Creek, Bridge
    24             Replacement                                   370,000  <--
    25             (Base Construction Allocation -
    26             $300,000)
    27             (Land Allocation - $5,000)
    28             (Design and Contingencies - $65,000)
    29             REPLACEMENT                                   640,000  <--
    30             (BASE CONSTRUCTION ALLOCATION -
    19970S0186B0698                 - 170 -

     1             $425,000)
     2             (LAND ALLOCATION - $40,000)
     3             (DESIGN AND CONTINGENCIES - $175,000)
     4         (4)  German Township, Footedale Bridge
     5             No.66 over Dunlap Creek, Bridge
     6             Replacement                                   415,000  <--
     7             (Base Construction Allocation -
     8             $330,000)
     9             (Land Allocation - $10,000)
    10             (Design and Contingencies - $75,000)
    11             REPLACEMENT                                   498,000  <--
    12             (BASE CONSTRUCTION ALLOCATION -
    13             $313,000)
    14             (LAND ALLOCATION - $35,000)
    15             (DESIGN AND CONTINGENCIES - $150,000)
    16         (5)  German Township, County Bridge No.54
    17             over Browns Run, Bridge Replacement           430,000  <--
    18             (Base Construction Allocation -
    19             $355,000)
    20             (Land Allocation - $5,000)
    21             (Design and Contingencies - $70,000)
    22             OVER BROWNS RUN, BRIDGE REPLACEMENT           793,000  <--
    23             (BASE CONSTRUCTION ALLOCATION -
    24             $563,000)
    25             (LAND ALLOCATION - $50,000)
    26             (DESIGN AND CONTINGENCIES - $180,000)
    27         (6)  German Township, Leckrone Bridge No.54
    28             over Browns Run, Bridge Replacement           430,000
    29             (Base Construction Allocation -
    30             $350,000)
    19970S0186B0698                 - 171 -

     1             (Land Allocation - $5,000)
     2             (Design and Contingencies - $75,000)
     3         (7)  Menallen Township, T-509, Bridge over
     4             Branch of Dunlap Creek, Bridge
     5             Replacement                                   165,000
     6             (Base Construction Allocation -
     7             $110,000)
     8             (Land Allocation - $5,000)
     9             (Design and Contingencies - $50,000)
    10         (8)  Menallen Township, Fan Hallow Road
    11             Bridge over Fans Run, Bridge
    12             Replacement                                   145,000
    13             (Base Construction Allocation -
    14             $90,000)
    15             (Land Allocation - $5,000)
    16             (Design and Contingencies - $50,000)
    17         (9)  Menallen and North Union Townships,
    18             Fan Hollow Bridge No.184 over Jennings
    19             Run, Bridge Replacement                       440,000
    20             (Base Construction Allocation -
    21             $350,000)
    22             (Land Allocation - $10,000)
    23             (Design and Contingencies - $80,000)
    24         (10)  Nicholson Township, County Bridge
    25             No.29 over York Run, Bridge
    26             Replacement                                   360,000  <--
    27             (Base Construction Allocation -
    28             $295,000)
    29             (Land Allocation - $5,000)
    30             (Design and Contingencies - $60,000)
    19970S0186B0698                 - 172 -

     1             REPLACEMENT                                   535,000  <--
     2             (BASE CONSTRUCTION ALLOCATION -
     3             $350,000)
     4             (LAND ALLOCATION - $35,000)
     5             (DESIGN AND CONTINGENCIES - $150,000)
     6         (11)  Redstone Township, Merrittstown
     7             Bridge No.147 over Dunlap Creek, Bridge
     8             Replacement                                   435,000
     9             (Base Construction Allocation -
    10             $350,000)
    11             (Land Allocation - $10,000)
    12             (Design and Contingencies - $75,000)
    13         (12)  South Union Township, Leith Bridge                   <--
    14             No.41 over Redstone Creek, Bridge
    15             Replacement                                   450,000
    16             (Base Construction Allocation -
    17             $360,000)
    18             (Land Allocation - $10,000)
    19             (Design and Contingencies - $80,000)
    20         (13)  Steward Township, Meadow Run Bridge
    21             No.82 over Meadow Run, Bridge
    22             Replacement                                   450,000
    23             (Base Construction Allocation -
    24             $360,000)
    25             (Land Allocation - $10,000)
    26             (Design and Contingencies - $80,000)
    27         (12)  SOUTH UNION TOWNSHIP, T-479, LEITH                   <--
    28             BRIDGE NO.41 OVER REDSTONE CREEK,
    29             BRIDGE REPLACEMENT                            690,000
    30             (BASE CONSTRUCTION ALLOCATION -
    19970S0186B0698                 - 173 -

     1             $475,000)
     2             (LAND ALLOCATION - $40,000)
     3             (DESIGN AND CONTINGENCIES - $175,000)
     4         (13)  STEWARD TOWNSHIP, T-798, MEADOW RUN
     5             BRIDGE NO.82 OVER MEADOW RUN, BRIDGE
     6             REPLACEMENT                                   825,000
     7             (BASE CONSTRUCTION ALLOCATION -
     8             $575,000)
     9             (LAND ALLOCATION - $55,000)
    10             (DESIGN AND CONTINGENCIES - $195,000)
    11         (14)  Springhill Township, T-335, County
    12             Bridge No.92 over York Run, Bridge
    13             Replacement                                 1,438,000
    14             (Base Construction Allocation -
    15             $1,113,000)
    16             (Land Allocation - $75,000)
    17             (Design and Contingencies - $250,000)
    18         (15)  Springfield Township, T-593, County
    19             Bridge No.111 over Mill Run, Bridge
    20             Replacement                                   320,000
    21             (Base Construction Allocation -
    22             $225,000)
    23             (Land Allocation - $20,000)
    24             (Design and Contingencies - $75,000)
    25         (16)  North Union Township, T-535 over
    26             Redstone Creek, Bridge Replacement            825,000
    27             (Base Construction Allocation -
    28             $625,000)
    29             (Land Allocation - $25,000)
    30             (Design and Contingencies - $175,000)
    19970S0186B0698                 - 174 -

     1         (17)  North Union Township, T-557 over
     2             Redstone Creek, Bridge Replacement            450,000
     3             (Base Construction Allocation -
     4             $275,000)
     5             (Land Allocation - $50,000)
     6             (Design and Contingencies - $125,000)
     7         (18)  GEORGES TOWNSHIP, T-387, COUNTY                      <--
     8             BRIDGE NO.102 OVER YORK RUN, BRIDGE
     9             REHABILITATION                                320,000
    10             (BASE CONSTRUCTION ALLOCATION -
    11             $225,000)
    12             (LAND ALLOCATION - $20,000)
    13             (DESIGN AND CONTINGENCIES - $75,000)
    14         (19)  SOUTH UNION TOWNSHIP, T-459, TOWNSHIP
    15             BRIDGE NO.1 OVER LICK RUN, BRIDGE
    16             REPLACEMENT                                   280,000
    17             (BASE CONSTRUCTION ALLOCATION -
    18             $175,000)
    19             (LAND ALLOCATION - $25,000)
    20             (DESIGN AND CONTINGENCIES - $80,000)
    21         (20)  STEWART TOWNSHIP, T-415, COUNTY
    22             BRIDGE NO.63 OVER MEADOW RUN, BRIDGE
    23             REPLACEMENT                                 1,005,000
    24             (BASE CONSTRUCTION ALLOCATION -
    25             $775,000)
    26             (LAND ALLOCATION - $50,000)
    27             (DESIGN AND CONTINGENCIES - $180,000)
    28         (21)  GERMAN TOWNSHIP, COUNTY BRIDGE NO.54
    29             OVER BROWNS RUN AT LEITH COMMUNITY,
    30             BRIDGE REPLACEMENT                            430,000
    19970S0186B0698                 - 175 -

     1             (BASE CONSTRUCTION ALLOCATION -
     2             $350,000)
     3             (LAND ALLOCATION - $5,000)
     4             (DESIGN AND CONTINGENCIES - $75,000)
     5     (b)  State Bridges
     6         (1)  SR 0021, Masontown Bridge over
     7             Monongahela River, Railroad and Private
     8             Road, German Township, Bridge Painting      1,500,000
     9             (Base Construction Allocation -
    10             $1,500,000)
    11         (2)  SR 0031, Jacobs Creek Bridge over
    12             Branch of Jacobs Creek, Bullskin
    13             Township, Bridge Replacement                  290,000
    14             (Base Construction Allocation -
    15             $180,000)
    16             (Land Allocation - $35,000)
    17             (Design and Contingencies - $75,000)
    18         (3)  SR 0119, Memorial Bridge over
    19             Youghiogheny River, Connellsville
    20             Borough, Bridge Painting                      100,000
    21             (Base Construction Allocation -
    22             $100,000)
    23         (4)  SR 0201, Furnace Run Bridge over
    24             Furnace Run, Franklin Township, Bridge
    25             Replacement                                   445,000
    26             (Base Construction Allocation -
    27             $245,000)
    28             (Land Allocation - $25,000)
    29             (Design and Contingencies - $175,000)
    30         (5)  SR 0711, Crawford Avenue Bridge over
    19970S0186B0698                 - 176 -

     1             Youghiogheny River, Connellsville
     2             Borough, Bridge Painting                      100,000
     3             (Base Construction Allocation -
     4             $100,000)
     5         (6)  SR 0982, Jacobs Creek Bridge over
     6             Branch of Jacobs Creek, Bullskin
     7             Township, Bridge Replacement                  335,000
     8             (Base Construction Allocation -
     9             $225,000)
    10             (Land Allocation - $35,000)
    11             (Design and Contingencies - $75,000)
    12         (7)  SR 0982, Bridge over Mounts Creek,
    13             Bullskin Township, Bridge Painting            105,000
    14             (Base Construction Allocation -
    15             $105,000)
    16         (8)  SR 1051, Mounts Creek Bridge over
    17             Mounts Creek, Bullskin Township, Bridge
    18             Replacement                                   436,000
    19             (Base Construction Allocation -
    20             $236,000)
    21             (Land Allocation - $25,000)
    22             (Design and Contingencies - $175,000)
    23         (9)  SR 3013, Browns Run Bridge over Browns
    24             Run, German Township, Bridge
    25             Replacement                                   631,000
    26             (Base Construction Allocation -
    27             $431,000)
    28             (Land Allocation - $25,000)
    29             (Design and Contingencies - $175,000)
    30         (10)  SR 3015, Muddy Run Bridge over Muddy
    19970S0186B0698                 - 177 -

     1             Run, Georges Township, Bridge Painting         33,000
     2             (Base Construction Allocation -
     3             $33,000)
     4         (11)  SR 4038, Washington Run Bridge over
     5             Washington Run, Perry Township, Bridge
     6             Replacement                                   640,000
     7             (Base Construction Allocation -
     8             $440,000)
     9             (Land Allocation - $25,000)
    10             (Design and Contingencies - $175,000)
    11         (12)  SR 0381, SR 0381 over Stoney Run,
    12             Wharton Township, Bridge Replacement          663,000
    13             (Base Construction Allocation -
    14             $463,000)
    15             (Land Allocation - $50,000)
    16             (Design and Contingencies - $150,000)
    17         (13)  SR 0819, SR 0819 over Branch of
    18             Jacobs Creek, Lower Tyrone Township,
    19             Bridge Replacement                            240,000
    20             (Base Construction Allocation -
    21             $125,000)
    22             (Land Allocation - $15,000)
    23             (Design and Contingencies - $100,000)
    24         (14)  SR 1021, SR 1021 over Breakneck Run,
    25             Bullskin Township, Bridge Replacement         650,000
    26             (Base Construction Allocation -
    27             $475,000)
    28             (Land Allocation - $50,000)
    29             (Design and Contingencies - $125,000)
    30         (15)  SR 1031, SR 1031 over Galley Run,
    19970S0186B0698                 - 178 -

     1             Upper Tyrone Township, Bridge
     2             Replacement                                   475,000
     3             (Base Construction Allocation -
     4             $325,000)
     5             (Land Allocation - $25,000)
     6             (Design and Contingencies - $125,000)
     7         (16)  SR 1031, SR 1031 over Branch of
     8             Galley Run, Upper Tyrone Township,
     9             Bridge Replacement                            613,000
    10             (Base Construction Allocation -
    11             $413,000)
    12             (Land Allocation - $50,000)
    13             (Design and Contingencies - $150,000)
    14         (17)  SR 1044, SR 1044 over Branch of
    15             Mounts Creek, Bullskin Township, Bridge
    16             Replacement                                   350,000
    17             (Base Construction Allocation -
    18             $200,000)
    19             (Land Allocation - $25,000)
    20             (Design and Contingencies - $125,000)
    21         (18)  SR 2003, SR 2003 over Chaney Run,
    22             Wharton Township, Bridge Replacement          290,000
    23             (Base Construction Allocation -
    24             $175,000)
    25             (Land Allocation - $15,000)
    26             (Design and Contingencies - $100,000)
    27         (19)  SR 3003, SR 3003 at Nicholson
    28             Township Border, Springhill Township,
    29             Bridge Replacement                          1,400,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 179 -

     1             $1,125,000)
     2             (Land Allocation - $75,000)
     3             (Design and Contingencies - $200,000)
     4         (20)  SR 3003, SR 3003 over Georges Creek,
     5             Springhill Township, Bridge
     6             Replacement                                 1,450,000
     7             (Base Construction Allocation -
     8             $1,150,000)
     9             (Land Allocation - $75,000)
    10             (Design and Contingencies - $225,000)
    11         (21)  SR 3003, SR 3003 Nicholson Township
    12             over Georges Creek, Springhill
    13             Township, Bridge Replacement                1,200,000
    14             (Base Construction Allocation -
    15             $975,000)
    16             (Land Allocation - $50,000)
    17             (Design and Contingencies - $175,000)
    18         (22)  SR 3009, SR 3009 over Georges Creek,
    19             Springhill Township, Bridge
    20             Replacement                                   863,000
    21             (Base Construction Allocation -
    22             $688,000)
    23             (Land Allocation - $25,000)
    24             (Design and Contingencies - $150,000)
    25         (23)  SR 3013, SR 3013 over Middle Run,
    26             German Township, Bridge Replacement           900,000
    27             (Base Construction Allocation -
    28             $650,000)
    29             (Land Allocation - $75,000)
    30             (Design and Contingencies - $175,000)
    19970S0186B0698                 - 180 -

     1         (24)  SR 4027, SR 4027 over Little Redstone
     2             Creek, Jefferson Township, Bridge
     3             Replacement                                   538,000
     4             (Base Construction Allocation -
     5             $338,000)
     6             (Land Allocation - $50,000)
     7             (Design and Contingencies - $150,000)
     8         (25)  SR 4044, SR 4044 over Downers Run,
     9             Washington Township, Bridge
    10             Replacement                                   800,000
    11             (Base Construction Allocation -
    12             $575,000)
    13             (Land Allocation - $50,000)
    14             (Design and Contingencies - $175,000)
    15         (26)  SR 4046, SR 4046 over Lutz Run and
    16             Abandoned Railroad, Washington
    17             Township, Bridge Replacement                1,400,000
    18             (Base Construction Allocation -
    19             $1,075,000)
    20             (Land Allocation - $75,000)
    21             (Design and Contingencies - $250,000)
    22         (27)  SR 1045, BRIDGE OVER BRANCH OF                       <--
    23             DICKERSON RUN, VANDERBILT BOROUGH,
    24             BRIDGE REPLACEMENT                            330,000
    25             (BASE CONSTRUCTION ALLOCATION -
    26             $225,000)
    27             (LAND ALLOCATION - $5,000)
    28             (DESIGN AND CONTINGENCIES - $100,000
    29         (28)  SR 0201, BRIDGE OVER VIRGIN RUN,
    30             FRANKLIN TOWNSHIP, BRIDGE REPLACEMENT         330,000
    19970S0186B0698                 - 181 -

     1             (BASE CONSTRUCTION ALLOCATION -
     2             $225,000)
     3             (LAND ALLOCATION - $5,000)
     4             (DESIGN AND CONTINGENCIES - $100,000
     5         (29)  SR 4016, BRIDGE OVER REDSTONE CREEK,
     6             REDSTONE TOWNSHIP, BRIDGE REPLACEMENT       1,030,000
     7             (BASE CONSTRUCTION ALLOCATION -
     8             $830,000)
     9             (LAND ALLOCATION - $$25,000)
    10             (DESIGN AND CONTINGENCIES - $175,000)
    11         (30)  SR 1021, BRIDGE OVER BREAKNECK RUN,
    12             BULLSKIN TOWNSHIP, BRIDGE REPLACEMENT         505,000
    13             (BASE CONSTRUCTION ALLOCATION -
    14             $325,000)
    15             (LAND ALLOCATION - $5,000)
    16             (DESIGN AND CONTINGENCIES - $175,000)
    17         (31)  SR 1031, BRIDGE OVER BRANCH OF GALLEY
    18             RUN, UPPER TYRONE TOWNSHIP, BRIDGE
    19             REPLACEMENT                                   465,000
    20             (BASE CONSTRUCTION ALLOCATION -
    21             $300,000
    22             (LAND ALLOCATION - $15,000)
    23             (DESIGN AND CONTINGENCIES - $150,000)
    24         (32)  SR 3003, BRIDGE OVER GEORGES CREEK,
    25             SPRINGHILL/NICHOLSON TOWNSHIP, BRIDGE
    26             REPLACEMENT                                   785,000
    27             (BASE CONSTRUCTION ALLOCATION -
    28             $600,000)
    29             (LAND ALLOCATION - $10,000)
    30             (DESIGN AND CONTINGENCIES - $175,000)
    19970S0186B0698                 - 182 -

     1         (33)  SR 3003, BRIDGE OVER GEORGES CREEK,
     2             SPRINGHILL/NICHOLSON TOWNSHIP, BRIDGE
     3             REPLACEMENT                                   885,000
     4             (BASE CONSTRUCTION ALLOCATION -
     5             $700,000)
     6             (LAND ALLOCATION - $10,000)
     7             (DESIGN AND CONTINGENCIES -$175,000)
     8         (34)  SR 4027, BRIDGE OVER LITTLE REDSTONE
     9             CREEK, JEFFERSON TOWNSHIP, BRIDGE
    10             REPLACEMENT                                   355,000
    11             (BASE CONSTRUCTION ALLOCATION -
    12             $250,000)
    13             (LAND ALLOCATION - $5,000)
    14             (DESIGN AND CONTINGENCIES - $100,000)
    15         (35)  SR 3007, BRIDGE OVER GEORGES CREEK,
    16             GEORGES TOWNSHIP, BRIDGE REPLACEMENT          700,000
    17             (BASE CONSTRUCTION ALLOCATION -
    18             $500,000)
    19             (LAND ALLOCATION - $25,000)
    20             (DESIGN AND CONTINGENCIES - $175,000)
    21         (36)  SR 0031, JACOBS CREEK BRIDGE OVER
    22             JACOBS CREEK, BULLSKIN TOWNSHIP,
    23             FAYETTE COUNTY, AND MT. PLEASANT
    24             TOWNSHIP, WESTMORELAND COUNTY, BRIDGE
    25             REPLACEMENT                                   715,000
    26             (BASE CONSTRUCTION ALLOCATION -
    27             $500,000)
    28             (LAND ALLOCATION - $40,000)
    29             (DESIGN AND CONTINGENCIES - $175,000)
    30  Section 31.  Forest County.
    19970S0186B0698                 - 183 -

     1     (a)  Local Bridges (Reserved)
     2     (b)  State Bridges
     3         (1)  SR 0227, SR 0227 over West Hickory
     4             Creek, Harmony Township, Bridge
     5             Replacement                                   480,000
     6             (Base Construction Allocation -
     7             $400,000)
     8             (Land Allocation - $20,000)
     9             (Design and Contingencies - $60,000)
    10         (2)  SR 3001, SR 3001 over Little Tionesta
    11             Creek, Tionesta Township, Bridge
    12             Replacement                                   400,000
    13             (Base Construction Allocation -
    14             $310,000)
    15             (Land Allocation - $10,000)
    16             (Design and Contingencies - $80,000)
    17         (3)  SR 3004, SR 3004 over Little Hickory
    18             Creek, Hickory Township, Bridge
    19             Replacement                                   390,000
    20             (Base Construction Allocation -
    21             $300,000)
    22             (Land Allocation - $30,000)
    23             (Design and Contingencies - $60,000)
    24         (4)  SR 3004, SR 3004 over Piney Run, Green
    25             Township, Bridge Replacement                  390,000
    26             (Base Construction Allocation -
    27             $300,000)
    28             (Land Allocation - $10,000)
    29             (Design and Contingencies - $80,000)
    30         (5)  SR 3001, Red Brush Road Bridge over
    19970S0186B0698                 - 184 -

     1             Little Tionesta Creek, Tionesta
     2             Township, Bridge Rehabilitation               605,000
     3             (Base Construction Allocation -
     4             $550,000)
     5             (Design and Contingencies - $55,000)
     6  Section 32.  Franklin County.
     7     (a)  Local Bridges (Reserved)
     8     (b)  State Bridges
     9         (1)  SR 3012, Social Island Road Bridge
    10             over Conococheague Creek, Hamilton
    11             Township, Bridge Replacement                  786,000
    12             (Base Construction Allocation -
    13             $636,000)
    14             (Land Allocation - $95,000)
    15             (Design and Contingencies - $55,000)
    16         (2)  SR 4010, Edenville Road Bridge over
    17             Wilson Run, St. Thomas Township, Bridge
    18             Replacement                                   335,000
    19             (Base Construction Allocation -
    20             $225,000)
    21             (Land Allocation - $10,000)
    22             (Design and Contingencies - $100,000)
    23         (3)  SR 4009, over Wilson Run, St. Thomas
    24             Township, Bridge Replacement                  750,000
    25             (Base Construction Allocation -
    26             $500,000)
    27             (Land Allocation - $50,000)
    28             (Design and Contingencies - $200,000)
    29  Section 33.  (Reserved).
    30  Section 34.  Greene County.
    19970S0186B0698                 - 185 -

     1     (a)  Local Bridges
     2         (1)  Morgan Township, County Bridge No.89
     3             over Browns Run, Bridge Replacement           286,000
     4             (Base Construction Allocation -
     5             $166,000)
     6             (Land Allocation - $20,000)
     7             (Design and Contingencies - $100,000)
     8         (2)  Morgan Township, County Bridge No.90
     9             over Browns Run, Bridge Replacement           282,000
    10             (Base Construction Allocation -
    11             $162,000)
    12             (Land Allocation - $20,000)
    13             (Design and Contingencies - $100,000)
    14         (3)  Morgan Township, County Bridge No.91
    15             over Browns Run, Bridge Replacement           273,000
    16             (Base Construction Allocation -
    17             $153,000)
    18             (Land Allocation - $20,000)
    19             (Design and Contingencies - $100,000)
    20         (4)  Cumberland Township, T-517, County
    21             Bridge No.4, Ullery Road over Goose
    22             Run, Bridge Replacement                       360,000
    23             (Base Construction Allocation -
    24             $200,000)
    25             (Land Allocation - $10,000)
    26             (Design and Contingencies - $150,000)
    27         (5)  Cumberland Township, T-634, County
    28             Bridge No.15, Coal Hill Road over Muddy
    29             Creek, Bridge Replacement                     410,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 186 -

     1             $240,000)
     2             (Land Allocation - $10,000)
     3             (Design and Contingencies - $160,000)
     4         (6)  Greene Township, T-411, County Bridge
     5             No.20 over Whitely Creek, Bridge
     6             Replacement                                   490,000  <--
     7             (Base Construction Allocation -
     8             $300,000)
     9             (Land Allocation - $15,000)
    10             (Design and Contingencies - $175,000)
    11             REPLACEMENT                                 1,075,000  <--
    12             (BASE CONSTRUCTION ALLOCATION -
    13             $900,000)
    14             (LAND ALLOCATION - $25,000)
    15             (DESIGN AND CONTINGENCIES - $150,000)
    16         (7)  Gray Township, T-392, County Bridge
    17             No.63 over Grays Creek, Bridge
    18             Replacement                                   380,000
    19             (Base Construction Allocation -
    20             $220,000)
    21             (Land Allocation - $10,000)
    22             (Design and Contingencies - $150,000)
    23         (8)  Washington Township, T-550, County
    24             Bridge No.97 over Craynes Run, Bridge
    25             Replacement                                   360,000
    26             (Base Construction Allocation -
    27             $200,000)
    28             (Land Allocation - $10,000)
    29             (Design and Contingencies - $150,000)
    30         (9)  Morris Township, T-629, County Bridge
    19970S0186B0698                 - 187 -

     1             No.73 over Bates Fork Creek, Bridge
     2             Replacement                                   490,000
     3             (Base Construction Allocation -
     4             $350,000)
     5             (Land Allocation - $15,000)
     6             (Design and Contingencies - $125,000)
     7         (10)  Cumberland Township, T-660, County
     8             Bridge No.13 over Muddy Creek, Bridge
     9             Replacement                                   565,000
    10             (Base Construction Allocation -
    11             $400,000)
    12             (Land Allocation - 15,000)
    13             (Design and Contingencies - $150,000)
    14         (11)  Aleppo Township, T-304, County Bridge
    15             No.108 over Branch of Harts Run, Bridge
    16             Replacement                                   575,000
    17             (Base Construction Allocation -
    18             $425,000)
    19             (Land Allocation - $25,000)
    20             (Design and Contingencies - $125,000)
    21         (12)  FRANKLIN TOWNSHIP, T-511, BRIDGE                     <--
    22             NO.30 OVER SMITH CREEK, BRIDGE
    23             REPLACEMENT                                   625,000
    24             (BASE CONSTRUCTION ALLOCATION -
    25             $475,000)
    26             (LAND ALLOCATION - $25,000)
    27             (DESIGN AND CONTINGENCIES - $125,000)
    28         (13)  MORGAN TOWNSHIP, T-659, BRIDGE NO.87
    29             OVER TEN MILE CREEK, BRIDGE
    30             REPLACEMENT                                 1,275,000
    19970S0186B0698                 - 188 -

     1             (BASE CONSTRUCTION ALLOCATION -
     2             $1,100,000)
     3             (LAND ALLOCATION - $25,000)
     4             (DESIGN AND CONTINGENCIES - $150,000)
     5         (14)  RICHHILL TOWNSHIP, T-356, BRIDGE
     6             NO.57 OVER NORTH FORK OF WHEELING
     7             CREEK, BRIDGE REPLACEMENT                     765,000
     8             (BASE CONSTRUCTION ALLOCATION -
     9             $625,000)
    10             (LAND ALLOCATION - $15,000)
    11             (DESIGN AND CONTINGENCIES - $125,000)
    12         (15)  JACKSON TOWNSHIP, T-381, BRIDGE
    13             NO.109 OVER JOB CREEK, BRIDGE
    14             REPLACEMENT                                   465,000
    15             (BASE CONSTRUCTION ALLOCATION -
    16             $325,000)
    17             (LAND ALLOCATION - $15,000)
    18             (DESIGN AND CONTINGENCIES - $125,000)
    19     (b)  State Bridges
    20         (1)  SR 0018, Bridge over South Fork of Ten
    21             Mile Creek, Franklin Township, Bridge
    22             Rehabilitation                                320,000
    23             (Base Construction Allocation -
    24             $280,000)
    25             (Design and Contingencies - $40,000)
    26         (2)  SR 0018, Bates Creek Bridge over Bates
    27             Fork and Browns Creeks, Washington
    28             Township, Bridge Replacement                  650,000
    29             (Base Construction Allocation -
    30             $450,000)
    19970S0186B0698                 - 189 -

     1             (Land Allocation - $25,000)
     2             (Design and Contingencies - $175,000)
     3         (3)  SR 0021, Grinnage Run Bridge over
     4             Grinnage Run, Gray Township, Bridge
     5             Replacement                                   453,000
     6             (Base Construction Allocation -
     7             $253,000)
     8             (Land Allocation - $25,000)
     9             (Design and Contingencies - $175,000)
    10         (4)  SR 0079, I-79 Bridge over T-631,
    11             Washington Township, Bridge
    12             Replacement                                   980,000
    13             (Base Construction Allocation -
    14             $740,000)
    15             (Land Allocation - $40,000)
    16             (Design and Contingencies - $200,000)
    17         (5)  SR 0079, I-79 Bridge over T-631,
    18             Washington Township, Bridge
    19             Rehabilitation                                945,000
    20             (Base Construction Allocation -
    21             $705,000)
    22             (Land Allocation - $40,000)
    23             (Design and Contingencies - $200,000)
    24         (6)  SR 0079, I-79 Bridge over PA 221,
    25             Washington Township, Bridge
    26             Replacement                                 2,074,000
    27             (Base Construction Allocation -
    28             $1,784,000)
    29             (Land Allocation - $40,000)
    30             (Design and Contingencies - $250,000)
    19970S0186B0698                 - 190 -

     1         (7)  SR 0079, I-79 Bridge No.2 over PA 221,
     2             Washington Township, Bridge
     3             Replacement                                 2,074,000
     4             (Base Construction Allocation -
     5             $1,784,000)
     6             (Land Allocation - $40,000)
     7             (Design and Contingencies - $250,000)
     8         (8)  SR 0079, I-79 Bridge over T-512,
     9             Washington Township, Bridge
    10             Rehabilitation                                980,000
    11             (Base Construction Allocation -
    12             $740,000)
    13             (Land Allocation - $40,000)
    14             (Design and Contingencies - $200,000)
    15         (9)  SR 0079, I-79 Bridge No.2 over T-512,
    16             Washington Township, Bridge
    17             Replacement                                 1,020,000
    18             (Base Construction Allocation -
    19             $780,000)
    20             (Land Allocation - $40,000)
    21             (Design and Contingencies - $200,000)
    22         (10)  SR 0088, Albert Gallatin Bridge over
    23             Monongahela River, Dunkard Township,
    24             Bridge Painting                             1,500,000
    25             (Base Construction Allocation -
    26             $1,500,000)
    27         (11)  SR 0088, Point Marion Bridge over
    28             Monongahela River, Dunkard Township,
    29             Bridge Replacement                          6,200,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 191 -

     1             $5,500,000)
     2             (Land Allocation - $200,000)
     3             (Design and Contingencies - $500,000)
     4         (12)  SR 0218, Roberts Run Bridge No.2 over
     5             Roberts Run, Wayne Township, Bridge
     6             Replacement                                   768,000
     7             (Base Construction Allocation -
     8             $568,000)
     9             (Land Allocation - $25,000)
    10             (Design and Contingencies - $175,000)
    11         (13)  SR 2003, Bridge over Branch of
    12             Dunkard Creek, Perry Township, Bridge
    13             Replacement                                   625,000
    14             (Base Construction Allocation -
    15             $400,000)
    16             (Land Allocation - $25,000)
    17             (Design and Contingencies - $200,000)
    18         (14)  SR 3007, Bridge over Branch of
    19             Wheeling Creek, Richill Township,
    20             Bridge Replacement                            375,000
    21             (Base Construction Allocation -
    22             $175,000)
    23             (Land Allocation - $25,000)
    24             (Design and Contingencies - $175,000)
    25  Section 35.  Huntingdon County.
    26     (a)  Local Bridges
    27         (1)  Mill Creek Borough, Main Street Bridge
    28             over Mill Creek, Bridge Rehabilitation         30,000
    29             (Base Construction Allocation -
    30             $30,000)
    19970S0186B0698                 - 192 -

     1         (2)  Juniata Township, T-428, Corbin Bridge
     2             over Raystown Branch of Juniata River,
     3             Bridge Replacement                            920,000
     4             (Base Construction Allocation -
     5             $920,000)
     6         (3)  Springfield Township, T-313, Walnut
     7             Grove Bridge, County Bridge No.2 over
     8             Sideling Hill Creek, Bridge
     9             Replacement                                   975,000
    10             (Base Construction Allocation -
    11             $800,000)
    12             (Land Allocation - $25,000)
    13             (Design and Contingencies - $150,000)
    14     (b)  State Bridges (Reserved)
    15  Section 36.  Indiana County.
    16     (a)  Local Bridges
    17         (1)  Banks Township, T-974, County Bridge
    18             No.13, Bear Run Bridge over Bear Run,
    19             Bridge Replacement                            500,000
    20             (Base Construction Allocation -
    21             $400,000)
    22             (Land Allocation - $20,000)
    23             (Design and Contingencies - $80,000)
    24         (2)  Blacklick Township, T-574, Muddy Run
    25             Bridge over Muddy Run, Bridge
    26             Replacement                                   380,000
    27             (Base Construction Allocation -
    28             $300,000)
    29             (Land Allocation - $10,000)
    30             (Design and Contingencies - $70,000)
    19970S0186B0698                 - 193 -

     1         (3)  Cherryhill Township, T-686, County
     2             Bridge No.65, Grace Church Bridge over
     3             Two Lick Creek, Bridge Replacement            600,000
     4             (Base Construction Allocation -
     5             $500,000)
     6             (Land Allocation - $20,000)
     7             (Design and Contingencies - $80,000)
     8         (4)  Cherryhill Township, T-978, Allen
     9             Bridge over Two Lick Reservoir, Bridge
    10             Rehabilitation                                264,000
    11             (Base Construction Allocation -
    12             $200,000)
    13             (Land Allocation - $10,000)
    14             (Design and Contingencies - $54,000)
    15         (5)  Rayne Township, T-760, County Bridge
    16             No.23-A, Chambersville Bridge over
    17             Crooked Creek, Bridge Rehabilitation          190,000
    18             (Base Construction Allocation -
    19             $150,000)
    20             (Land Allocation - $10,000)
    21             (Design and Contingencies - $30,000)
    22         (6)  Grant Township, T-820 over Crooked
    23             Run, Bridge Replacement                       245,000
    24             (Base Construction Allocation -
    25             $200,000)
    26             (Land Allocation - $10,000)
    27             (Design and Contingencies - $35,000)
    28     (b)  State Bridges
    29         (1)  SR 0022, Chestnut Ridge Bridge over SR
    30             0119, Burrell Township, Bridge
    19970S0186B0698                 - 194 -

     1             Painting                                       90,000
     2             (Base Construction Allocation -
     3             $75,000)
     4             (Design and Contingencies - $15,000)
     5         (2)  SR 0022, Armagh Bridge over SR 0056,
     6             West Wheatfield Township, Bridge
     7             Painting                                      145,000
     8             (Base Construction Allocation -
     9             $130,000)
    10             (Design and Contingencies - $15,000)
    11         (3)  SR 0119, Blacklick Bridge over
    12             Blacklick Creek, Burrell Township,
    13             Bridge Painting                               280,000
    14             (Base Construction Allocation -
    15             $265,000)
    16             (Design and Contingencies - $15,000)
    17         (4)  SR 0119, Bypass Steel Bridge No.1 over
    18             Wayne Avenue Ramps, White Township,
    19             Bridge Painting                               170,000
    20             (Base Construction Allocation -
    21             $155,000)
    22             (Design and Contingencies - $15,000)
    23         (5)  SR 0119, Bypass Steel Bridge No.2 over
    24             Wayne Avenue Ramps, White Township,
    25             Bridge Painting                               170,000
    26             (Base Construction Allocation -
    27             $155,000)
    28             (Design and Contingencies - $15,000)
    29         (6)  SR 0119, Bypass Steel Bridge No.3 over
    30             SR 0422, White Township, Bridge
    19970S0186B0698                 - 195 -

     1             Painting                                      240,000
     2             (Base Construction Allocation -
     3             $225,000)
     4             (Design and Contingencies - $15,000)
     5         (7)  SR 0119, Bypass Steel Bridge No.4 over
     6             SR 0422, White Township, Bridge
     7             Painting                                      240,000
     8             (Base Construction Allocation -
     9             $225,000)
    10             (Design and Contingencies - $15,000)
    11         (8)  SR 0119, Bypass Steel Bridge No.5 over
    12             SR 0954, White Township, Bridge
    13             Painting                                      195,000
    14             (Base Construction Allocation -
    15             $180,000)
    16             (Design and Contingencies - $15,000)
    17         (9)  SR 0119, Bypass Steel Bridge No.6 over
    18             SR 0954, White Township, Bridge
    19             Painting                                      175,000
    20             (Base Construction Allocation -
    21             $160,000)
    22             (Design and Contingencies - $15,000)
    23         (10)  SR 0119, Bypass Steel Bridge No.7
    24             over SR 0286, White Township, Bridge
    25             Painting                                      235,000
    26             (Base Construction Allocation -
    27             $220,000)
    28             (Design and Contingencies - $15,000)
    29         (11)  SR 0119, Bypass Steel Bridge No.8
    30             over SR 0286, White Township, Bridge
    19970S0186B0698                 - 196 -

     1             Painting                                      215,000
     2             (Base Construction Allocation -
     3             $200,000)
     4             (Design and Contingencies - $15,000)
     5         (12)  SR 0119, Bypass Steel Bridge No.9
     6             over SR 1003, White Township, Bridge
     7             Painting                                      200,000
     8             (Base Construction Allocation -
     9             $185,000)
    10             (Design and Contingencies - $15,000)
    11         (13)  SR 0119, Bypass Steel Bridge No.10
    12             over SR 1003, White Township, Bridge
    13             Painting                                      175,000
    14             (Base Construction Allocation -
    15             $160,000)
    16             (Design and Contingencies - $15,000)
    17         (14)  SR 0119, Bypass Steel Bridge No.11
    18             over SR 0110, White Township, Bridge
    19             Painting                                      125,000
    20             (Base Construction Allocation -
    21             $110,000)
    22             (Design and Contingencies - $15,000)
    23         (15)  SR 0119, Bypass Steel Bridge No.12
    24             over SR 0110, White Township, Bridge
    25             Painting                                      125,000
    26             (Base Construction Allocation -
    27             $110,000)
    28             (Design and Contingencies - $15,000)
    29         (16)  SR 0217, Torrance Bridge over
    30             Conemaugh River, Burrell Township,
    19970S0186B0698                 - 197 -

     1             Bridge Painting                               435,000
     2             (Base Construction Allocation -
     3             $420,000)
     4             (Design and Contingencies - $15,000)
     5         (17)  SR 0217, Blacklick Creek Bridge over
     6             Blacklick Creek, Burrell Township,
     7             Bridge Painting                               400,000
     8             (Base Construction Allocation -
     9             $385,000)
    10             (Design and Contingencies - $15,000)
    11         (18)  SR 0259, Heshbon Bridge over
    12             Blacklick Creek, West Wheatfield
    13             Township, Bridge Painting                     200,000
    14             (Base Construction Allocation -
    15             $185,000)
    16             (Design and Contingencies - $15,000)
    17         (19)  SR 0286, Clymer Bridge over Twolick
    18             Creek, Clymer Borough, Bridge Painting        175,000
    19             (Base Construction Allocation -
    20             $160,000)
    21             (Design and Contingencies - $15,000)
    22         (20)  SR 0422, Twolick Eastbound Bridge
    23             over Twolick Creek, White Township,
    24             Bridge Painting                               360,000
    25             (Base Construction Allocation -
    26             $345,000)
    27             (Design and Contingencies - $15,000)
    28         (21)  SR 0422, Twolick Westbound Bridge
    29             over Twolick Creek, White Township,
    30             Bridge Painting                               360,000
    19970S0186B0698                 - 198 -

     1             (Base Construction Allocation -
     2             $345,000)
     3             (Design and Contingencies - $15,000)
     4         (22)  SR 0422, Penn Run Exit Bridge
     5             Eastbound over TR 840, White Township,
     6             Bridge Painting                               190,000
     7             (Base Construction Allocation -
     8             $175,000)
     9             (Design and Contingencies - $15,000)
    10         (23)  SR 0422, Penn Run Exit Bridge
    11             Westbound over TR 840, White Township,
    12             Bridge Painting                               190,000
    13             (Base Construction Allocation -
    14             $175,000)
    15             (Design and Contingencies - $15,000)
    16         (24)  SR 0580, Cush Cushion Creek Bridge
    17             over Cush Cushion Creek, Green
    18             Township, Bridge Painting                      85,000
    19             (Base Construction Allocation -
    20             $70,000)
    21             (Design and Contingencies - $15,000)
    22         (25)  SR 0954, Yellow Creek Bridge over
    23             Yellow Creek, White Township, Bridge
    24             Painting                                      125,000
    25             (Base Construction Allocation -
    26             $110,000)
    27             (Design and Contingencies - $15,000)
    28         (26)  SR 0954, Creekside Bridge over
    29             Crooked Creek, White Township, Bridge
    30             Painting                                      125,000
    19970S0186B0698                 - 199 -

     1             (Base Construction Allocation -
     2             $110,000)
     3             (Design and Contingencies - $15,000)
     4         (27)  SR 0954, South Branch Bridge over
     5             South Branch of Plum Creek, Washington
     6             Township, Bridge Painting                      75,000
     7             (Base Construction Allocation -
     8             $60,000)
     9             (Design and Contingencies - $15,000)
    10         (28)  SR 1004, Philadelphia Street Exit
    11             Bridge over SR 0119, White Township,
    12             Bridge Painting                               235,000
    13             (Base Construction Allocation -
    14             $220,000)
    15             (Design and Contingencies - $15,000)
    16         (29)  SR 1006, Jimmy Stewart Airport Bridge
    17             over SR 0119, White Township, Bridge
    18             Painting                                      245,000
    19             (Base Construction Allocation -
    20             $230,000)
    21             (Design and Contingencies - $15,000)
    22         (30)  SR 1007, Tanoma Bridge over Crooked
    23             Creek, Rayne Township, Bridge Painting         75,000
    24             (Base Construction Allocation -
    25             $60,000)
    26             (Design and Contingencies - $15,000)
    27         (31)  SR 1014, Diamondville Bridge over
    28             North Branch of Twolick Creek, Green
    29             Township, Bridge Painting                      75,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 200 -

     1             $60,000)
     2             (Design and Contingencies - $15,000)
     3         (32)  SR 1017, Pine Flats Bridge over South
     4             Branch of Twolick Creek, Green
     5             Township, Bridge Painting                      95,000
     6             (Base Construction Allocation -
     7             $80,000)
     8             (Design and Contingencies - $15,000)
     9         (33)  SR 1033, Gypsy Bridge over Cush
    10             Creek, Montgomery Township, Bridge
    11             Painting                                       85,000
    12             (Base Construction Allocation -
    13             $70,000)
    14             (Design and Contingencies - $15,000)
    15         (34)  SR 1034, Lower Wilgus Bridge over
    16             Branch of Cush Creek, Montgomery
    17             Township, Bridge Painting                      55,000
    18             (Base Construction Allocation -
    19             $40,000)
    20             (Design and Contingencies - $15,000)
    21         (35)  SR 1038, Crooked Run Bridge over
    22             Crooked Run, East Mahoning Township,
    23             Bridge Painting                                60,000
    24             (Base Construction Allocation -
    25             $45,000)
    26             (Design and Contingencies - $15,000)
    27         (36)  SR 1045, Broadhead Run Bridge over
    28             Broadhead Run, Canoe Township, Bridge
    29             Painting                                       70,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 201 -

     1             $55,000)
     2             (Design and Contingencies - $15,000)
     3         (37)  SR 1045, Juneau Bridge over Canoe
     4             Creek, Canoe Township, Bridge Painting         75,000
     5             (Base Construction Allocation -
     6             $60,000)
     7             (Design and Contingencies - $15,000)
     8         (38)  SR 1046, Straight Run Bridge over
     9             Straight Run, Banks Township, Bridge
    10             Painting                                       80,000
    11             (Base Construction Allocation -
    12             $65,000)
    13             (Design and Contingencies - $15,000)
    14         (39)  SR 2019, Tearing Run Bridge No.1 over
    15             Tearing Run, Center Township, Bridge
    16             Painting                                       55,000
    17             (Base Construction Allocation -
    18             $40,000)
    19             (Design and Contingencies - $15,000)
    20         (40)  SR 2019, Tearing Run Bridge No.2 over
    21             Tearing Run, Center Township, Bridge
    22             Painting                                       65,000
    23             (Base Construction Allocation -
    24             $50,000)
    25             (Design and Contingencies - $15,000)
    26         (41)  SR 3003, Tunnelton Bridge over
    27             Conemaugh River, Conemaugh Township,
    28             Bridge Painting                               525,000
    29             (Base Construction Allocation -
    30             $510,000)
    19970S0186B0698                 - 202 -

     1             (Design and Contingencies - $15,000)
     2         (42)  SR 3007, Clarksburg Bridge over
     3             Blacklegs Creek, Conemaugh Township,
     4             Bridge Painting                               105,000
     5             (Base Construction Allocation -
     6             $90,000)
     7             (Design and Contingencies - $15,000)
     8         (43)  SR 3011, Blacklick Creek Bridge No.1
     9             over Blacklick Creek, Brush Valley
    10             Township, Bridge Painting                     405,000
    11             (Base Construction Allocation -
    12             $390,000)
    13             (Design and Contingencies - $15,000)
    14         (44)  SR 3011, Blacklick Creek Bridge No.2
    15             over Blacklick Creek, Blacklick
    16             Township, Bridge Painting                     405,000
    17             (Base Construction Allocation -
    18             $390,000)
    19             (Design and Contingencies - $15,000)
    20         (45)  SR 3013, Muddy Run Bridge over Muddy
    21             Run, Blacklick Township, Bridge
    22             Painting                                       65,000
    23             (Base Construction Allocation -
    24             $50,000)
    25             (Design and Contingencies - $15,000)
    26         (46)  SR 3016, Homer City Bridge over
    27             Twolick Creek, Homer City Borough,
    28             Bridge Painting                               125,000
    29             (Base Construction Allocation -
    30             $110,000)
    19970S0186B0698                 - 203 -

     1             (Design and Contingencies - $15,000)
     2         (47)  SR 3031, Blacklegs Run Bridge over
     3             Blacklegs Run, Young Township, Bridge
     4             Painting                                       65,000
     5             (Base Construction Allocation -
     6             $50,000)
     7             (Design and Contingencies - $15,000)
     8         (48)  SR 3037, Walker Run Bridge over
     9             Walker Run, Armstrong Township, Bridge
    10             Painting                                       55,000
    11             (Base Construction Allocation -
    12             $40,000)
    13             (Design and Contingencies - $15,000)
    14         (49)  SR 3039, Anthony Run Bridge over
    15             Anthony Run, Armstrong Township, Bridge
    16             Painting                                       55,000
    17             (Base Construction Allocation -
    18             $40,000)
    19             (Design and Contingencies - $15,000)
    20         (50)  SR 4001, Fisher Siding Bridge over
    21             Crooked Creek, Armstrong Township,
    22             Bridge Painting                               110,000
    23             (Base Construction Allocation -
    24             $95,000)
    25             (Design and Contingencies - $15,000)
    26         (51)  SR 4001, Five Points Bridge over
    27             South Branch of Plum Creek, Washington
    28             Township, Bridge Painting                     100,000
    29             (Base Construction Allocation -
    30             $85,000)
    19970S0186B0698                 - 204 -

     1             (Design and Contingencies - $15,000)
     2         (52)  SR 4006, Reddings Run Bridge over
     3             Reddings Run, Washington Township,
     4             Bridge Painting                                55,000
     5             (Base Construction Allocation -
     6             $40,000)
     7             (Design and Contingencies - $15,000)
     8         (53)  SR 4008, Kimmel Station Bridge No.1
     9             over Branch of Crooked Creek, Rayne
    10             Township, Bridge Painting                      50,000
    11             (Base Construction Allocation -
    12             $35,000)
    13             (Design and Contingencies - $15,000)
    14         (54)  SR 4008, Kimmel Station Bridge No.2
    15             over Branch of Crooked Creek, Rayne
    16             Township, Bridge Painting                      50,000
    17             (Base Construction Allocation -
    18             $35,000)
    19             (Design and Contingencies - $15,000)
    20         (55)  SR 4035, Plumville Bridge over Plum
    21             Creek, Plumville Borough, Bridge
    22             Painting                                       75,000
    23             (Base Construction Allocation -
    24             $60,000)
    25             (Design and Contingencies - $15,000)
    26         (56)  SR 0056, Seward Conrail Overpass,
    27             East Wheatfield Township, Bridge
    28             Replacement                                 2,570,000
    29             (Base Construction Allocation -
    30             $2,080,000)
    19970S0186B0698                 - 205 -

     1             (Land Allocation - $150,000)
     2             (Design and Contingencies - $340,000)
     3  Section 37.  Jefferson County.
     4     (a)  Local Bridges
     5         (1)  Summerville Borough, County Bridge 40-
     6             A, Anderson Road Bridge over Runaway
     7             Run, Bridge Rehabilitation                    415,000
     8             (Base Construction Allocation -
     9             $345,000)
    10             (Land Allocation - $10,000)
    11             (Design and Contingencies - $60,000)
    12         (2)  Sykesville Borough, Station Street
    13             Bridge over Stump Creek, Bridge
    14             Replacement                                   570,000
    15             (Base Construction Allocation -
    16             $500,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $60,000)
    19         (3)  Eldred Township, T-346 over Mill
    20             Creek, Bridge Replacement                     420,000
    21             (Base Construction Allocation -
    22             $330,000)
    23             (Land Allocation - $10,000)
    24             (Design and Contingencies - $80,000)
    25         (4)  Eldred Township, T-353 over Mill Run,
    26             Bridge Replacement                            245,000
    27             (Base Construction Allocation -
    28             $200,000)
    29             (Land Allocation - $10,000)
    30             (Design and Contingencies - $35,000)
    19970S0186B0698                 - 206 -

     1         (5)  Oliver Township, T-718 over Little
     2             Sandy Creek, Bridge Replacement               490,000
     3             (Base Construction Allocation -
     4             $400,000)
     5             (Land Allocation - $10,000)
     6             (Design and Contingencies - $80,000)
     7         (6)  Union Township, T-320 over Little Mill
     8             Creek, Bridge Replacement                     245,000
     9             (Base Construction Allocation -
    10             $200,000)
    11             (Land Allocation - $10,000)
    12             (Design and Contingencies - $35,000)
    13         (7)  Union Township, T-321 over Runaway
    14             Run, Bridge Replacement                       145,000
    15             (Base Construction Allocation -
    16             $100,000)
    17             (Land Allocation - $5,000)
    18             (Design and Contingencies - $40,000)
    19         (8)  Young Township, T-632, BRIDGE NO.JC-36                <--
    20             over Saw Mill Run, Bridge Replacement         310,000  <--
    21             (Base Construction Allocation -
    22             $250,000)
    23             (Land Allocation - $10,000)
    24             (Design and Contingencies - $50,000)
    25             RUN, BRIDGE REPLACEMENT                       330,000  <--
    26             (BASE CONSTRUCTION ALLOCATION -
    27             $270,000)
    28             (DESIGN AND CONTINGENCIES - $60,000)
    29     (b)  State Bridges
    30         (1)  SR 3033, T-830, Knox No.1 Bridge over
    19970S0186B0698                 - 207 -

     1             Swamp Run, Knox Township, Bridge
     2             Replacement                                   446,000
     3             (Base Construction Allocation -
     4             $376,000)
     5             (Land Allocation - $10,000)
     6             (Design and Contingencies - $60,000)
     7         (2)  SR 0036, Sawmill Run Bridge over
     8             Sawmill Run, Punxsutawney Borough,
     9             Bridge Painting                                60,000
    10             (Base Construction Allocation -
    11             $45,000)
    12             (Design and Contingencies - $15,000)
    13         (3)  SR 0119, Punxsutawney Bridge over
    14             Mahoning Creek, Punxsutawney Borough,
    15             Bridge Painting                               250,000
    16             (Base Construction Allocation -
    17             $235,000)
    18             (Design and Contingencies - $15,000)
    19         (4)  SR 0410, Beaver Run Bridge over Beaver
    20             Run, Henderson Township, Bridge
    21             Painting                                       55,000
    22             (Base Construction Allocation -
    23             $40,000)
    24             (Design and Contingencies - $15,000)
    25         (5)  SR 0830, Falls Creek Bridge over Falls
    26             Creek, Falls Creek Township, Bridge
    27             Painting                                       80,000
    28             (Base Construction Allocation -
    29             $65,000)
    30             (Design and Contingencies - $15,000)
    19970S0186B0698                 - 208 -

     1         (6)  SR 0949, Corsica Exit Bridge over I-
     2             80, Union Township, Bridge Painting           205,000
     3             (Base Construction Allocation -
     4             $190,000)
     5             (Design and Contingencies - $15,000)
     6         (7)  SR 1009, Kyle's Run Bridge over Kyle's
     7             Run, Washington Township, Bridge
     8             Painting                                       60,000
     9             (Base Construction Allocation -
    10             $45,000)
    11             (Design and Contingencies - $15,000)
    12         (8)  SR 1027, Egypt Bridge over North Fork
    13             Creek, Rock Township, Bridge Painting         125,000
    14             (Base Construction Allocation -
    15             $110,000)
    16             (Design and Contingencies - $15,000)
    17         (9)  SR 2007, Clover Run Bridge over Clover
    18             Run, Gaskill Township, Bridge Painting         95,000
    19             (Base Construction Allocation -
    20             $80,000)
    21             (Design and Contingencies - $15,000)
    22         (10)  SR 2008, Stump Creek Bridge over
    23             Stump Creek, Henderson Township, Bridge
    24             Painting                                      100,000
    25             (Base Construction Allocation -
    26             $85,000)
    27             (Design and Contingencies - $15,000)
    28         (11)  SR 2023, Anita Bridge over Elk Run,
    29             McCalmont Township, Bridge Painting            60,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 209 -

     1             $45,000)
     2             (Design and Contingencies - $15,000)
     3         (12)  SR 2023, Charcoal Plant Bridge over
     4             Sandy Lick Creek, Pine Creek Township,
     5             Bridge Painting                               125,000
     6             (Base Construction Allocation -
     7             $110,000)
     8             (Design and Contingencies - $15,000)
     9         (13)  SR 3003, Baxter Bridge over Redbank
    10             Creek, Clover Township, Bridge
    11             Painting                                      235,000
    12             (Base Construction Allocation -
    13             $220,000)
    14             (Design and Contingencies - $15,000)
    15         (14)  SR 4006, North Fork Creek Bridge over
    16             North Fork Creek, Warsaw Township,
    17             Bridge Painting                               110,000
    18             (Base Construction Allocation -
    19             $95,000)
    20             (Design and Contingencies - $15,000)
    21         (15)  SR 0310, Bridge over Branch of Trout
    22             Run, Winslow Township, Bridge
    23             Replacement                                   490,000
    24             (Base Construction Allocation -
    25             $350,000)
    26             (Land Allocation - $20,000)
    27             (Design and Contingencies - $120,000)
    28         (16)  SR 3018, Bridge over Little Sandy
    29             Creek, Limestone Township, Bridge
    30             Replacement                                   670,000
    19970S0186B0698                 - 210 -

     1             (Base Construction Allocation -
     2             $500,000)
     3             (Land Allocation - $20,000)
     4             (Design and Contingencies - $150,000)
     5  Section 38.  Juniata County.
     6     (a)  Local Bridges
     7         (1)  Fayette Township, T-558 over West
     8             Branch of Cocolamus Creek, Bridge
     9             Rehabilitation                                 21,000
    10             (Base Construction Allocation -
    11             $18,000)
    12             (Design and Contingencies - $3,000)
    13         (2)  Fayette Township, T-602 over Little
    14             Lost Creek, Bridge Rehabilitation              19,000
    15             (Base Construction Allocation -
    16             $17,000)
    17             (Design and Contingencies - $2,000)
    18     (b)  State Bridges
    19         (1)  SR 0850, Laurel Run Bridge over Laurel
    20             Run, Village of Honey Grove, Tuscarora
    21             Township, Bridge Replacement                  670,000
    22             (Base Construction Allocation -
    23             $500,000)
    24             (Land Allocation - $20,000)
    25             (Design and Contingencies - $150,000)
    26         (2)  SR 0850, Bridge over Tuscarora Creek,
    27             Tuscarora Township, Bridge
    28             Rehabilitation                                155,000
    29             (Base Construction Allocation -
    30             $150,000)
    19970S0186B0698                 - 211 -

     1             (Design and Contingencies - $5,000)
     2         (3)  SR 0850, Bridge over Tuscarora Creek,
     3             Tuscarora Township, Bridge Replacement      1,420,000
     4             (Base Construction Allocation -
     5             $1,280,000)
     6             (Land Allocation - $40,000)
     7             (Design and Contingencies - $100,000)
     8  Section 39.  Lackawanna County.
     9     (a)  Local Bridges
    10         (1)  Mayfield Borough, Poplar Street Bridge
    11             No.1 at Junction of South Washington
    12             Avenue, Bridge Rehabilitation                 150,000
    13             (Base Construction Allocation -
    14             $130,000)
    15             (Design and Contingencies - $20,000)
    16     (b)  State Bridges
    17         (1)  SR 1016, Hill Street Bridge over
    18             Lackawanna River, Jessup and Blakely
    19             Boroughs, Bridge Deck Rehabilitation          890,000
    20             (Base Construction Allocation -
    21             $800,000)
    22             (Land Allocation - $10,000)
    23             (Design and Contingencies - $80,000)
    24         (2)  SR 3011, Keyser Avenue Bridge over
    25             Lindy Creek, City of Scranton, Bridge
    26             Replacement                                   185,000
    27             (Base Construction Allocation -
    28             $100,000)
    29             (Land Allocation - $10,000)
    30             (Design and Contingencies - $75,000)
    19970S0186B0698                 - 212 -

     1         (3)  SR 0171, Bridge over Elk Creek at
     2             Junction of SR 1011, Fell Township,
     3             Bridge Replacement                            660,000
     4             (Base Construction Allocation -
     5             $520,000)
     6             (Land Allocation - $10,000)
     7             (Design and Contingencies - $130,000)
     8         (4)  SR 0247, Bridge over South Branch of
     9             Tunkhannock Creek, North of TR 438,
    10             Scott Township, Bridge Replacement            426,000
    11             (Base Construction Allocation -
    12             $330,000)
    13             (Land Allocation - $10,000)
    14             (Design and Contingencies - $86,000)
    15         (5)  SR 2003, Bridge over Wallenpaupack
    16             Creek, North of TR 348, Jefferson
    17             Township, Bridge Replacement                  355,000
    18             (Base Construction Allocation -
    19             $275,000)
    20             (Land Allocation - $10,000)
    21             (Design and Contingencies - $70,000)
    22         (6)  SR 3013, Main Street Bridge, Old Forge
    23             Borough, Bridge Painting                      660,000
    24             (Base Construction Allocation -
    25             $600,000)
    26             (Design and Contingencies - $60,000)
    27         (7)  State Bridges, Countywide Bridge Zone
    28             Painting, Bridge Painting                     370,000
    29             (Base Construction Allocation -
    30             $350,000)
    19970S0186B0698                 - 213 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $10,000)
     3         (8)  SR 1013, Bridge over Elm Brook, 0.7
     4             Mile North of SR 1006, Scott Township,
     5             Bridge Replacement                            240,000
     6             (Base Construction Allocation -
     7             $200,000)
     8             (Land Allocation - $10,000)
     9             (Design and Contingencies - $30,000)
    10         (9)  SR 0524, Kennedy Creek Bridge, 0.5
    11             Mile East of TR 407, North Abington
    12             Township, Bridge Replacement                  330,000
    13             (Base Construction Allocation -
    14             $280,000)
    15             (Land Allocation - $10,000)
    16             (Design and Contingencies - $40,000)
    17         (10)  SR 0011, Roaring Brook Retaining
    18             Wall, Spruce Street Complex, City of
    19             Scranton, Bridge Replacement                1,320,000
    20             (Base Construction Allocation -
    21             $1,160,000)
    22             (Land Allocation - $10,000)
    23             (Design and Contingencies - $150,000)
    24  Section 40.  Lancaster County.
    25     (a)  Local Bridges
    26         (1)  Manor Township, T-599, West Roseville
    27             Road Bridge over Little Conestoga
    28             Creek, Bridge Replacement                     375,000
    29             (Base Construction Allocation -
    30             $286,000)
    19970S0186B0698                 - 214 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $150,000)
     3         (2)  Mt. Joy Township, T-350, Risser Mill
     4             Bridge over Tributary of Little
     5             Chickies Creek, Bridge Rehabilitation         550,000
     6             (Base Construction Allocation -
     7             $400,000)
     8             (Design and Contingencies - $150,000)
     9         (3)  Pequea Township, Silver Mine Road at
    10             Burnt Mills, Bridge Replacement               100,000
    11             (Base Construction Allocation -
    12             $90,000)
    13             (Design and Contingencies - $10,000)
    14         (4)  EAST HEMPFIELD AND MANHEIM TOWNSHIPS,                 <--
    15             SHREINER STATION ROAD BRIDGE OVER
    16             CONESTOGA CREEK, BRIDGE REPLACEMENT           477,000
    17             (BASE CONSTRUCTION ALLOCATION -
    18             $377,000)
    19             (LAND ALLOCATION - $20,000)
    20             (DESIGN AND CONTINGENCIES - $80,000)
    21     (b)  State Bridges
    22         (1)  SR 1024, Bridge over Little Cocalico
    23             Creek, East Cocalico Township, Bridge
    24             Replacement                                   675,000
    25             (Base Construction Allocation -
    26             $550,000)
    27             (Land Allocation - $25,000)
    28             (Design and Contingencies - $100,000)
    29  Section 41.  Lawrence County.
    30     (a)  Local Bridges
    19970S0186B0698                 - 215 -

     1         (1)  City of New Castle, Willard Avenue
     2             Bridge over Tributary of Shenango
     3             River, Bridge Replacement                     210,000
     4             (Base Construction Allocation -
     5             $150,000)
     6             (Land Allocation - $20,000)
     7             (Design and Contingencies - $40,000)
     8         (2)  Wampum Borough, Main Street Bridge
     9             over Eckles Run, Bridge Rehabilitation        190,000
    10             (Base Construction Allocation -
    11             $150,000)
    12             (Design and Contingencies - $40,000)
    13     (b)  State Bridges
    14         (1)  SR 0018, Mahoning Avenue Viaduct over
    15             Shenango River and Railroad, City of
    16             New Castle, Bridge Replacement              9,320,000
    17             (Base Construction Allocation -
    18             $9,000,000)
    19             (Land Allocation - $20,000)
    20             (Design and Contingencies - $300,000)
    21         (2)  SR 0018, Liberty Street Bridge over
    22             Hickory Run, New Castle City, Bridge
    23             Rehabilitation                                450,000
    24             (Base Construction Allocation -
    25             $300,000)
    26             (Land Allocation - $50,000)
    27             (Design and Contingencies - $100,000)
    28         (3)  SR 0060, SR 0060 Southbound over SR
    29             4004, Neshannock Township, Bridge
    30             Replacement                                   350,000
    19970S0186B0698                 - 216 -

     1             (Base Construction Allocation -
     2             $200,000)
     3             (Land Allocation - $50,000)
     4             (Design and Contingencies - $100,000)
     5         (4)  SR 0065, Ellwood Road Bridge over B&O
     6             Railroad, Shenango Township, Bridge
     7             Replacement                                   400,000
     8             (Base Construction Allocation -
     9             $250,000)
    10             (Land Allocation - $50,000)
    11             (Design and Contingencies - $100,000)
    12         (5)  SR 0488, Portersville Road Bridge over
    13             Morrison Run, Perry Township, Bridge
    14             Replacement                                   250,000
    15             (Base Construction Allocation -
    16             $100,000)
    17             (Land Allocation - $50,000)
    18             (Design and Contingencies - $100,000)
    19         (6)  SR 0488, Portersville Road Bridge over
    20             Morrison Run, Perry Township, Bridge
    21             Replacement                                   250,000
    22             (Base Construction Allocation -
    23             $100,000)
    24             (Land Allocation - $50,000)
    25             (Design and Contingencies - $100,000)
    26         (7)  SR 3001, South Main Street Bridge over
    27             Bessemer Haul Road, Bessemer Borough,
    28             Bridge Rehabilitation                         950,000
    29             (Base Construction Allocation -
    30             $800,000)
    19970S0186B0698                 - 217 -

     1             (Design and Contingencies - $150,000)
     2         (8)  SR 4004, Union and Neshannock
     3             Townships, Bridge Rehabilitation              800,000
     4             (Base Construction Allocation -
     5             $700,000)
     6             (Design and Contingencies - $100,000)
     7         (9)  SR 0060, Beaver Valley Expansion
     8             Bridge over SR 4005, Neshannock
     9             Township, Bridge Rehabilitation               650,000
    10             (Base Construction Allocation -
    11             $500,000)
    12             (Design and Contingencies - $150,000)
    13         (10)  SR 0060, Beaver Valley Extension
    14             Bridge over SR 4005, Neshannock
    15             Township, Bridge Rehabilitation               127,000
    16             (Base Construction Allocation -
    17             $116,000)
    18             (Design and Contingencies - $11,000)
    19         (11)  SR 0081, US 224 State Street Bridge
    20             over SR 0422 and Ramp K, Union
    21             Township, Bridge Rehabilitation               706,000
    22             (Base Construction Allocation -
    23             $644,000)
    24             (Design and Contingencies - $62,000)
    25         (12)  SR 0422, Westbound Bridge over Beaver
    26             River, Railroad and Local Street,
    27             Taylor Township, Bridge Rehabilitation      6,841,000
    28             (Base Construction Allocation -
    29             $6,741,000)
    30             (Design and Contingencies - $100,000)
    19970S0186B0698                 - 218 -

     1         (13)  SR 0422, Eastbound Bridge over Beaver
     2             River, Railroad and Local Street,
     3             Taylor Township, Bridge Replacement         6,963,000
     4             (Base Construction Allocation -
     5             $6,863,000)
     6             (Design and Contingencies - $100,000)
     7         (14)  SR 0422, Bridge over Business US 422,
     8             Union Township, Bridge Rehabilitation       1,379,000
     9             (Base Construction Allocation -
    10             $1,254,000)
    11             (Design and Contingencies - $125,000)
    12         (15)  SR 0422, Ben Franklin Highway Bridge
    13             over Business US 422, Union Township,
    14             Bridge Rehabilitation                         436,000
    15             (Base Construction Allocation -
    16             $398,000)
    17             (Design and Contingencies - $38,000)
    18         (16)  SR 0551, Main Street Bridge over
    19             Beaver Creek, Little Beaver Township,
    20             Bridge Replacement                            624,000
    21             (Base Construction Allocation -
    22             $524,000)
    23             (Design and Contingencies - $100,000)
    24         (17)  SR 2020, Pleasant Road Bridge over
    25             Camp Run, Perry Township, Bridge
    26             Replacement                                   400,000
    27             (Base Construction Allocation -
    28             $300,000)
    29             (Design and Contingencies - $100,000)
    30         (18)  SR 3002, Beaver Dam Road Bridge over
    19970S0186B0698                 - 219 -

     1             Honey Creek, Little Beaver Township,
     2             Bridge Painting                                30,000
     3             (Base Construction Allocation -
     4             $25,000)
     5             (Design and Contingencies - $5,000)
     6         (19)  SR 3004, Wallace Road Bridge over
     7             Sugar Creek, North Beaver Township,
     8             Bridge Replacement                            130,000
     9             (Base Construction Allocation -
    10             $120,000)
    11             (Design and Contingencies - $10,000)
    12         (20)  SR 3004, Wallace Road Bridge over
    13             Branch of Honey Creek, North Beaver
    14             Township, Bridge Painting                      30,000
    15             (Base Construction Allocation -
    16             $25,000)
    17             (Design and Contingencies - $5,000)
    18         (21)  SR 3004, Wallace Road Bridge over
    19             Branch of Honey Creek, North Beaver
    20             Township, Bridge Painting                     325,000
    21             (Base Construction Allocation -
    22             $300,000)
    23             (Design and Contingencies - $25,000)
    24         (22)  SR 4006, Coffee Run Bridge over
    25             Coffee Run, Mahoning Township, Bridge
    26             Replacement                                   335,000
    27             (Base Construction Allocation -
    28             $270,000)
    29             (Land Allocation - $15,000)
    30             (Design and Contingencies - $50,000)
    19970S0186B0698                 - 220 -

     1         (23)  SR 0224, Bridge over Conrail,
     2             Mahoning Township, Bridge Replacement       2,000,000
     3             (Base Construction Allocation -
     4             $1,700,000)
     5             (Land Allocation - $100,000)
     6             (Design and Contingencies - $200,000)
     7  Section 42.  Lebanon County.
     8     (a)  Local Bridges
     9         (1)  Union Township, T-617, Green Point
    10             School House Bridge over Trout Run,
    11             Bridge Replacement                            255,000
    12             (Base Construction Allocation -
    13             $170,000)
    14             (Land Allocation - $10,000)
    15             (Design and Contingencies - $75,000)
    16         (2)  Bethel Township, Market Drive, T-545
    17             over Beach Run, Bridge Replacement             30,000
    18             (Base Construction Allocation -
    19             $20,000)
    20             (Design and Contingencies - $10,000)
    21         (3)  South Londonderry Township, Patrick
    22             Road, T-331 over Tributary of Little
    23             Conewago Creek, Bridge Rehabilitation           5,000
    24             (Base Construction Allocation - $4,000)
    25             (Design and Contingencies - $1,000)
    26         (4)  South Londonderry Township, Eckert
    27             Road, T-304 over Little Conewago Creek,
    28             Bridge Rehabilitation                           5,000
    29             (Base Construction Allocation - $4,000)
    30             (Design and Contingencies - $1,000)
    19970S0186B0698                 - 221 -

     1         (5)  South Londonderry Township, Risser
     2             Road, T-300 over Conewago Creek, Bridge
     3             Rehabilitation                                  4,000
     4             (Base Construction Allocation - $3,000)
     5             (Design and Contingencies - $1,000)
     6         (6)  South Londonderry Township, Long Road,
     7             T-304 over Tributary of Conewago Creek,
     8             Bridge Rehabilitation                           4,000
     9             (Base Construction Allocation - $3,000)
    10             (Design and Contingencies - $1,000)
    11         (7)  South Londonderry Township, Eckert
    12             Road, T-304 over Tributary of Little
    13             Conewago Creek, Bridge Rehabilitation           5,000
    14             (Base Construction Allocation - $4,000)
    15             (Design and Contingencies - $1,000)
    16         (8)  South Londonderry Township, Church
    17             Road, T-303 over Unnamed Creek, Bridge
    18             Rehabilitation                                  3,000
    19             (Base Construction Allocation - $2,000)
    20             (Design and Contingencies - $1,000)
    21         (9)  South Londonderry Township, Patrick
    22             Road, T-331 over Tributary of Little
    23             Conewago Creek, Bridge Rehabilitation           4,000
    24             (Base Construction Allocation - $3,000)
    25             (Design and Contingencies - $1,000)
    26         (10)  South Londonderry Township, Hinkle
    27             Road, T-433 over Killinger Creek,
    28             Bridge Rehabilitation                           4,000
    29             (Base Construction Allocation - $3,000)
    30             (Design and Contingencies - $1,000)
    19970S0186B0698                 - 222 -

     1         (11)  South Londonderry Township, Brandt
     2             Road, T-346 over Killinger Creek,
     3             Bridge Rehabilitation                           3,000
     4             (Base Construction Allocation - $2,000)
     5             (Design and Contingencies - $1,000)
     6         (12)  Union Township, Green Point School
     7             House Road, T-617 over Trout Run,
     8             Bridge Replacement                             90,000
     9             (Base Construction Allocation -
    10             $70,000)
    11             (Design and Contingencies - $20,000)
    12     (b)  State Bridges (Reserved)
    13  Section 43.  Lehigh County.
    14     (a)  Local Bridges (Reserved)
    15     (b)  State Bridges
    16         (1)  SR 4007, Schlicher's Bridge over
    17             Jordan Creek, North Whitehall Township,
    18             Bridge Replacement                            875,000
    19             (Base Construction Allocation -
    20             $560,000)
    21             (Land Allocation - $145,000)
    22             (Design and Contingencies - $170,000)
    23         (2)  SR 3011, Farmington Road over
    24             Tributary of Schaffer Run, Upper
    25             Macungie Township, Bridge
    26             Rehabilitation                                330,000
    27             (Base Construction Allocation -
    28             $175,000)
    29             (Land Allocation - $55,000)
    30             (Design and Contingencies - $100,000)
    19970S0186B0698                 - 223 -

     1         (3)  SR 1027, Cold Springs Road over Spring
     2             Creek, Whitehall Township, Bridge
     3             Replacement                                 2,550,000
     4             (Base Construction Allocation -
     5             $1,640,000)
     6             (Land Allocation - $420,000)
     7             (Design and Contingencies - $490,000)
     8  Section 44.  Luzerne County.
     9     (a)  Local Bridges
    10         (1)  Ashley Borough, Ashley Street Bridge,
    11             Bridge Removal                                260,000
    12             (Base Construction Allocation -
    13             $200,000)
    14             (Land Allocation - $5,000)
    15             (Design and Contingencies - $55,000)
    16         (2)  Franklin Township, T-784, Bridge over
    17             Sutton Creek, Bridge Replacement              320,000
    18             (Base Construction Allocation -
    19             $250,000)
    20             (Land Allocation - $15,000)
    21             (Design and Contingencies - $55,000)
    22         (3)  Black Creek Township, T-309 over Falls
    23             Run Creek, Bridge Replacement                 395,000
    24             (Base Construction Allocation -
    25             $265,000)
    26             (Land Allocation - $5,000)
    27             (Design and Contingencies - $125,000)
    28         (4)  Black Creek Township, T-314 over
    29             Branch of Black Creek, Bridge
    30             Replacement                                   440,000
    19970S0186B0698                 - 224 -

     1             (Base Construction Allocation -
     2             $310,000)
     3             (Land Allocation - $5,000)
     4             (Design and Contingencies - $125,000)
     5         (5)  Butler Township, T-356 over Nescopeck
     6             Creek, Bridge Replacement                     405,000
     7             (Base Construction Allocation -
     8             $275,000)
     9             (Land Allocation - $5,000)
    10             (Design and Contingencies - $125,000)
    11         (6)  City of Wilkes-Barre, Division Street
    12             over Solomon's Creek, Bridge
    13             Replacement                                   955,000
    14             (Base Construction Allocation -
    15             $800,000)
    16             (Land Allocation - $5,000)
    17             (Design and Contingencies - $150,000)
    18         (7)  Dallas Township, County Road No.12
    19             over Toby's Creek, Bridge Replacement         405,000
    20             (Base Construction Allocation -
    21             $275,000)
    22             (Land Allocation - $5,000)
    23             (Design and Contingencies - $125,000)
    24         (8)  Dennison Township, County Road No.41
    25             over Nescopeck Creek, Bridge
    26             Replacement                                   405,000
    27             (Base Construction Allocation -
    28             $275,000)
    29             (Land Allocation - $5,000)
    30             (Design and Contingencies - $125,000)
    19970S0186B0698                 - 225 -

     1         (9)  Dorrance Township, County Road No.30
     2             over Wapwallopen Creek, Bridge
     3             Replacement                                   405,000
     4             (Base Construction Allocation -
     5             $275,000)
     6             (Land Allocation - $5,000)
     7             (Design and Contingencies - $125,000)
     8         (10)  Fairmount Township, T-563 over Maple
     9             Run Creek, Bridge Replacement                 395,000
    10             (Base Construction Allocation -
    11             $265,000)
    12             (Land Allocation - $5,000)
    13             (Design and Contingencies - $125,000)
    14         (11)  Franklin Township, T-782 over Sutton
    15             Creek, Bridge Replacement                     405,000
    16             (Base Construction Allocation -
    17             $275,000)
    18             (Land Allocation - $5,000)
    19             (Design and Contingencies - $125,000)
    20         (12)  Hunlock Township, T-534 over Hunlock
    21             Creek, Bridge Replacement                     405,000
    22             (Base Construction Allocation -
    23             $275,000)
    24             (Land Allocation - $5,000)
    25             (Design and Contingencies - $125,000)
    26         (13)  Jackson Township, County Road No.16
    27             over Toby's Creek, Bridge Replacement         350,000
    28             (Base Construction Allocation -
    29             $225,000)
    30             (Land Allocation - $5,000)
    19970S0186B0698                 - 226 -

     1             (Design and Contingencies - $120,000)
     2         (14)  Jackson Township, County Road No.16
     3             over Toby's Creek, Bridge Replacement         370,000
     4             (Base Construction Allocation -
     5             $240,000)
     6             (Land Allocation - $5,000)
     7             (Design and Contingencies - $125,000)
     8         (15)  Jackson Township, T-605 over Branch
     9             of Harvey's Creek, Bridge Replacement         395,000
    10             (Base Construction Allocation -
    11             $265,000)
    12             (Land Allocation - $5,000)
    13             (Design and Contingencies - $125,000)
    14         (16)  Jackson Township, County Road No.13
    15             over Toby's Creek, Bridge Replacement         395,000
    16             (Base Construction Allocation -
    17             $265,000)
    18             (Land Allocation - $5,000)
    19             (Design and Contingencies - $125,000)
    20         (17)  Lake Township, T-796 over Beaver Run
    21             Creek, Bridge Replacement                     410,000
    22             (Base Construction Allocation -
    23             $280,000)
    24             (Land Allocation - $5,000)
    25             (Design and Contingencies - $125,000)
    26         (18)  Lake Township, T-779 over Bryant Pond
    27             Outlet, Bridge Replacement                    430,000
    28             (Base Construction Allocation -
    29             $300,000)
    30             (Land Allocation - $5,000)
    19970S0186B0698                 - 227 -

     1             (Design and Contingencies - $125,000)
     2         (19)  Nescopeck Township, T-381 over Branch
     3             of Nescopeck Creek, Bridge Replacement        410,000
     4             (Base Construction Allocation -
     5             $280,000)
     6             (Land Allocation - $5,000)
     7             (Design and Contingencies - $125,000)
     8         (20)  Ross Township, T-680 over Huntingdon
     9             Creek, Bridge Replacement                     410,000
    10             (Base Construction Allocation -
    11             $280,000)
    12             (Land Allocation - $5,000)
    13             (Design and Contingencies - $125,000)
    14         (21)  Ross Township, T-571 over Outlet
    15             North Pond, Bridge Replacement                420,000
    16             (Base Construction Allocation -
    17             $290,000)
    18             (Land Allocation - $5,000)
    19             (Design and Contingencies - $125,000)
    20         (22)  Ross Township, T-575 over Huntingdon
    21             Creek, Bridge Replacement                     455,000
    22             (Base Construction Allocation -
    23             $325,000)
    24             (Land Allocation - $5,000)
    25             (Design and Contingencies - $125,000)
    26         (23)  Ross Township, County Road No.2 over
    27             Marsh Creek, Bridge Replacement               440,000
    28             (Base Construction Allocation -
    29             $310,000)
    30             (Land Allocation - $5,000)
    19970S0186B0698                 - 228 -

     1             (Design and Contingencies - $125,000)
     2         (24)  Sugarloaf Township, T-332 over Branch
     3             of Nescopeck Creek, Bridge Replacement        430,000
     4             (Base Construction Allocation -
     5             $300,000)
     6             (Land Allocation - $5,000)
     7             (Design and Contingencies - $125,000)
     8         (25)  Plymouth Township, T-497 over Mud
     9             Pond Inlet, Bridge Replacement                405,000
    10             (Base Construction Allocation -
    11             $275,000)
    12         (26)  Slocum Township, T-454 over Black
    13             Creek, Bridge Replacement                     395,000
    14             (Base Construction Allocation -
    15             $265,000)
    16             (Land Allocation - $5,000)
    17             (Design and Contingencies - $125,000)
    18         (27)  Wright Township, County Road No.21
    19             over Wapwallopen Creek, Bridge
    20             Replacement                                   395,000
    21             (Base Construction Allocation -
    22             $265,000)
    23             (Land Allocation - $5,000)
    24             (Design and Contingencies - $125,000)
    25         (28)  City of Wilkes-Barre, Stanton Street,
    26             Bowman Spring Run Bridge, Intersection
    27             of Empire Street, Bridge Replacement          170,000
    28             (Base Construction Allocation -
    29             $140,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 229 -

     1             (Design and Contingencies - $20,000)
     2         (29)  BOROUGH OF LARKSVILLE, NESBITT STREET                <--
     3             BRIDGE, BRIDGE REPLACEMENT                    109,000
     4             (BASE CONSTRUCTION ALLOCATION -
     5             $95,000)
     6             (DESIGN AND CONTINGENCIES - $14,000)
     7     (b)  State Bridges
     8         (1)  SR 0011, Erie-Lackawanna Railroad
     9             Bridge over Erie-Lackawanna Railroad,
    10             Plymouth Township, Bridge Removal             185,000
    11             (Base Construction Allocation -
    12             $150,000)
    13             (Land Allocation - $10,000)
    14             (Design and Contingencies - $25,000)
    15         (2)  SR 1030, Harvey's Lake Bridge at
    16             Junction of SR 1053, Lake Township,
    17             Bridge Replacement                            460,000
    18             (Base Construction Allocation -
    19             $350,000)
    20             (Land Allocation - $20,000)
    21             (Design and Contingencies - $90,000)
    22         (3)  SR 3007, Bridge over Wapwallopen
    23             Creek, South of SR 3010, Dorrance
    24             Township, Bridge Replacement                  530,000
    25             (Base Construction Allocation -
    26             $420,000)
    27             (Land Allocation - $10,000)
    28             (Design and Contingencies - $100,000)
    29         (4)  State Bridges, Countywide Bridge Zone
    30             Painting, Bridge Painting                     370,000
    19970S0186B0698                 - 230 -

     1             (Base Construction Allocation -
     2             $350,000)
     3             (Land Allocation - $10,000)
     4             (Design and Contingencies - $10,000)
     5         (5)  SR 3038, Black Creek Stone Arch
     6             Bridge, 0.1 Mile North of SR 3018,
     7             Black Creek Township, Bridge
     8             Replacement                                   240,000
     9             (Base Construction Allocation -
    10             $200,000)
    11             (Land Allocation - $10,000)
    12             (Design and Contingencies - $30,000)
    13         (6)  SR 1034, Pikes Creek Bridge, 132 Feet
    14             East of TR 11, Lake Township, Bridge
    15             Replacement                                   180,000
    16             (Base Construction Allocation -
    17             $150,000)
    18             (Land Allocation - $10,000)
    19             (Design and Contingencies - $20,000)
    20         (7)  SR 2041, Wright Creek Bridge, 2 Miles
    21             North of TR 940, Dennison Township,
    22             Bridge Replacement                            400,000
    23             (Base Construction Allocation -
    24             $340,000)
    25             (Land Allocation - $10,000)
    26             (Design and Contingencies - $50,000)
    27  Section 45.  Lycoming County.
    28     (a)  Local Bridges
    29         (1)  Mifflin Township, T-651 over Larry's
    30             Creek, Bridge Replacement                     528,000
    19970S0186B0698                 - 231 -

     1             (Base Construction Allocation -
     2             $438,000)
     3             (Land Allocation - $20,000)
     4             (Design and Contingencies - $70,000)
     5         (2)  McIntyre Township, T-667, Rolston
     6             Bridge over Lycoming Creek, Bridge
     7             Replacement                                 1,620,000
     8             (Base Construction Allocation -
     9             $1,400,000)
    10             (Land Allocation - $20,000)
    11             (Design and Contingencies - $200,000)
    12         (3)  FRANKLIN TOWNSHIP, T-710, BRIDGE OVER                 <--
    13             BEAVER RUN, BRIDGE REPLACEMENT                265,000
    14             (BASE CONSTRUCTION ALLOCATION -
    15             $212,000)
    16             (LAND ALLOCATION - $40,000)
    17             (DESIGN AND CONTINGENCIES - $13,000)
    18         (4)  PIATT TOWNSHIP, T-365, BRIDGE OVER
    19             LARRY'S CREEK, BRIDGE REPLACEMENT           1,251,000
    20             (BASE CONSTRUCTION ALLOCATION -
    21             $1,039,000)
    22             (LAND ALLOCATION - $30,000)
    23             (DESIGN AND CONTINGENCIES - $182,000)
    24         (5)  MCINTYRE TOWNSHIP, T-673, BRIDGE OVER
    25             LYCOMING CREEK, BRIDGE REPLACEMENT            902,000
    26             (BASE CONSTRUCTION ALLOCATION -
    27             $744,000)
    28             (LAND ALLOCATION - $23,000)
    29             (DESIGN AND CONTINGENCIES - $135,000)
    30         (6)  SHREWSBURY TOWNSHIP, T-686, BRIDGE
    19970S0186B0698                 - 232 -

     1             OVER ROCK RUN, BRIDGE REPLACEMENT             288,000
     2             (BASE CONSTRUCTION ALLOCATION -
     3             $238,000)
     4             (LAND ALLOCATION - $7,000)
     5             (DESIGN AND CONTINGENCIES - $43,000)
     6         (7)  PIATT TOWNSHIP, T-343, BRIDGE OVER
     7             PINE RUN, BRIDGE REPLACEMENT                  353,000
     8             (BASE CONSTRUCTION ALLOCATION -
     9             $291,000)
    10             (LAND ALLOCATION - $9,000)
    11             (DESIGN AND CONTINGENCIES - $53,000)
    12         (8)  WASHINGTON TOWNSHIP, T-397, BRIDGE
    13             OVER DEER HOLE CREEK, BRIDGE
    14             REPLACEMENT                                   517,000
    15             (BASE CONSTRUCTION ALLOCATION -
    16             $426,000)
    17             (LAND ALLOCATION - $13,000)
    18             (DESIGN AND CONTINGENCIES - $78,000)
    19         (9)  SOUTH WILLIAMSPORT BOROUGH, EAST
    20             CENTRAL AVENUE, BRIDGE OVER HAGERMANS
    21             RUN, BRIDGE REPLACEMENT                       519,000
    22             (BASE CONSTRUCTION ALLOCATION -
    23             $428,000)
    24             (LAND ALLOCATION - $13,000)
    25             (DESIGN AND CONTINGENCIES - $78,000)
    26         (10)  MORELAND TOWNSHIP, T-443, BRIDGE OVER
    27             LITTLE MUNCY CREEK, BRIDGE REPLACEMENT        780,000
    28             (BASE CONSTRUCTION ALLOCATION -
    29             $630,000)
    30             (LAND ALLOCATION - $20,000)
    19970S0186B0698                 - 233 -

     1             (DESIGN AND CONTINGENCIES - $130,000)
     2         (11)  MUNCY CREEK TOWNSHIP, T-437, BRIDGE
     3             OVER BRANCH OF MUNCY CREEK, BRIDGE
     4             REPLACEMENT                                   335,000
     5             (BASE CONSTRUCTION ALLOCATION -
     6             $268,000)
     7             (LAND ALLOCATION - $17,000)
     8             (DESIGN AND CONTINGENCIES - $50,000)
     9         (12)  MUNCY CREEK TOWNSHIP, T-811, BRIDGE
    10             OVER WOLF RUN, BRIDGE REPLACEMENT             150,000
    11             (BASE CONSTRUCTION ALLOCATION -
    12             $120,000)
    13             (LAND ALLOCATION - $10,000)
    14             (DESIGN AND CONTINGENCIES - $20,000)
    15     (b)  State Bridges
    16         (1)  SR 0220, Quenshukeny Run Bridge over
    17             Quenshukeny Run, Village of Linden,
    18             Bridge Replacement                            395,000
    19             (Base Construction Allocation -
    20             $316,000)
    21             (Land Allocation - $20,000)
    22             (Design and Contingencies - $59,000)
    23         (2)  SR 0973, Bridge over Hoagland Run, 3
    24             Miles West of Cogan Station, Bridge
    25             Rehabilitation                                195,000
    26             (Base Construction Allocation -
    27             $156,000)
    28             (Land Allocation - $10,000)
    29             (Design and Contingencies - $29,000)
    30         (3)  SR 1006, Wallis Run Bridge over Wallis
    19970S0186B0698                 - 234 -

     1             Run, Cascade Township, Bridge
     2             Replacement                                    65,000
     3             (Base Construction Allocation -
     4             $50,000)
     5             (Land Allocation - $5,000)
     6             (Design and Contingencies - $10,000)
     7         (4)  SR 2022, Mill Creek Bridge, North of
     8             Montoursville, Bridge Replacement             668,000
     9             (Base Construction Allocation -
    10             $575,000)
    11             (Land Allocation - $43,000)
    12             (Design and Contingencies - $50,000)
    13         (5)  SR 2051, Wolf Run Bridge over Wolf
    14             Run, South of SR 0220, Muncy Township,
    15             Bridge Replacement                            638,000
    16             (Base Construction Allocation -
    17             $510,000)
    18             (Land Allocation - $32,000)
    19             (Design and Contingencies - $96,000)
    20         (6)  SR 3024, Jobs Run Road Bridge over
    21             Tributary of Larrys Creek, East of
    22             Salladasburg, Bridge Replacement              108,000
    23             (Base Construction Allocation -
    24             $92,000)
    25             (Land Allocation - $8,000)
    26             (Design and Contingencies - $8,000)
    27         (7)  SR 3028, West 4th Street, Lycoming
    28             Creek Bridge, City of Williamsport,
    29             Bridge Rehabilitation                         216,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 235 -

     1             $185,000)
     2             (Land Allocation - $15,000)
     3             (Design and Contingencies - $16,000)
     4         (8)  SR 0044, Bridge over Conrail, Bridge
     5             Painting                                      210,000
     6             (Base Construction Allocation -
     7             $200,000)
     8             (Design and Contingencies - $10,000)
     9         (9)  SR 0180, I-180 Eastbound Bridge over
    10             Loyalsock Creek, Bridge Painting              135,000
    11             (Base Construction Allocation -
    12             $125,000)
    13             (Design and Contingencies - $10,000)
    14         (10)  SR 0180, I-180 Westbound Bridge over
    15             Loyalsock Creek, Bridge Painting              135,000
    16             (Base Construction Allocation -
    17             $125,000)
    18             (Design and Contingencies - $10,000)
    19         (11)  SR 2014, Bridge over Lycoming Creek,
    20             Bridge Painting                               780,000
    21             (Base Construction Allocation -
    22             $770,000)
    23             (Design and Contingencies - $10,000)
    24         (12)  SR 2061, Bridge over Little Muncy
    25             Creek, Bridge Painting                         80,000
    26             (Base Construction Allocation -
    27             $70,000)
    28             (Design and Contingencies - $10,000)
    29         (13)  SR 0014, SR 0014 over Trout Run,
    30             Lewis Township, Bridge Replacement            640,000
    19970S0186B0698                 - 236 -

     1             (Base Construction Allocation -
     2             $512,000)
     3             (Land Allocation - $32,000)
     4             (Design and Contingencies - $96,000)
     5         (14)  SR 0044, SR 0044 over Ramsey Run,
     6             Cummings Township, Bridge Replacement         394,000
     7             (Base Construction Allocation -
     8             $315,000)
     9             (Land Allocation - $20,000)
    10             (Design and Contingencies - $59,000)
    11         (15)  SR 0044, SR 0044 over Pine Bottom
    12             Run, Cummings Township, Bridge
    13             Replacement                                   360,000
    14             (Base Construction Allocation -
    15             $288,000)
    16             (Land Allocation - $18,000)
    17             (Design and Contingencies - $54,000)
    18         (16)  SR 0118, SR 0118 over Big Run,
    19             Franklin Township, Bridge Replacement         382,000
    20             (Base Construction Allocation -
    21             $307,000)
    22             (Land Allocation - $19,000)
    23             (Design and Contingencies - $56,000)
    24         (17)  SR 0284, SR 0284 over Blacks Creek,
    25             Pine Township, Bridge Replacement             700,000
    26             (Base Construction Allocation -
    27             $570,000)
    28             (Land Allocation - $30,000)
    29             (Design and Contingencies - $100,000)
    30         (18)  SR 0405, SR 0405 over West Branch of
    19970S0186B0698                 - 237 -

     1             Susquehanna River, Muncy Creek
     2             Township, Bridge Replacement               24,924,000
     3             (Base Construction Allocation -
     4             $19,939,000)
     5             (Land Allocation - $1,246,000)
     6             (Design and Contingencies - $3,739,000)
     7         (19)  SR 0654, SR 0654 over Mosquito Creek,
     8             Anthony Township, Bridge Replacement          674,000
     9             (Base Construction Allocation -
    10             $539,000)
    11             (Land Allocation - $34,000)
    12             (Design and Contingencies - $101,000)
    13         (20)  SR 0973, SR 0973 over Mud Run,
    14             Mifflin Township, Bridge Replacement          294,000
    15             (Base Construction Allocation -
    16             $252,000)
    17             (Land Allocation - $20,000)
    18             (Design and Contingencies - $22,000)
    19         (21)  SR 1005, SR 1005 over Plunketts
    20             Creek, Plunketts Creek Township, Bridge
    21             Replacement                                   366,000
    22             (Base Construction Allocation -
    23             $293,000)
    24             (Land Allocation - $18,000)
    25             (Design and Contingencies - $55,000)
    26         (22)  SR 2061, SR 2061 over Sugar Run,
    27             Moreland Township, Bridge Replacement         443,000
    28             (Base Construction Allocation -
    29             $354,000)
    30             (Land Allocation - $22,000)
    19970S0186B0698                 - 238 -

     1             (Design and Contingencies - $67,000)
     2         (23)  SR 2085, SR 2085 over Muncy Creek,
     3             Penn Township, Bridge Replacement           1,050,000
     4             (Base Construction Allocation -
     5             $840,000)
     6             (Land Allocation - $53,000)
     7             (Design and Contingencies - $157,000)
     8         (24)  SR 0405, East Water Street over Glade
     9             Run, Muncy Borough, Bridge Replacement        500,000
    10             (Base Construction Allocation -
    11             $350,000)
    12             (Land Allocation - $50,000)
    13             (Design and Contingencies - $100,000)
    14         (25)  SR 1003, Bridge over Wallis Run,
    15             Gamble Township, Bridge Replacement         1,020,000
    16             (Base Construction Allocation -
    17             $820,000)
    18             (Land Allocation - $50,000)
    19             (Design and Contingencies - $150,000)
    20         (26)  SR 1003, Bridge over Salt Run, Gamble
    21             Township, Bridge Replacement                  390,000
    22             (Base Construction Allocation -
    23             $300,000)
    24             (Land Allocation - $30,000)
    25             (Design and Contingencies - $60,000)
    26         (27)  US 15, Bridge over 2nd Avenue, South
    27             Williamsport Borough, Bridge
    28             Replacement                                 1,550,000
    29             (Base Construction Allocation -
    30             $1,250,000)
    19970S0186B0698                 - 239 -

     1             (Land Allocation - $50,000)
     2             (Design and Contingencies - $250,000)
     3         (28)  SR 44, Bridge over Conrail, Nippenose
     4             Township, Bridge Replacement                2,425,000
     5             (Base Construction Allocation -
     6             $2,000,000)
     7             (Land Allocation - $100,000)
     8             (Design and Contingencies - $325,000)
     9         (29)  US 220, Southbound Bridge over SR
    10             3005, Jersey Shore Borough, Deck
    11             Replacement                                   275,000
    12             (Base Construction Allocation -
    13             $225,000)
    14             (Design and Contingencies - $50,000)
    15         (30)  US 220, Northbound Bridge over
    16             Railroad, Porter Township, Bridge
    17             Replacement                                   900,000
    18             (Base Construction Allocation -
    19             $750,000)
    20             (Design and Contingencies - $150,000)
    21         (31)  US 220, Southbound Bridge over
    22             Railroad, Porter Township, Bridge
    23             Rehabilitation                                900,000
    24             (Base Construction Allocation -
    25             $750,000)
    26             (Design and Contingencies - $150,000)
    27         (32)  US 220, Northbound Bridge over SR
    28             3005, Jersey Shore Borough, Bridge
    29             Rehabilitation                                275,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 240 -

     1             $225,000)
     2             (Design and Contingencies - $50,000)
     3         (33)  US 220, Ramp on US 220, Jersey Shore
     4             Borough, Deck Replacement                   1,500,000
     5             (Base Construction Allocation -
     6             $1,250,000)
     7             (Design and Contingencies - $250,000)
     8         (34)  US 220, Northbound Bridge over Ramp
     9             A, Woodward Township, Bridge
    10             Rehabilitation                                550,000
    11             (Base Construction Allocation -
    12             $500,000)
    13             (Design and Contingencies - $50,000)
    14         (35)  US 220, Northbound Bridge over T-331,
    15             Woodward Township, Bridge
    16             Rehabilitation                                275,000
    17             (Base Construction Allocation -
    18             $250,000)
    19             (Design and Contingencies - $25,000)
    20         (36)  US 220, Northbound Bridge over
    21             Railroad, Woodward Township, Bridge
    22             Rehabilitation                                825,000
    23             (Base Construction Allocation -
    24             $750,000)
    25             (Design and Contingencies - $75,000)
    26         (37)  US 220, Southbound Bridge over Ramp,
    27             Woodward Township, Bridge
    28             Rehabilitation                                550,000
    29             (Base Construction Allocation -
    30             $500,000)
    19970S0186B0698                 - 241 -

     1             (Design and Contingencies - $50,000)
     2         (38)  US 220, Southbound Bridge over T-331,
     3             Woodward Township, Bridge
     4             Rehabilitation                                275,000
     5             (Base Construction Allocation -
     6             $250,000)
     7             (Design and Contingencies - $25,000)
     8         (39)  US 220, Southbound Bridge over
     9             Railroad, Woodward Township, Bridge
    10             Rehabilitation                                825,000
    11             (Base Construction Allocation -
    12             $750,000)
    13             (Design and Contingencies - $75,000)
    14         (40)  US 220, Reach Road over US 220, City
    15             of Williamsport, Deck Replacement           1,400,000
    16             (Base Construction Allocation -
    17             $1,250,000)
    18             (Design and Contingencies - $150,000)
    19         (41)  US 220, Northbound Bridge over Arch
    20             Street, City of Williamsport, Bridge
    21             Rehabilitation                                385,000
    22             (Base Construction Allocation -
    23             $350,000)
    24             (Design and Contingencies - $35,000)
    25         (42)  US 220, Southbound Bridge over Arch
    26             Street, City of Williamsport, Bridge
    27             Rehabilitation                                385,000
    28             (Base Construction Allocation -
    29             $350,000)
    30             (Design and Contingencies - $35,000)
    19970S0186B0698                 - 242 -

     1         (43)  US 220, Northbound Bridge over
     2             Lycoming Creek, City of Williamsport,
     3             Bridge Rehabilitation                       1,100,000
     4             (Base Construction Allocation -
     5             $1,000,000)
     6             (Design and Contingencies - $100,000)
     7         (44)  I-180, Eastbound Bridge over Maynard
     8             Street, City of Williamsport, Bridge
     9             Widening and Deck Replacement                 950,000
    10             (Base Construction Allocation -
    11             $800,000)
    12             (Design and Contingencies - $150,000)
    13         (45)  I-180, Westbound Bridge over Maynard
    14             Street, City of Williamsport, Bridge
    15             Widening and Deck Replacement                 950,000
    16             (Base Construction Allocation -
    17             $800,000)
    18             (Design and Contingencies - $150,000)
    19         (46)  I-180, Eastbound and Westbound
    20             Bridges over Railroad, City of
    21             Williamsport, Bridge Widening and Deck
    22             Replacement                                   900,000
    23             (Base Construction Allocation -
    24             $750,000)
    25             (Design and Contingencies - $150,000)
    26         (47)  I-180, Eastbound Bridge over Hepburn
    27             Street, City of Williamsport, Bridge
    28             Widening and Deck Replacement               1,200,000
    29             (Base Construction Allocation -
    30             $1,000,000)
    19970S0186B0698                 - 243 -

     1             (Design and Contingencies - $200,000)
     2         (48)  I-180, Westbound Bridge over Hepburn
     3             Street, City of Williamsport, Bridge
     4             Widening and Deck Replacement               1,200,000
     5             (Base Construction Allocation -
     6             $1,000,000)
     7             (Design and Contingencies - $200,000)
     8         (49)  I-180, Eastbound Bridge over Basin
     9             Street, City of Williamsport, Bridge
    10             Rehabilitation                                550,000
    11             (Base Construction Allocation -
    12             $500,000)
    13             (Design and Contingencies - $50,000)
    14         (50)  I-180, Westbound Bridge over Basin
    15             Street, City of Williamsport, Bridge
    16             Rehabilitation                                550,000
    17             (Base Construction Allocation -
    18             $500,000)
    19             (Design and Contingencies - $50,000)
    20         (51)  I-180, Eastbound and Westbound
    21             Bridges over Muncy Creek, Muncy Creek
    22             Township, Bridge Rehabilitation             1,100,000
    23             (Base Construction Allocation -
    24             $1,000,000)
    25             (Design and Contingencies - $100,000)
    26         (52)  I-180, Eastbound and Westbound
    27             Bridges over PA 405, Muncy Creek
    28             Township, Bridge Rehabilitation             1,100,000
    29             (Base Construction Allocation -
    30             $1,000,000)
    19970S0186B0698                 - 244 -

     1             (Design and Contingencies - $100,000)
     2         (53)  I-180, Eastbound Bridge over SR 4024,
     3             Muncy Creek Township, Bridge
     4             Rehabilitation                                550,000
     5             (Base Construction Allocation -
     6             $500,000)
     7             (Design and Contingencies - $50,000)
     8         (54)  I-180, Eastbound and Westbound
     9             Bridges over SR 2061, Muncy Creek
    10             Township, Bridge Rehabilitation               660,000
    11             (Base Construction Allocation -
    12             $600,000)
    13             (Design and Contingencies - $60,000)
    14         (55)  I-180, Eastbound and Westbound
    15             Bridges over SR 2014, Muncy Creek
    16             Township, Bridge Rehabilitation               660,000
    17             (Base Construction Allocation -
    18             $600,000)
    19             (Design and Contingencies - $60,000)
    20  Section 46.  McKean County.
    21     (a)  Local Bridges
    22         (1)  Foster Township, T-359, Garlock Hollow
    23             Bridge over Kendall Creek, Bridge
    24             Replacement                                   580,000
    25             (Base Construction Allocation -
    26             $400,000)
    27             (Land Allocation - $20,000)
    28             (Design and Contingencies - $160,000)
    29     (b)  State Bridges
    30         (1)  SR 3009, Kinzua Creek Bridge over
    19970S0186B0698                 - 245 -

     1             Kinzua Creek, Borough of Mt. Jewett,
     2             Bridge Replacement                            880,000
     3             (Base Construction Allocation -
     4             $700,000)
     5             (Land Allocation - $30,000)
     6             (Design and Contingencies - $150,000)
     7         (2)  SR 4005, Kendall Creek Bridge over
     8             Kendall Creek, City of Bradford, Bridge
     9             Replacement                                   800,000
    10             (Base Construction Allocation -
    11             $650,000)
    12             (Land Allocation - $50,000)
    13             (Design and Contingencies - $100,000)
    14  Section 47.  Mercer County.
    15     (a)  Local Bridges
    16         (1)  City of Sharon, Service Avenue Bridge
    17             over Pine Run, Bridge Replacement             240,000
    18             (Base Construction Allocation -
    19             $210,000)
    20             (Land Allocation - $5,000)
    21             (Design and Contingencies - $25,000)
    22         (2)  City of Sharon, Wengler Avenue Bridge
    23             over Pine Hollow Run, Bridge
    24             Replacement                                   218,000
    25             (Base Construction Allocation -
    26             $193,000)
    27             (Land Allocation - $5,000)
    28             (Design and Contingencies - $20,000)
    29         (3)  Pine Township, T-355, Pinchlong Road
    30             Bridge over Swamp Run, Bridge
    19970S0186B0698                 - 246 -

     1             Replacement                                   203,000
     2             (Base Construction Allocation -
     3             $178,000)
     4             (Land Allocation - $5,000)
     5             (Design and Contingencies - $20,000)
     6         (4)  Pine Township, T-878, Diamond Road
     7             Bridge over Wolf Creek, Bridge
     8             Replacement                                 1,813,000
     9             (Base Construction Allocation -
    10             $1,668,000)
    11             (Land Allocation - $60,000)
    12             (Design and Contingencies - $85,000)
    13         (5)  Pine Township, T-413, Daugherty Road
    14             Bridge over Wolf Run, Bridge
    15             Replacement                                   407,000
    16             (Base Construction Allocation -
    17             $352,000)
    18             (Land Allocation - $15,000)
    19             (Design and Contingencies - $40,000)
    20         (6)  Shenango Township, T-955, Oak Hill
    21             Road Bridge over Turkey Run, Bridge
    22             Replacement                                   297,000
    23             (Base Construction Allocation -
    24             $257,000)
    25             (Land Allocation - $10,000)
    26             (Design and Contingencies - $30,000)
    27         (7)  Shenango Township, Heasley Road Bridge
    28             over Tributary of Shenango River,
    29             Bridge Replacement                            173,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 247 -

     1             $155,000)
     2             (Land Allocation - $3,000)
     3             (Design and Contingencies - $15,000)
     4         (8)  Springfield Township, T-722, Spring
     5             Road Bridge over Mill Run, Bridge
     6             Replacement                                   230,000
     7             (Base Construction Allocation -
     8             $200,000)
     9             (Land Allocation - $5,000)
    10             (Design and Contingencies - $25,000)
    11         (9)  Worth Township, T-912, Jack Atwell
    12             Road Bridge over Wolf Creek, Bridge
    13             Replacement                                   297,000
    14             (Base Construction Allocation -
    15             $257,000)
    16             (Land Allocation - $10,000)
    17             (Design and Contingencies - $30,000)
    18     (b)  State Bridges
    19         (1)  SR 0058, SR 0058 over Sugar Creek,
    20             Greene Township, Bridge Replacement           270,000
    21             (Base Construction Allocation -
    22             $200,000)
    23             (Land Allocation - $20,000)
    24             (Design and Contingencies - $50,00)
    25         (2)  SR 0058, SR 0058 over Tributary of
    26             Shenango River, Greenville Borough,
    27             Bridge Replacement                            250,000
    28             (Base Construction Allocation -
    29             $200,000)
    30             (Land Allocation - $20,000)
    19970S0186B0698                 - 248 -

     1             (Design and Contingencies - $30,000)
     2         (3)  SR 0058, SR 0058 over I-79, Findley
     3             Township, Bridge Replacement                1,630,000
     4             (Base Construction Allocation -
     5             $1,500,000)
     6             (Land Allocation - $30,000)
     7             (Design and Contingencies - $100,000)
     8         (4)  SR 0062, SR 0062 over Shenango
     9             River/Riverside Drive, City of Sharon,
    10             Bridge Replacement                          2,780,000
    11             (Base Construction Allocation -
    12             $2,500,000)
    13             (Land Allocation - $30,000)
    14             (Design and Contingencies - $250,000)
    15         (5)  SR 0158, SR 0158 over Little
    16             Neshannock Creek, Wilmington Township,
    17             Bridge Replacement                            770,000
    18             (Base Construction Allocation -
    19             $650,000)
    20             (Land Allocation - $40,000)
    21             (Design and Contingencies - $80,000)
    22         (6)  SR 0173, SR 0173 over Mill Creek, New
    23             Lebanon Borough, Bridge Replacement           430,000
    24             (Base Construction Allocation -
    25             $350,000)
    26             (Land Allocation - $20,000)
    27             (Design and Contingencies - $60,000)
    28         (7)  SR 0208, SR 0208 over Wolf Creek,
    29             Grove City Borough, Bridge Replacement      1,000,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 249 -

     1             $870,000)
     2             (Land Allocation - $30,000)
     3             (Design and Contingencies - $100,000)
     4         (8)  SR 0258, SR 0258 over Daley Run,
     5             Jefferson Township, Bridge Replacement        430,000
     6             (Base Construction Allocation -
     7             $350,000)
     8             (Land Allocation - $20,000)
     9             (Design and Contingencies - $60,000)
    10         (9)  SR 0318, SR 0318 over Shenango
    11             River/Street/Railroad, West Middlesex
    12             Borough, Bridge Replacement                 4,400,000
    13             (Base Construction Allocation -
    14             $3,700,000)
    15             (Land Allocation - $100,000)
    16             (Design and Contingencies - $600,000)
    17         (10)  SR 0518, SR 0518 over Pine Hollow
    18             Run, City of Hermitage, Bridge
    19             Replacement                                   410,000
    20             (Base Construction Allocation -
    21             $300,000)
    22             (Land Allocation - $30,000)
    23             (Design and Contingencies - $80,000)
    24         (11)  SR 0846, SR 0846 over Shenango
    25             Reservoir, South Pymatuning Township,
    26             Bridge Replacement                          1,500,000
    27             (Base Construction Allocation -
    28             $1,340,000)
    29             (Land Allocation - $10,000)
    30             (Design and Contingencies - $150,000)
    19970S0186B0698                 - 250 -

     1         (12)  SR 2006, SR 2006 over I-79,
     2             Springfield Township, Bridge
     3             Replacement                                 1,100,000
     4             (Base Construction Allocation -
     5             $1,000,000)
     6             (Land Allocation - $10,000)
     7             (Design and Contingencies - $90,000)
     8         (13)  SR 2014, SR 2014 over Mill Creek,
     9             Findley Township, Bridge Replacement          330,000
    10             (Base Construction Allocation -
    11             $240,000)
    12             (Land Allocation - $20,000)
    13             (Design and Contingencies - $70,000)
    14         (14)  SR 2025, SR 2025 over Lake Barmore
    15             Outlet, Pine Township, Bridge
    16             Replacement                                   300,000
    17             (Base Construction Allocation -
    18             $230,000)
    19             (Land Allocation - $10,000)
    20             (Design and Contingencies - $60,000)
    21         (15)  SR 3011, SR 3011 over I-80, Shenango
    22             Township, Bridge Replacement                  810,000
    23             (Base Construction Allocation -
    24             $700,000)
    25             (Land Allocation - $10,000)
    26             (Design and Contingencies - $100,000)
    27         (16)  SR 4014, SR 4014 over Shenango River,
    28             Delaware Township, Bridge Replacement         920,000
    29             (Base Construction Allocation -
    30             $800,000)
    19970S0186B0698                 - 251 -

     1             (Land Allocation - $20,000)
     2             (Design and Contingencies - $100,000)
     3         (17)  SR 0518, PA 516 (Walnut Street)
     4             Bridge over Pine Hollow Road, City of
     5             Hermitage, Bridge Replacement                 550,000
     6             (Base Construction Allocation -
     7             $500,000)
     8             (Design and Contingencies - $50,000)
     9  Section 48.  Mifflin County.
    10     (a)  Local Bridges
    11         (1)  Oliver Township, T-803, Bridge over
    12             Musser Run, Bridge Replacement                492,000
    13             (Base Construction Allocation -
    14             $390,000)
    15             (Land Allocation - $2,000)
    16             (Design and Contingencies - $100,000)
    17         (2)  Decatur Township, T-379, Bridge over
    18             Meadow Creek, Bridge Replacement              370,000
    19             (Base Construction Allocation -
    20             $300,000)
    21             (Land Allocation - $10,000)
    22             (Design and Contingencies - $60,000)
    23     (b)  State Bridges
    24         (1)  SR 0022, Bridge over Kish Creek,
    25             Lewistown Borough, Bridge Painting            800,000
    26             (Base Construction Allocation -
    27             $720,000)
    28             (Design and Contingencies - $80,000)
    29         (2)  SR 3017, Bridge over Juniata River,
    30             Wayne Township, Bridge Painting               935,000
    19970S0186B0698                 - 252 -

     1             (Base Construction Allocation -
     2             $850,000)
     3             (Design and Contingencies - $85,000)
     4  Section 49.  Monroe County.
     5     (a)  Local Bridges
     6         (1)  Smithfield Township, T-522, Bridge                    <--
     7             over Marshalls Creek, Bridge
     8             Replacement                                   134,000
     9             (Base Construction Allocation -
    10             $116,000)
    11             (Land Allocation - $6,000)
    12             (Design and Contingencies - $12,000)
    13         (1)  HAMILTON TOWNSHIP, T-202, BRIDGE OVER                 <--
    14             LAKE CREEK, BRIDGE REPLACEMENT                320,000
    15             (BASE CONSTRUCTION ALLOCATION -
    16             $270,000)
    17             (LAND ALLOCATION - $10,000)
    18             (DESIGN AND CONTINGENCIES - $40,000)
    19         (2)  STROUD TOWNSHIP, T-420, BRIDGE OVER
    20             CHERRY CREEK, BRIDGE REPLACEMENT              360,000
    21             (BASE CONSTRUCTION ALLOCATION -
    22             $230,000)
    23             (LAND ALLOCATION - $10,000)
    24             (DESIGN AND CONTINGENCIES - $120,000)
    25         (3)  SMITHFIELD TOWNSHIP, T-539, BRIDGE
    26             OVER MARSHALLS CREEK, BRIDGE
    27             REHABILITATION                                348,000
    28             (BASE CONSTRUCTION ALLOCATION -
    29             $288,000)
    30             (LAND ALLOCATION - $10,000)
    19970S0186B0698                 - 253 -

     1             (DESIGN AND CONTINGENCIES - $50,000)
     2         (4)  SMITHFIELD TOWNSHIP, T-522, BRIDGE
     3             OVER MARSHALLS CREEK, BRIDGE
     4             REPLACEMENT                                   134,000
     5             (BASE CONSTRUCTION ALLOCATION -
     6             $116,000)
     7             (LAND ALLOCATION - $6,000)
     8             (DESIGN AND CONTINGENCIES - $12,000)
     9         (5)  BARRETT TOWNSHIP, T-612, BRIDGE OVER
    10             BRODHEAD CREEK, BRIDGE REPLACEMENT            174,000
    11             (BASE CONSTRUCTION ALLOCATION -
    12             $152,000)
    13             (LAND ALLOCATION - $7,000)
    14             (DESIGN AND CONTINGENCIES - $15,000)
    15         (6)  HAMILTON TOWNSHIP, T-414, COUNTY
    16             BRIDGE NO. 7 OVER MCMICHAEL CREEK,
    17             BRIDGE REPLACEMENT                          1,070,000
    18             (BASE CONSTRUCTION ALLOCATION -
    19             $840,000)
    20             (LAND ALLOCATION - $30,000)
    21             (DESIGN AND CONTINGENCIES - $200,000)
    22         (7)  TUNKHANNOCK TOWNSHIP, T-633, BRIDGE
    23             OVER TUNKHANNOCK CREEK, BRIDGE
    24             REPLACEMENT                                   139,000
    25             (BASE CONSTRUCTION ALLOCATION -
    26             $121,000)
    27             (LAND ALLOCATION - $6,000)
    28             (DESIGN AND CONTINGENCIES - $12,000)
    29         (8)  HAMILTON TOWNSHIP, T-233, COUNTY
    30             BRIDGE NO. 9 OVER MCMICHAEL CREEK,
    19970S0186B0698                 - 254 -

     1             BRIDGE REPLACEMENT                            665,000
     2             (BASE CONSTRUCTION ALLOCATION -
     3             $515,000)
     4             (LAND ALLOCATION - $10,000)
     5             (DESIGN AND CONTINGENCIES - $140,000)
     6         (9)  JACKSON TOWNSHIP, T-486, BRIDGE OVER
     7             TROUT LAKE SPILLWAY, BRIDGE
     8             REPLACEMENT                                   184,000
     9             (BASE CONSTRUCTION ALLOCATION -
    10             $160,000)
    11             (LAND ALLOCATION - $8,000)
    12             (DESIGN AND CONTINGENCIES - $16,000)
    13         (10)  HAMILTON TOWNSHIP, T-231, COUNTY
    14             BRIDGE NO. 8 OVER APPENZELL CREEK,
    15             BRIDGE REPLACEMENT                            565,000
    16             (BASE CONSTRUCTION ALLOCATION -
    17             $415,000)
    18             (LAND ALLOCATION - $10,000)
    19             (DESIGN AND CONTINGENCIES - $140,000)
    20         (11)  COOLBAUGH TOWNSHIP, T-591, STEAMTOWN
    21             RAILROAD BRIDGE, BRIDGE REPLACEMENT         1,031,000
    22             (BASE CONSTRUCTION ALLOCATION -
    23             $937,000)
    24             (DESIGN AND CONTINGENCIES - $94,000)
    25         (12)  JACKSON TOWNSHIP, T-434, COUNTY
    26             BRIDGE NO. 13 OVER APPENZELL CREEK,
    27             BRIDGE REPLACEMENT                            667,000
    28             (BASE CONSTRUCTION ALLOCATION -
    29             $525,000)
    30             (LAND ALLOCATION - $12,000)
    19970S0186B0698                 - 255 -

     1             (DESIGN AND CONTINGENCIES - $130,000)
     2         (13)  HAMILTON TOWNSHIP, T-237, COUNTY
     3             BRIDGE NO. 12 OVER LAKE CREEK, BRIDGE
     4             REPLACEMENT                                   430,000
     5             (BASE CONSTRUCTION ALLOCATION -
     6             $300,000)
     7             (LAND ALLOCATION - $10,000)
     8             (DESIGN AND CONTINGENCIES - $120,000)
     9     (b)  State Bridges
    10         (1)  SR 0447, SR 0447 over Broadhead Creek
    11             and Railroad, Stroud Township, Bridge
    12             Rehabilitation                              1,395,000
    13             (Base Construction Allocation -
    14             $1,071,000)
    15             (Design and Contingencies - $324,000)
    16         (2)  SR 3003, Silver Spring Boulevard over
    17             Chapple Creek, Eldred Township, Bridge
    18             Replacement                                   280,000
    19             (Base Construction Allocation -
    20             $130,000)
    21             (Land Allocation - $50,000)
    22             (Design and Contingencies - $100,000)
    23         (3)  SR 2012, SR 2012 over Broadhead Creek,
    24             East Stroudsburg Borough, Bridge
    25             Rehabilitation                              1,500,000
    26             (Base Construction Allocation -
    27             $1,150,000)
    28             (Design and Contingencies - $350,000)
    29         (4)  SR 0080, I-80 Westbound over
    30             Tunkhannock Creek at County Line,
    19970S0186B0698                 - 256 -

     1             Tobyhanna Township, Bridge
     2             Rehabilitation                                935,000
     3             (Base Construction Allocation -
     4             $720,000)
     5             (Design and Contingencies - $215,000)
     6         (5)  SR 0080, I-80 Eastbound over
     7             Tunkhannock Creek at County Line,
     8             Tunkhannock Township, Bridge
     9             Rehabilitation                                935,000
    10             (Base Construction Allocation -
    11             $720,000)
    12             (Design and Contingencies - $215,000)
    13         (6)  SR 4003, SR 4003 over Lehigh River at
    14             Lackawanna County Line, Coolbaugh
    15             Township, Bridge Rehabilitation               390,000
    16             (Base Construction Allocation -
    17             $295,000)
    18             (Design and Contingencies - $95,000)
    19         (7)  Norristown Borough, Markley Street                    <--
    20             Bridge over Stoney Creek, Bridge
    21             Replacement                                 1,250,000
    22             (Base Construction Allocation -
    23             $1,000,000)
    24             (Land Allocation - $50,000)
    25             (Design and Contingencies - $200,000)
    26         (8)  Norristown Borough, Markley Street
    27             Bridge over Stoney Creek, Bridge
    28             Rehabilitation                                500,000
    29             (Base Construction Allocation -
    30             $400,000)
    19970S0186B0698                 - 257 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $90,000)
     3         (9)  Horsham Township, Davis Grove Road
     4             over Park Creek, Bridge Replacement           300,000
     5             (Base Construction Allocation -
     6             $230,000)
     7             (Land Allocation - $20,000)
     8             (Design and Contingencies - $50,000)
     9         (10)  Franconia Township, Keller Creamery
    10             Road over Indian Creek, Bridge
    11             Replacement                                   320,000
    12             (Base Construction Allocation -
    13             $250,000)
    14             (Land Allocation - $20,000)
    15             (Design and Contingencies - $50,000)
    16         (11)  East Norriton Township, Germantown
    17             Pike over Five Mile Run Creek, Bridge
    18             Replacement                                   500,000
    19             (Base Construction Allocation -
    20             $430,000)
    21             (Land Allocation - $20,000)
    22             (Design and Contingencies - $50,000)
    23         (12)  Upper Hanover Township, Eleventh
    24             Street over Macoby Creek, Bridge
    25             Replacement                                   400,000
    26             (Base Construction Allocation -
    27             $340,000)
    28             (Land Allocation - $20,000)
    29             (Design and Contingencies - $40,000)
    30         (13)  Lower Merion Township, Black Rock
    19970S0186B0698                 - 258 -

     1             Road over Mill Creek, Bridge
     2             Replacement                                   350,000
     3             (Base Construction Allocation -
     4             $295,000)
     5             (Land Allocation - $20,000)
     6             (Design and Contingencies - $35,000)
     7         (14)  Lower Merion Township, Morris Road
     8             over Mill Creek, Bridge Replacement           350,000
     9             (Base Construction Allocation -
    10             $285,000)
    11             (Land Allocation - $20,000)
    12             (Design and Contingencies - $45,000)
    13         (15)  Upper Merion Township, Conrail over
    14             South Gulph Road, Bridge Replacement        4,500,000
    15             (Base Construction Allocation -
    16             $4,250,000)
    17             (Land Allocation - $50,000)
    18             (Design and Contingencies - $200,000)
    19         (16)  Trappe Borough, College Avenue over
    20             Buckwalter Tributary, Bridge
    21             Replacement                                   140,000
    22             (Base Construction Allocation -
    23             $120,000)
    24             (Design and Contingencies - $20,000)
    25         (7)  SR 0033, NORTHBOUND BRIDGE OVER US 209                <--
    26             WESTBOUND, HAMILTON TOWNSHIP, BRIDGE
    27             REHABILITATION                                180,000
    28             (BASE CONSTRUCTION ALLOCATION -
    29             $180,000)
    30         (8)  SR 0191, STITES BRIDGE, STROUDSBURG
    19970S0186B0698                 - 259 -

     1             TOWNSHIP, BRIDGE REHABILITATION               600,000
     2             (BASE CONSTRUCTION ALLOCATION -
     3             $500,000)
     4             (DESIGN AND CONTINGENCIES - $100,000)
     5         (9)  SR 0209, BRIDGE OVER I-80, SMITHFIELD
     6             TOWNSHIP, BRIDGE REHABILITATION               434,000
     7             (BASE CONSTRUCTION ALLOCATION -
     8             $334,000)
     9             (DESIGN AND CONTINGENCIES - $100,000)
    10         (10)  SR 0402, RESSICA FALLS BRIDGE OVER
    11             BIG BUSHKILL CREEK, MIDDLE SMITHFIELD
    12             TOWNSHIP, BRIDGE REPLACEMENT                1,520,000
    13             (BASE CONSTRUCTION ALLOCATION -
    14             $1,060,000)
    15             (LAND ALLOCATION - $60,000)
    16             (DESIGN AND CONTINGENCIES - $400,000)
    17         (11)  SR 0423, WARNERTOWN BRIDGE OVER
    18             TOBYHANNA CREEK, COOLBAUGH TOWNSHIP,
    19             BRIDGE REHABILITATION                         977,000
    20             (BASE CONSTRUCTION ALLOCATION -
    21             $600,000)
    22             (LAND ALLOCATION - $27,000)
    23             (DESIGN AND CONTINGENCIES - $350,000)
    24         (12)  SR 0940, POCONO SUMMIT BRIDGE OVER
    25             CONRAIL, TOBYHANNA TOWNSHIP, BRIDGE
    26             REHABILITATION                              1,250,000
    27             (BASE CONSTRUCTION ALLOCATION -
    28             $1,000,000)
    29             (LAND ALLOCATION - $50,000)
    30             (DESIGN AND CONTINGENCIES - $200,000)
    19970S0186B0698                 - 260 -

     1         (13)  SR 1010, BRIDGE OVER STONY CREEK,
     2             PRICE TOWNSHIP, BRIDGE REPLACEMENT            310,000
     3             (BASE CONSTRUCTION ALLOCATION -
     4             $200,000)
     5             (LAND ALLOCATION - $10,000)
     6             (DESIGN AND CONTINGENCIES - $100,000)
     7         (14)  SR 2003, BRIDGE OVER CHERRY CREEK,
     8             HAMILTON TOWNSHIP, BRIDGE REPLACEMENT         205,000
     9             (BASE CONSTRUCTION ALLOCATION -
    10             $139,000)
    11             (LAND ALLOCATION - $13,000)
    12             (DESIGN AND CONTINGENCIES - $53,000)
    13         (15)  SR 2004, SAYLORSBURG BRIDGE OVER SR
    14             0033, HAMILTON TOWNSHIP, BRIDGE
    15             REHABILITATION                                335,000
    16             (BASE CONSTRUCTION ALLOCATION -
    17             $304,000)
    18             (DESIGN AND CONTINGENCIES - $31,000)
    19         (16)  SR 2017, BRIDGE OVER I-80 AT EXIT 51,
    20             EAST STROUDSBURG BOROUGH, BRIDGE
    21             REHABILITATION                                689,000
    22             (BASE CONSTRUCTION ALLOCATION -
    23             $625,000)
    24             (DESIGN AND CONTINGENCIES - $64,000)
    25         (17)  SR 2030, WATER GAP BRIDGE OVER US
    26             209, SMITHFIELD TOWNSHIP, BRIDGE
    27             REHABILITATION                              1,390,000
    28             (BASE CONSTRUCTION ALLOCATION -
    29             $1,158,000)
    30             (DESIGN AND CONTINGENCIES - $232,000)
    19970S0186B0698                 - 261 -

     1         (18)  SR 3011, BRIDGE OVER SUGAR HOLLOW
     2             CREEK, CHESTNUTHILL TOWNSHIP, BRIDGE
     3             REPLACEMENT                                   129,000
     4             (BASE CONSTRUCTION ALLOCATION -
     5             $117,000)
     6             (DESIGN AND CONTINGENCIES - $12,000)
     7         (19)  SR 3016, BRIDGE OVER POHOPOCO CREEK,
     8             CHESTNUTHILL TOWNSHIP, BRIDGE
     9             REPLACEMENT                                   139,000
    10             (BASE CONSTRUCTION ALLOCATION -
    11             $121,000)
    12             (LAND ALLOCATION - $6,000)
    13             (DESIGN AND CONTINGENCIES - $12,000)
    14         (20)  SR 3018, BRIDGE NO.1 OVER KETTLE
    15             CREEK, HAMILTON TOWNSHIP, BRIDGE
    16             REPLACEMENT                                    80,000
    17             (BASE CONSTRUCTION ALLOCATION -
    18             $70,000)
    19             (LAND ALLOCATION - $3,000)
    20             (DESIGN AND CONTINGENCIES - $7,000)
    21         (21)  SR 3018, BRIDGE NO.2 OVER KETTLE
    22             CREEK, HAMILTON TOWNSHIP, BRIDGE
    23             REPLACEMENT                                    68,000
    24             (BASE CONSTRUCTION ALLOCATION -
    25             $59,000)
    26             (LAND ALLOCATION - $3,000)
    27             (DESIGN AND CONTINGENCIES - $6,000)
    28         (22)  SR 3022, BRIDGE OVER MCMICHAEL CREEK,
    29             HAMILTON TOWNSHIP, BRIDGE REPLACEMENT         161,000
    30             (BASE CONSTRUCTION ALLOCATION -
    19970S0186B0698                 - 262 -

     1             $140,000)
     2             (LAND ALLOCATION - $7,000)
     3             (DESIGN AND CONTINGENCIES - $14,000)
     4         (23)  SR 4001, LONG POND BRIDGE OVER
     5             TUNKHANNOCK CREEK, TUNKHANNOCK
     6             TOWNSHIP, BRIDGE REPLACEMENT                1,454,000
     7             (BASE CONSTRUCTION ALLOCATION -
     8             $900,000)
     9             (LAND ALLOCATION - $50,000)
    10             (DESIGN AND CONTINGENCIES - $500,000)
    11         (24)  SR 4007, POCONO MANOR BRIDGE OVER E L
    12             RAILROAD, BOROUGH OF MT. POCONO, BRIDGE
    13             REPLACEMENT                                 1,185,000
    14             (BASE CONSTRUCTION ALLOCATION -
    15             $935,000)
    16             (LAND ALLOCATION - $50,000)
    17             (DESIGN AND CONTINGENCIES - $200,000)
    18  Section 50.  Montgomery County.
    19     (a)  Local Bridges
    20         (1)  Norristown Borough, Hospital Bridge
    21             over Stony Creek, Bridge Replacement          412,000
    22             (Base Construction Allocation -
    23             $365,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $37,000)
    26         (2)  Trappe Borough, College Avenue Bridge
    27             over Tributary of Perkiomen Creek,
    28             Bridge Replacement                            360,000
    29             (Base Construction Allocation -
    30             $300,000)
    19970S0186B0698                 - 263 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $50,000)
     3         (3)  Towamencin Township, Bustard Road
     4             Bridge over Towamencin Creek, Bridge
     5             Replacement                                   454,000
     6             (Base Construction Allocation -
     7             $400,000)
     8             (Land Allocation - $10,000)
     9             (Design and Contingencies - $44,000)
    10         (4)  Upper Hanover Township, T-444,
    11             Treichler Road Bridge under Reading
    12             Railroad, Bridge Removal                      151,000
    13             (Base Construction Allocation -
    14             $126,000)
    15             (Land Allocation - $5,000)
    16             (Design and Contingencies - $20,000)
    17         (5)  Upper Providence Township, T-400,
    18             Supio Road Bridge under Reading
    19             Railroad, Bridge Removal                      187,000
    20             (Base Construction Allocation -
    21             $157,000)
    22             (Land Allocation - $5,000)
    23             (Design and Contingencies - $25,000)
    24         (6)  Upper Salford Township, T-444, Bridge
    25             over Abandoned Railroad, Bridge
    26             Removal                                     1,175,000
    27             (Base Construction Allocation -
    28             $1,000,000)
    29             (Land Allocation - $25,000)
    30             (Design and Contingencies - $150,000)
    19970S0186B0698                 - 264 -

     1         (7)  Norristown Borough, Markley Street
     2             Bridge over Stoney Creek, Bridge
     3             Replacement                                 1,250,000
     4             (Base Construction Allocation -
     5             $1,000,000)
     6             (Land Allocation - $50,000)
     7             (Design and Contingencies - $200,000)
     8         (8)  Norristown Borough, Markley Street
     9             Bridge over Stoney Creek, Bridge
    10             Rehabilitation                                500,000
    11             (Base Construction Allocation -
    12             $400,000)
    13             (Land Allocation - $10,000)
    14             (Design and Contingencies - $90,000)
    15         (9)  Horsham Township, Davis Grove Road
    16             over Park Creek, Bridge Replacement           300,000
    17             (Base Construction Allocation -
    18             $230,000)
    19             (Land Allocation - $20,000)
    20             (Design and Contingencies - $50,000)
    21         (10)  Franconia Township, Keller Creamery
    22             Road over Indian Creek, Bridge
    23             Replacement                                   320,000
    24             (Base Construction Allocation -
    25             $250,000)
    26             (Land Allocation - $20,000)
    27             (Design and Contingencies - $50,000)
    28         (11)  East Norriton Township, Germantown
    29             Pike over Five Mile Run Creek, Bridge
    30             Replacement                                   500,000
    19970S0186B0698                 - 265 -

     1             (Base Construction Allocation -
     2             $430,000)
     3             (Land Allocation - $20,000)
     4             (Design and Contingencies - $50,000)
     5         (12)  Upper Hanover Township, Eleventh
     6             Street over Macoby Creek, Bridge
     7             Replacement                                   400,000
     8             (Base Construction Allocation -
     9             $340,000)
    10             (Land Allocation - $20,000)
    11             (Design and Contingencies - $40,000)
    12         (13)  Lower Merion Township, Black Rock
    13             Road over Mill Creek, Bridge
    14             Replacement                                   350,000
    15             (Base Construction Allocation -
    16             $295,000)
    17             (Land Allocation - $20,000)
    18             (Design and Contingencies - $35,000)
    19         (14)  Lower Merion Township, Morris Road
    20             over Mill Creek, Bridge Replacement           350,000
    21             (Base Construction Allocation -
    22             $285,000)
    23             (Land Allocation - $20,000)
    24             (Design and Contingencies - $45,000)
    25         (15)  Upper Merion Township, Conrail over
    26             South Gulph Road, Bridge Replacement        4,500,000
    27             (Base Construction Allocation -
    28             $4,250,000)
    29             (Land Allocation - $50,000)
    30             (Design and Contingencies - $200,000)
    19970S0186B0698                 - 266 -

     1         (16)  Trappe Borough, College Avenue over
     2             Buckwalter Tributary, Bridge
     3             Replacement                                   140,000
     4             (Base Construction Allocation -
     5             $120,000)
     6             (Design and Contingencies - $20,000)
     7     (b)  State Bridges
     8         (1)  SR 2009, Byberry Road Bridge over
     9             Southampton Creek, Upper Moreland
    10             Township and Bryn Athyn Borough,
    11             Historic Bridge Replacement                   680,000
    12             (Base Construction Allocation -
    13             $500,000)
    14             (Land Allocation - $20,000)
    15             (Design and Contingencies - $160,000)
    16         (2)  SR 2018, Bethlehem Pike Bridge over
    17             Branch of Wissahickon Creek,
    18             Springfield Township, Bridge
    19             Rehabilitation                                525,000
    20             (Base Construction Allocation -
    21             $400,000)
    22             (Land Allocation - $25,000)
    23             (Design and Contingencies - $100,000)
    24         (3)  SR 4030, New Hanover Square Road
    25             Bridge over West Swamp Creek (Two
    26             Bridges), New Hanover Township, Bridge
    27             Replacement                                 1,150,000
    28             (Base Construction Allocation -
    29             $900,000)
    30             (Land Allocation - $50,000)
    19970S0186B0698                 - 267 -

     1             (Design and Contingencies - $200,000)
     2         (4)  SR 0100, Extended, (Three Bridges),
     3             High Street to Farmington Road,
     4             Pottstown Borough and Upper Pottsgrove
     5             Township, Bridge Rehabilitation             1,650,000
     6             (Base Construction Allocation -
     7             $1,500,000)
     8             (Land Allocation - $50,000)
     9             (Design and Contingencies - $100,000)
    10         (5)  SR 1017, Salfordville Road Bridge over
    11             East Branch of Perkiomen Creek, Lower
    12             Salford Township, Bridge Replacement        1,500,000
    13             (Base Construction Allocation -
    14             $1,250,000)
    15             (Land Allocation - $50,000)
    16             (Design and Contingencies - $200,000)
    17         (6)  SR 1024, Salford Station (Two Bridges)
    18             over Perkiomen Creek, Upper Salford and
    19             Lower Fredrick Townships, Bridge
    20             Replacement                                 1,200,000
    21             (Base Construction Allocation -
    22             $1,000,000)
    23             (Land Allocation - $50,000)
    24             (Design and Contingencies - $150,000)
    25         (7)  SR 3020, Dannehower Bridge over River
    26             and New US 202, Upper Merion Township,
    27             Bridgeport and Norristown Boroughs,
    28             Bridge Painting                               872,000
    29             (Base Construction Allocation -
    30             $802,000)
    19970S0186B0698                 - 268 -

     1             (Design and Contingencies - $70,000)
     2         (8)  SR 3039, South Gulph Road Overpass
     3             under Conrail, Upper Merion Township,
     4             Bridge Replacement                          1,500,000
     5             (Base Construction Allocation -
     6             $1,300,000)
     7             (Land Allocation - $50,000)
     8             (Design and Contingencies - $150,000)
     9         (9)  SR 4003, Black Rock Road Bridge over
    10             Abandoned Reading Track, Upper
    11             Providence Township, Bridge Removal           205,000
    12             (Base Construction Allocation -
    13             $175,000)
    14             (Land Allocation - $10,000)
    15             (Design and Contingencies - $20,000)
    16         (10)  SR 4012, Graterford Road Bridge over
    17             Perkiomen Creek, Skippack and Perkiomen
    18             Townships, Bridge Replacement               1,475,000
    19             (Base Construction Allocation -
    20             $1,300,000)
    21             (Land Allocation - $50,000)
    22             (Design and Contingencies - $125,000)
    23         (11)  SR 4031, Ridge Pike Bridge over
    24             Manatawny Creek, Pottstown Borough,
    25             Bridge Replacement                          2,053,000
    26             (Base Construction Allocation -
    27             $1,935,000)
    28             (Land Allocation - $45,000)
    29             (Design and Contingencies - $73,000)
    30  Section 51.  Montour County.
    19970S0186B0698                 - 269 -

     1     (a)  Local Bridges
     2         (1)  Derry Township, T-407, County Bridge
     3             No.13 over West Branch of Chillisquaque
     4             Creek near Washingtonville Borough,
     5             Bridge Replacement                            350,000
     6             (Base Construction Allocation -
     7             $265,000)
     8             (Land Allocation - $35,000)
     9             (Design and Contingencies - $50,000)
    10     (b)  State Bridges
    11         (1)  SR 1004, Bridge over Chillisquaque
    12             Creek, North of Washingtonville
    13             Borough, Bridge Replacement                   620,000
    14             (Base Construction Allocation -
    15             $500,000)
    16             (Land Allocation - $40,000)
    17             (Design and Contingencies - $80,000)
    18         (2)  SR 1006, Bridge over Branch of
    19             Chillisquaque Creek, 3 Miles Northwest
    20             of Washingtonville Borough, Bridge
    21             Replacement                                   510,000
    22             (Base Construction Allocation -
    23             $410,000)
    24             (Land Allocation - $25,000)
    25             (Design and Contingencies - $80,000)
    26         (3)  SR 3004, Bridge over Beaver Run, 2
    27             Miles West of Moresburg, Bridge
    28             Replacement                                   285,000
    29             (Base Construction Allocation -
    30             $227,000)
    19970S0186B0698                 - 270 -

     1             (Land Allocation - $14,000)
     2             (Design and Contingencies - $44,000)
     3         (4)  SR 4001, Bridge over Chillisquaque
     4             Creek, Anthony Township, Bridge
     5             Replacement                                   458,000
     6             (Base Construction Allocation -
     7             $366,000)
     8             (Land Allocation - $23,000)
     9             (Design and Contingencies - $69,000)
    10         (5)  SR 0011, SR 0011 over Sechler Run,
    11             Mahoning Township, Bridge Replacement         582,000
    12             (Base Construction Allocation -
    13             $466,000)
    14             (Land Allocation - $29,000)
    15             (Design and Contingencies - $87,000)
    16         (6)  SR 0054, SR 0054 over Chillisquaque
    17             Creek, Anthony Township, Bridge
    18             Replacement                                   547,000
    19             (Base Construction Allocation -
    20             $438,000)
    21             (Land Allocation - $27,000)
    22             (Design and Contingencies - $82,000)
    23         (7)  SR 0642, SR 0642 over Mahoning Creek,
    24             West Hemlock Township, Bridge
    25             Replacement                                   213,000
    26             (Base Construction Allocation -
    27             $170,000)
    28             (Land Allocation - $11,000)
    29             (Design and Contingencies - $32,000)
    30         (8)  SR 1009, SR 1009 over Branch of Lowry
    19970S0186B0698                 - 271 -

     1             Run, Anthony Township, Bridge
     2             Replacement                                   431,000
     3             (Base Construction Allocation -
     4             $345,000)
     5             (Land Allocation - $21,000)
     6             (Design and Contingencies - $65,000)
     7         (9)  SR 1011, SR 1011 over Tributary of
     8             Chillisquaque Creek, Anthony Township,
     9             Bridge Replacement                            212,000
    10             (Base Construction Allocation -
    11             $170,000)
    12             (Land Allocation - $11,000)
    13             (Design and Contingencies - $31,000)
    14  Section 52.  Northampton County.
    15     (a)  Local Bridges
    16         (1)  Lehigh Township, Indiantrail Road
    17             Bridge over Indian Creek, Bridge
    18             Painting                                       16,000
    19             (Base Construction Allocation -
    20             $14,000)
    21             (Design and Contingencies - $2,000)
    22         (2)  Lehigh Township, T-548, Bridge over
    23             Bertsch Creek, Bridge Replacement             400,000
    24             (Base Construction Allocation -
    25             $300,000)
    26             (Land Allocation - $20,000)
    27             (Design and Contingencies - $80,000)
    28         (3)  Lehigh Township, Wood Drive Bridge,
    29             Bridge Replacement                             65,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 272 -

     1             $41,000)
     2             (Land Allocation - $4,000)
     3             (Design and Contingencies - $20,000)
     4         (4)  Freemansburg Borough, LVRR Bridge over
     5             Main Street, Bridge Removal                   898,000
     6             (Base Construction Allocation -
     7             $694,000)
     8             (Land Allocation - $100,000)
     9             (Design and Contingencies - $104,000)
    10         (5)  CITY OF BETHLEHEM, COUNTY BRIDGE                      <--
    11             NO.88, BRIDGE OVER MONOCACY CREEK,
    12             BRIDGE REHABILITATION                         275,000
    13             (BASE CONSTRUCTION ALLOCATION -
    14             $250,000)
    15             (DESIGN AND CONTINGENCIES - $25,000)
    16     (b)  State Bridges
    17         (1)  SR 2017, Tatamy Road over Tributary of
    18             Bushkill Creek, Palmer Township, Bridge
    19             Rehabilitation                                240,000
    20             (Base Construction Allocation -
    21             $100,000)
    22             (Land Allocation - $40,000)
    23             (Design and Contingencies - $100,000)
    24         (2)  SR 4020, Maple Drive over Tributary of
    25             Bertsch Creek, Lehigh Township, Bridge
    26             Rehabilitation                                465,000
    27             (Base Construction Allocation -
    28             $275,000)
    29             (Land Allocation - $80,000)
    30             (Design and Contingencies - $110,000)
    19970S0186B0698                 - 273 -

     1  Section 53.  Northumberland County.
     2     (a)  Local Bridges
     3         (1)  Borough of Milton, Ridge Avenue over
     4             Limestone Run, Bridge Replacement             520,000
     5             (Base Construction Allocation -
     6             $380,000)
     7             (Land Allocation - $20,000)
     8             (Design and Contingencies - $120,000)
     9         (2)  Lewis Township, T-631, Old State Road
    10             Bridge over Branch of Beaver Run,
    11             Bridge Replacement                            220,000
    12             (Base Construction Allocation -
    13             $200,000)
    14             (Design and Contingencies - $20,000)
    15     (b)  State Bridges
    16         (1)  SR 0642, Chillisquaque Creek Bridge
    17             over Chillisquaque Creek, 0.5 Mile East
    18             of Pottsgrove, Bridge Deck Replacement      1,184,000
    19             (Base Construction Allocation -
    20             $947,000)
    21             (Land Allocation - $59,000)
    22             (Design and Contingencies - $178,000)
    23         (2)  SR 1005, Delaware Run Bridge over
    24             Delaware Run, 3 Miles North of
    25             Watsontown Borough, Bridge Replacement        509,000
    26             (Base Construction Allocation -
    27             $408,000)
    28             (Land Allocation - $25,000)
    29             (Design and Contingencies - $76,000)
    30         (3)  SR 0045, Bridge over Chillisquaque
    19970S0186B0698                 - 274 -

     1             Creek, East of SR 0147, Bridge
     2             Painting                                      260,000
     3             (Base Construction Allocation -
     4             $250,000)
     5             (Design and Contingencies - $10,000)
     6         (4)  SR 0054, SR 0054 over North Branch of
     7             Shamokin Creek, Mt. Carmel Township,
     8             Bridge Replacement                            721,000
     9             (Base Construction Allocation -
    10             $577,000)
    11             (Land Allocation - $36,000)
    12             (Design and Contingencies - $108,000)
    13         (5)  SR 2001, SR 2001 over Little Roaring
    14             Creek, Rush Township, Bridge
    15             Replacement                                   415,000
    16             (Base Construction Allocation -
    17             $335,000)
    18             (Land Allocation - $20,000)
    19             (Design and Contingencies - $60,000)
    20         (6)  SR 2023, SR 2023 over Conrail, Mt.
    21             Carmel Township, Bridge Replacement         1,275,000
    22             (Base Construction Allocation -
    23             $1,020,000)
    24             (Land Allocation - $64,000)
    25             (Design and Contingencies - $191,000)
    26         (7)  SR 4013, SR 4013 over Plum Creek,
    27             Rockefeller Township, Bridge
    28             Replacement                                   361,000
    29             (Base Construction Allocation -
    30             $289,000)
    19970S0186B0698                 - 275 -

     1             (Land Allocation - $18,000)
     2             (Design and Contingencies - $54,000)
     3  Section 54.  Perry County.
     4     (a)  Local Bridges
     5         (1)  Tyrone Township, County Bridge No.4,
     6             Rices Bridge over Shermans Creek,
     7             Covered Bridge Replacement                    768,000
     8             (Base Construction Allocation -
     9             $552,000)
    10             (Land Allocation - $77,000)
    11             (Design and Contingencies - $139,000)
    12         (2)  Northeast Madison Township, T-403 over
    13             Bixler Run, Bridge Replacement                585,000
    14             (Base Construction Allocation -
    15             $400,000)
    16             (Land Allocation - $10,000)
    17             (Design and Contingencies - $175,000)
    18         (3)  Tyrone Township, Rices Bridge (County
    19             Bridge No.4) over Shermans Creek,
    20             Bridge Replacement                            768,000
    21             (Base Construction Allocation -
    22             $552,000)
    23             (Land Allocation - $77,000)
    24             (Design and Contingencies - $139,000)
    25     (b)  State Bridges
    26         (1)  SR 4006, Raccoon Creek Bridge over
    27             Raccoon Creek, Tuscarora Township,
    28             Bridge Replacement                            466,000
    29             (Base Construction Allocation -
    30             $288,000)
    19970S0186B0698                 - 276 -

     1             (Land Allocation - $20,000)
     2             (Design and Contingencies - $158,000)
     3         (2)  SR 3002, Horse Valley Road Bridges
     4             (Two Bridges) over Horse Valley Run,
     5             Toboyne Township, Bridge Replacement          725,000
     6             (Base Construction Allocation -
     7             $700,000)
     8             (Land Allocation - $5,000)
     9             (Design and Contingencies - $20,000)
    10  Section 55.  Philadelphia County.
    11     (a)  Local Bridges
    12         (1)  City of Philadelphia, Byberry Road
    13             Bridge over Conrail, Temporary Bridge
    14             Construction                                  511,000
    15             (Base Construction Allocation -
    16             $390,000)
    17             (Land Allocation - $51,000)
    18             (Design and Contingencies - $70,000)
    19         (2)  City of Philadelphia, Wyoming Avenue
    20             Bridge over Former Course Frankford
    21             Creek, West of Castor Avenue, Bridge
    22             Replacement                                 1,300,000
    23             (Base Construction Allocation -
    24             $1,200,000)
    25             (Design and Contingencies - $100,000)
    26         (3)  City of Philadelphia, Chelten Avenue
    27             Bridge over SEPTA, West of Wayne
    28             Avenue, Bridge Replacement                  2,300,000
    29             (Base Construction Allocation -
    30             $2,100,000)
    19970S0186B0698                 - 277 -

     1             (Design and Contingencies - $200,000)
     2         (4)  City of Philadelphia, Fisher's Lane
     3             Bridge over Tacony Creek, West of
     4             Ramona Avenue, Bridge Replacement           1,625,000
     5             (Base Construction Allocation -
     6             $1,400,000)
     7             (Design and Contingencies - $225,000)
     8         (5)  City of Philadelphia, Kingsessing
     9             Avenue Bridge over SEPTA, Bridge
    10             Replacement                                 2,550,000
    11             (Base Construction Allocation -
    12             $2,200,000)
    13             (Land Allocation - $100,000)
    14             (Design and Contingencies - $250,000)
    15         (6)  City of Philadelphia, Montgomery
    16             Bridge over Amtrak, Bridge Replacement      5,275,000
    17             (Base Construction Allocation -
    18             $4,750,000)
    19             (Land Allocation - $125,000)
    20             (Design and Contingencies - $400,000)
    21         (7)  City of Philadelphia, Thomas Avenue
    22             Bridge over SEPTA, Bridge Replacement       3,150,000
    23             (Base Construction Allocation -
    24             $2,750,000)
    25             (Land Allocation - $100,000)
    26             (Design and Contingencies - $300,000)
    27         (8)  City of Philadelphia, Sedgley Avenue
    28             Bridge over Conrail, Bridge
    29             Replacement                                 1,000,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 278 -

     1             $800,000)
     2             (Land Allocation - $100,000)
     3             (Design and Contingencies - $100,000)
     4         (9)  City of Philadelphia, Lexington Avenue
     5             Bridge over Conrail, Bridge
     6             Replacement                                   420,000
     7             (Base Construction Allocation -
     8             $360,000)
     9             (Land Allocation - $20,000)
    10             (Design and Contingencies - $40,000)
    11         (10)  City of Philadelphia, Greenland
    12             Bridge over Conrail and I-76, Bridge
    13             Replacement                                 1,350,000
    14             (Base Construction Allocation -
    15             $1,100,000)
    16             (Land Allocation - $100,000)
    17             (Design and Contingencies - $150,000)
    18         (11)  City of Philadelphia, Glenwood Drive
    19             Bridge over Conrail, Bridge
    20             Replacement                                 1,450,000
    21             (Base Construction Allocation -
    22             $1,200,000)
    23             (Land Allocation - $100,000)
    24             (Design and Contingencies - $150,000)
    25         (12)  City of Philadelphia, Second Street
    26             Bridge over Conrail, Bridge
    27             Replacement                                   740,000
    28             (Base Construction Allocation -
    29             $650,000)
    30             (Land Allocation - $20,000)
    19970S0186B0698                 - 279 -

     1             (Design and Contingencies - $70,000)
     2         (13)  City of Philadelphia, Cambria Street
     3             Bridge over Conrail, Bridge
     4             Replacement                                 2,750,000
     5             (Base Construction Allocation -
     6             $2,400,000)
     7             (Land Allocation - $100,000)
     8             (Design and Contingencies - $250,000)
     9     (b)  State Bridges
    10         (1)  SR 4007, Germantown Avenue Bridge,
    11             Conrail Overpass, City of Philadelphia,
    12             Bridge Removal                                125,000
    13             (Base Construction Allocation -
    14             $100,000)
    15             (Land Allocation - $10,000)
    16             (Design and Contingencies - $15,000)
    17         (2)  SR 0076, Schuylkill Expressway Bridge
    18             over Schuylkill River, City of
    19             Philadelphia, Bridge Painting               2,580,000
    20             (Base Construction Allocation -
    21             $2,390,000)
    22             (Design and Contingencies - $190,000)
    23         (3)  SR 2003, 5th Street Bridge over
    24             Amtrak, City of Philadelphia, Bridge
    25             Replacement                                 2,400,000
    26             (Base Construction Allocation -
    27             $2,000,000)
    28             (Land Allocation - $200,000)
    29             (Design and Contingencies - $200,000)
    30         (4)  SR 3008, Chestnut Street Bridge over
    19970S0186B0698                 - 280 -

     1             Schuylkill River, City of Philadelphia,
     2             Bridge Painting                               477,000
     3             (Base Construction Allocation -
     4             $426,000)
     5             (Design and Contingencies - $51,000)
     6         (5)  SR 3037, JFK Boulevard Bridge over
     7             Schuylkill River, City of Philadelphia,
     8             Bridge Painting                               857,000
     9             (Base Construction Allocation -
    10             $794,000)
    11             (Design and Contingencies - $63,000)
    12         (6)  SR 0095, Delaware River Expressway
    13             over Westmoreland and Tioga Streets,
    14             City of Philadelphia, Bridge
    15             Rehabilitation                              4,450,000
    16             (Base Construction Allocation -
    17             $4,200,000)
    18             (Land Allocation - $50,000)
    19             (Design and Contingencies - $200,000)
    20  Section 56.  Pike County.
    21     (a)  Local Bridges (Reserved)
    22     (b)  State Bridges
    23         (1)  SR 0390, Bridge Kill Creek Bridge,
    24             North of SR 3002, Green Township,
    25             Bridge Replacement                            430,000
    26             (Base Construction Allocation -
    27             $340,000)
    28             (Land Allocation - $10,000)
    29             (Design and Contingencies - $80,000)
    30         (2)  SR 2011, Bridge over Outlet to Sawkill
    19970S0186B0698                 - 281 -

     1             Pond, South of TR 6, Dingman Township,
     2             Bridge Replacement                            355,000
     3             (Base Construction Allocation -
     4             $275,000)
     5             (Land Allocation - $10,000)
     6             (Design and Contingencies - $70,000)
     7         (3)  SR 0434, Shohola Bridge over Delaware
     8             River, Shohola Township and New York
     9             State Line, Bridge Painting                 2,200,000
    10             (Base Construction Allocation -
    11             $2,000,000)
    12             (Design and Contingencies - $200,000)
    13         (4)  State Bridges, Countywide Bridge Zone
    14             Painting, Bridge Painting                     370,000
    15             (Base Construction Allocation -
    16             $350,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $10,000)
    19  Section 57.  (Reserved).
    20  Section 58.  Schuylkill County.
    21     (a)  Local Bridges
    22         (1)  City of Pottsville, Washington Street
    23             Bridge No.2 over Conrail and PA 61,
    24             Bridge Replacement                          2,225,000
    25             (Base Construction Allocation -
    26             $2,000,000)
    27             (Land Allocation - $25,000)
    28             (Design and Contingencies - $200,000)
    29         (2)  Pine Grove Township, Penn Central
    30             Bridge over T-390, Bridge Removal             551,000
    19970S0186B0698                 - 282 -

     1             (Base Construction Allocation -
     2             $435,000)
     3             (Land Allocation - $50,000)
     4             (Design and Contingencies - $66,000)
     5         (3)  Rush Township, T-862, Bridge No.42
     6             over Pine Creek, Bridge Replacement           139,000
     7             (Base Construction Allocation -
     8             $121,000)
     9             (Land Allocation - $6,000)
    10             (Design and Contingencies - $12,000)
    11         (4)  St. Clair Borough, Russell Street
    12             Bridge over Mill Creek, Bridge
    13             Replacement                                   223,000
    14             (Base Construction Allocation -
    15             $193,000)
    16             (Land Allocation - $10,000)
    17             (Design and Contingencies - $20,000)
    18         (5)  Upper Mahantongo Township, T-473,
    19             Bridge over Mahantongo Creek, Bridge
    20             Replacement                                   202,000
    21             (Base Construction Allocation -
    22             $175,000)
    23             (Land Allocation - $9,000)
    24             (Design and Contingencies - $18,000)
    25         (6)  EAST BRUNSWICK TOWNSHIP, T-753, BRIDGE                <--
    26             OVER INDIAN RUN, BRIDGE REPLACEMENT           400,000
    27             (BASE CONSTRUCTION ALLOCATION -
    28             $290,000)
    29             (LAND ALLOCATION - $10,000)
    30             (DESIGN AND CONTINGENCIES - $100,000)
    19970S0186B0698                 - 283 -

     1         (7)  WEST BRUNSWICK TOWNSHIP, COUNTY BRIDGE
     2             NO.94 OVER SCHUYLKILL RIVER, BRIDGE
     3             REPLACEMENT                                   384,000
     4             (BASE CONSTRUCTION ALLOCATION -
     5             $384,000)
     6         (8)  TREMONT BOROUGH, MAPLE STREET BRIDGE
     7             NO.22 OVER GOODSPRING CREEK, BRIDGE
     8             REPLACEMENT                                   214,000
     9             (BASE CONSTRUCTION ALLOCATION -
    10             $178,000)
    11             (DESIGN AND CONTINGENCIES - $36,000)
    12         (9)  GILBERTON BOROUGH, BRIDGE STREET
    13             BRIDGE OVER MAHANOY CREEK, BRIDGE
    14             REPLACEMENT                                   520,000
    15             (BASE CONSTRUCTION ALLOCATION -
    16             $400,000)
    17             (LAND ALLOCATION - $20,000)
    18             (DESIGN AND CONTINGENCIES - $100,000)
    19         (10)  PORTER TOWNSHIP, T-416, BRIDGE NO.79
    20             OVER WICONISCO CREEK, BRIDGE
    21             REPLACEMENT                                   287,000
    22             (BASE CONSTRUCTION ALLOCATION -
    23             $250,000)
    24             (LAND ALLOCATION - $12,000)
    25             (DESIGN AND CONTINGENCIES - $25,000)
    26         (11)  UNION TOWNSHIP, T-594, BRIDGE OVER
    27             LITTLE CATAWISSA CREEK, BRIDGE
    28             REPLACEMENT                                   296,000
    29             (BASE CONSTRUCTION ALLOCATION -
    30             $230,000)
    19970S0186B0698                 - 284 -

     1             (LAND ALLOCATION - $5,000)
     2             (DESIGN AND CONTINGENCIES - $61,000)
     3         (12)  DEER LAKE BOROUGH, DREHERSVILLE ROAD
     4             BRIDGE OVER PINE CREEK, BRIDGE
     5             REPLACEMENT                                   484,000
     6             (BASE CONSTRUCTION ALLOCATION -
     7             $324,000)
     8             (LAND ALLOCATION - $10,000)
     9             (DESIGN AND CONTINGENCIES - $150,000)
    10         (13)  PORT CARBON BOROUGH, MILL STREET
    11             BRIDGE NO.106 OVER SCHUYLKILL RIVER,
    12             BRIDGE REPLACEMENT                          1,050,000
    13             (BASE CONSTRUCTION ALLOCATION -
    14             $750,000)
    15             (LAND ALLOCATION - $50,000)
    16             (DESIGN AND CONTINGENCIES - $250,000)
    17         (14)  HEGINS TOWNSHIP, T-478, BROAD STREET
    18             BRIDGE OVER PINE CREEK, BRIDGE
    19             REPLACEMENT                                   357,000
    20             (BASE CONSTRUCTION ALLOCATION -
    21             $290,000)
    22             (LAND ALLOCATION - $5,000)
    23             (DESIGN AND CONTINGENCIES - $62,000)
    24         (15)  FRACKVILLE BOROUGH, SPRING STREET
    25             READING RAILROAD BRIDGE, BRIDGE
    26             REMOVAL                                       112,000
    27             (BASE CONSTRUCTION ALLOCATION -
    28             $52,000)
    29             (LAND ALLOCATION - $10,000)
    30             (DESIGN AND CONTINGENCIES - $50,000)
    19970S0186B0698                 - 285 -

     1         (16)  ELDRED TOWNSHIP, T-383, BRIDGE OVER
     2             MAHANTANGO CREEK, BRIDGE REPLACEMENT          121,000
     3             (BASE CONSTRUCTION ALLOCATION -
     4             $110,000)
     5             (DESIGN AND CONTINGENCIES - $11,000)
     6         (17)  PORT CLINTON BOROUGH, BROAD STREET,
     7             COUNTY BRIDGE NO.123 OVER SCHUYLKILL
     8             RIVER, BRIDGE REPLACEMENT                     828,000
     9             (BASE CONSTRUCTION ALLOCATION -
    10             $692,000)
    11             (LAND ALLOCATION - $32,000)
    12             (DESIGN AND CONTINGENCIES - $104,000)
    13         (18)  SOUTH MANHEIM TOWNSHIP, T-676 COUNTY
    14             BRIDGE NO.112 OVER BEAR CREEK, BRIDGE
    15             REPLACEMENT                                   470,000
    16             (BASE CONSTRUCTION ALLOCATION -
    17             $300,000)
    18             (LAND ALLOCATION - $20,000)
    19             (DESIGN AND CONTINGENCIES - $150,000)
    20         (19)  PORT CARBON BOROUGH, WASHINGTON
    21             STREET BRIDGE OVER MILL CREEK, BRIDGE
    22             REPLACEMENT                                   684,000
    23             (BASE CONSTRUCTION ALLOCATION -
    24             $564,000)
    25             (LAND ALLOCATION - $20,000)
    26             (DESIGN AND CONTINGENCIES - $100,000)
    27         (20)  CITY OF POTTSVILLE, WASHINGTON STREET
    28             OVER CONRAIL AND SR 0061, BRIDGE
    29             REHABILITATION                                803,000
    30             (BASE CONSTRUCTION ALLOCATION -
    19970S0186B0698                 - 286 -

     1             $669,000)
     2             (DESIGN AND CONTINGENCIES - $134,000)
     3         (21)  ST. CLAIR BOROUGH, RUSSELL STREET
     4             BRIDGE OVER MILL CREEK, BRIDGE
     5             REPLACEMENT                                   480,000
     6             (BASE CONSTRUCTION ALLOCATION -
     7             $350,000)
     8             (LAND ALLOCATION - $10,000)
     9             (DESIGN AND CONTINGENCIES - $120,000)
    10         (22)  NORTH UNION TOWNSHIP, T-455, BRIDGE
    11             OVER TOMHICKEN CREEK, BRIDGE
    12             REPLACEMENT                                   360,000
    13             (BASE CONSTRUCTION ALLOCATION -
    14             $250,000)
    15             (LAND ALLOCATION - $10,000)
    16             (DESIGN AND CONTINGENCIES - $100,000)
    17         (23)  WEST BRUNSWICK TOWNSHIP, T-723,
    18             INDUSTRIAL ROAD OVER PINE CREEK, BRIDGE
    19             REPLACEMENT                                   584,000
    20             (BASE CONSTRUCTION ALLOCATION -
    21             $434,000)
    22             (LAND ALLOCATION - $20,000)
    23             (DESIGN AND CONTINGENCIES - $130,000)
    24         (24)  LANDINGVILLE BOROUGH, CANAL STREET
    25             BRIDGE OVER SCHUYLKILL RIVER, BRIDGE
    26             REPLACEMENT                                   810,000
    27             (BASE CONSTRUCTION ALLOCATION -
    28             $640,000)
    29             (LAND ALLOCATION - $20,000)
    30             (DESIGN AND CONTINGENCIES - $150,000)
    19970S0186B0698                 - 287 -

     1         (25)  NORTH MANHEIM TOWNSHIP, MEMORIAL
     2             DRIVE OVERPASS, BRIDGE REMOVAL                295,000
     3             (BASE CONSTRUCTION ALLOCATION -
     4             $250,000)
     5             (LAND ALLOCATION - $20,000)
     6             (DESIGN AND CONTINGENCIES - $25,000)
     7         (26)  BRANCH TOWNSHIP, T-564, BRIDGE OVER
     8             MUDDY CREEK, BRIDGE REPLACEMENT               360,000
     9             (BASE CONSTRUCTION ALLOCATION -
    10             $250,000)
    11             (LAND ALLOCATION - $10,000)
    12             (DESIGN AND CONTINGENCIES - $100,000)
    13         (27)  ELDRED TOWNSHIP, T-395, BRIDGE OVER
    14             LITTLE MAHANTANGO CREEK, BRIDGE
    15             REPLACEMENT                                   362,000
    16             (BASE CONSTRUCTION ALLOCATION -
    17             $250,000)
    18             (LAND ALLOCATION - $12,000)
    19             (DESIGN AND CONTINGENCIES - $100,000)
    20     (b)  State Bridges
    21         (1)  SR 0054, SR 0054 over Mahanoy Creek,
    22             Mahanoy Township, Bridge Replacement        1,005,000
    23             (Base Construction Allocation -
    24             $770,000)
    25             (Design and Contingencies - $235,000)
    26         (2)  SR 0054, SR 0054 over Reading Blue
    27             Mountain and Northern Railroad, Mahanoy
    28             Township, Bridge Rehabilitation               650,000
    29             (Base Construction Allocation -
    30             $500,000)
    19970S0186B0698                 - 288 -

     1             (Design and Contingencies - $150,000)
     2         (3)  SR 0081, SR 0081 Southbound over
     3             Swatara Creek, Pine Grove Township,
     4             Bridge Rehabilitation                         970,000
     5             (Base Construction Allocation -
     6             $745,000)
     7             (Design and Contingencies - $225,000)
     8         (4)  SR 0081, SR 0081 Northbound over
     9             Swatara Creek, Pine Grove Township,
    10             Bridge Rehabilitation                         970,000
    11             (Base Construction Allocation -
    12             $745,000)
    13             (Design and Contingencies - $225,000)
    14         (5)  SR 0081, SR 0081 Southbound over SR
    15             0443 and Exit Ramp 3, Pine Grove
    16             Township, Bridge Rehabilitation               715,000
    17             (Base Construction Allocation -
    18             $550,000)
    19             (Design and Contingencies - $165,000)
    20         (6)  SR 0081, SR 0081 Northbound over SR
    21             0443 and Exit Ramp 31, Pine Grove
    22             Township, Bridge Rehabilitation               515,000
    23             (Base Construction Allocation -
    24             $390,000)
    25             (Design and Contingencies - $125,000)
    26         (7)  SR 0081, I-81 Southbound over T-886,
    27             Oak Grove Road, Pine Grove Township,
    28             Bridge Rehabilitation                         300,000
    29             (Base Construction Allocation -
    30             $200,000)
    19970S0186B0698                 - 289 -

     1             (Design and Contingencies - $100,000)
     2         (8)  SR 0081, I-81 Northbound over T-886,
     3             Oak Grove Road, Pine Grove Township,
     4             Bridge Rehabilitation                         300,000
     5             (Base Construction Allocation -
     6             $200,000)
     7             (Design and Contingencies - $100,000)
     8         (9)  SR 0061, Bridge over Mahannon Creek at
     9             South Liberty Street, North Manheim
    10             Township, Bridge Rehabilitation               265,000
    11             (Base Construction Allocation -
    12             $175,000)
    13             (Design and Contingencies - $90,000)
    14         (10)  SR 0895, SR 0895 over Lizard Creek,
    15             Village of Snyders, West Penn Township,
    16             Bridge Rehabilitation                         290,000
    17             (Base Construction Allocation -
    18             $190,000)
    19             (Design and Contingencies - $100,000)
    20         (11)  SR 0901, SR 0901 over Mahanoy Creek,
    21             Bridge Rehabilitation                         680,000
    22             (Base Construction Allocation -
    23             $520,000)
    24             (Design and Contingencies - $160,000)
    25         (12)  SR 1011, SR 1011 over Big Creek,
    26             Village of Brockton, Schuylkill
    27             Township, Bridge Replacement                  340,000
    28             (Base Construction Allocation -
    29             $160,000)
    30             (Land Allocation - $55,000)
    19970S0186B0698                 - 290 -

     1             (Design and Contingencies - $125,000)
     2         (13)  SR 1011, SR 1011 over Locust Creek,
     3             Ryan Township, Bridge Rehabilitation          365,000
     4             (Base Construction Allocation -
     5             $180,000)
     6             (Land Allocation - $60,000)
     7             (Design and Contingencies - $125,000)
     8         (14)  SR 2018, SR 2018 over Little
     9             Schuylkill River, Drehersville, East
    10             Brunswick Township, Bridge
    11             Rehabilitation                                385,000
    12             (Base Construction Allocation -
    13             $285,000)
    14             (Design and Contingencies - $100,000)
    15         (15)  SR 4013, SR 4013 over Rausch Creek,
    16             Hegins Township, Bridge Rehabilitation        280,000
    17             (Base Construction Allocation -
    18             $180,000)
    19             (Design and Contingencies - $100,000)
    20         (16)  SR 4022, SR 4022 over Tributary of
    21             Mahantango Creek, Eldred Township,
    22             Bridge Replacement                            310,000
    23             (Base Construction Allocation -
    24             $150,000)
    25             (Land Allocation - $50,000)
    26             (Design and Contingencies - $110,000)
    27         (17)  SR 0209, Broad Street over Little
    28             Schuylkill River, Tamaqua Borough,
    29             Bridge Replacement                            600,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 291 -

     1             $360,000)
     2             (Land Allocation - $100,000)
     3             (Design and Contingencies - $140,000)
     4         (18)  SR 4022, Broad Street Bridge over
     5             Panther Creek, Tamaqua Borough, Bridge
     6             Replacement                                 1,780,000
     7             (Base Construction Allocation -
     8             $1,220,000)
     9             (Land Allocation - $195,000)
    10             (Design and Contingencies - $365,000)
    11         (19)  SR 4022, SR 4022 over Mahanoy Creek,
    12             Village of Helfenstein, Eldred
    13             Township, Bridge Replacement                1,170,000
    14             (Base Construction Allocation -
    15             $750,000)
    16             (Land Allocation - $195,000)
    17             (Design and Contingencies - $225,000)
    18         (20)  SR 0339, SR 0339 over Catawissa
    19             Creek, North Union Township, Bridge
    20             Replacement                                   984,000
    21             (Base Construction Allocation -
    22             $630,000)
    23             (Land Allocation - $165,000)
    24             (Design and Contingencies - $189,000)
    25         (21)  SR 0443, Dock Street Bridge over
    26             Tributary of Schuylkill River, Borough
    27             of Schuylkill Haven, Bridge
    28             Replacement                                   325,000
    29             (Base Construction Allocation -
    30             $150,000)
    19970S0186B0698                 - 292 -

     1             (Land Allocation - $50,000)
     2             (Design and Contingencies - $125,000)
     3         (22)  SR 0895, SR 0895 over Schuylkill
     4             River, Bridge Replacement                   2,370,000
     5             (Base Construction Allocation -
     6             $1,480,000)
     7             (Land Allocation - $390,000)
     8             (Design and Contingencies - $500,000)
     9         (23)  SR 4011, SR 4011 over Pine Creek,
    10             Hegins Township, Bridge Replacement           720,000
    11             (Base Construction Allocation -
    12             $450,000)
    13             (Land Allocation - $120,000)
    14             (Design and Contingencies - $150,000)
    15         (24)  SR 0895, Auburn Arch over Schuylkill
    16             River, South Manheim Township, Bridge
    17             Replacement                                   550,000
    18             (Base Construction Allocation -
    19             $350,000)
    20             (Land Allocation - $50,000)
    21             (Design and Contingencies - $150,000)
    22         (25)  SR 0061, MADY'S BIG BRIDGE OVER                      <--
    23             CONRAIL, CITY OF POTTSVILLE, BRIDGE
    24             REHABILITATION                              1,323,000
    25             (BASE CONSTRUCTION ALLOCATION -
    26             $1,202,000)
    27             (DESIGN AND CONTINGENCIES - $121,000)
    28         (26)  SR 0061, MADY'S SMALL BRIDGE OVER
    29             SCHUYLKILL RIVER, CITY OF POTTSVILLE,
    30             BRIDGE REHABILITATION                         329,000
    19970S0186B0698                 - 293 -

     1             (BASE CONSTRUCTION ALLOCATION -
     2             $299,000)
     3             (DESIGN AND CONTINGENCIES - $30,000)
     4         (27)  SR 0125, PITMAN BRIDGE OVER LITTLE
     5             MAHANTANGO CREEK, ELDRED TOWNSHIP,
     6             BRIDGE REPLACEMENT                            480,000
     7             (BASE CONSTRUCTION ALLOCATION -
     8             $390,000)
     9             (LAND ALLOCATION - $10,000)
    10             (DESIGN AND CONTINGENCIES - $80,000)
    11         (28)  SR 0325, BRIDGE OVER WICONISCO CREEK,
    12             PORTER TOWNSHIP, BRIDGE REPLACEMENT         1,175,000
    13             (BASE CONSTRUCTION ALLOCATION -
    14             $800,000)
    15             (LAND ALLOCATION - $40,000)
    16             (DESIGN AND CONTINGENCIES - $335,000)
    17         (29)  SR 0501, BRIDGE OVER LITTLE SWATARA
    18             CREEK, PINE GROVE TOWNSHIP, BRIDGE
    19             REPLACEMENT                                 1,400,000
    20             (BASE CONSTRUCTION ALLOCATION -
    21             $1,000,000)
    22             (LAND ALLOCATION - $50,000)
    23             (DESIGN AND CONTINGENCIES - $350,000)
    24         (30)  SR 0501, SMALL BRIDGE OVER LITTLE
    25             SWATARA CREEK, PINE GROVE TOWNSHIP,
    26             BRIDGE REPLACEMENT                            250,000
    27             (BASE CONSTRUCTION ALLOCATION -
    28             $150,000)
    29             (LAND ALLOCATION - $10,000)
    30             (DESIGN AND CONTINGENCIES - $90,000)
    19970S0186B0698                 - 294 -

     1         (31)  SR 1013, TUSCARORA PARK BRIDGE OVER
     2             TRIBUTARY OF LOCUST CREEK, RYAN
     3             TOWNSHIP, BRIDGE DECK REPLACEMENT             485,000
     4             (BASE CONSTRUCTION ALLOCATION -
     5             $375,000)
     6             (LAND ALLOCATION - $10,000)
     7             (DESIGN AND CONTINGENCIES - $100,000)
     8         (32)  SR 1016, LOFTY BRIDGE OVER POCONO
     9             N.E. RAILROAD, DELANO TOWNSHIP, BRIDGE
    10             REPLACEMENT                                   715,000
    11             (BASE CONSTRUCTION ALLOCATION -
    12             $500,000)
    13             (LAND ALLOCATION - $15,000)
    14             (DESIGN AND CONTINGENCIES - $200,000)
    15         (33)  SR 2006, BRIDGE OVER MAHANNON CREEK,
    16             WEST BRUNSWICK TOWNSHIP, BRIDGE
    17             REPLACEMENT                                   107,000
    18             (BASE CONSTRUCTION ALLOCATION -
    19             $92,000)
    20             (LAND ALLOCATION - $5,000)
    21             (DESIGN AND CONTINGENCIES - $10,000)
    22         (34)  SR 3003, BRIDGE OVER WEST BRANCH
    23             SCHUYLKILL RIVER, NORTH MANHEIM
    24             TOWNSHIP, BRIDGE DECK REPLACEMENT             224,000
    25             (BASE CONSTRUCTION ALLOCATION -
    26             $195,000)
    27             (DESIGN AND CONTINGENCIES - $29,000)
    28         (35)  SR 3015, BRIDGE OVER WICONISCO CREEK,
    29             PORTER TOWNSHIP, BRIDGE REPLACEMENT           200,000
    30             (BASE CONSTRUCTION ALLOCATION -
    19970S0186B0698                 - 295 -

     1             $175,000)
     2             (LAND ALLOCATION - $8,000)
     3             (DESIGN AND CONTINGENCIES - $17,000)
     4         (36)  SR 4016, BRIDGE OVER LITTLE
     5             MAHANTANGO CREEK, UPPER MAHANTONGO
     6             TOWNSHIP, BRIDGE REPLACEMENT                  165,000
     7             (BASE CONSTRUCTION ALLOCATION -
     8             $150,000)
     9             (DESIGN AND CONTINGENCIES - $15,000)
    10         (37)  SR 4033, BRIDGE OVER TOMHICKEN CREEK,
    11             NORTH UNION TOWNSHIP, BRIDGE DECK
    12             REPLACEMENT                                   350,000
    13             (BASE CONSTRUCTION ALLOCATION -
    14             $250,000)
    15             (DESIGN AND CONTINGENCIES - $100,000)
    16         (38)  SR 4036, RINGTOWN BRIDGE OVER LITTLE
    17             CATAWISSA CREEK, UNION TOWNSHIP, BRIDGE
    18             REPLACEMENT                                   240,000
    19             (BASE CONSTRUCTION ALLOCATION -
    20             $216,000)
    21             (LAND ALLOCATION - $3,000)
    22             (DESIGN AND CONTINGENCIES - $21,000)
    23         (39)  SR 4039, HAAS BRIDGE OVER MAHANTANGO
    24             CREEK, UPPER MAHANTONGO TOWNSHIP,
    25             BRIDGE REPLACEMENT                            153,000
    26             (BASE CONSTRUCTION ALLOCATION -
    27             $130,000)
    28             (LAND ALLOCATION - $10,000)
    29             (DESIGN AND CONTINGENCIES - $13,000)
    30  Section 59.  Snyder County.
    19970S0186B0698                 - 296 -

     1     (a)  Local Bridges (Reserved)
     2     (b)  State Bridges
     3         (1)  SR 1011, Pine Street Bridge over Penns
     4             Creek, Selinsgrove, Bridge
     5             Rehabilitation                              1,150,000
     6             (Base Construction Allocation -
     7             $940,000)
     8             (Land Allocation - $10,000)
     9             (Design and Contingencies - $200,000)
    10         (2)  SR 3002, Bridge over Mahantango Creek,
    11             1.5 Miles South of Meiserville, Perry
    12             and Chapman Townships Line, Bridge
    13             Rehabilitation                              1,425,000
    14             (Base Construction Allocation -
    15             $1,211,000)
    16             (Design and Contingencies - $214,000)
    17         (3)  SR 4007, Middle Creek Bridge over
    18             Middle Creek, North of SR 0522 and
    19             South of SR 4012, Bridge Replacement        1,158,000
    20             (Base Construction Allocation -
    21             $926,000)
    22             (Land Allocation - $58,000)
    23             (Design and Contingencies - $174,000)
    24         (4)  SR 0522, Bridge over Middle Creek,
    25             Bridge Painting                               180,000
    26             (Base Construction Allocation -
    27             $170,000)
    28             (Design and Contingencies - $10,000)
    29         (5)  SR 0035, SR 0035 over Tributary of
    30             Mahantango Creek, Perry Township,
    19970S0186B0698                 - 297 -

     1             Bridge Replacement                            815,000
     2             (Base Construction Allocation -
     3             $652,000)
     4             (Land Allocation - $41,000)
     5             (Design and Contingencies - $122,000)
     6         (6)  SR 0104, SR 0104 over Branch of
     7             Mahantango Creek, Perry Township,
     8             Bridge Replacement                            430,000
     9             (Base Construction Allocation -
    10             $345,000)
    11             (Land Allocation - $20,000)
    12             (Design and Contingencies - $65,000)
    13         (7)  SR 0104, SR 0104 over Middle Creek,
    14             Franklin Township, Bridge Replacement         440,000
    15             (Base Construction Allocation -
    16             $350,000)
    17             (Land Allocation - $20,000)
    18             (Design and Contingencies - $70,000)
    19         (8)  SR 0522, SR 0522 over Tributary of
    20             Middle Creek, Spring Township, Bridge
    21             Replacement                                   500,000
    22             (Base Construction Allocation -
    23             $400,000)
    24             (Land Allocation - $25,000)
    25             (Design and Contingencies - $75,000)
    26         (9)  SR 0522, SR 0522 over Tributary of
    27             Middle Creek, Spring Township, Bridge
    28             Replacement                                   896,000
    29             (Base Construction Allocation -
    30             $717,000)
    19970S0186B0698                 - 298 -

     1             (Land Allocation - $45,000)
     2             (Design and Contingencies - $134,000)
     3         (10)  SR 0522, SR 0522 over Tributary of
     4             Middle Creek, Beavertown Borough,
     5             Bridge Replacement                            244,000
     6             (Base Construction Allocation -
     7             $195,000)
     8             (Land Allocation - $12,000)
     9             (Design and Contingencies - $37,000)
    10         (11)  SR 0522, SR 0522 over Tributary of
    11             Middle Creek, Beavertown Borough,
    12             Bridge Replacement                            245,000
    13             (Base Construction Allocation -
    14             $196,000)
    15             (Land Allocation - $12,000)
    16             (Design and Contingencies - $37,000)
    17         (12)  SR 0522, SR 0522 over Kern Run,
    18             Beavertown Borough, Bridge Replacement        570,000
    19             (Base Construction Allocation -
    20             $456,000)
    21             (Land Allocation - $29,000)
    22             (Design and Contingencies - $85,000)
    23         (13)  SR 0522, SR 0522 over Penns Creek,
    24             Selinsgrove Borough, Bridge
    25             Replacement                                 3,167,000
    26             (Base Construction Allocation -
    27             $2,534,000)
    28             (Land Allocation - $158,000)
    29             (Design and Contingencies - $475,000)
    30         (14)  SR 1011, SR 1011 over Tributary of
    19970S0186B0698                 - 299 -

     1             Penns Creek, Jackson Township, Bridge
     2             Replacement                                   241,000
     3             (Base Construction Allocation -
     4             $193,000)
     5             (Land Allocation - $12,000)
     6             (Design and Contingencies - $36,000)
     7         (15)  SR 2013, SR 2013 over Tributary of
     8             Susquehanna River, Chapman Township,
     9             Bridge Replacement                            202,000
    10             (Base Construction Allocation -
    11             $162,000)
    12             (Land Allocation - $10,000)
    13             (Design and Contingencies - $30,000)
    14         (16)  SR 3009, SR 3009 over Paxtonville
    15             Creek, Franklin Township, Bridge
    16             Replacement                                 1,512,000
    17             (Base Construction Allocation -
    18             $1,209,000)
    19             (Land Allocation - $76,000)
    20             (Design and Contingencies - $227,000)
    21  Section 60.  Somerset County.
    22     (a)  Local Bridges
    23         (1)  Middlecreek Township, T-338, Blue Hole
    24             Creek Bridge over Blue Hole Creek,
    25             Bridge Replacement                            505,000
    26             (Base Construction Allocation -
    27             $400,000)
    28             (Land Allocation - $10,000)
    29             (Design and Contingencies - $95,000)
    30         (2)  Paint Borough, Pennsylvania Railroad
    19970S0186B0698                 - 300 -

     1             Bridge over Bedford Street, Bridge
     2             Replacement                                   350,000
     3             (Base Construction Allocation -
     4             $250,000)
     5             (Land Allocation - $25,000)
     6             (Design and Contingencies - $75,000)
     7         (3)  Shade Township, T-712, Lipinski Road
     8             Bridge over Dark Shade Creek, Bridge
     9             Replacement                                   560,000
    10             (Base Construction Allocation -
    11             $450,000)
    12             (Land Allocation - $10,000)
    13             (Design and Contingencies - $100,000)
    14         (4)  Somerset Borough, Church Street Bridge
    15             over Parsons Run, Bridge Replacement          350,000
    16             (Base Construction Allocation -
    17             $250,000)
    18             (Land Allocation - $25,000)
    19             (Design and Contingencies - $75,000)
    20         (5)  Windber Borough, South 22nd Street
    21             Bridge over Seese Run, Bridge
    22             Replacement                                   350,000
    23             (Base Construction Allocation -
    24             $250,000)
    25             (Land Allocation - $25,000)
    26             (Design and Contingencies - $75,000)
    27         (6)  Windber Borough, 24th Street Bridge
    28             over Seese Run, Bridge Replacement            350,000
    29             (Base Construction Allocation -
    30             $250,000)
    19970S0186B0698                 - 301 -

     1             (Land Allocation - $25,000)
     2             (Design and Contingencies - $75,000)
     3         (7)  Windber Borough, Village Street Bridge
     4             over Seese Run, Bridge Replacement            350,000
     5             (Base Construction Allocation -
     6             $250,000)
     7             (Land Allocation - $25,000)
     8             (Design and Contingencies - $75,000)
     9         (8)  Summit Township, Keystone Viaduct over
    10             SR 2006, CSX Mainline and Flaugherty
    11             Creek, Bridge Rehabilitation                  715,000
    12             (Base Construction Allocation -
    13             $663,000)
    14             (Design and Contingencies - $52,000)
    15     (b)  State Bridges
    16         (1)  SR 0160, SR 0160 over Tributary of
    17             Boones Run, Stoney Creek Township,
    18             Bridge Replacement                            580,000
    19             (Base Construction Allocation -
    20             $430,000)
    21             (Land Allocation - $25,000)
    22             (Design and Contingencies - $125,000)
    23         (2)  SR 0523, SR 0523 over Whites Creek,
    24             Addison Township, Bridge Replacement          690,000
    25             (Base Construction Allocation -
    26             $510,000)
    27             (Land Allocation - $50,000)
    28             (Design and Contingencies - $130,000)
    29         (3)  SR 1007, SR 1007 over Lambert Run,
    30             Stoney Creek Township, Bridge
    19970S0186B0698                 - 302 -

     1             Replacement                                   490,000
     2             (Base Construction Allocation -
     3             $355,000)
     4             (Land Allocation - $25,000)
     5             (Design and Contingencies - $110,000)
     6         (4)  SR 1017, SR 1017 over Breastwork Run,
     7             Allegheny Township, Bridge Replacement        650,000
     8             (Base Construction Allocation -
     9             $490,000)
    10             (Land Allocation - $25,000)
    11             (Design and Contingencies - $135,000)
    12         (5)  SR 1017, SR 1017 over Breastwork Run,
    13             Allegheny Township, Bridge Replacement        580,000
    14             (Base Construction Allocation -
    15             $440,000)
    16             (Land Allocation - $25,000)
    17             (Design and Contingencies - $135,000)
    18         (6)  SR 1018, SR 1018 over Beaverdam Run,
    19             Shade Township, Bridge Replacement            545,000
    20             (Base Construction Allocation -
    21             $400,000)
    22             (Land Allocation - $25,000)
    23             (Design and Contingencies - $120,000)
    24         (7)  SR 1018, SR 1018 over Beaverdam Run,
    25             Shade Township, Bridge Replacement            515,000
    26             (Base Construction Allocation -
    27             $375,000)
    28             (Land Allocation - $25,000)
    29             (Design and Contingencies - $115,000)
    30         (8)  SR 2005, SR 2005 over Elk Lick Creek,
    19970S0186B0698                 - 303 -

     1             Elk Lick Township, Bridge Replacement         520,000
     2             (Base Construction Allocation -
     3             $380,000)
     4             (Land Allocation - $25,000)
     5             (Design and Contingencies - $115,000)
     6         (9)  SR 4013, SR 4013 over North Branch of
     7             Quemahoning Creek, Lincoln Township,
     8             Bridge Replacement                            585,000
     9             (Base Construction Allocation -
    10             $435,000)
    11             (Land Allocation - $25,000)
    12             (Design and Contingencies - $125,000)
    13         (10)  SR 4019, SR 4019 over Quemahoning
    14             Creek, Quemahoning Township, Bridge
    15             Replacement                                   800,000
    16             (Base Construction Allocation -
    17             $625,000)
    18             (Land Allocation - $25,000)
    19             (Design and Contingencies - $150,000)
    20         (11)  SR 3039, SR 3039 over Allen Creek,
    21             Middlecreek Township, Bridge
    22             Replacement                                   200,000
    23             (Base Construction Allocation -
    24             $150,000)
    25             (Land Allocation - $5,000)
    26             (Design and Contingencies - $45,000)
    27         (12)  SR 3039, SR 3039 over Allen Creek,
    28             Middlecreek Township, Bridge
    29             Replacement                                   220,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 304 -

     1             $150,000)
     2             (Land Allocation - $10,000)
     3             (Design and Contingencies - $60,000)
     4         (13)  SR 4001, SR 4001 over Clear Run,
     5             Jefferson Township, Bridge Replacement        295,000
     6             (Base Construction Allocation -
     7             $200,000)
     8             (Land Allocation - $10,000)
     9             (Design and Contingencies - $85,000)
    10  Section 61.  Sullivan County.
    11     (a)  Local Bridges
    12         (1)  Forks Township, T-448, Old TR 87
    13             Bridge, County Bridge No.55 over Little
    14             Loyalsock Creek, Bridge Replacement           860,000
    15             (Base Construction Allocation -
    16             $700,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $150,000)
    19         (2)  Forks and Laporte Townships, T-346
    20             over Loyalsock Creek, Bridge
    21             Replacement                                   840,000
    22             (Base Construction Allocation -
    23             $730,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $100,000)
    26     (b)  State Bridges
    27         (1)  SR 0087, SR 0087 over Lick Run, Forks
    28             Township, Bridge Replacement                  635,000
    29             (Base Construction Allocation -
    30             $508,000)
    19970S0186B0698                 - 305 -

     1             (Land Allocation - $32,000)
     2             (Design and Contingencies - $95,000)
     3         (2)  SR 0087, SR 0087 over Little Loyalsock
     4             Creek, Cherry Township, Bridge
     5             Replacement                                   655,000
     6             (Base Construction Allocation -
     7             $524,000)
     8             (Land Allocation - $33,000)
     9             (Design and Contingencies - $98,000)
    10         (3)  SR 0154, SR 0154 over Black Water Run,
    11             Elkland Township, Bridge Replacement          194,000
    12             (Base Construction Allocation -
    13             $166,000)
    14             (Design and Contingencies - $28,000)
    15         (4)  SR 0154, SR 0154 over Kings Creek,
    16             Elkland Township, Bridge Replacement          404,000
    17             (Base Construction Allocation -
    18             $323,000)
    19             (Land Allocation - $20,000)
    20             (Design and Contingencies - $61,000)
    21         (5)  SR 1012, SR 1012 over Little Loyalsock
    22             Creek, Cherry Township, Bridge
    23             Replacement                                   260,000
    24             (Base Construction Allocation -
    25             $208,000)
    26             (Land Allocation - $13,000)
    27             (Design and Contingencies - $39,000)
    28  Section 62.  Susquehanna County.
    29     (a)  Local Bridges (Reserved)
    30     (b)  State Bridges
    19970S0186B0698                 - 306 -

     1         (1)  SR 0167, Owego Street Bridge over
     2             Branch of Fall Brook, Bridgewater
     3             Township, Bridge Replacement                  413,000
     4             (Base Construction Allocation -
     5             $342,000)
     6             (Land Allocation - $10,000)
     7             (Design and Contingencies - $61,000)
     8         (2)  SR 1016, Salt Lick Creek Bridge over
     9             Branch of Salt Lick Creek, New Milford
    10             Township, Bridge Replacement                  100,000
    11             (Base Construction Allocation -
    12             $86,000)
    13             (Land Allocation - $3,000)
    14             (Design and Contingencies - $11,000)
    15         (3)  SR 0081, Bridge over Trowbridge Creek,
    16             1 Mile South of the Pennsylvania and
    17             New York State Line, Great Bend
    18             Township, Bridge Replacement                  890,000
    19             (Base Construction Allocation -
    20             $700,000)
    21             (Land Allocation - $10,000)
    22             (Design and Contingencies - $180,000)
    23         (4)  SR 1017, Gulf Street Bridge, 0.5 Mile
    24             North of SR 1015, Lanesboro Borough,
    25             Bridge Replacement                            305,000
    26             (Base Construction Allocation -
    27             $220,000)
    28             (Land Allocation - $10,000)
    29             (Design and Contingencies - $75,000)
    30         (5)  SR 3003, Bridge over Transue Creek,
    19970S0186B0698                 - 307 -

     1             1.5 Miles South of SR 3005, Auburn
     2             Township, Bridge Painting                      60,000
     3             (Base Construction Allocation -
     4             $50,000)
     5             (Design and Contingencies - $10,000)
     6         (6)  SR 3006, Bridge over White Creek, 1.5
     7             Miles West of SR 3004, Springville
     8             Township, Bridge Painting                      70,000
     9             (Base Construction Allocation -
    10             $60,000)
    11             (Design and Contingencies - $10,000)
    12         (7)  SR 0011, Bridge over Salt Lick Creek,
    13             0.6 Mile North of TR 492, New Milford
    14             Borough, Bridge Replacement                   660,000
    15             (Base Construction Allocation -
    16             $510,000)
    17             (Land Allocation - $20,000)
    18             (Design and Contingencies - $130,000)
    19         (8)  SR 0367, Bridge over Tuscarora Creek,
    20             North of SR 3005, Auburn Township,
    21             Bridge Replacement                            330,000
    22             (Base Construction Allocation -
    23             $265,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $65,000)
    26         (9)  SR 1010, Bridge over Bedbug Creek,
    27             West of SR 1021, Oakland Township,
    28             Bridge Replacement                            325,000
    29             (Base Construction Allocation -
    30             $250,000)
    19970S0186B0698                 - 308 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $65,000)
     3         (10)  SR 1010, Bridge over Tributary of
     4             Susquehanna River, 2 Miles West of SR
     5             1021, Great Bend Township, Bridge
     6             Replacement                                   288,000
     7             (Base Construction Allocation -
     8             $220,000)
     9             (Land Allocation - $10,000)
    10             (Design and Contingencies - $58,000)
    11         (11)  SR 2046, Bridge over Branch of
    12             Tunkhannock Creek, East of TR 92,
    13             Gibson Township, Bridge Replacement           513,000
    14             (Base Construction Allocation -
    15             $400,000)
    16             (Land Allocation - $10,000)
    17             (Design and Contingencies - $103,000)
    18         (12)  SR 3017, Bridge over Thomas Creek,
    19             Southeast of TR 29, Springville
    20             Township, Bridge Replacement                  285,000
    21             (Base Construction Allocation -
    22             $220,000)
    23             (Land Allocation - $10,000)
    24             (Design and Contingencies - $50,000)
    25         (13)  State Bridges, Countywide Bridge Zone
    26             Painting, Bridge Painting                     370,000
    27             (Base Construction Allocation -
    28             $350,000)
    29             (Land Allocation - $10,000)
    30             (Design and Contingencies - $10,000)
    19970S0186B0698                 - 309 -

     1         (14)  SR 0858, Branch of Apolacon Creek,
     2             0.3 Mile North of SR 4013, Apolacon
     3             Township, Bridge Replacement                  220,000
     4             (Base Construction Allocation -
     5             $180,000)
     6             (Land Allocation - $10,000)
     7             (Design and Contingencies - $30,000)
     8         (15)  SR 1010, SR 1010 over Tributary of
     9             Susquehanna River, Great Bend Township,
    10             Bridge Replacement                            230,000
    11             (Base Construction Allocation -
    12             $190,000)
    13             (Land Allocation - $10,000)
    14             (Design and Contingencies - $30,000)
    15         (16)  SR 1010, SR 1010 over Bedbug Creek,
    16             Oakland Township, Bridge Replacement          270,000
    17             (Base Construction Allocation -
    18             $220,000)
    19             (Land Allocation - $10,000)
    20             (Design and Contingencies - $40,000)
    21         (17)  SR 2046, SR 2046 over Tunkhannock
    22             Creek, Gibson Township, Bridge
    23             Replacement                                   440,000
    24             (Base Construction Allocation -
    25             $370,000)
    26             (Land Allocation - $10,000)
    27             (Design and Contingencies - $60,000)
    28         (18)  SR 1011, Bridge over Hemlock Creek,
    29             0.2 Mile North of SR 1009, Harmony
    30             Township, Bridge Replacement                  330,000
    19970S0186B0698                 - 310 -

     1             (Base Construction Allocation -
     2             $280,000)
     3             (Land Allocation - $10,000)
     4             (Design and Contingencies - $40,000)
     5         (19)  SR 4002, Bridge over Choconut Creek,
     6             0.1 Mile East of TR 267, Choconut
     7             Township, Bridge Replacement                  290,000
     8             (Base Construction Allocation -
     9             $240,000)
    10             (Land Allocation - $10,000)
    11             (Design and Contingencies - $40,000)
    12         (20)  SR 3009, Bridge over White Creek, 1.8
    13             Miles North of County Line, Auburn
    14             Township, Bridge Replacement                  240,000
    15             (Base Construction Allocation -
    16             $200,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $30,000)
    19         (21)  SR 3023, Bridge over East Branch of
    20             Wyalusing Creek, 0.1 Mile South of TR
    21             706, Rush Township, Bridge Replacement
    22             and Intersection Realignment                1,520,000
    23             (Base Construction Allocation -
    24             $1,300,000)
    25             (Land Allocation - $20,000)
    26             (Design and Contingencies - $200,000)
    27         (22)  SR 4008, Bridge over Laurel Lake
    28             Creek, 1.7 Miles East of TR 167, Silver
    29             Lake Township, Bridge Replacement             430,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 311 -

     1             $360,000)
     2             (Land Allocation - $10,000)
     3             (Design and Contingencies - $60,000)
     4  Section 63.  Tioga County.
     5     (a)  Local Bridges
     6         (1)  Elkland Borough, North Buffalo Street
     7             over Camp Brook Creek, Bridge
     8             Replacement                                   510,000
     9             (Base Construction Allocation) -
    10             $360,000)
    11             (Land Allocation - $20,000)
    12             (Design and Contingencies - $130,000)
    13         (2)  Middlebury Township, T-658 (Monkey Run
    14             Road), Bridge over Tributary of Losey
    15             Creek, Bridge Replacement                     390,000
    16             (Base Construction Allocation -
    17             $250,000)
    18             (Land Allocation - $10,000)
    19             (Design and Contingencies - $130,000)
    20         (3)  Farmington Township, T-758 (Short Hole
    21             Road), Bridge over Thorn Bottom Creek,
    22             Bridge Replacement                            390,000
    23             (Base Construction Allocation -
    24             $250,000)
    25             (Land Allocation - $10,000)
    26             (Design and Contingencies - $130,000)
    27     (b)  State Bridges
    28         (1)  SR 0249, Losey Creek Bridge, South of
    29             SR 4017 in Village of Keeneyville,
    30             Middlebury Township, Bridge
    19970S0186B0698                 - 312 -

     1             Rehabilitation                                250,000
     2             (Base Construction Allocation -
     3             $210,000)
     4             (Land Allocation - $5,000)
     5             (Design and Contingencies - $35,000)
     6         (2)  SR 1002, Corey Creek Bridge over Corey
     7             Creek, Northeast of Mansfield, Bridge
     8             Replacement                                   346,000
     9             (Base Construction Allocation -
    10             $277,000)
    11             (Land Allocation - $17,000)
    12             (Design and Contingencies - $52,000)
    13         (3)  SR 3001, Kettle Creek Bridge, 11 Miles
    14             South of Watrous, Bridge Replacement          366,000
    15             (Base Construction Allocation -
    16             $293,000)
    17             (Land Allocation - $18,000)
    18             (Design and Contingencies - $55,000)
    19         (4)  SR 3023, Heise Run North Bridge, West
    20             of Wellsboro, Bridge Replacement              240,000
    21             (Base Construction Allocation -
    22             $192,000)
    23             (Land Allocation - $12,000)
    24             (Design and Contingencies - $36,000)
    25         (5)  SR 4017, Holden Creek Bridge No.1,
    26             Bridge Replacement                            584,000
    27             (Base Construction Allocation -
    28             $467,000)
    29             (Land Allocation - $29,000)
    30             (Design and Contingencies - $88,000)
    19970S0186B0698                 - 313 -

     1         (6)  SR 4024, Elkhorn Creek Bridge, West of
     2             Tioga Borough, Bridge Replacement             451,000
     3             (Base Construction Allocation -
     4             $401,000)
     5             (Land Allocation - $15,000)
     6             (Design and Contingencies - $35,000)
     7         (7)  SR 3007, Bridge over Stoney Fork
     8             Creek, Bridge Painting                        160,000
     9             (Base Construction Allocation -
    10             $150,000)
    11             (Design and Contingencies - $10,000)
    12         (8)  SR 4017, Bridge over Cowanesque River,
    13             Bridge Painting                               475,000
    14             (Base Construction Allocation -
    15             $465,000)
    16             (Design and Contingencies - $10,000)
    17         (9)  SR 0049, SR 0049 over Cowanesque
    18             River, Westfield Township, Bridge
    19             Replacement                                 1,802,000
    20             (Base Construction Allocation -
    21             $1,442,000)
    22             (Land Allocation - $90,000)
    23             (Design and Contingencies - $270,000)
    24         (10)  SR 0287, SR 0287 over Wellsboro
    25             Street - Conrail, Tioga Township,
    26             Bridge Replacement                          1,709,000
    27             (Base Construction Allocation -
    28             $1,367,000)
    29             (Land Allocation - $86,000)
    30             (Design and Contingencies - $256,000)
    19970S0186B0698                 - 314 -

     1         (11)  SR 0328, SR 0328 over Hammond Creek,
     2             Jackson Township, Bridge Replacement          256,000
     3             (Base Construction Allocation -
     4             $205,000)
     5             (Land Allocation - $13,000)
     6             (Design and Contingencies - $38,000)
     7         (12)  SR 0349, SR 0349 over Mill Creek,
     8             Clymer Township, Bridge Replacement         1,000,000
     9             (Base Construction Allocation -
    10             $800,000)
    11             (Land Allocation - $50,000)
    12             (Design and Contingencies - $150,000)
    13         (13)  SR 1030, SR 1030 over Conrail, Tioga
    14             Township, Bridge Replacement                  561,000
    15             (Base Construction Allocation -
    16             $449,000)
    17             (Land Allocation - $28,000)
    18             (Design and Contingencies - $84,000)
    19         (14)  SR 2017, SR 2017 over Mill Creek,
    20             Union Township, Bridge Replacement            584,000
    21             (Base Construction Allocation -
    22             $467,000)
    23             (Land Allocation - $27,000)
    24             (Design and Contingencies - $88,000)
    25         (15)  SR 4017, SR 4017 Bridge No.2 over
    26             Holden Creek, Osceola Township, Bridge
    27             Replacement                                   542,000
    28             (Base Construction Allocation -
    29             $434,000)
    30             (Land Allocation - $27,000)
    19970S0186B0698                 - 315 -

     1             (Design and Contingencies - $81,000)
     2         (16)  SR 0015, Mill Creek Bridge spanning
     3             Tioga Dam Impoundment at Confluence,
     4             Two-Lane Bridge Construction                6,875,000
     5             (Base Construction Allocation -
     6             $6,250,000)
     7             (Design and Contingencies - $625,000)
     8         (17)  PA 249, Bridge over Crooked Creek,
     9             Village of Little Marsh, Chatham
    10             Township, Bridge Replacement                1,250,000
    11             (Base Construction Allocation -
    12             $1,000,000)
    13             (Land Allocation - $50,000)
    14             (Design and Contingencies - $200,000)
    15  Section 64.  Union County.
    16     (a)  Local Bridges (Reserved)
    17     (b)  State Bridges
    18         (1)  SR 0192, Rapid Run Bridge II over
    19             Rapid Run, Lewis Township, Bridge
    20             Rehabilitation                                250,000
    21             (Base Construction Allocation -
    22             $200,000)
    23             (Land Allocation - $13,000)
    24             (Design and Contingencies - $37,000)
    25         (2)  SR 0192, Rapid Run Bridge I over Rapid
    26             Run, Lewis Township, Bridge
    27             Rehabilitation                                205,000
    28             (Base Construction Allocation -
    29             $164,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 316 -

     1             (Design and Contingencies - $31,000)
     2         (3)  SR 0044, Bridge over Spring Creek,
     3             Bridge Painting                               110,000
     4             (Base Construction Allocation -
     5             $100,000)
     6             (Design and Contingencies - $10,000)
     7         (4)  SR 1004, Bridge over Little Buffalo
     8             Creek, Bridge Painting                         75,000
     9             (Base Construction Allocation -
    10             $65,000)
    11             (Design and Contingencies - $10,000)
    12         (5)  SR 1012, Bridge over White Deer Hole
    13             Creek, Bridge Painting                        160,000
    14             (Base Construction Allocation -
    15             $150,000)
    16             (Design and Contingencies - $10,000)
    17         (6)  SR 0235, SR 0235 over Laurel Run,
    18             Hartley Township, Bridge Replacement        1,118,000
    19             (Base Construction Allocation -
    20             $894,000)
    21             (Land Allocation - $56,000)
    22             (Design and Contingencies - $168,000)
    23         (7)  SR 0235, SR 0235 over Buffalo Creek,
    24             Lewis Township, Bridge Replacement            395,000
    25             (Base Construction Allocation -
    26             $316,000)
    27             (Land Allocation - $20,000)
    28             (Design and Contingencies - $59,000)
    29         (8)  US 15, Bridge over White Deer Hole
    30             Creek, Village of Allenwood, Gregg
    19970S0186B0698                 - 317 -

     1             Township, Deck Replacement                  1,850,000
     2             (Base Construction Allocation -
     3             $1,500,000)
     4             (Land Allocation - $50,000)
     5             (Design and Contingencies - $300,000)
     6         (9)  US 15, Bridge over SR 1004, Village of
     7             West Milton, Kelly Township,
     8             Superstructure Replacement                  2,450,000
     9             (Base Construction Allocation -
    10             $2,000,000)
    11             (Land Allocation - $50,000)
    12             (Design and Contingencies - $400,000)
    13         (10)  US 15, Bridge over White Deer Creek,
    14             White Deer Township, Deck Replacement       2,430,000
    15             (Base Construction Allocation -
    16             $2,000,000)
    17             (Land Allocation - $30,000)
    18             (Design and Contingencies - $400,000)
    19         (11)  US 15, Bridge over SR 1010, White
    20             Deer Township, Deck Replacement             1,230,000
    21             (Base Construction Allocation -
    22             $1,000,000)
    23             (Land Allocation - $30,000)
    24             (Design and Contingencies - $200,000)
    25  Section 65.  Venango County.
    26     (a)  Local Bridges
    27         (1)  Richland Township, T-552 over Mill
    28             Creek, Bridge Replacement                     475,000
    29             (Base Construction Allocation -
    30             $355,000)
    19970S0186B0698                 - 318 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $110,000)
     3         (2)  Richland Township, T-361 over unnamed
     4             tributary of Mill Creek, Bridge
     5             Replacement                                   337,000
     6             (Base Construction Allocation -
     7             $242,000)
     8             (Land Allocation - $10,000)
     9             (Design and Contingencies - $85,000)
    10         (3)  Richland Township, T-377 over Sage
    11             Run, Bridge Replacement                       385,000
    12             (Base Construction Allocation -
    13             $290,000)
    14             (Land Allocation - $10,000)
    15             (Design and Contingencies - $85,000)
    16         (4)  Pinegrove Township, T-628 over East
    17             Sandy Creek, Bridge Replacement               363,000
    18             (Base Construction Allocation -
    19             $307,000)
    20             (Land Allocation - $6,000)
    21             (Design and Contingencies - $50,000)
    22         (5)  Cranberry Township, T-679 over Branch
    23             of Sage Run, Bridge Replacement               106,000
    24             (Base Construction Allocation -
    25             $100,000)
    26             (Land Allocation - $1,000)
    27             (Design and Contingencies - $5,000)
    28         (6)  Oakland Township, T-567 over Branch of
    29             Two Mile Run, Bridge Replacement              106,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 319 -

     1             $100,000)
     2             (Land Allocation - $1,000)
     3             (Design and Contingencies - $5,000)
     4         (7)  Rockland Township, T-512 over East
     5             Sandy Creek, Bridge Replacement               360,000
     6             (Base Construction Allocation -
     7             $300,000)
     8             (Land Allocation - $10,000)
     9             (Design and Contingencies - $50,000)
    10         (8)  Pinegrove Township, T-628 over East
    11             Sandy Creek, Bridge Replacement               510,000
    12             (Base Construction Allocation -
    13             $400,000)
    14             (Land Allocation - $10,000)
    15             (Design and Contingencies - $100,000)
    16     (b)  State Bridges
    17         (1)  SR 4001, SR 4001 over Two Mile Run
    18             West Branch, Sugarcreek Borough, Bridge
    19             Replacement                                   205,000
    20             (Base Construction Allocation -
    21             $150,000)
    22             (Land Allocation - $5,000)
    23             (Design and Contingencies - $50,000)
    24         (2)  SR 0227, SR 0227 over Cherry Run,
    25             Cornplanter Township, Bridge
    26             Replacement                                   280,000
    27             (Base Construction Allocation -
    28             $200,000)
    29             (Land Allocation - $20,000)
    30             (Design and Contingencies - $60,000)
    19970S0186B0698                 - 320 -

     1         (3)  SR 0322, SR 0322 over Halls Run,
     2             Cranberry Township, Bridge Replacement      2,600,000
     3             (Base Construction Allocation -
     4             $2,000,000)
     5             (Land Allocation - $100,000)
     6             (Design and Contingencies - $500,000)
     7         (4)  SR 3009, SR 3009 over I-80, Scrubgrass
     8             Township, Bridge Replacement                  810,000
     9             (Base Construction Allocation -
    10             $700,000)
    11             (Land Allocation - $10,000)
    12             (Design and Contingencies - $100,000)
    13         (5)  SR 3017, SR 3017 over Warden Run,
    14             Canal Township, Bridge Replacement            920,000
    15             (Base Construction Allocation -
    16             $800,000)
    17             (Land Allocation - $20,000)
    18             (Design and Contingencies - $100,000)
    19         (6)  SR 0038, SR 0038 over Pine Run,
    20             Richland Township, Bridge
    21             Rehabilitation                                110,000
    22             (Base Construction Allocation -
    23             $100,000)
    24             (Design and Contingencies - $10,000)
    25         (7)  SR 3025, SR 3025 over Hays Run, City
    26             of Oil City, Bridge Replacement               340,000
    27             (Base Construction Allocation -
    28             $300,000)
    29             (Land Allocation - $5,000)
    30             (Design and Contingencies - $35,000)
    19970S0186B0698                 - 321 -

     1  Section 66.  Warren County.
     2     (a)  Local Bridges (Reserved)
     3     (b)  State Bridges
     4         (1)  SR 0006, SR 0006 over Wintroth Run,
     5             Brokenstraw Township, Bridge
     6             Replacement                                   260,000
     7             (Base Construction Allocation -
     8             $180,000)
     9             (Land Allocation - $20,000)
    10             (Design and Contingencies - $60,000)
    11         (2)  SR 0006, SR 0006 over Six Mile Run,
    12             Mead Township, Bridge Replacement             320,000
    13             (Base Construction Allocation -
    14             $250,000)
    15             (Land Allocation - $10,000)
    16             (Design and Contingencies - $60,000)
    17         (3)  SR 0027, SR 0027 over Pine Creek,
    18             Southwest Township, Bridge Replacement        800,000
    19             (Base Construction Allocation -
    20             $580,000)
    21             (Land Allocation - $20,000)
    22             (Design and Contingencies - $200,000)
    23         (4)  SR 0027, SR 0027 over Hazeltine Hollow
    24             Run, Brokenstraw Township, Bridge
    25             Replacement                                   310,000
    26             (Base Construction Allocation -
    27             $210,000)
    28             (Land Allocation - $20,000)
    29             (Design and Contingencies - $80,000)
    30         (5)  SR 0062, SR 0062 over Bully Run,
    19970S0186B0698                 - 322 -

     1             Watson Township, Bridge Replacement           300,000
     2             (Base Construction Allocation -
     3             $230,000)
     4             (Land Allocation - $20,000)
     5             (Design and Contingencies - $50,000)
     6         (6)  SR 0957, SR 0957 over Little
     7             Brokenstraw Creek, Freehold Township,
     8             Bridge Replacement                            800,000
     9             (Base Construction Allocation -
    10             $620,000)
    11             (Land Allocation - $20,000)
    12             (Design and Contingencies - $160,000)
    13         (7)  SR 3009, SR 3009 over Tidioute Creek,
    14             Deerfield Township, Bridge Replacement        470,000
    15             (Base Construction Allocation -
    16             $400,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $60,000)
    19         (8)  SR 4013, SR 4013 over Mathews Run,
    20             Youngsville Borough, Bridge
    21             Replacement                                   430,000
    22             (Base Construction Allocation -
    23             $360,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $60,000)
    26         (9)  SR 4021, SR 4021 over Brands Run,
    27             Sugar Grove Borough, Bridge
    28             Replacement                                   240,000
    29             (Base Construction Allocation -
    30             $180,000)
    19970S0186B0698                 - 323 -

     1             (Land Allocation - $20,000)
     2             (Design and Contingencies - $40,000)
     3         (10)  SR 0027, Bridge over Hazeltine Hollow
     4             Run, Brokenstraw Township, Bridge
     5             Replacement                                   500,000
     6             (Base Construction Allocation -
     7             $450,000)
     8             (Design and Contingencies - $50,000)
     9         (11)  SR 0062, US 62, Bridge over Bully
    10             Run, Watson Township, Bridge
    11             Replacement                                   410,000
    12             (Base Construction Allocation -
    13             $370,000)
    14             (Design and Contingencies - $40,000)
    15         (12)  SR 3009, Tidioute Creek Road Bridge
    16             No.5 over Tidioute Creek, Triumph
    17             Township, Bridge Replacement                  290,000
    18             (Base Construction Allocation -
    19             $270,000)
    20             (Design and Contingencies - $20,000)
    21  Section 67.  Washington County.
    22     (a)  Local Bridges
    23         (1)  Burgettstown Borough, Raccoon Bridge
    24             No.23 over Raccoon Creek, Bridge
    25             Rehabilitation                                433,000
    26             (Base Construction Allocation -
    27             $313,000)
    28             (Land Allocation - $20,000)
    29             (Design and Contingencies - $100,000)
    30         (2)  Chartiers Township, Allison Hollow
    19970S0186B0698                 - 324 -

     1             Road, One-Lane Bridge, Bridge
     2             Replacement                                   195,000
     3             (Base Construction Allocation -
     4             $150,000)
     5             (Land Allocation - $5,000)
     6             (Design and Contingencies - $40,000)
     7         (3)  Chartiers Township, Allison Hollow
     8             Road, One-Lane Bridge, Bridge
     9             Replacement                                   195,000
    10             (Base Construction Allocation -
    11             $150,000)
    12             (Land Allocation - $5,000)
    13             (Design and Contingencies - $40,000)
    14         (4)  Chartiers Township, McGovern Road
    15             Bridge, Bridge Replacement                    145,000
    16             (Base Construction Allocation -
    17             $100,000)
    18             (Land Allocation - $5,000)
    19             (Design and Contingencies - $40,000)
    20         (5)  North Strabane Township, T-643, Galley
    21             Road Bridge over Little Chartiers
    22             Creek, Bridge Replacement                     570,000
    23             (Base Construction Allocation -
    24             $450,000)
    25             (Land Allocation - $20,000)
    26             (Design and Contingencies - $100,000)
    27         (6)  Donegal Township, T-541, Lindsay
    28             Bridge over Buck Run, Bridge
    29             Replacement                                   285,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 325 -

     1             $255,000)
     2             (Design and Contingencies - $30,000)
     3         (7)  Donegal Township, T-423, Mays Bridge
     4             over Middle Wheeling Creek, Bridge
     5             Replacement                                   245,000
     6             (Base Construction Allocation -
     7             $215,000)
     8             (Design and Contingencies - $30,000)
     9         (8)  Independence Township, T-649, Cummins
    10             Bridge over Sugar Camp Run, Bridge
    11             Replacement                                   330,000
    12             (Base Construction Allocation -
    13             $300,000)
    14             (Design and Contingencies - $30,000)
    15         (9)  Mount Pleasant Township, T-749, Sabo
    16             Road over Westland Run, Bridge
    17             Replacement                                    25,000
    18             (Base Construction Allocation -
    19             $20,000)
    20             (Design and Contingencies - $5,000)
    21         (10)  Mount Pleasant Township, T-606,
    22             Primrose Road over Millers Run, Bridge
    23             Replacement                                    25,000
    24             (Base Construction Allocation -
    25             $20,000)
    26             (Design and Contingencies - $5,000)
    27         (11)  Mount Pleasant Township, T-493,
    28             Meriage Street over Robinson Run
    29             Tributary, Bridge Replacement                  25,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 326 -

     1             $20,000)
     2             (Design and Contingencies - $5,000)
     3         (12)  North Bethlehem Township, T-445,
     4             Dague Bridge over Pigeon Creek, Bridge
     5             Replacement                                   250,000
     6             (Base Construction Allocation -
     7             $220,000)
     8             (Design and Contingencies - $30,000)
     9         (13)  North Franklin Township, T-526, Cario
    10             Drive over Unnamed Tributary of Catfish
    11             Creek, Bridge Replacement                      46,000
    12             (Base Construction Allocation -
    13             $42,000)
    14             (Design and Contingencies - $4,000)
    15         (14)  Nottingham Township, T-782, Sundust
    16             Road Culvert, 35 Feet North of
    17             Intersection with SR 1059, Bridge
    18             Replacement                                   101,000
    19             (Base Construction Allocation -
    20             $91,000)
    21             (Design and Contingencies - $10,000)
    22         (15)  Nottingham Township, T-828, Barr
    23             Bridge over Mingo Creek, Bridge
    24             Replacement                                   350,000
    25             (Base Construction Allocation -
    26             $310,000)
    27             (Design and Contingencies - $40,000)
    28         (16)  Robinson Township, T-500, Chamberlain
    29             Bridge over Chamberlain Run, Bridge
    30             Replacement                                   285,000
    19970S0186B0698                 - 327 -

     1             (Base Construction Allocation -
     2             $255,000)
     3             (Design and Contingencies - $30,000)
     4         (17)  Smith Township, T-843, Dunbar Bridge
     5             over Raccoon Creek, Bridge Replacement        285,000
     6             (Base Construction Allocation -
     7             $255,000)
     8             (Design and Contingencies - $30,000)
     9         (18)  City of Washington, Hanna Street
    10             Bridge over Catfish Creek, Bridge
    11             Replacement                                    40,000
    12             (Base Construction Allocation -
    13             $30,000)
    14             (Design and Contingencies - $10,000)
    15         (19)  City of Washington, Rosewood Avenue
    16             Bridge over Catfish Creek, Bridge
    17             Replacement                                    40,000
    18             (Base Construction Allocation -
    19             $30,000)
    20             (Design and Contingencies - $10,000)
    21         (20)  West Pike Run Township, T-840, Suzy
    22             Lane over Pike Run Creek, Bridge
    23             Replacement                                   230,000
    24             (Base Construction Allocation -
    25             $210,000)
    26             (Design and Contingencies - $20,000)
    27         (21)  California Borough, Daisytown Bridge
    28             over Pike Run, Bridge Replacement             925,000
    29             (Base Construction Allocation -
    30             $700,000)
    19970S0186B0698                 - 328 -

     1             (Land Allocation - $50,000)
     2             (Design and Contingencies - $175,000)
     3         (22)  Coal Center Borough, Water Street
     4             Bridge over Pike Run, Bridge
     5             Replacement                                 1,588,000
     6             (Base Construction Allocation -
     7             $1,288,000)
     8             (Land Allocation - $50,000)
     9             (Design and Contingencies - $250,000)
    10         (23)  West Pike Run Township, T-948 over
    11             Pike Run, Bridge Replacement                1,075,000
    12             (Base Construction Allocation -
    13             $850,000)
    14             (Land Allocation - $50,0000)
    15             (Design and Contingencies - $175,000)
    16         (24)  Midway Borough, North Avenue over
    17             Robinson Run Creek, Bridge Replacement         95,000
    18             (Base Construction Allocation -
    19             $55,000)
    20             (Land Allocation - $20,000)
    21             (Design and Contingencies - $20,000)
    22         (25)  Canonsburg Borough, Adams Street over
    23             Brush Run, Bridge Replacement                 176,000
    24             (Base Construction Allocation -
    25             $150,000)
    26             (Land Allocation - $1,000)
    27             (Design and Contingencies - $25,000)
    28         (26)  East Finley Township, T-375, County
    29             Bridge No. 32 over Templeton Fork,
    30             Bridge Replacement                            355,000
    19970S0186B0698                 - 329 -

     1             (Base Construction Allocation -
     2             $300,000)
     3             (Land Allocation - $5,000)
     4             (Design and Contingencies - $50,000)
     5     (b)  State Bridges
     6         (1)  SR 0018, Bridge over Abandoned
     7             Railroad, City of Washington, Bridge
     8             Replacement                                   650,000
     9             (Base Construction Allocation -
    10             $500,000)
    11             (Land Allocation - $25,000)
    12             (Design and Contingencies - $125,000)
    13         (2)  SR 0019, Bridge over Chartiers Creek,
    14             North Strabane and Peters Townships,
    15             Bridge Painting                               161,000
    16             (Base Construction Allocation -
    17             $156,000)
    18             (Design and Contingencies - $5,000)
    19         (3)  SR 0070, I-70 Westbound Bridge over SR
    20             3009, Buffalo Township, Bridge
    21             Painting                                      148,000
    22             (Base Construction Allocation -
    23             $143,000)
    24             (Design and Contingencies - $5,000)
    25         (4)  SR 0070, I-70 Eastbound Bridge over SR
    26             3009, Buffalo Township, Bridge
    27             Painting                                      163,000
    28             (Base Construction Allocation -
    29             $158,000)
    30             (Design and Contingencies - $5,000)
    19970S0186B0698                 - 330 -

     1         (5)  SR 0070, I-70 Bridge over 8th Street,
     2             Donegal Township, Bridge Replacement        2,486,000
     3             (Base Construction Allocation -
     4             $2,211,000)
     5             (Land Allocation - $25,000)
     6             (Design and Contingencies - $250,000)
     7         (6)  SR 0070, I-70 Bridge over Turnback
     8             Road, South Strabane Township, Bridge
     9             Rehabilitation                                990,000
    10             (Base Construction Allocation -
    11             $750,000)
    12             (Land Allocation - $40,000)
    13             (Design and Contingencies - $200,000)
    14         (7)  SR 0070, I-70 Bridge over SR 0519,
    15             Somerset Township, Bridge
    16             Rehabilitation                              2,000,000
    17             (Base Construction Allocation -
    18             $1,720,000)
    19             (Land Allocation - $40,000)
    20             (Design and Contingencies - $240,000)
    21         (8)  SR 0070, I-70 Bridge over SR 2017,
    22             Somerset Township, Bridge
    23             Rehabilitation                              1,105,000
    24             (Base Construction Allocation -
    25             $865,000)
    26             (Land Allocation - $40,000)
    27             (Design and Contingencies - $200,000)
    28         (9)  SR 0088, Charleroi Bridge over Maple
    29             Creek, Charleroi and Speers Boroughs,
    30             Bridge Replacement                            725,000
    19970S0186B0698                 - 331 -

     1             (Base Construction Allocation -
     2             $500,000)
     3             (Land Allocation - $25,000)
     4             (Design and Contingencies - $200,000)
     5         (10)  SR 0088, Bridge over Peters Creek,
     6             Finleyville Borough, Bridge Painting           65,000
     7             (Base Construction Allocation -
     8             $65,000)
     9         (11)  SR 0917, Pigeon Creek Bridge over
    10             Branch of Pigeon Creek, Bentleyville
    11             Borough, Bridge Replacement                   570,000
    12             (Base Construction Allocation -
    13             $370,000)
    14             (Land Allocation - $25,000)
    15             (Design and Contingencies - $175,000)
    16         (12)  SR 1005, Bridge over Millers Run,
    17             Cecil Township, Bridge Painting                75,000
    18             (Base Construction Allocation -
    19             $75,000)
    20         (13)  SR 1022, Donora Webster Bridge over
    21             Monongahela River and Conrail, Donora
    22             Borough, Bridge Replacement                20,000,000
    23             (Base Construction Allocation -
    24             $15,000,000)
    25             (Land Allocation - $3,000,000)
    26             (Design and Contingencies - $2,000,000)
    27         (14)  SR 1077, Donora-Monessen Bridge over
    28             Monongahela River, PA 837 and 906 and
    29             Railroad, Donora Borough, Bridge
    30             Painting                                    1,000,000
    19970S0186B0698                 - 332 -

     1             (Base Construction Allocation -
     2             $1,000,000)
     3         (15)  SR 2005, Sowers Run Bridge over
     4             Sowers Run, Amwell Township, Bridge
     5             Replacement                                   435,000
     6             (Base Construction Allocation -
     7             $235,000)
     8             (Land Allocation - $25,000)
     9             (Design and Contingencies - $175,000)
    10         (16)  SR 2011, Bridge over Branch of Little
    11             Tenmile Creek, West Bethlehem Township,
    12             Bridge Replacement                            460,000
    13             (Base Construction Allocation -
    14             $260,000)
    15             (Land Allocation - $25,000)
    16             (Design and Contingencies - $175,000)
    17         (17)  SR 2030, Gorby's Bridge II over Gorby
    18             Run, California Borough, Bridge
    19             Rehabilitation                                300,000
    20             (Base Construction Allocation -
    21             $300,000)
    22         (18)  SR 2037, Maple Creek Bridge over
    23             Branch of Maple Creek, Fallowfield
    24             Township, Bridge Replacement                  486,000
    25             (Base Construction Allocation -
    26             $286,000)
    27             (Land Allocation - $25,000)
    28             (Design and Contingencies - $175,000)
    29         (19)  SR 3009, Buffalo Arch Bridge over
    30             Branch of Buffalo Creek and Railroad,
    19970S0186B0698                 - 333 -

     1             Buffalo Township, Bridge Replacement          535,000
     2             (Base Construction Allocation -
     3             $300,000)
     4             (Land Allocation - $10,000)
     5             (Design and Contingencies - $225,000)
     6         (20)  SR 4015, Bridge over Cherry Run,
     7             Mount Pleasant Township, Bridge
     8             Painting                                       53,000
     9             (Base Construction Allocation -
    10             $51,000)
    11             (Design and Contingencies - $2,000)
    12         (21)  SR 4022, Chartiers Creek Bridge No.2
    13             over Branch of Chartiers Creek, Canton
    14             Township, Bridge Replacement                  415,000
    15             (Base Construction Allocation -
    16             $215,000)
    17             (Land Allocation - $25,000)
    18             (Design and Contingencies - $175,000)
    19         (22)  SR 4022, Chartiers Creek Bridge No.1
    20             over Branch of Chartiers Creek, Canton
    21             Township, Bridge Replacement                  405,000
    22             (Base Construction Allocation -
    23             $205,000)
    24             (Land Allocation - $25,000)
    25             (Design and Contingencies - $175,000)
    26         (23)  SR 2034, SR 2034 over Branch of Pike
    27             Run, West Pike Run Township, Bridge
    28             Replacement                                   438,000
    29             (Base Construction Allocation -
    30             $313,000)
    19970S0186B0698                 - 334 -

     1             (Land Allocation - $25,000)
     2             (Design and Contingencies - $100,000)
     3         (24)  SR 2079, SR 2079 over Pike Run, West
     4             Pike Run Township, Bridge Replacement         988,000
     5             (Base Construction Allocation -
     6             $788,000)
     7             (Land Allocation - $50,000)
     8             (Design and Contingencies - $150,000)
     9         (25)  SR 2030, Bridge No.1 over Gorby Run,
    10             California Borough, Bridge Replacement        430,000
    11             (Base Construction Allocation -
    12             $330,000)
    13             (Design and Contingencies - $100,000)
    14  Section 68.  Wayne County.
    15     (a)  Local Bridges
    16         (1)  Honesdale Borough, Old Willow Avenue,
    17             Bridge over Corley Brook at
    18             Intersection of TR 6, Bridge
    19             Replacement                                   410,000
    20             (Base Construction Allocation -
    21             $350,000)
    22             (Land Allocation - $10,000)
    23             (Design and Contingencies - $50,000)
    24     (b)  State Bridges
    25         (1)  SR 0371, Cochecton Bridge No.6 over
    26             Delaware River, Damascus Township,
    27             Bridge Rehabilitation                       1,050,000
    28             (Base Construction Allocation -
    29             $950,000)
    30             (Design and Contingencies - $100,000)
    19970S0186B0698                 - 335 -

     1         (2)  SR 0380, I-380 Bridge over Lehigh
     2             River, Lehigh Township, Bridge
     3             Rehabilitation                                284,000
     4             (Base Construction Allocation -
     5             $244,000)
     6             (Design and Contingencies - $40,000)
     7         (3)  SR 4009, Quarry Bridge over Dyberry
     8             Creek, Dyberry Township, Bridge
     9             Replacement                                   660,000
    10             (Base Construction Allocation -
    11             $500,000)
    12             (Land Allocation - $10,000)
    13             (Design and Contingencies - $150,000)
    14         (4)  SR 0371, Bridge No.6, Damascus
    15             Township, Bridge Painting                   2,200,000
    16             (Base Construction Allocation -
    17             $2,000,000)
    18             (Design and Contingencies - $200,000)
    19         (5)  SR 1020, Bridge No.7 over Delaware
    20             River, Damascus Township, Bridge
    21             Painting                                    3,300,000
    22             (Base Construction Allocation -
    23             $3,000,000)
    24             (Design and Contingencies - $300,000)
    25         (6)  SR 1004, Bridge over Outlet of Beach
    26             Lake, Intersection of SR 1011, Berlin
    27             Township, Bridge Replacement                  345,000
    28             (Base Construction Allocation -
    29             $265,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 336 -

     1             (Design and Contingencies - $70,000)
     2         (7)  SR 3028, Bridge over TR 191, East of
     3             SR 3031, Cherry Ridge Township, Bridge
     4             Replacement                                   450,000
     5             (Base Construction Allocation -
     6             $350,000)
     7             (Land Allocation - $10,000)
     8             (Design and Contingencies - $90,000)
     9         (8)  State Bridges, Countywide Bridge Zone
    10             Painting, Bridge Painting                     370,000
    11             (Base Construction Allocation -
    12             $350,000)
    13             (Land Allocation - $10,000)
    14             (Design and Contingencies - $10,000)
    15         (9)  SR 1004, SR 1004 over Outlet of Beach
    16             Lake, Berlin Township, Bridge
    17             Replacement                                   260,000
    18             (Base Construction Allocation -
    19             $220,000)
    20             (Land Allocation - $10,000)
    21             (Design and Contingencies - $30,000)
    22         (10)  SR 3028, SR 3028 over TR 191, Cherry
    23             Ridge Township, Bridge Replacement            400,000
    24             (Base Construction Allocation -
    25             $340,000)
    26             (Land Allocation - $10,000)
    27             (Design and Contingencies - $50,000)
    28         (11)  SR 0371, Bridge No.1 over Dyberry
    29             Creek at Junction of SR 1023, Lebanon
    30             Township, Bridge Replacement                  400,000
    19970S0186B0698                 - 337 -

     1             (Base Construction Allocation -
     2             $340,000)
     3             (Land Allocation - $10,000)
     4             (Design and Contingencies - $50,000)
     5         (12)  SR 0371, Bridge No.5 over Beaver Dam
     6             Creek, 0.1 Mile West of SR 1031,
     7             Damascus Township, Bridge Replacement         470,000
     8             (Base Construction Allocation -
     9             $400,000)
    10             (Land Allocation - $10,000)
    11             (Design and Contingencies - $60,000)
    12         (13)  SR 3006, Bridge No.3 over Ariel
    13             Creek, 0.6 Mile North of SR 3008, Salem
    14             Township, Bridge Replacement                  470,000
    15             (Base Construction Allocation -
    16             $400,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $60,000)
    19         (14)  SR 4014, Bridge No.4 over Balls
    20             Creek, 0.5 Mile East of SR 4037, Scott
    21             Township, Bridge Replacement                  380,000
    22             (Base Construction Allocation -
    23             $320,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $50,000)
    26         (15)  SR 0348, Bridge over Jones Creek, 0.1
    27             Mile West of SR 3019, Salem Township,
    28             Bridge Replacement                            470,000
    29             (Base Construction Allocation -
    30             $400,000)
    19970S0186B0698                 - 338 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $60,000)
     3         (16)  SR 4043, Bridge over Branch of Oquaga
     4             Creek, 1.5 Miles West of SR 4037, Scott
     5             Township, Bridge Replacement                  240,000
     6             (Base Construction Allocation -
     7             $200,000)
     8             (Land Allocation - $10,000)
     9             (Design and Contingencies - $30,000)
    10         (17)  SR 1007, Bridge over Branch of Boyd's
    11             Creek, 0.5 Mile East of SR 1019,
    12             Damascus Township, Bridge Replacement         310,000
    13             (Base Construction Allocation -
    14             $260,000)
    15             (Land Allocation - $10,000)
    16             (Design and Contingencies - $40,000)
    17  Section 69.  Westmoreland County.
    18     (a)  Local Bridges
    19         (1)  Hempfield Township, Airport Hill Road
    20             Bridge over Slate Creek, Bridge
    21             Replacement                                   350,000
    22             (Base Construction Allocation -
    23             $280,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $60,000)
    26         (2)  Hempfield Township, Sweitzer Road
    27             Bridge over Sewickley Creek, Bridge
    28             Replacement                                   975,000
    29             (Base Construction Allocation -
    30             $800,000)
    19970S0186B0698                 - 339 -

     1             (Land Allocation - $15,000)
     2             (Design and Contingencies - $160,000)
     3         (3)  Hempfield Township, Ladysmith Road
     4             Bridge over Little Sewickley Creek,
     5             Bridge Replacement                            610,000  <--
     6             (Base Construction Allocation -
     7             $500,000)
     8             (Land Allocation - $10,000)
     9             (Design and Contingencies - $100,000)
    10             BRIDGE REPLACEMENT                            813,000  <--
    11             (BASE CONSTRUCTION ALLOCATION -
    12             $613,000)
    13             (LAND ALLOCATION - $50,000)
    14             (DESIGN AND CONTINGENCIES - $150,000)
    15         (4)  Hempfield Township, Old Route 30
    16             Bridge over Slate Creek, Bridge
    17             Replacement                                   370,000
    18             (Base Construction Allocation -
    19             $300,000)
    20             (Land Allocation - $10,000)
    21             (Design and Contingencies - $60,000)
    22         (5)  Hempfield Township, Old Route 119
    23             Bridge over Tributary of Jacks Run,
    24             Bridge Replacement                            400,000  <--
    25             (Base Construction Allocation -
    26             $280,000)
    27             (Land Allocation - $20,000)
    28             (Design and Contingencies - $100,000)
    29             BRIDGE REPLACEMENT                            428,000  <--
    30             (BASE CONSTRUCTION ALLOCATION -
    19970S0186B0698                 - 340 -

     1             $288,000)
     2             (LAND ALLOCATION - $15,000)
     3             (DESIGN AND CONTINGENCIES - $125,000)
     4         (6)  Jeanette City, 6th Street Bridge over
     5             Brush Creek, Bridge Replacement               460,000
     6             (Base Construction Allocation -
     7             $340,000)
     8             (Land Allocation - $20,000)
     9             (Design and Contingencies - $100,000)
    10         (7)  Ligonier Township, T-605 Bridge over
    11             Two Mile Run, Bridge Replacement              320,000
    12             (Base Construction Allocation -
    13             $200,000)
    14             (Land Allocation - $20,000)
    15             (Design and Contingencies - $100,000)
    16         (8)  Ligonier Township, T-617, Bridge over
    17             Mill Run, Bridge Replacement                  310,000
    18             (Base Construction Allocation -
    19             $190,000)
    20             (Land Allocation - $20,000)
    21             (Design and Contingencies - $100,000)
    22         (9)  Hempfield Township, Possum Hollow Road
    23             Bridge over Tributary of Little
    24             Sewickley Creek, Bridge Replacement           300,000  <--
    25             (Base Construction Allocation -
    26             $180,000)
    27             (Land Allocation - $20,000)
    28             (Design and Contingencies - $100,000)
    29             SEWICKLEY CREEK, BRIDGE REPLACEMENT           428,000  <--
    30             (BASE CONSTRUCTION ALLOCATION -
    19970S0186B0698                 - 341 -

     1             $288,000)
     2             (LAND ALLOCATION - $15,000)
     3             (DESIGN AND CONTINGENCIES - $125,000)
     4         (10)  South Huntington Township, T-390,
     5             Williams Road Bridge, Bridge
     6             Replacement                                   125,000
     7             (Base Construction Allocation -
     8             $100,000)
     9             (Land Allocation - $5,000)
    10             (Design and Contingencies - $20,000)
    11         (11)  South Huntington Township, T-562,
    12             J.D. Smith Road Bridge, Bridge
    13             Replacement                                   155,000
    14             (Base Construction Allocation -
    15             $125,000)
    16             (Land Allocation - $5,000)
    17             (Design and Contingencies - $25,000)
    18         (12)  South Huntington Township, T-386,
    19             Bridge No. 1, Mount Etna Road Bridge,
    20             Bridge Replacement                            145,000
    21             (Base Construction Allocation -
    22             $115,000)
    23             (Land Allocation - $5,000)
    24             (Design and Contingencies - $25,000)
    25         (13)  South Huntington Township, T-386,
    26             Bridge No.2, Mount Etna Road at Remo
    27             Road, Bridge Replacement                      135,000
    28             (Base Construction Allocation -
    29             $110,000)
    30             (Land Allocation - $5,000)
    19970S0186B0698                 - 342 -

     1             (Design and Contingencies - $20,000)
     2         (14)  South Huntington Township, T-385,
     3             Commer Road Bridge, Bridge Replacement        150,000
     4             (Base Construction Allocation -
     5             $120,000)
     6             (Land Allocation - $5,000)
     7             (Design and Contingencies - $25,000)
     8         (15)  Washington Township, T-979, Pleasant
     9             View Road Bridge over Beaver Run,
    10             Bridge Replacement                            385,000
    11             (Base Construction Allocation -
    12             $265,000)
    13             (Land Allocation - $20,000)
    14             (Design and Contingencies - $100,000)
    15         (16)  Derry Township, T-924, Bridge over
    16             Union Run, Bridge Replacement                 578,000
    17             (Base Construction Allocation -
    18             $463,000)
    19             (Land Allocation - $15,000)
    20             (Design and Contingencies - $100,000)
    21         (17)  Derry Township, T-937, Bridge over
    22             Stony Run, Bridge Replacement                 553,000
    23             (Base Construction Allocation -
    24             $438,000)
    25             (Land Allocation - $15,000)
    26             (Design and Contingencies - $100,000)
    27         (18)  Derry Township, T-941, Bridge over
    28             Stony Run, Bridge Replacement                 590,000
    29             (Base Construction Allocation -
    30             $475,000)
    19970S0186B0698                 - 343 -

     1             (Land Allocation - $15,000)
     2             (Design and Contingencies - $100,000)
     3         (19)  Donegal Township, T-916, Bridge over
     4             Indian Creek, Bridge Replacement              465,000
     5             (Base Construction Allocation -
     6             $350,000)
     7             (Land Allocation - $15,000)
     8             (Design and Contingencies - $100,000)
     9         (20)  Donegal Township, T-880, Bridge over
    10             Four Mile Run, Bridge No.3, Bridge
    11             Replacement                                   415,000
    12             (Base Construction Allocation -
    13             $300,000)
    14             (Land Allocation - $15,000)
    15             (Design and Contingencies - $100,000)
    16         (21)  Donegal Township, T-880, Bridge over
    17             Four Mile Run, Bridge No.5, Bridge
    18             Replacement                                   415,000
    19             (Base Construction Allocation -
    20             $300,000)
    21             (Land Allocation - $15,000)
    22             (Design and Contingencies - $100,000)
    23         (22)  Fairfield Township, T-739, Berkey's
    24             Bridge over Unnamed Tributary, Bridge
    25             Replacement                                   200,000
    26             (Base Construction Allocation -
    27             $170,000)
    28             (Land Allocation - $10,000)
    29             (Design and Contingencies - $20,000)
    30         (23)  Fairfield Township, T-847, Bailey's
    19970S0186B0698                 - 344 -

     1             Bridge over Hendricks Run, Bridge
     2             Replacement                                   200,000
     3             (Base Construction Allocation -
     4             $170,000)
     5             (Land Allocation - $10,000)
     6             (Design and Contingencies - $20,000)
     7         (24)  Fairfield Township, T-847, Toby
     8             Bridge over Unnamed Tributary, Bridge
     9             Replacement                                   200,000
    10             (Base Construction Allocation -
    11             $170,000)
    12             (Land Allocation - $10,000)
    13             (Design and Contingencies - $20,000)
    14         (25)  Fairfield Township, T-931, Patterson
    15             Bridge No.1 over Bear Pond Run, Bridge
    16             Replacement                                   200,000
    17             (Base Construction Allocation -
    18             $170,000)
    19             (Land Allocation - $10,000)
    20             (Design and Contingencies - $20,000)
    21         (26)  Fairfield Township, T-984, Love
    22             Hollow Bridge No.1 over Hendricks Run,
    23             Bridge Replacement                            200,000
    24             (Base Construction Allocation -
    25             $170,000)
    26             (Land Allocation - $10,000)
    27             (Design and Contingencies - $20,000)
    28         (27)  Fairfield Township, T-984, Love
    29             Hollow Bridge No.2 over Hendricks Run,
    30             Bridge Replacement                            200,000
    19970S0186B0698                 - 345 -

     1             (Base Construction Allocation -
     2             $170,000)
     3             (Land Allocation - $10,000)
     4             (Design and Contingencies - $20,000)
     5         (28)  Fairfield Township, T-988, Yeager
     6             Hollow Bridge No.1 over Unnamed
     7             Tributary, Bridge Replacement                 200,000
     8             (Base Construction Allocation -
     9             $170,000)
    10             (Land Allocation - $10,000)
    11             (Design and Contingencies - $20,000)
    12         (29)  Fairfield Township, T-988, Yeager
    13             Hollow Bridge No.2 over Unnamed
    14             Tributary, Bridge Replacement                 200,000
    15             (Base Construction Allocation -
    16             $170,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $20,000)
    19         (30)  Fairfield Township, T-990, Patterson
    20             Bridge No.2 over Unnamed Tributary,
    21             Bridge Replacement                            200,000
    22             (Base Construction Allocation -
    23             $170,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $20,000)
    26         (31)  Ligonier Township, T-505, Horner Hill
    27             Road over Laughlintown Run, Bridge
    28             Replacement                                   175,000
    29             (Base Construction Allocation -
    30             $125,000)
    19970S0186B0698                 - 346 -

     1             (Land Allocation - $15,000)
     2             (Design and Contingencies - $35,000)
     3         (32)  Ligonier Township, T-607, Weller Road
     4             over Unnamed Stream, Bridge
     5             Replacement                                    10,000
     6             (Base Construction Allocation - $8,000)
     7             (Design and Contingencies - $2,000)
     8         (33)  Ligonier Township, T-617, Robb Road
     9             over Hannas Run, Bridge Replacement           310,000
    10             (Base Construction Allocation -
    11             $250,000)
    12             (Land Allocation - $10,000)
    13             (Design and Contingencies - $50,000)
    14         (34)  Ligonier Township, T-719, Peoples
    15             Road over Unnamed Stream, Bridge
    16             Replacement                                   100,000
    17             (Base Construction Allocation -
    18             $75,000)
    19             (Land Allocation - $5,000)
    20             (Design and Contingencies - $20,000)
    21         (35)  Ligonier Township, T-721, Bridge over
    22             North Fork of Trout Run, Bridge
    23             Replacement                                   200,000
    24             (Base Construction Allocation -
    25             $125,000)
    26             (Land Allocation - $10,000)
    27             (Design and Contingencies - $65,000)
    28         (36)  Ligonier Township, T-942, Zion Church
    29             Road over Unnamed Stream, Bridge
    30             Replacement                                    50,000
    19970S0186B0698                 - 347 -

     1             (Base Construction Allocation -
     2             $35,000)
     3             (Land Allocation - $5,000)
     4             (Design and Contingencies - $10,000)
     5         (37)  Ligonier Township, T-984, Mill Road
     6             over Mill Race, Bridge Replacement             50,000
     7             (Base Construction Allocation -
     8             $35,000)
     9             (Land Allocation - $5,000)
    10             (Design and Contingencies - $10,000)
    11         (38)  Ligonier Township, T-950, Old Lincoln
    12             Highway East over Unnamed Stream,
    13             Bridge Rehabilitation                          25,000
    14             (Base Construction Allocation -
    15             $20,000)
    16             (Design and Contingencies - $5,000)
    17         (39)  Ligonier Township, T-984, Harvey Road
    18             over Macks Run, Bridge Rehabilitation           5,000
    19             (Base Construction Allocation - $4,000)
    20             (Design and Contingencies - $1,000)
    21         (40)  Saint Clair Township, T-994, Bridge
    22             over Tubmill Creek, Bridge Replacement        440,000
    23             (Base Construction Allocation -
    24             $325,000)
    25             (Land Allocation - $15,000)
    26             (Design and Contingencies - $100,000)
    27         (41)  Sewickley Township, T-318, Bridge
    28             No.3 over Tributary of Youghiogheny
    29             River, Bridge Replacement                     100,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 348 -

     1             $70,000)
     2             (Land Allocation - $5,000)
     3             (Design and Contingencies - $25,000)
     4         (42)  Derry Township, Conrail Overpass over
     5             SR 0981, Bridge Replacement                 1,600,000
     6             (Base Construction Allocation -
     7             $1,200,000)
     8             (Land Allocation - $200,000)
     9             (Design and Contingencies - $200,000)
    10         (43)  Hempfield Township, T-399 over Jacks
    11             Run, Bridge Replacement                       428,000
    12             (Base Construction Allocation -
    13             $288,000)
    14             (Land Allocation - $15,000)
    15             (Design and Contingencies - $125,000)
    16         (44)  Hempfield Township, T-550 over
    17             Tributary to Little Sewickley Creek,
    18             Bridge Replacement                            428,000
    19             (Base Construction Allocation -
    20             $288,000)
    21             (Land Allocation - $15,000)
    22             (Design and Contingencies - $125,000)
    23         (45)  Ligonier Township, T-984 over Mill
    24             Creek, Bridge Replacement                     650,000
    25             (Base Construction Allocation -
    26             $450,000)
    27             (Land Allocation - $50,000)
    28             (Design and Contingencies - $150,000)
    29         (46)  Salem Township, T-881, Bridge over
    30             Loyalhanna Creek, Bridge Replacement           81,000
    19970S0186B0698                 - 349 -

     1             (Base Construction Allocation -
     2             $67,000)
     3             (Design and Contingencies - $14,000)
     4         (47)  SEWICKLEY TOWNSHIP, T-633, GREEN                     <--
     5             HILLS ROAD BRIDGE OVER LITTLE SEWICKLEY
     6             CREEK, BRIDGE REPLACEMENT                     465,000
     7             (BASE CONSTRUCTION ALLOCATION -
     8             $325,000)
     9             (LAND ALLOCATION - $15,000)
    10             (DESIGN AND CONTINGENCIES - $125,000)
    11     (b)  State Bridges
    12         (1)  SR 0030, Mill Creek Bridge over Mill
    13             Creek, Ligonier Township, Bridge
    14             Replacement                                   910,000
    15             (Base Construction Allocation -
    16             $710,000)
    17             (Land Allocation - $25,000)
    18             (Design and Contingencies - $175,000)
    19         (2)  SR 0031, Jacobs Creek Bridge over
    20             Jacobs Creek, Mount Pleasant and
    21             Bullskin Townships, Bridge Replacement        715,000
    22             (Base Construction Allocation -
    23             $500,000)
    24             (Land Allocation - $40,000)
    25             (Design and Contingencies - $175,000)
    26         (3)  SR0056, Seward Bridge over Conrail and
    27             Local Road, St. Clair Township, Bridge
    28             Painting                                      600,000
    29             (Base Construction Allocation -
    30             $600,000)
    19970S0186B0698                 - 350 -

     1         (4)  SR 0070, I-70 Bridge over N&W
     2             Railroad, Rostraver Township, Bridge
     3             Rehabilitation                              1,565,000
     4             (Base Construction Allocation -
     5             $1,305,000)
     6             (Land Allocation - $60,000)
     7             (Design and Contingencies - $200,000)
     8         (5)  SR 0070, I-70 Bridge over Conrail,
     9             South Huntington Township, Bridge
    10             Rehabilitation                              3,125,000
    11             (Base Construction Allocation -
    12             $2,780,000)
    13             (Land Allocation - $45,000)
    14             (Design and Contingencies - $300,000)
    15         (6)  SR 0119, Crabtree Creek Bridge No.2
    16             over Crabtree Creek, Hempfield
    17             Township, Bridge Replacement                  577,000
    18             (Base Construction Allocation -
    19             $377,000)
    20             (Land Allocation - $25,000)
    21             (Design and Contingencies - $175,000)
    22         (7)  SR 0136, West Newton Bridge over
    23             Youghiogheny River, West Newton
    24             Borough, Bridge Painting                      250,000
    25             (Base Construction Allocation -
    26             $250,000)
    27         (8)  SR 0259, Boliver Underpass Conrail
    28             Railroad over SR 0259, Fairfield
    29             Township, Bridge Replacement                  310,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 351 -

     1             $200,000)
     2             (Land Allocation - $10,000)
     3             (Design and Contingencies - $100,000)
     4         (9)  SR 0271, Bridge over Mill Creek,
     5             Ligonier Township, Bridge Painting             87,000
     6             (Base Construction Allocation -
     7             $87,000)
     8         (10)  SR 0711, Bridge over Mill Creek,
     9             Ligonier Township, Bridge Painting            125,000
    10             (Base Construction Allocation -
    11             $125,000)
    12         (11)  SR 0819, Bridge over Stauffer Bridge,
    13             Scottdale Borough, Bridge Painting             92,000
    14             (Base Construction Allocation -
    15             $92,000)
    16         (12)  SR 0981, Bridge over Branch of Barron
    17             Run, South Huntington Township, Bridge
    18             Replacement                                   250,000
    19             (Base Construction Allocation -
    20             $250,000)
    21         (13)  SR 0982, Bradenville Bridge over
    22             Saxman Run, Derry Township, Bridge
    23             Replacement                                   330,000
    24             (Base Construction Allocation -
    25             $330,000)
    26         (14)  SR 1027, Stoney Run Bridge over
    27             Stoney Run, Derry Township, Bridge
    28             Replacement                                   340,000
    29             (Base Construction Allocation -
    30             $255,000)
    19970S0186B0698                 - 352 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $75,000)
     3         (15)  SR 2008, Fourmile Run Bridge over
     4             Fourmile Run, Cook Township, Bridge
     5             Painting                                       83,000
     6             (Base Construction Allocation -
     7             $83,000)
     8         (16)  SR 2010, Bridge over Branch of Boyer
     9             Run, Mount Pleasant Township, Bridge
    10             Replacement                                   450,000
    11             (Base Construction Allocation -
    12             $250,000)
    13             (Land Allocation - $25,000)
    14             (Design and Contingencies - $175,000)
    15         (17)  SR 8036, New Stanton Ramp Bridge over
    16             SR 3091, New Stanton Borough, Bridge
    17             Rehabilitation                                475,000
    18             (Base Construction Allocation -
    19             $395,000)
    20             (Design and Contingencies - $80,000)
    21         (18)  SR 0030, SR 0030 over Mill Creek,
    22             Ligonier Township, Bridge
    23             Rehabilitation                                200,000
    24             (Base Construction Allocation -
    25             $150,000)
    26             (Design and Contingencies - $50,000)
    27         (19)  SR 0030, SR 0030 over Branch of
    28             Loyalhanna Creek, Unity Township,
    29             Bridge Replacement                            245,000
    30             (Base Construction Allocation -
    19970S0186B0698                 - 353 -

     1             $125,000)
     2             (Land Allocation - $20,000)
     3             (Design and Contingencies - $100,000)
     4         (20)  SR 0217, SR 0217 over Miller Run,
     5             Derry Township, Bridge Replacement            293,000
     6             (Base Construction Allocation -
     7             $188,000)
     8             (Land Allocation - $5,000)
     9             (Design and Contingencies - $100,000)
    10         (21)  SR 0259, SR 0259 over Branch of
    11             Freeman Run, Fairfield Township, Bridge
    12             Replacement                                   218,000
    13             (Base Construction Allocation -
    14             $113,000)
    15             (Land Allocation - $5,000)
    16             (Design and Contingencies - $100,000)
    17         (22)  SR 0381, SR 0381 over Branch of
    18             Loyalhanna Creek, Cook Township, Bridge
    19             Replacement                                   670,000
    20             (Base Construction Allocation -
    21             $450,000)
    22             (Land Allocation - $20,000)
    23             (Design and Contingencies - $200,000)
    24         (23)  SR 0381, SR 0381 over Camp Run,
    25             Donegal Township, Bridge Replacement          608,000
    26             (Base Construction Allocation -
    27             $388,000)
    28             (Land Allocation - $20,000)
    29             (Design and Contingencies - $200,000)
    30         (24)  SR 0711, SR 0711 over Mill Creek,
    19970S0186B0698                 - 354 -

     1             Ligonier Township, Bridge Replacement         600,000
     2             (Base Construction Allocation -
     3             $450,000)
     4             (Land Allocation - $50,000)
     5             (Design and Contingencies - $100,000)
     6         (25)  SR 0982, SR 0982 over Jacobs Creek,
     7             Mount Pleasant Township, Bridge
     8             Replacement                                   938,000
     9             (Base Construction Allocation -
    10             $688,000)
    11             (Land Allocation - $50,000)
    12             (Design and Contingencies - $200,000)
    13         (26)  SR 0982, SR 0982 over Nine Mile Run,
    14             Unity Township, Bridge Replacement            348,000
    15             (Base Construction Allocation -
    16             $238,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $100,000)
    19         (27)  SR 0982, SR 0982 over Indian Camp
    20             Run, Unity Township, Bridge
    21             Replacement                                   335,000
    22             (Base Construction Allocation -
    23             $225,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $100,000)
    26         (28)  SR 1004, SR 1004 over Hendricks
    27             Creek, Fairfield Township, Bridge
    28             Replacement                                   200,000
    29             (Base Construction Allocation -
    30             $170,000)
    19970S0186B0698                 - 355 -

     1             (Land Allocation - $10,000)
     2             (Design and Contingencies - $20,000)
     3         (29)  SR 1006, SR 1006 over Freeman Run,
     4             Fairfield Township, Bridge Replacement        833,000
     5             (Base Construction Allocation -
     6             $613,000)
     7             (Land Allocation - $20,000)
     8             (Design and Contingencies - $200,000)
     9         (30)  SR 1006, West Bolivar Bridge near
    10             Treasure Island, Fairfield Township,
    11             Bridge Replacement                            200,000
    12             (Base Construction Allocation -
    13             $170,000)
    14             (Land Allocation - $10,000)
    15             (Design and Contingencies - $20,000)
    16         (31)  SR 1007, SR 1007 over Tubmill Run,
    17             Fairfield Township, Bridge Replacement        465,000
    18             (Base Construction Allocation -
    19             $350,000)
    20             (Land Allocation - $15,000)
    21             (Design and Contingencies - $100,000)
    22         (32)  SR 1012, SR 1012 over Branch of Megee
    23             Run, Derry Township, Bridge
    24             Replacement                                   318,000
    25             (Base Construction Allocation -
    26             $213,000)
    27             (Land Allocation - $5,000)
    28             (Design and Contingencies - $100,000)
    29         (33)  SR 1014, SR 1014 over Abandoned
    30             Railroad, Derry Township, Bridge
    19970S0186B0698                 - 356 -

     1             Replacement                                   268,000
     2             (Base Construction Allocation -
     3             $163,000)
     4             (Land Allocation - $5,000)
     5             (Design and Contingencies - $100,000)
     6         (34)  SR 1015, SR 1015 over Hypocrite
     7             Creek, Fairfield Township, Bridge
     8             Replacement                                   200,000
     9             (Base Construction Allocation -
    10             $170,000)
    11             (Land Allocation - $10,000)
    12             (Design and Contingencies - $20,000)
    13         (35)  SR 1027, SR 1027 over Branch of Stony
    14             Run, Derry Township, Bridge
    15             Replacement                                   305,000
    16             (Base Construction Allocation -
    17             $200,000)
    18             (Land Allocation - $5,000)
    19             (Design and Contingencies - $100,000)
    20         (36)  SR 1031, SR 1031 over McCune Run,
    21             Derry Township, Bridge Replacement            293,000
    22             (Base Construction Allocation -
    23             $188,000)
    24             (Land Allocation - $5,000)
    25             (Design and Contingencies - $100,000)
    26         (37)  SR 2006, SR 2006 over Branch of
    27             Jacobs Creek, Mt. Pleasant Township,
    28             Bridge Replacement                            403,000
    29             (Base Construction Allocation -
    30             $288,000)
    19970S0186B0698                 - 357 -

     1             (Land Allocation - $15,000)
     2             (Design and Contingencies - $100,000)
     3         (38)  SR 2007, SR 2007 over Shupe Run, Mt.
     4             Pleasant Township, Bridge Replacement         218,000
     5             (Base Construction Allocation -
     6             $113,000)
     7             (Land Allocation - $5,000)
     8             (Design and Contingencies - $100,000)
     9         (39)  SR 2012, SR 2012 over Brinker Run,
    10             Mt. Pleasant Township, Bridge
    11             Replacement                                   415,000
    12             (Base Construction Allocation -
    13             $300,000)
    14             (Land Allocation - $15,000)
    15             (Design and Contingencies - $100,000)
    16         (40)  SR 2021, SR 2021 over Sewickley
    17             Creek, Mt. Pleasant Township, Bridge
    18             Replacement                                 1,463,000
    19             (Base Construction Allocation -
    20             $1,213,000)
    21             (Land Allocation - $50,000)
    22             (Design and Contingencies - $200,000)
    23         (41)  SR 2025, SR 2025 over Tributary of
    24             Jacobs Creek, Mt. Pleasant Township,
    25             Bridge Replacement                            250,000
    26             (Base Construction Allocation -
    27             $225,000)
    28             (Design and Contingencies - $25,000)
    29         (42)  SR 4034, SR 4034 over Pine Run,
    30             Allegheny Township, Bridge Replacement        818,000
    19970S0186B0698                 - 358 -

     1             (Base Construction Allocation -
     2             $588,000)
     3             (Land Allocation - $30,000)
     4             (Design and Contingencies - $200,000)
     5         (43)  SR 4071, SR 4071 over Branch of Pine
     6             Run, Allegheny Township, Bridge
     7             Replacement                                   305,000
     8             (Base Construction Allocation -
     9             $200,000)
    10             (Land Allocation - $5,000)
    11             (Design and Contingencies - $100,000)
    12         (44)  SR 4089, SR 4089 over Branch of
    13             Chartiers Run, Allegheny Township,
    14             Bridge Replacement                            348,000
    15             (Base Construction Allocation -
    16             $238,000)
    17             (Land Allocation - $10,000)
    18             (Design and Contingencies - $100,000)
    19         (45)  T-987, (formerly SR 1071) over
    20             Hypocrite Creek, Fairfield Township,
    21             Four State Bridges, Bridge Replacement        800,000
    22             (Base Construction Allocation -
    23             $680,000)
    24             (Land Allocation - $40,000)
    25             (Design and Contingencies - $80,000)
    26         (46)  SR 0381, SR 0381 over Laughlintown
    27             Run, Ligonier Township, Bridge
    28             Replacement                                   465,000
    29             (Base Construction Allocation -
    30             $350,000)
    19970S0186B0698                 - 359 -

     1             (Land Allocation - $15,000)
     2             (Design and Contingencies - $100,000)
     3         (47)  SR 2043, SR 2043 over Two Mile Run,
     4             Ligonier Township, Bridge Replacement         465,000
     5             (Base Construction Allocation -
     6             $350,000)
     7             (Land Allocation - $15,000)
     8             (Design and Contingencies - $100,000)
     9         (48)  SR 2045, SR 2045 over Two Mile Run,
    10             Ligonier Township, Bridge Replacement         465,000
    11             (Base Construction Allocation -
    12             $350,000)
    13             (Land Allocation - $15,000)
    14             (Design and Contingencies - $100,000)
    15         (49)  SR 2045, SR 2045 over Loyalhanna
    16             Creek, Ligonier Township, Bridge
    17             Replacement                                 1,588,000
    18             (Base Construction Allocation -
    19             $1,313,000)
    20             (Land Allocation - $75,000)
    21             (Design and Contingencies - $200,000)
    22         (50)  SR 0119, Bridge No.2 over Crabtree
    23             Creek, Hempfield Township, Bridge
    24             Replacement                                   577,000
    25             (Base Construction Allocation -
    26             $377,000)
    27             (Land Allocation - $25,000)
    28             (Design and Contingencies - $175,000)
    29         (51)  SR 8036, New Stanton Ramp Bridge over
    30             SR 3091, Turnback Project, New Stanton
    19970S0186B0698                 - 360 -

     1             Borough, Bridge Rehabilitation                475,000
     2             (Base Construction Allocation -
     3             $395,000)
     4             (Design and Contingencies - $80,000)
     5         (52)  SR 2045, BRIDGE OVER LOYALHANNA                      <--
     6             CREEK, LIGONIER TOWNSHIP, BRIDGE
     7             REPLACEMENT                                   800,000
     8             (BASE CONSTRUCTION ALLOCATION -
     9             $600,000)
    10             (LAND ALLOCATION - $25,000)
    11             (DESIGN AND CONTINGENCIES - $175,000)
    12  Section 70.  Wyoming County.
    13     (a)  Local Bridges
    14         (1)  Exeter Township, T-336, Bridge No.1, 2
    15             Miles Southwest of Falls, Bridge
    16             Replacement                                   280,000
    17             (Base Construction Allocation -
    18             $240,000)
    19             (Land Allocation - $10,000)
    20             (Design and Contingencies - $30,000)
    21         (2)  Falls Township, T-336 over White Lock
    22             Stream, Bridge Replacement                    280,000
    23             (Base Construction Allocation -
    24             $240,000)
    25             (Land Allocation - $10,000)
    26             (Design and Contingencies - $30,000)
    27         (3)  Exeter Township, T-336 over Mill
    28             Creek, Bridge Replacement                     214,000
    29             (Base Construction Allocation -
    30             $166,000)
    19970S0186B0698                 - 361 -

     1             (Land Allocation - $20,000)
     2             (Design and Contingencies - $28,000)
     3         (4)  Eaton Township, T-413, Pedestrian
     4             Bridge over Bowman's Creek at
     5             Eatonville, Bridge Rehabilitation             125,000
     6             (Base Construction Allocation -
     7             $113,000)
     8             (Design and Contingencies - $12,000)
     9     (b)  State Bridges
    10         (1)  SR 3001, Bridge at Junction with SR
    11             4004 over Branch of Susquehanna River,
    12             Windham Township, Bridge Painting              60,000
    13             (Base Construction Allocation -
    14             $50,000)
    15             (Design and Contingencies - $10,000)
    16         (2)  State Bridges, Countywide Bridge Zone
    17             Painting, Bridge Painting                     370,000
    18             (Base Construction Allocation -
    19             $350,000)
    20             (Land Allocation - $10,000)
    21             (Design and Contingencies - $10,000)
    22  Section 71.  York County.
    23     (a)  Local Bridges
    24         (1)  Carroll Township, Gettysburg Road
    25             Bridge over Yellow Breeches Creek,
    26             Bridge Replacement                            860,000
    27             (Base Construction Allocation -
    28             $700,000)
    29             (Land Allocation - $10,000)
    30             (Design and Contingencies - $150,000)
    19970S0186B0698                 - 362 -

     1         (2)  Codorus Township, Seitzville Road over
     2             South Branch of Codorus Creek, Bridge
     3             Replacement                                   300,000
     4             (Base Construction Allocation -
     5             $200,000)
     6             (Land Allocation - $15,000)
     7             (Design and Contingencies - $85,000)
     8         (3)  Dover Township, Cardinal Lane over Fox
     9             Run, Bridge Replacement                       115,000
    10             (Base Construction Allocation -
    11             $70,000)
    12             (Land Allocation - $15,000)
    13             (Design and Contingencies - $30,000)
    14         (4)  Dover Township, Conewago Road over
    15             Salem Run, Bridge Replacement                 300,000
    16             (Base Construction Allocation -
    17             $200,000)
    18             (Land Allocation - $15,000)
    19             (Design and Contingencies - $85,000)
    20         (5)  East Hopewell Township, South Church
    21             Street Extended, Bridge No.1, Bridge
    22             Rehabilitation                                  9,000
    23             (Base Construction Allocation - $8,000)
    24             (Design and Contingencies - $1,000)
    25         (6)  East Hopewell Township, South Church
    26             Street Extended, Bridge No.2, over
    27             Rambo Run, Bridge Rehabilitation               60,000
    28             (Base Construction Allocation -
    29             $50,000)
    30             (Design and Contingencies - $10,000)
    19970S0186B0698                 - 363 -

     1         (7)  East Hopewell Township, Manifold
     2             School Road Bridge, Bridge
     3             Rehabilitation                                  7,000
     4             (Base Construction Allocation - $6,000)
     5             (Design and Contingencies - $1,000)
     6         (8)  East Hopewell Township, Trout School
     7             Road Bridge, Bridge Replacement                45,000
     8             (Base Construction Allocation -
     9             $30,000)
    10             (Land Allocation - $5,000)
    11             (Design and Contingencies - $10,000)
    12         (9)  Hellam Township, Valley Acres Road
    13             over Tributary of Kreutz Creek, Bridge
    14             Rehabilitation                                 40,000
    15             (Base Construction Allocation -
    16             $35,000)
    17             (Design and Contingencies - $5,000)
    18         (10)  Hellam Township, Libhart Mill Road
    19             over Tributary of Kreutz Creek, Bridge
    20             Rehabilitation                                 40,000
    21             (Base Construction Allocation -
    22             $35,000)
    23             (Design and Contingencies - $5,000)
    24         (11)  Manchester Township, T-900, Woodland
    25             View Drive over Conrail, Bridge
    26             Replacement                                   395,000
    27             (Base Construction Allocation -
    28             $275,000)
    29             (Land Allocation - $30,000)
    30             (Design and Contingencies - $90,000)
    19970S0186B0698                 - 364 -

     1         (12)  Manchester Township, T-940, Bear Road
     2             2,000 Feet North of Susquehanna Trail,
     3             Bridge Replacement                             40,000
     4             (Base Construction Allocation -
     5             $25,000)
     6             (Land Allocation - $5,000)
     7             (Design and Contingencies - $10,000)
     8         (13)  Manheim Township, T-320 over Unnamed
     9             Tributary of Gunpowder Falls Creek,
    10             Bridge Replacement                            150,000
    11             (Base Construction Allocation -
    12             $100,000)
    13             (Land Allocation - $10,000)
    14             (Design and Contingencies - $40,000)
    15         (14)  Manheim Township, T-346 over West
    16             Branch of Codorus Creek, Bridge
    17             Replacement                                   250,000
    18             (Base Construction Allocation -
    19             $190,000)
    20             (Land Allocation - $10,000)
    21             (Design and Contingencies - $50,000)
    22         (15)  Manheim Township, T-357 over Unnamed
    23             Tributary of West Branch of Codorus
    24             Creek, Bridge Replacement                     160,000
    25             (Base Construction Allocation -
    26             $110,000)
    27             (Land Allocation - $10,000)
    28             (Design and Contingencies - $40,000)
    29         (16)  Manheim Township, T-370 over West
    30             Branch of Codorus Creek, Bridge
    19970S0186B0698                 - 365 -

     1             Replacement                                   200,000
     2             (Base Construction Allocation -
     3             $140,000)
     4             (Land Allocation - $10,000)
     5             (Design and Contingencies - $50,000)
     6         (17)  Manheim Township, T-413 over West
     7             Branch of Codorus Creek, Bridge
     8             Replacement                                   150,000
     9             (Base Construction Allocation -
    10             $100,000)
    11             (Land Allocation - $10,000)
    12             (Design and Contingencies - $40,000)
    13         (18)  Manheim Township, Tannery Road over
    14             West Branch of Codorus Creek, Bridge
    15             Replacement                                   250,000
    16             (Base Construction Allocation -
    17             $180,000)
    18             (Land Allocation - $10,000)
    19             (Design and Contingencies - $60,000)
    20         (19)  Paradise Township, Shady Dell Road,
    21             Bridge Replacement                            190,000
    22             (Base Construction Allocation -
    23             $110,000)
    24             (Land Allocation - $10,000)
    25             (Design and Contingencies - $70,000)
    26         (20)  Paradise Township, Beaver Creek Road
    27             over Beaver Creek, Bridge Replacement         275,000
    28             (Base Construction Allocation -
    29             $195,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 366 -

     1             (Design and Contingencies - $70,000)
     2         (21)  Penn Township, Center Street over
     3             Tributary of Oil Creek, Bridge
     4             Replacement                                   183,000
     5             (Base Construction Allocation -
     6             $163,000)
     7             (Land Allocation - $10,000)
     8             (Design and Contingencies - $10,000)
     9         (22)  Penn Township, Westminster Avenue
    10             over Plum Creek, Bridge Replacement           230,000
    11             (Base Construction Allocation -
    12             $207,000)
    13             (Land Allocation - $8,000)
    14             (Design and Contingencies - $15,000)
    15         (23)  Penn Township, Park Heights over
    16             Tributary of Plum Creek, Bridge
    17             Replacement                                   244,000
    18             (Base Construction Allocation -
    19             $234,000)
    20             (Design and Contingencies - $10,000)
    21         (24)  Red Lion Borough, North Charles
    22             Street over Former Maryland and
    23             Pennsylvania Railroad, Bridge
    24             Replacement                                   395,000
    25             (Base Construction Allocation -
    26             $275,000)
    27             (Land Allocation - $30,000)
    28             (Design and Contingencies - $90,000)
    29         (25)  Spring Garden Township, Tri Hill Road
    30             over Tyler Run, Bridge Replacement            200,000
    19970S0186B0698                 - 367 -

     1             (Base Construction Allocation -
     2             $120,000)
     3             (Land Allocation - $20,000)
     4             (Design and Contingencies - $60,000)
     5         (26)  Windsor Borough, West Gay Street over
     6             Fishing Creek, Bridge Replacement             200,000
     7             (Base Construction Allocation -
     8             $120,000)
     9             (Land Allocation - $20,000)
    10             (Design and Contingencies - $60,000)
    11         (27)  York Township, School Street over
    12             Branch of Mill Creek, Bridge
    13             Replacement                                   250,000
    14             (Base Construction Allocation -
    15             $200,000)
    16             (Design and Contingencies - $50,000)
    17     (b)  State Bridges
    18         (1)  SR 0194, Broadway Street Bridge over
    19             Red Run, Washington Township, Bridge
    20             Replacement                                   245,000
    21             (Base Construction Allocation -
    22             $150,000)
    23             (Land Allocation - $10,000)
    24             (Design and Contingencies - $85,000)
    25         (2)  SR 0234, East Berlin Road Bridge over
    26             Paradise Creek, Jackson Township,
    27             Bridge Replacement                            325,000
    28             (Base Construction Allocation -
    29             $250,000)
    30             (Land Allocation - $10,000)
    19970S0186B0698                 - 368 -

     1             (Design and Contingencies - $65,000)
     2         (3)  SR 3074, Smoketown Road Bridge over
     3             Cod Creek, Manheim Township, Bridge
     4             Replacement                                   325,000
     5             (Base Construction Allocation -
     6             $215,000)
     7             (Land Allocation - $10,000)
     8             (Design and Contingencies - $100,000)
     9         (4)  SR 0116, York Street over Tributary of
    10             Oil Creek, Penn Township, Bridge
    11             Replacement                                   275,000
    12             (Base Construction Allocation -
    13             $240,000)
    14             (Land Allocation - $15,000)
    15             (Design and Contingencies - $20,000)
    16         (5)  SR 0116, SR 0116 over Codorus Creek,
    17             Spring Grove Borough, Bridge
    18             Replacement                                   300,000
    19             (Base Construction Allocation -
    20             $240,000)
    21             (Land Allocation - $15,000)
    22             (Design and Contingencies - $45,000)
    23         (6)  SR 0194, Frederick Street over Plum
    24             Creek, Penn Township, Bridge
    25             Replacement                                   262,000
    26             (Base Construction Allocation -
    27             $234,000)
    28             (Land Allocation - $8,000)
    29             (Design and Contingencies - $20,000)
    30         (7)  SR 1012, Emig Road over Conrail,
    19970S0186B0698                 - 369 -

     1             Manchester Township, Bridge
     2             Replacement                                   395,000
     3             (Base Construction Allocation -
     4             $275,000)
     5             (Land Allocation - $30,000)
     6             (Design and Contingencies - $90,000)
     7         (8)  SR 2031, Penn Street over Fishing
     8             Creek, Windsor Borough, Bridge
     9             Replacement                                   200,000
    10             (Base Construction Allocation -
    11             $120,000)
    12             (Land Allocation - $20,000)
    13             (Design and Contingencies - $60,000)
    14         (9)  SR 3001, South George Street over
    15             Tyler Run, Spring Garden Township,
    16             Bridge Replacement                            200,000
    17             (Base Construction Allocation -
    18             $120,000)
    19             (Land Allocation - $20,000)
    20             (Design and Contingencies - $60,000)
    21         (10)  SR 3074, Smoketown Road Bridge over
    22             Codorus Creek, Manheim Township, Bridge
    23             Replacement                                   240,000
    24             (Base Construction Allocation -
    25             $150,000)
    26             (Land Allocation - $10,000)
    27             (Design and Contingencies - $80,000)
    28  Section 72.  Statewide.
    29     Construction of advanced wetland mitigation
    30  projects necessary to replace wetlands displaced
    19970S0186B0698                 - 370 -

     1  by bridge projects authorized under the act of
     2  December 8, 1982 (P.L.848, No.235), known as the
     3  Highway-Railroad and Highway Bridge Capital Budget
     4  Act for 1982-1983                                      3,100,000
     5             (Base Construction Allocation -
     6             $2,500,000)
     7             (Land Allocation - $350,000)
     8             (Design and Contingencies - $250,000)
     9  Section 72.1.  State forestry bridge projects itemized.
    10     Projects in the category of State forestry bridge projects to
    11  be constructed by the Department of Conservation and Natural
    12  Resources, its successors or assigns, and to be financed by oil
    13  company franchise tax revenues pursuant to 75 Pa.C.S. §
    14  9502(a)(2)(iv) (relating to imposition of tax), are hereby
    15  itemized, together with their respective estimated costs, as
    16  follows:
    17  (a)  State Bridges
    18     (1)  Adams County
    19         (A)  Replacement of Bridge No.01-0005,
    20             District Road Bridge over Carbaugh Run        120,000
    21         (B)  Replacement of Bridge No.01-0004, Dead
    22             Womans Hollow Road Bridge over Mountain
    23             Creek                                         150,000
    24     (2)  Bedford County
    25         (A)  Replacement of Bridge No.02-0002,
    26             Wertz Road Bridge over Cove Creek             100,000
    27         (B)  Replacement of Bridge No.02-0001,
    28             Wertz Road Bridge over Cove Creek             150,000
    29     (3)  Cameron County
    30         (A)  Replacement of Bridge No.13-0012,
    19970S0186B0698                 - 371 -

     1             Brooks Run Road Bridge over Brooks
     2             Road                                          220,000
     3         (B)  Replacement of Bridge No.13-0060,
     4             Brooks State House Bridge over Brooks
     5             Road                                          250,000
     6         (C)  Replacement of Bridge No.13-0037, Mix
     7             Run Road Bridge over Mix Run                  200,000
     8         (D)  Replacement of Bridge No.13-0038, Mix
     9             Run Road over Mix Run                         166,000
    10     (4)  Centre County
    11         (A)  Replacement of Bridge No.07-0010,
    12             Siglerville Millheim Pike Bridge              162,000
    13         (B)  Replacement of Bridge No.07-0015,
    14             Green Valley Road Bridge                      260,000
    15         (C)  Replacement of Bridge No.07-0033, Pine
    16             Creek Road Bridge                             386,000
    17         (D)  Replacement of Bridge No.07-0045,
    18             McCall Dam Road Bridge over White Deer
    19             Creek                                         180,000
    20         (E)  Replacement of Bridge No.09-0030, Six
    21             Mile Run Bridge                               192,000
    22         (F)  Replacement of Bridge No.10-0028,
    23             State Line Road Bridge                        196,000
    24         (G)  Replacement of Bridge No.05-0003,
    25             Krise Valley Road Bridge over Potter
    26             Run                                           100,000
    27         (H)  Replacement of Bridge No.05-0004, Bear
    28             Meadows Road Bridge over Sinking Creek        100,000
    29         (I)  Replacement of Bridge No.05-0005, Bear
    30             Meadows Road Bridge over Galbraith Run        150,000
    19970S0186B0698                 - 372 -

     1         (J)  Replacement of Bridge No.07-0008, Poe
     2             Valley Road Bridge over Big Poe Creek         200,000
     3         (K)  Replacement of Bridge No.07-0028,
     4             Cherry Run Road Bridge over Cherry Run        102,000
     5         (L)  Replacement of Bridge No.07-0029,
     6             Cherry Run Road Bridge over Cherry Run        240,000
     7         (M)  Replacement of Bridge No.07-0035,
     8             Stoney Run Road Bridge over Pine Creek        375,000
     9         (N)  Replacement of Bridge No.09-0026,
    10             Huckleberry Road Bridge over Black
    11             Moshannon Creek                               250,000
    12         (O)  Replacement of Bridge No.09-0029,
    13             Claymine Road Bridge over Six Mile Run        200,000
    14         (P)  Replacement of Bridge No.10-0026,
    15             Panther Road Bridge over Wolf Run             150,000
    16         (Q)  Replacement of Bridge No.07-0007, Poe
    17             Paddy Drive Bridge over Big Poe Creek         170,000
    18     (5)  Clearfield County
    19         (A)  Replacement of Bridge No.09-0005,
    20             Tyler Road Bridge over Laurel Run             284,000
    21         (B)  Replacement of Bridge No.09-0019,
    22             Dent's Branch Road Bridge                     282,000
    23         (C)  Replacement of Bridge No.09-0022,
    24             Merrill Road Bridge                           197,000
    25         (D)  Replacement of Bridge No.09-0012,
    26             Little Medix Road Bridge over Little
    27             Medix Run                                     220,000
    28         (E)  Replacement of Bridge No.09-0013,
    29             Little Medix Road Bridge over Little
    30             Medix Run                                     100,000
    19970S0186B0698                 - 373 -

     1         (F)  Replacement of Bridge No.09-0014,
     2             Little Medix Road Bridge over Little
     3             Medix Run                                     100,000
     4         (G)  Replacement of Bridge No.09-0015,
     5             Little Medix Road Bridge over Little
     6             Medix Run                                     100,000
     7         (H)  Replacement of Bridge No.09-0018,
     8             Dent's Branch Road Bridge over Dent's
     9             Branch Street                                 160,000
    10         (I)  Replacement of Bridge No.09-0020,
    11             Dent's Branch Road Bridge over Dent's
    12             Branch Street                                 165,000
    13         (J)  Replacement of Bridge No.09-0021, Ames
    14             Road Bridge over Deer Creek                   145,000
    15         (K)  Replacement of Bridge No.09-0023, Lost
    16             Run Road Bridge over Giffor Run               138,000
    17         (L)  Replacement of Bridge No.09-0034,
    18             Reservoir Road Bridge over Upper Three
    19             Run                                           120,000
    20     (6)  Clinton County
    21         (A)  Replacement of Bridge No.10-0033,
    22             Cooks Run Road Bridge over Cooks Run          110,000
    23         (B)  Replacement of Bridge No.10-0042, Two
    24             Mile Road Bridge                              100,000
    25         (C)  Replacement of Bridge No.10-0043, Big
    26             Basin Road Bridge over Shintown Run           206,000
    27         (D)  Replacement of Bridge No.10-059,
    28             Bridge over Right Branch of Young
    29             Womans Creek Road                             287,000
    30         (E)  Replacement of Bridge No.10-0064,
    19970S0186B0698                 - 374 -

     1             Trout Run Bridge                              255,000
     2         (F)  Replacement of Bridge No.15-0021,
     3             County Line Road Bridge                       167,000
     4         (G)  Replacement of Bridge No.10-0032,
     5             Cooks Run Road Bridge over Crowley Run        145,000
     6         (H)  Replacement of Bridge No.10-0044,
     7             Robbins Road Bridge over Shintown Run         120,000
     8         (I)  Replacement of Bridge No.10-0051, Fork
     9             Hill Road Bridge over Lebo Run                168,000
    10         (J)  Replacement of Bridge No.10-0052, Left
    11             Branch Young Womans Road Bridge over
    12             Mud Lick Run                                  140,000
    13         (K)  Replacement of Bridge No.10-0053, Left
    14             Branch Young Womans Road Bridge over
    15             Shingle Branch                                145,000
    16         (L)  Replacement of Bridge No.10-0054, Left
    17             Branch Young Womans Road Bridge over
    18             Greenlick Run                                 135,000
    19         (M)  Replacement of Bridge No.10-0057,
    20             Sandy Run Road Bridge over Paddy Run          140,000
    21         (N)  Replacement of Bridge No.10-0061,
    22             Graham Road Bridge over Ferney Run            135,000
    23         (O)  Replacement of Bridge No.10-0063,
    24             Hyner Run Road Bridge over Long Fork          110,000
    25         (P)  Replacement of Bridge No.10-0035,
    26             Bridge over Camp Run                          100,000
    27         (Q)  Replacement of Bridge No.10-0037,
    28             Bridge over Cooks Run                         160,000
    29         (R)  Replacement of Bridge No.12-0032,
    30             Gotshall Road Bridge over Gotshall Run        120,000
    19970S0186B0698                 - 375 -

     1         (S)  REPLACEMENT OF BRIDGE NO.10-0036, OVER                <--
     2             ROCK RUN                                       90,000
     3         (T)  REPLACEMENT OF BRIDGE NO.07-0054, LONG
     4             RUN                                            91,000
     5         (U)  REPLACEMENT OF BRIDGE NO.07-0055, OVER
     6             COOPER RUN                                     70,000
     7     (7)  Cumberland County
     8         (A)  Replacement of Bridge No.01-0006,
     9             Woodrow Road Run Bridge over Mountain
    10             Creek                                         150,000
    11         (B)  Replacement of Bridge No.01-0010,
    12             Milesburn Road Bridge                         102,000
    13         (C)  Replacement of Bridge No.01-0008,
    14             Strohms Hollow Road Bridge over Strohms
    15             Hollow Run                                    138,000
    16         (D)  Replacement of Bridge No.01-0023, Togg
    17             Run Road Bridge over Togg Run                 138,000
    18     (8)  Dauphin County
    19         (A)  Replacement of large culvert, White
    20             Oak Road Bridge over White Oak Run            100,000
    21     (9)  Elk County
    22         (A)  Replacement of Bridge No.13-0040, Red
    23             Run Road Bridge                               160,000
    24         (B)  Replacement of Bridge No.13-0049,
    25             Shaffer Draft Road Bridge                     175,000
    26         (C)  Replacement of Bridge No.13-0050, West
    27             Hicks Run Road Bridge                         175,000
    28         (D)  Replacement of Bridge No.13-0052,
    29             Bridge over East Branch of Hicks Run          175,000
    30         (E)  Replacement of Bridge No.13-0053,
    19970S0186B0698                 - 376 -

     1             Bridge over East Branch of Hicks Run          175,000
     2         (F)  Replacement of Bridge No.09-0006,
     3             Blackwell Road Bridge over Laurel Road        142,000
     4         (G)  Replacement of Bridge No.13-0028,
     5             Porcupine Road Bridge over Dent's Run         183,000
     6         (H)  Replacement of Bridge No.13-0032,
     7             Dent's Run Road Bridge over Little
     8             Dent's Run                                    110,000
     9         (I)  Replacement of Bridge No.13-0039, Mix
    10             Run Road Bridge over Red Run                  184,000
    11     (10)  Franklin County
    12         (A)  Replacement of Bridge No.01-0016, Wirt
    13             Road Bridge                                   147,000
    14         (B)  Replacement of Bridge No.01-0022,
    15             Rattlesnake Run Road Bridge                   149,000
    16         (C)  Replacement of Bridge No.01-0021,
    17             Lindsay Lot Road Bridge over Furnace
    18             Run                                           100,000
    19         (D)  Replacement of Bridge No.01-0019,
    20             Biesecker Gap Road Bridge over
    21             Biesecker Run                                 110,000
    22     (11)  Huntingdon County
    23         (A)  Replacement of Bridge No.05-0012,
    24             Colerain Road Bridge                          235,000
    25         (B)  Replacement of Bridge No.05-0014,
    26             Coopers Gap Road Bridge                       160,000
    27         (C)  Replacement of Bridge No.05-0021,
    28             Stone Creek Road Bridge                       182,000
    29         (D)  Replacement of Bridge No.05-0027,
    30             Diamond Valley Road Bridge over Globe
    19970S0186B0698                 - 377 -

     1             Run                                           100,000
     2         (E)  Replacement of Bridge No.05-0028,
     3             Laurel Run Road Bridge                        213,000
     4         (F)  Replacement of Bridge No.05-0051,
     5             Coopers Gap Road Bridge                       174,000
     6         (G)  Replacement of Bridge No.05-0010,
     7             Martin Road Bridge over Standing Stone
     8             Creek                                         173,000
     9         (H)  Replacement of Bridge No.05-0011,
    10             Pennsylvania Furnace Road Bridge over
    11             Globe Run                                     140,000
    12         (I)  Replacement of Bridge No.05-0017, Pine
    13             Swamp Road Bridge over Shaver Creek           150,000
    14         (J)  Replacement of Bridge No.05-0018,
    15             Beidler Road Bridge over Laurel Run           142,000
    16         (K)  Replacement of Bridge No.05-0020, Rag
    17             Hollow Road Bridge over East Branch
    18             Stone Creek                                   150,000
    19         (L)  Replacement of Bridge No.05-0026,
    20             Pennsylvania Furnace Road Bridge over
    21             Pennsylvania Furnace Run                      110,000
    22         (M)  REPLACEMENT OF BRIDGE NO.05-0019,                     <--
    23             STONE CREEK ROAD OVER DETWEILER RUN            60,000
    24         (N)  REPLACEMENT OF BRIDGE NO.05-0022,
    25             SEEGER ROAD OVER STOIVE CREEK                  70,000
    26     (12)  Jefferson County
    27         (A)  Replacement of Bridge No.08-0003,
    28             Callen Run Road Bridge over Callen Run        200,000
    29         (B)  Replacement of Bridge No.08-0001,
    30             Corbett Road Bridge over Clear Creek          170,000
    19970S0186B0698                 - 378 -

     1     (13)  Juniata County
     2         (A)  Replacement of Bridge No.03-0007,
     3             Spectacle Gap Bridge                          158,000
     4         (B)  Replacement of Bridge No.03-0005, East
     5             Licking Drive Bridge over East Licking
     6             Creek                                         242,000
     7         (C)  Replacement of Bridge No.03-0006, East
     8             Licking Drive Bridge over East Licking
     9             Creek                                         222,000
    10     (13.1)  LACKAWANNA COUNTY                                      <--
    11         (A)  REPLACEMENT OF BRIDGE NO.11-9000,
    12             SASSAFRAS ROAD OVER SPRING RUN                 80,000
    13     (14)  Lycoming County
    14         (A)  Replacement of Bridge No.12-0015, Rock
    15             Run Road Bridge                               175,000
    16         (B)  Replacement of Bridge No.12-0016, Rock
    17             Run Road Bridge                               164,000
    18         (C)  Replacement of Bridge No.12-0019,
    19             Little Bear Bridge                            193,000
    20         (D)  Replacement of Bridge No.12-0020,
    21             Little Bear Bridge                            193,000
    22         (E)  Replacement of Bridge No.12-0021,
    23             Little Bear Bridge                            193,000
    24         (F)  Replacement of Bridge No.12-0022,
    25             Little Bear Creek Road Bridge                 237,000
    26         (G)  Replacement of Bridge No.12-0028,
    27             Fourth Gap Road Bridge                        100,000
    28         (H)  Replacement of Large Culvert, Frances
    29             Road at Big Hollow                            100,000
    30         (I)  Replacement of Bridge No.12-0017,
    19970S0186B0698                 - 379 -

     1             Yellow Dog Road Bridge over Rock Run          245,000
     2         (J)  Replacement of Bridge No.12-0040,
     3             English Run Road Bridge over English
     4             Run                                           238,000
     5         (K)  Replacement of Bridge No.12-0046,
     6             Morris Run Road Bridge over Slate Run         240,000
     7         (L)  Replacement of Bridge No.12-0013,
     8             Hillgrove Road Bridge over Pleasant
     9             Stream                                        150,000
    10         (M)  Replacement of Bridge No.12-0027, Cove
    11             Road Bridge over Fourth Gap                   140,000
    12         (N)  Replacement of Bridge No.12-0023,
    13             Little Bear Road Bridge over Little
    14             Bear Creek                                    120,000
    15     (15)  Mifflin County
    16         (A)  Replacement of Bridge No.03-0008,
    17             Spectacle Gap Road Bridge over East
    18             Licking Creek                                 150,000
    19         (B)  Replacement of Bridge No.07-0004,
    20             Havice Valley Road Bridge over Panther
    21             Run                                           257,000
    22         (C)  Replacement of Bridge No.05-0051,
    23             Cooper Gap Road Bridge over Cooper Gap
    24             Run                                           172,000
    25         (D)  Replacement of Bridge No.07-0057,
    26             Stillhouse Hollow Road Bridge over
    27             Greens Valley Street                          128,000
    28         (E)  Replacement of Bridge No.07-0003,
    29             Havice Valley Road Bridge over Swift
    30             Run                                           125,000
    19970S0186B0698                 - 380 -

     1     (16)  Monroe County
     2         (A)  Replacement of Bridge No.19-0001,
     3             Laurel Run Road Bridge                        159,000
     4     (17)  Perry County
     5         (A)  Replacement of Bridge No.03-0010, Elk
     6             Hill Road Bridge                              152,000
     7         (B)  Replacement of Bridge No.03-0011, Elk
     8             Hill Road Bridge                              152,000
     9         (C)  Replacement of Bridge No.03-0014,
    10             Laurel Run Road Bridge over Laurel Run,
    11             North Branch                                  100,000
    12         (D)  Replacement of Bridge No.03-0015,
    13             Sheaffer Run Bridge, Undermining at
    14             South Abutment                                150,000
    15         (E)  Replacement of Bridge No.03-0016,
    16             Laurel Run Road Bridge                        185,000
    17         (F)  Replacement of Bridge No.03-0018, Twin
    18             Bridge over Laurel Run                        180,000
    19         (G)  Replacement of Culvert, Shearer Dug
    20             Box Culvert                                   100,000
    21     (18)  Pike County
    22         (A)  Replacement of Bridge No.19-0004, Pine
    23             Flats Run Road Bridge                         160,000
    24         (B)  Replacement of Bridge No.19-0005,
    25             Bruce Lake Road Bridge over Tributary
    26             Egypt Meadow Lake                             120,000
    27         (C)  Replacement of Bridge No.19-0803,
    28             Bruce Lake Road Bridge over Egypt
    29             Meadow Lake                                   145,000
    30         (D)  Replacement of Bridge No.19-0002, Hay
    19970S0186B0698                 - 381 -

     1             Road Bridge over Middle Branch                115,000
     2     (19)  Potter County
     3         (A)  Replacement of Bridge No.15-0013,
     4             Windfall Road Bridge                          160,000
     5         (B)  Replacement of Bridge No.15-0015,
     6             Joerg Run Road Bridge                         160,000
     7         (C)  Replacement of Bridge No.15-0018, Lebo
     8             Run Road Bridge                               160,000
     9         (D)  Replacement of Bridge No.15-0020,
    10             Robinson Road Bridge                          230,000
    11         (E)  Replacement of Bridge No.15-0024,
    12             Robinson Road Bridge                          140,000
    13         (F)  Replacement of Bridge No.16-0015,
    14             Butternut Hollow Road Bridge over
    15             Kettle Creek                                  110,000
    16         (G)  Replacement of Bridge No.15-0003,
    17             Jones Run Road Bridge over Freeman Run        175,000
    18         (H)  Replacement of Bridge No.15-0010,
    19             Black Diamond Road Bridge over Big
    20             Moores Run                                    163,000
    21         (I)  Replacement of Bridge No.15-0011,
    22             Horton Run Road Bridge over East Fork
    23             Sinnemahoning Creek                           125,000
    24         (J)  Replacement of Bridge No.15-0014,
    25             Hungry Hollow Road Bridge over Cross
    26             Fork Creek                                    192,000
    27         (K)  Replacement of Bridge No.15-0025,
    28             Nelson Run Road Bridge over Big Nelson
    29             Run                                           138,000
    30         (L)  Replacement of Bridge No.15-0027,
    19970S0186B0698                 - 382 -

     1             Ellis Hollow Road Bridge over Nine Mile
     2             Run                                           146,000
     3         (M)  Replacement of Bridge No.15-0012,
     4             Bailey Run Bridge over Bailey Run             250,000
     5         (N)  Replacement of Bridge No.15-0019,
     6             Twelve Mile Bridge over Spring Brook          107,000
     7     (20)  Schuykill County
     8         (A)  Replacement of Bridge No.18-0003,
     9             Panther Road Bridge over Panther Creek         80,000
    10     (21)  Snyder County
    11         (A)  Replacement of Bridge No.07-0025,
    12             Swift Run Road Bridge over Swift Run          138,000
    13     (22)  Somerset County
    14         (A)  Replacement of Bridge No.04-0002, Blue
    15             Hole Road Bridge                              192,000
    16         (B)  Replacement of Bridge No.04-0008, Cole
    17             Run Road Bridge                               138,000
    18         (C)  Replacement of Bridge No.04-0004,
    19             South Wolf Run Road Bridge over Tub
    20             Mill Run                                      184,000
    21         (D)  Replacement of Bridge No.04-0006,
    22             Jones Mill Run Road Bridge over Jones
    23             Mill Run                                      140,000
    24         (E)  Replacement of Bridge No.06-0002,
    25             State Forest Road Bridge over Tributary
    26             to Roaring Fork                                82,000
    27         (F)  Replacement of Bridge No.06-0004,
    28             Shade Road Bridge over Mile Run               131,000
    29     (23)  Sullivan County
    30         (A)  Replacement of Bridge No.20-0002,
    19970S0186B0698                 - 383 -

     1             Brunnerdale Road Bridge                       220,000
     2         (B)  Replacement of Bridge No.20-0008,
     3             Shanerburg Road Bridge                        212,000
     4         (C)  Replacement of Bridge No.20-0011,
     5             Shanerburg Road Bridge over Shanerburg
     6             Run                                           110,000
     7         (D)  Replacement of Bridge No.20-0004, Mill
     8             Creek Road Bridge over Mill Creek             135,000
     9         (E)  Replacement of Bridge No.20-0005, Mill
    10             Creek Road Bridge over Mill Creek             100,000
    11     (24)  Tioga County
    12         (A)  Replacement of Bridge No.16-0004, Left
    13             Asaph Road Bridge                             248,000
    14         (B)  Replacement of Bridge No.16-0005,
    15             Asaph Run Bridge                              414,000
    16         (C)  Replacement of Bridge No.16-0010,
    17             Painter Leetonia Road Bridge                  170,000
    18         (D)  Replacement of Bridge No.16-0011,
    19             Cedar Run Bridge                              170,000
    20         (E)  Replacement of Bridge No.16-0020, Mine
    21             Hole Road Bridge                              107,000
    22         (F)  Replacement of Bridge No.16-0003, Left
    23             Asaph Road Bridge over Left Asaph Run         186,000
    24         (G)  Replacement of Bridge No.16-0008,
    25             Owasse Road Bridge over Chimney Hollow        120,000
    26         (H)  Replacement of Bridge No.16-0015,
    27             Butternut Hollow Road Bridge over
    28             Kettle Creek                                  145,000
    29         (I)  Replacement of Bridge No.12-0049,
    30             Francis Road Bridge over Francis
    19970S0186B0698                 - 384 -

     1             Branch                                        150,000
     2         (J)  Replacement of Bridge No.16-0016, Bear
     3             Run Road Bridge over Cushman Branch           160,000
     4         (K)  Replacement of Bridge No.16-0018, Mine
     5             Hole Road Bridge over Mine Hole Run           150,000
     6         (L)  REPLACEMENT OF BRIDGE NO.12-0002, LEFT                <--
     7             ASAPH OVER BAKER BRANCH                       200,000
     8     (25)  Union County
     9         (A)  Replacement of Bridge No.07-0016,
    10             Hoofnagle Road Bridge                         235,000
    11         (B)  Replacement of Bridge No.07-0017,
    12             Weikert Run Road Bridge                       235,000
    13         (C)  Replacement of Bridge No.07-0047,
    14             White Deer Creek Road Bridge                  234,000
    15         (D)  Replacement of Bridge No.07-0046,
    16             Cooper Mill Road Bridge over White Deer
    17             Creek                                         212,000
    18         (E)  Replacement of Bridge No.07-0048,
    19             White Deer Creek Road Bridge over White
    20             Deer Creek                                    235,000
    21         (F)  Replacement of Bridge No.07-0041,
    22             Brandon Road Bridge over North Branch
    23             of Buffalo Creek                              107,000
    24         (G)  Replacement of Bridge No.07-0040, Pine
    25             Creek Road Bridge over Rapid Run              165,000
    26     (26)  Westmoreland County
    27         (A)  Replacement of Bridge No.04-0011, Linn
    28             Run Road Bridge over Linn Run                 125,000
    29         (B)  Replacement of Bridge No.04-0012, Linn
    30             Run Road Bridge over Rock Run                 135,000
    19970S0186B0698                 - 385 -

     1  SECTION 72.2.  STATEWIDE BICYCLE AND PEDESTRIAN                   <--
     2  STRUCTURES.
     3     REHABILITATION, CONSTRUCTION AND DEMOLITION OF
     4  BRIDGES AND OTHER CROSSING STRUCTURES ON BICYCLE
     5  AND PEDESTRIAN WAYS TO BE IDENTIFIED BY THE
     6  DEPARTMENT OF CONSERVATION AND NATURAL RESOURCES       5,000,000
     7  Section 73.  Limitation on expenditure of funds.
     8     Any moneys derived from the incurring of debt shall be used
     9  solely for effecting the rehabilitation, replacement or removal
    10  of bridges located on State highways or State forestry bridges.
    11  All other bridge rehabilitation, replacement or removal shall be
    12  financed and State bridge or State forestry bridge
    13  rehabilitation, replacement or removal may also be financed from
    14  current revenue.
    15  Section 74.  Debt authorization.
    16     The Governor, Auditor General and State Treasurer are hereby
    17  authorized and directed to borrow from time to time, in addition
    18  to any authorization heretofore or hereafter enacted, on the
    19  credit of the Commonwealth, subject to the limitations provided
    20  in the current capital budget, money not exceeding in the
    21  aggregate the sum of $962,844,000 $989,925,000 as may be found    <--
    22  necessary to carry out the acquisition and construction of the
    23  State projects specifically itemized in this act.
    24  Section 75.  Issue of bonds.
    25     The indebtedness authorized in this act shall be incurred
    26  from time to time and shall be evidenced by one or more series
    27  of general obligation bonds of the Commonwealth in such
    28  aggregate principal amount for each series as the Governor,
    29  Auditor General and State Treasurer shall determine, but the
    30  latest stated maturity date shall not exceed 30 years from the
    19970S0186B0698                 - 386 -

     1  date of the bond first issued for each series.
     2  Section 76.  Estimated useful life of projects.
     3     The General Assembly states the estimated useful life of the
     4  projects itemized in this act as 30 years.
     5  Section 77.  Appropriation.
     6     The net proceeds of the sale of the obligations authorized in
     7  this act are hereby appropriated from the Capital Facilities
     8  Fund to the department in the maximum amount of $962,844,000      <--
     9  $989,925,000 to be used by it exclusively to defray the
    10  financial costs of the State projects specifically itemized in
    11  this capital budget. After reserving or paying the expenses of
    12  the sale of the obligation, the State Treasurer shall pay out to
    13  the department the moneys as required and certified by it to be
    14  legally due and payable.
    15  Section 78.  Federal funds.
    16     In addition to those funds appropriated in section 77, all
    17  moneys received from the Federal Government for the public
    18  improvement projects specifically itemized in this act are also
    19  hereby appropriated for those projects.
    20  Section 79.  Allocation of funds.
    21     (a)  General rule.--Whenever the department or the Department
    22  of Conservation and Natural Resources determines that the full
    23  estimated financial costs of the projects itemized in this act
    24  are not necessary for the proper design, acquisition or
    25  construction of such projects, the excess funds no longer
    26  required may be allocated by the department or the Department of
    27  Conservation and Natural Resources to increase the estimated
    28  costs of any one or more of the projects specifically itemized
    29  in a capital budget.
    30     (b)  Reimbursement of municipal expenditures.--Moneys raised
    19970S0186B0698                 - 387 -

     1  or expended by municipalities after the effective date of this
     2  act, in anticipation of receipt of funds authorized for projects
     3  itemized by this act, may be reimbursable to those
     4  municipalities.
     5  Section 80.  Policy on jobs and materials.
     6     (a)  Jobs.--It is the declared policy of the Commonwealth
     7  that the construction projects authorized in this act be used,
     8  to the greatest extent possible, to provide for the creation of
     9  jobs and the rehiring of the unemployed in this Commonwealth. In
    10  order to reach this goal, firms with Commonwealth-based
    11  facilities shall be actively solicited to make bids on contracts
    12  to furnish products and materials, including, but not limited
    13  to, steel and steel products, to be used in these projects.
    14     (b)  Materials.--Every contract document entered into to
    15  undertake a project contained in this act shall provide that any
    16  steel or other products to be used or supplied in the
    17  performance of this contract shall be required to be
    18  manufactured by plants in the United States unless the secretary
    19  determines, on a contract by contract basis, that certain
    20  required products are not produced in the United States in
    21  sufficient quantities to meet the requirements of the contract.
    22  Such a determination and the reasons therefor shall be published
    23  in the Pennsylvania Bulletin. Decisions made under this
    24  subsection shall not be inconsistent with the general provisions
    25  of the act of March 3, 1978 (P.L.6, No.3), known as the Steel
    26  Products Procurement Act.
    27     (c)  Minorities and women.--It is also the declared policy of
    28  the Commonwealth to require and encourage substantial
    29  participation by minorities and women in the construction
    30  projects authorized by this act.
    19970S0186B0698                 - 388 -

     1  Section 81.  Payment of capital debt service.
     2     The repayment of any debt incurred pursuant to this act shall
     3  be made from the account and such repayment shall have first
     4  claim on the revenues of the account.
     5  Section 82.  Authorization and debt cumulation.
     6     The additional authorization and debt allowance provided for
     7  in this act shall be added to the total authorizations and debt
     8  incurred pursuant to the act of December 8, 1982 (P.L.848,
     9  No.235), known as the Highway-Railroad and Highway Bridge
    10  Capital Budget Act for 1982-1983, as amended and supplemented.
    11  Section 83.  Editorial changes.
    12     In editing and preparing this act for printing following the
    13  final enactment, the Legislative Reference Bureau shall insert
    14  or revise letters or numbers for projects where the letters or
    15  numbers are missing or require revision. The bureau shall also
    16  revise the total monetary amounts for the total authorization,
    17  debt authorization, appropriations and departmental totals as
    18  necessary to agree with the total monetary amounts of the
    19  projects.
    20  Section 84.  Effective date.
    21     This act shall take effect immediately.






    A3L86BIL/19970S0186B0698        - 389 -