See other bills
under the
same topic
                                                      PRINTER'S NO. 2205

THE GENERAL ASSEMBLY OF PENNSYLVANIA


SENATE BILL

No. 1513 Session of 2002


        INTRODUCED BY MOWERY, LEMMOND, M. WHITE AND A. WILLIAMS,
           AUGUST 30, 2002

        REFERRED TO STATE GOVERNMENT, AUGUST 30, 2002

                                     AN ACT

     1  Amending Title 62 (Procurement) of the Pennsylvania Consolidated
     2     Statutes, further providing for time for awarding contract;
     3     providing for claims for concealed or unknown conditions;
     4     further providing for retainage, for government agency's
     5     progress payment obligations, for penalty and attorney fees,
     6     for applicability and for substantial/final payment under
     7     contract; providing for mediation; further providing for
     8     arbitration; and providing for role of architect or engineer.

     9     The General Assembly of the Commonwealth of Pennsylvania
    10  hereby enacts as follows:
    11     Section 1.  Section 3911 of Title 62 of the Pennsylvania
    12  Consolidated Statutes is amended by adding a subsection to read:
    13  § 3911.  Time for awarding contract.
    14     * * *
    15     (e)  Delays beyond contractor's control.--If a contractor is
    16  prevented from completing any part of the work within the
    17  mandated times or milestones of the construction contract or
    18  construction schedule due to delay beyond the control of the
    19  contractor, the contract times or milestones will be extended in
    20  an amount equal to the time lost due to the delay if a request


     1  for extension is made in writing. Delays beyond the control of
     2  the contractor shall include, but not be limited to, acts or
     3  neglect by the government agency and the engineer or architect,
     4  acts or neglect of utility owners or other contractors
     5  performing other work on separate contracts, fires, floods,
     6  strikes, unforeseen material shortages, epidemics, abnormal
     7  weather conditions or acts of God.
     8     Section 2.  Title 62 is amended by adding a section to read:
     9  § 3914.  Claims for concealed or unknown conditions.
    10     (a)  General rule.--If conditions are encountered at the site
    11  which are:
    12         (1)  subsurface or otherwise concealed physical
    13     conditions which differ materially from those indicated in
    14     the construction contract or construction drawings or plans
    15     accompanying the contract; or
    16         (2)  unknown physical conditions of an unusual nature
    17     which differ materially from those ordinarily found to exist
    18     and generally recognized as inherent in construction
    19     activities of the character provided for in the construction
    20     contract or construction drawings or plans accompanying the
    21     contract.
    22  Notice by the observing party shall be given to the other party
    23  promptly before conditions are disturbed and in no event later
    24  than 21 days after the first observance of the conditions. The
    25  architect or engineer will promptly investigate the conditions
    26  and, if they differ materially and cause an increase or decrease
    27  in the contractor's cost of or time required for performance of
    28  any part of the work, shall recommend an equitable adjustment in
    29  the contract sum, contract time, or both.
    30     (b)  Nonserious conditions.--If the architect or engineer
    20020S1513B2205                  - 2 -

     1  determines that the conditions at the site are not materially
     2  different from those indicated in the construction contract or
     3  construction drawings or plans accompanying the contract and
     4  that no change in the terms of the contract is justified, the
     5  architect or engineer shall so notify the owner and contractor
     6  in writing, stating the reasons.
     7     (c)  Objections.--Claims by either party in opposition to a
     8  determination under subsection (a) or (b) must be made within 21
     9  days after the architect or engineer has given notice of the
    10  decision.
    11     (d)  Materially different conditions.--If the conditions
    12  encountered are materially different, the contract sum and
    13  contract time shall be equitably adjusted, but if the owner and
    14  contractor cannot agree on an adjustment in the contract sum or
    15  contract time, the adjustment shall be subject to arbitration
    16  under section 3942 (relating to arbitration).
    17     Section 3.  Sections 3921(a), 3932(c), 3935, 3938, 3941(a)
    18  and 3942 of Title 62 are amended to read:
    19  § 3921.  Retainage.
    20     (a)  Contract provision.--A contract may include a provision
    21  for the retainage of a portion of the amount due the contractor
    22  to insure the proper performance of the contract except that the
    23  sum withheld by the government agency from the contractor shall
    24  not exceed [10%] 6% of the amount due the contractor until 50%
    25  of the contract is completed. When the contract is 50%
    26  completed, one-half of the amount retained by the government
    27  agency shall be returned to the contractor. However, the
    28  architect or engineer must approve the application for payment,
    29  which approval shall not be unreasonably withheld. The
    30  contractor must be making satisfactory progress, and there must
    20020S1513B2205                  - 3 -

     1  be no specific cause for greater withholding. If the engineer or
     2  architect determines that there is a specific cause for greater
     3  withholding, the reason or reasons must be specified in detail
     4  to the contractor. The decision can be challenged by the
     5  contractor on the basis of reasonableness in the arbitration
     6  procedure provided for in section 3942 (relating to
     7  arbitration). The sum withheld by the government agency from the
     8  contractor after the contract is 50% completed shall not exceed
     9  [5%] 3% of the value of completed work based on monthly progress
    10  payment requests. In the event a dispute arises between the
    11  government agency and any prime contractor, which dispute is
    12  based upon increased costs claimed by one prime contractor
    13  occasioned by delays or other actions of another prime
    14  contractor, additional retainage in the sum of one and one-half
    15  times the amount of any possible liability may be withheld until
    16  [such time as] a final resolution is agreed to by all parties
    17  directly or indirectly involved or the justification and
    18  reasonableness for the additional withholding is decided by
    19  arbitration under section 3942, unless the contractor causing
    20  the additional claim furnishes a bond satisfactory to the
    21  government agency to indemnify the agency against the claim. All
    22  money retained by the government agency may be withheld from the
    23  contractor until substantial completion of the contract.
    24     * * *
    25  § 3932.  Government agency's progress payment obligations.
    26     * * *
    27     (c)  Interest on progress payments not timely made.--[Except
    28  as otherwise agreed by the parties, if any progress payment] If
    29  a progress payment, which shall include payment for change
    30  orders or claims against the government agency which are either
    20020S1513B2205                  - 4 -

     1  agreed to or later found to be proper and warranting payment,
     2  less the applicable retainage amount [as] authorized [in] under
     3  section 3921, is not made to a contractor or design professional
     4  by the due date established in the contract or in subsection
     5  (b), the government agency shall pay to the contractor or design
     6  professional, in addition to the amount due, interest on the
     7  amount due, and the interest shall be computed at the rate
     8  determined by the Secretary of Revenue for interest payments on
     9  overdue taxes or the refund of taxes as provided in sections 806
    10  and 806.1 of the act of April 9, 1929 (P.L.343, No.176), known
    11  as The Fiscal Code.
    12     * * *
    13  § 3935.  Penalty and attorney fees.
    14     (a)  Penalty.--If arbitration or a claim with the Board of
    15  Claims or a court of competent jurisdiction is commenced to
    16  recover payment due under this subchapter and it is determined
    17  that the government agency, contractor or subcontractor has
    18  failed to comply with the payment terms of this subchapter[,] or
    19  has improperly withheld payment to the contractor for reasons
    20  including those set forth in subsection (b), the arbitrator, the
    21  Board of Claims or the court [may] shall award, in addition to
    22  all other damages due, a penalty equal to 1% per month of the
    23  amount that was withheld.[in bad faith. An amount shall be
    24  deemed to have been withheld in bad faith to the extent that the
    25  withholding was arbitrary or vexatious. An amount shall not be
    26  deemed to have been withheld in bad faith to the extent it was
    27  withheld pursuant to section 3934 (relating to withholding of
    28  payment for good faith claims).]
    29     (b)  Attorney fees.--Notwithstanding any agreement to the
    30  contrary, the prevailing party in any proceeding to recover any
    20020S1513B2205                  - 5 -

     1  payment under this subchapter [may] shall be awarded a
     2  reasonable attorney fee in an amount to be determined by the
     3  Board of Claims, court or arbitrator, together with expenses, if
     4  it is determined that the government agency, contractor or
     5  subcontractor [acted in bad faith. An amount shall be deemed to
     6  have been withheld in bad faith to the extent that the
     7  withholding was arbitrary or vexatious.] withheld payment
     8  improperly. Failure on the part of the architect or engineer to
     9  do any of the following shall constitute withholding payment
    10  improperly by the government agency:
    11         (1)  make a final inspection;
    12         (2)  issue a certificate of completion when warranted
    13     under section 3941 (relating to substantial/final payment
    14     under contract);
    15         (3)  list in detail each uncompleted item and a
    16     reasonable cost of completion as required under section 3941;
    17         (4)  arbitrarily withhold amounts due to the contractor,
    18     including payment for approved change orders;
    19         (5)  improperly deduct or continue to withhold payment to
    20     the contractor of retainage due.
    21  § 3938.  Applicability.
    22     (a)  Not applicable in certain situations.--[This subchapter
    23  shall not apply in the following situations:
    24         (1)  Section 3932 (relating to government agency's
    25     progress payment obligations) shall not apply when the
    26     Commonwealth agency's nonpayment on a particular project is
    27     caused by the failure of the General Assembly to enact a
    28     budget for the fiscal year of payment.
    29         (2)  Section 3932 shall not apply when a local government
    30     unit's nonpayment on a particular project is caused by
    20020S1513B2205                  - 6 -

     1     failure of the Federal or State Government to pay funds due
     2     and payable to the local government unit.
     3         (3)  Section 3932 shall not apply when a government
     4     agency's nonpayment on a particular project is caused by the
     5     failure of the General Assembly to enact an operating budget
     6     for the fiscal year of payment or a capital budget for the
     7     capital project or by failure of the Federal, State or local
     8     government to pay funds designated or to be designated for
     9     the specific project.
    10         (4)]  Nothing in this subchapter shall be construed to
    11     require payment of interest penalties by the Federal or State
    12     Government if the local government unit is liable for the
    13     interest.
    14     (b)  Not applicable to following entities.--This chapter
    15  shall not apply to any of the following provided that all
    16  bidders to contracts entered into are informed of the status of
    17  the government agency and are advised that this chapter does not
    18  apply to all contracts bid and awarded by the government agency:
    19         (1)  A municipality determined to be distressed under the
    20     act of July 10, 1987 (P.L.246, No.47), known as the
    21     Municipalities Financial Recovery Act.
    22         (2)  A school district which has been determined to be a
    23     distressed school district under section 691 of the act of
    24     March 10, 1949 (P.L.30, No.14), known as the Public School
    25     Code of 1949.
    26         (3)  A city of the first class that has entered into an
    27     intergovernmental cooperation agreement under the act of June
    28     5, 1991 (P.L.9, No.6), known as the Pennsylvania
    29     Intergovernmental Cooperation Authority Act for Cities of the
    30     First Class, for so long as any deficit-reducing bonds issued
    20020S1513B2205                  - 7 -

     1     by the authority pursuant to section 301(b)(1) of that act
     2     are outstanding and payable.
     3         (4)  A corporate entity or school district as defined in
     4     the Pennsylvania Intergovernmental Cooperation Authority Act
     5     for Cities of the First Class.
     6         (5)  A transportation authority organized or operating
     7     under 74 Pa.C.S. Ch. 17 (relating to metropolitan
     8     transportation authorities).
     9  § 3941.  Substantial/final payment under contract.
    10     (a)  Contract containing provision for retainage.--
    11         (1)  A contract containing a provision for retainage as
    12     provided in section 3921 (relating to retainage) shall
    13     contain a provision requiring the architect or engineer to
    14     make final inspection within 30 days of receipt of the
    15     request of the contractor for final inspection and
    16     application for final payment.
    17         (2)  If the work is substantially completed, the
    18     architect or engineer shall issue a certificate of completion
    19     and a final certificate for payment, and the government
    20     agency shall make payment in full within 45 days except as
    21     provided in section 3921, less only one and one-half times
    22     the amount required to complete any then-remaining
    23     uncompleted minor items, which amount shall be certified by
    24     the architect or engineer and, upon receipt by the government
    25     agency of any guarantee bonds which may be required, in
    26     accordance with the contract, to insure proper workmanship
    27     for a designated period of time.
    28         (3)  If the architect or engineer unreasonably withholds
    29     a determination of substantial completion or the issuance of
    30     a certificate of completion and a final certificate for
    20020S1513B2205                  - 8 -

     1     payment, such action shall constitute failure to comply with
     2     the payment terms under section 3935(a) (relating to penalty
     3     and attorney fees) and withholding payment improperly under
     4     section 3935(b) on the part of the government agency.
     5         (4)  The certificate given by the architect or engineer
     6     shall list in detail each uncompleted item and a reasonable
     7     cost of completion. If the architect or engineer fails to
     8     provide a list in detail, together with the reasonable cost
     9     of completion, within 30 days after receipt of the request of
    10     the contractor for final inspection and application for final
    11     payment and substantial completion has been attained, it will
    12     be presumed that there are no uncompleted items and final
    13     payment, including release of retainage, shall be made to the
    14     contractor within 45 days of the final payment application.
    15         (5)  If a claim is filed by a contractor under this
    16     section and it is disputed by the government agency, the
    17     contractor may request that it be decided by the use of the
    18     expedited arbitration procedure of the Construction Industry
    19     Rules of the American Arbitration Association.
    20         (6)  Final payment of any amount withheld for the
    21     completion of [the] minor items shall be paid upon completion
    22     of [the items] each such item in the certificate of the
    23     engineer or architect.
    24     * * *
    25  § 3942.  Arbitration.
    26     If a dispute should arise between the contractor and the
    27  government agency over the payment of retainages and final
    28  payment or under or arising from the terms or performance of the
    29  construction contract, which dispute is not submitted to or
    30  resolved by mediation, then the dispute shall be arbitrated
    20020S1513B2205                  - 9 -

     1  under the applicable terms of the contract. If the contract
     2  contains no provision for arbitration, [then both parties may
     3  mutually agree to arbitrate] the dispute shall be arbitrated
     4  under the rules of the American Arbitration Association or in
     5  accordance with 42 Pa.C.S. Ch. 73 (relating to arbitration) at
     6  the choice of the claimant. In any event, either party shall
     7  have the right of appeal from any decision and award as provided
     8  by law.
     9     Section 4.  Title 62 is amended by adding a section to read:
    10  § 3942.1.  Mediation.
    11     (a)  General rule.--A claim arising under the terms of the
    12  construction contract or the performance of the contract shall,
    13  after initial decision by the architect or engineer, be subject
    14  to mediation at the request of either party.
    15     (b)  Procedure.--
    16         (1)  The parties shall endeavor to resolve their claims
    17     by mediation which, unless the parties mutually agree
    18     otherwise, shall be in accordance with the Construction
    19     Industry Mediation Rules of the American Arbitration
    20     Association currently in effect. A request for mediation
    21     shall be filed in writing with the other party to the
    22     contract and with the American Arbitration Association.
    23         (2)  The request may be made concurrently with the filing
    24     of a demand for arbitration, in which case mediation shall
    25     proceed in advance of arbitration or legal or equitable
    26     proceedings which shall be stayed pending mediation for a
    27     period of 30 days from the date of filing unless stayed for a
    28     longer period by agreement of the parties.
    29         (3)  The parties shall share the mediator's fee and any
    30     filing fees equally.
    20020S1513B2205                 - 10 -

     1         (4)  The mediation shall be held in the area where the
     2     project is located unless another location is mutually agreed
     3     upon.
     4         (5)  Agreements reached in mediation shall be enforceable
     5     as settlement agreements in a court having jurisdiction.
     6     Section 6.  Chapter 39 of Title 62 is amended by adding a
     7  subchapter to read:
     8                            SUBCHAPTER F
     9                   ROLE OF ARCHITECT OR ENGINEER
    10  Sec.
    11  3951.  General rules.
    12  § 3951.  General rules.
    13     (a)  Government agency's representative and agent.--
    14  Construction contracts awarded by a government agency shall
    15  provide that the architect or engineer will be the government
    16  agency's representative and agent during the construction
    17  period.
    18     (b)  Contract provisions.--Construction contracts shall also
    19  provide that the architect and engineer are bound to the
    20  provisions of the contract in carrying out their duties and
    21  responsibilities in a professional and competent manner, and no
    22  indemnification or waiver clause in a construction contract
    23  shall vary or lessen their duties and responsibilities.
    24     (c)  Impartiality.--While functioning as architect or
    25  engineer under any construction contract awarded by a government
    26  agency, the architect or engineer must not show partiality in
    27  interpretations and decisions of provisions of the contract, but
    28  must serve in an impartial manner.
    29     Section 7.  This act shall take effect in 60 days.

    F19L62MRD/20020S1513B2205       - 11 -